WEEK 4Introduction to Project Management
AgendaPhase 2: Planning
◦Communication Plan◦Scheduling Preparation
Build an AON Diagram Determine Critical Path
◦Resource Planning Build a RACI Chart
PROJECT PLANNING REVIEW
Planning Projects
“Planning is laying out the project groundwork to ensure your goals are met“
Initiating Plannin
g
Executing
Controlling Closing
COMMUNICATION PLANNING
Communication Plan ObjectivesObjective is to determine:
◦Who needs to know what?
◦How will they be told?
◦When will they be told and how
often?
Communication Plan Example
SCHEDULING
Purpose of SchedulingShows relationships of each
activity to others in the whole project
Identifies the precedence relations among activities
Encourages the setting of realistic time and cost estimates for each activity
Helps make better use of people, money, and material resources by identifying critical bottlenecks in the project
Scheduling TechniquesCommon tools
Gantt charts
Project calendars
Milestones charts
Critical Path Method (CPM)
Program Evaluation and Review
Technique (PERT)
Sample Gantt Chart
TimeJ F M A M J J A S
Design
Prototype
Test
Revise
Production
MS Project Example of Gantt Chart
Activity on Node (AON) Explained
AON (Activity on Node)Example: ABC Paper Manufacturing Activities & predecessors
A
Start
BStart Activity
Activity A(Build Internal Components)
Activity B(Modify Roof and Floor)
AON – Step 1
C
D
A
Start
B
Activity A Precedes Activity C
Activities A and B Precede Activity D
AON
G
E
F
H
CA
Start
DB
Arrows Show Precedence Relationships
AON (Finished Product)
Perform a Critical Path Analysis
Determining the Project Schedule
Activity Description Time (weeks)A Build internal components 2B Modify roof and floor 3C Construct collection stack 2D Pour concrete and install frame 4E Build high-temperature burner 4F Install pollution control system 3G Install air pollution device 5H Inspect and test 2
Total Time (weeks) 25
Perform a Critical Path Analysis The critical path is the longest path
through the network The critical path is the shortest time
in which the project can be completed
Any delay in critical path activities delays the project
Determining the Project Schedule
Exercise: Calculate the Critical Path
RESOURCE PLANNING
Resource PlanningQuestions to be answered when
planning resources:◦What needs to be done?◦Who or what can do the work?◦ Is this resource available?◦How will this resource affect schedules and
costs?◦RACI (responsible, accountable, consulted,
informed) Chart◦Estimating would be completed here but we
are not going to get into this in this course
RACI ChartResponsibleAccountable or
ApproveConsultedInformed
Activities 1 -5
PM Director
Service Mgr
Legal Dept
A1 R A
A2 A C I
A3 RA I C
A4 A R C
RACI ModelSteps in a RACI process
◦Identify all the activities◦Identify the roles◦Complete the cells accordingly
(R,A,C,I)◦Resolve overlaps & gaps
Every process should contain only one R Every process must contain at least one
R
WORKSHOP
Group Work ActivityEach group is to create the
following for the fundraising day project◦Communication Plan◦AON (for advertising)◦RACI (for advertising)
Use the templates provided
Hybrid / HomeworkRead Chapter 2Complete all activities required
while reading chapter 2Complete the Matching exercise
for Chapter 2Complete the Multiple Choice for
Chapter 2
Quiz Time
BB
Start MyAlgonuin
Posters
Finish
Write script
Write electronic script
Posters on wall
BB
Start MyAlgonuin
Posters
Finish
Write script
Write electronic script
Posters on wall
BB1h
Start 0
MyAlgonuin1h
BuildPoster
s72h
Finish
Write script
1h
Write electronic script
3h
Posters on wall6h