Project No. 11821008.03 Schnabel Engineering WEEKLY PROGRESS REPORT Woodlake Dam Breach Job Number: 17C2100800 NCDEQ Date: July 15, 2017 Subject: Weekly Project Status From: Schnabel Engineering To: Shane Cook PERIOD: 07-10 through 07-15, 2017 CONTRACT SCHEDULE: Elapsed Contract Time: 27 days WORK COMPLETED THIS WEEK: Cofferdam constructed. Additional stockpile space cleared at the staging area & constructed on the cofferdam. Filled and compacted the scour hole in the downstream, central area of the spillway. WORK IN PROGRESS THIS WEEK: Construction of trenches and sumps to dewater the spillway prior to compaction. Grading and filling the spillway to the specified subgrade. Stockpiling riprap and bedding stone. WORK PLANNED FOR NEXT WEEK: Continue dewatering of the spillway. Compact the spillway to the required specifications and bring it to subgrade. Lay down geosynthetic fabric and bedding stone. Lay down riprap. PHOTOS View of spillway at beginning of week Additional area cleared at the staging area Cofferdam used as additional stockpile area

Upload: others

Post on 01-Aug-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: WEEKLY PROGRESS REPORT - North Carolina Mineral and Land... · 2018-06-19 · WEEKLY PROGRESS REPORT Woodlake Dam Breach Job Number: 17C2100800 NCDEQ Date: July 15, 2017 Subject:

Project No. 11821008.03 Schnabel Engineering

WEEKLY PROGRESS REPORT

Woodlake Dam Breach Job Number: 17C2100800 NCDEQ Date: July 15, 2017 Subject: Weekly Project Status From: Schnabel Engineering To: Shane Cook PERIOD: 07-10 through 07-15, 2017 CONTRACT SCHEDULE: Elapsed Contract Time: 27 days WORK COMPLETED THIS WEEK: Cofferdam constructed. Additional stockpile space cleared at the

staging area & constructed on the cofferdam.

Filled and compacted the scour hole in the downstream, central area of the spillway.

WORK IN PROGRESS THIS WEEK: Construction of trenches and sumps to

dewater the spillway prior to compaction.

Grading and filling the spillway to the specified subgrade.

Stockpiling riprap and bedding stone. WORK PLANNED FOR NEXT WEEK: Continue dewatering of the spillway. Compact the spillway to the required

specifications and bring it to subgrade. Lay down geosynthetic fabric and

bedding stone. Lay down riprap.

PHOTOS

View of spillway at beginning of week

Additional area cleared at the staging area

Cofferdam used as additional stockpile area

Page 2: WEEKLY PROGRESS REPORT - North Carolina Mineral and Land... · 2018-06-19 · WEEKLY PROGRESS REPORT Woodlake Dam Breach Job Number: 17C2100800 NCDEQ Date: July 15, 2017 Subject:

Project No. 11821008.03 Schnabel Engineering

Water beginning to show on spillway

View of the failure hole being dewatered

Bringing the spillway down to the subgrade

View of the dewatered failure hole

Failure hole has been entirely filled in

Water beginning to seep out of spillway

Page 3: WEEKLY PROGRESS REPORT - North Carolina Mineral and Land... · 2018-06-19 · WEEKLY PROGRESS REPORT Woodlake Dam Breach Job Number: 17C2100800 NCDEQ Date: July 15, 2017 Subject:

Project No. 11821008.03 Schnabel Engineering

Spillway sides being filled and compacted

View of the cofferdam from a sandbar

View of the completed dewatering trench

The dewatering trench filled up

Began of construction of a second trench

Trench filled with bedding stone