weekly report[2.2013]
TRANSCRIPT
-
7/29/2019 Weekly Report[2.2013]
1/17
NEW CC CONSTRUCTION CONSULTANTS Co., Ltd.18B Road N.02 Lu Gia Resident Area- Dist 11- HCMC Tel: 08-8641262 fax: 08-8641258
E m a i l : c t t v x d c c @ h c m . v n n . v n
PROJECT: TECHNOMEIJI FACTORY
WEEKLY REPORT(Week No.xx from xxxx , 2012 xxxx , 2012)
-----------------------------------------------------------------------------------------------------------------
Reported by
xxxx Site Manager
Sent to:
Mr. xxxx xxxx the Emplyer
Mr. xxxx xxxx the H/Q CM company
Mr. xxxx xxxx- the Contractor
CONTENTS
WORK PROGRESS
Work in this week:
CONSTRUCTION:- Installing wall cladding of factory 80% completed.- Fabrication steel structure at work shop 100% completed..- Plastering for factory95% completed.- Infrastructure piping works 85% completed.- Brick wall for office area 100% completed.- Plastering for office area 90% completed.- Brick wall for transformer 70% completed.- Crush stone 0x4 for ground floor of factory 100% completed.- Crush stone 0x4 for ground floor of factory 5% completed.- Putty work for office area 10% completed.
M & E:Welding and painting pipe forFire Fighting 70% completedInstalling system pipe Fire Fighting 70% completedDrill hole, installation of hanging rod 50% completed.
II. Quality control
ID Task name Situation Consultants request Remark
1 Concrete Take concrete sample
2 Rebar Take sample for tensile
test & bending test
3 Materials Take sample for material
testing (sand, stone 1x2,
cement, brick)
4 Inspection Supervisor inspects all
work, every day.
+ Request the contractor to add more 02 strengthen plate for steel column of factory 01 at the drill holes
+Request the contractor to add screw for wall cladding
1/17
-
7/29/2019 Weekly Report[2.2013]
2/17
NEW CC CONSTRUCTION CONSULTANTS Co., Ltd.18B Road N.02 Lu Gia Resident Area- Dist 11- HCMC Tel: 08-8641262 fax: 08-8641258
E m a i l : c t t v x d c c @ h c m . v n n . v n
2/17
-
7/29/2019 Weekly Report[2.2013]
3/17
NEW CC CONSTRUCTION CONSULTANTS Co., Ltd.18B Road N.02 Lu Gia Resident Area- Dist 11- HCMC Tel: 08-8641262 fax: 08-8641258
E m a i l : c t t v x d c c @ h c m . v n n . v n
Wall appears some crack
Request the contractor adjust wall purlin, repaint & clean metal sheet of wall before installing wall
cladding
3/17
-
7/29/2019 Weekly Report[2.2013]
4/17
NEW CC CONSTRUCTION CONSULTANTS Co., Ltd.18B Road N.02 Lu Gia Resident Area- Dist 11- HCMC Tel: 08-8641262 fax: 08-8641258
E m a i l : c t t v x d c c @ h c m . v n n . v n
Request the contractor repair bracing beam on the top of the rolling door grid X5-X6/1Y8
4/17
-
7/29/2019 Weekly Report[2.2013]
5/17
NEW CC CONSTRUCTION CONSULTANTS Co., Ltd.18B Road N.02 Lu Gia Resident Area- Dist 11- HCMC Tel: 08-8641262 fax: 08-8641258
E m a i l : c t t v x d c c @ h c m . v n n . v n
Request contractor touch up painting and clear for steel structure
5/17
-
7/29/2019 Weekly Report[2.2013]
6/17
NEW CC CONSTRUCTION CONSULTANTS Co., Ltd.18B Road N.02 Lu Gia Resident Area- Dist 11- HCMC Tel: 08-8641262 fax: 08-8641258
E m a i l : c t t v x d c c @ h c m . v n n . v n
To add some nuts & connection bolt for bracing beam and purlin
6/17
-
7/29/2019 Weekly Report[2.2013]
7/17
NEW CC CONSTRUCTION CONSULTANTS Co., Ltd.18B Road N.02 Lu Gia Resident Area- Dist 11- HCMC Tel: 08-8641262 fax: 08-8641258
E m a i l : c t t v x d c c @ h c m . v n n . v n
Insulation air bubble is broken
III. Safety and environmental
ID STT Task name Situation Schedule Remark
1 Safety No Safety Inform in Next week
2 Cleaning work
IV. Weather
TUE WED THU FRI SAT SUN MON12
1
2
3
4
57
8
9
10
1112
1
2
3
4
57
8
9
10
1112
1
2
3
4
57
8
9
10
1112
1
2
3
4
57
8
9
10
1112
1
2
3
4
57
8
9
10
1112
1
2
3
4
57
8
9
10
1112
1
2
3
4
57
8
9
10
11
xxx xxx xxx xxx xxx xxx xxxMARCH 2012
Off day Rainy chart Raining
Note: Red day is non-working day
7/17
-
7/29/2019 Weekly Report[2.2013]
8/17
NEW CC CONSTRUCTION CONSULTANTS Co., Ltd.18B Road N.02 Lu Gia Resident Area- Dist 11- HCMC Tel: 08-8641262 fax: 08-8641258
E m a i l : c t t v x d c c @ h c m . v n n . v n
Plan of next week
Civil works
* Factory
+ Fabrication of steel frame at workshop: 100%+ Lower soil and sub-grading / 100%
+ Plastering for factory / 100%
+ Infrastructure piping / 100%.
+ Concrete for man hole bottom /100%.
+ Crush stone base course for ground slab of factory 02 / 100% completed.
+ Installing wall cladding of factory 02 & factory 03 / 80% completed.
+ Crush stone base course for ground slab of factory 03: 50% completed.
* Office+ Putty on wall / 100% completed.
+ Brick wall /100% completed.
+ Compacted soil for ground slab /100% completed.+ Plastering for office area / 100% completed.
* Transformer+ Concrete for roof floor/ 100% completed.
+ Brick wall / 100% completed.
* Motor cycle parking+ Lower soil & subgrading / 100% completed.
+ Installing anchor bolt & casting concrete for column /
* M&E (cng tc lp t):+ Welding and paiting pipe fire fighting/ PCC: 100%.
+Installation the pipe for Fire Fighting
/100%.+ Drill hole, installing of hanging rod / 100%
Man Power
No. Title
xxx-xxxTue(xx)
Wed(xx)
Thu(xx)
Fri(xx)
Sat(xx)
Sun(xx)
Mon(xx)
1 Site manager 1 1 1 1 1 1 1
2 Site Eng. 3 3 3 3 3 3 3
3 Surveyor Staff 1 1 1 1 1 1 1
4 Foreman 1 1 1 1 1 1 1
6 Worker 55 50 65 65 50 12 60
7 Total 61 56 71 71 56 18 66
8/17
-
7/29/2019 Weekly Report[2.2013]
9/17
NEW CC CONSTRUCTION CONSULTANTS Co., Ltd.18B Road N.02 Lu Gia Resident Area- Dist 11- HCMC Tel: 08-8641262 fax: 08-8641258
E m a i l : c t t v x d c c @ h c m . v n n . v n
Equipments:
MACHINE AND EQUIPMENT REPORT
No. Title
xxxx xxxx
Tue(xx) Wed(xx) Thu(xx) Fri(xx) Sat(xx) Sun(xx) Mon(xx)1 Bulldozer 1 1 1 1 1 1 1
2 Truck 0 1 1 1 1 0 0
3 Excavator 1 1 1 1 1 1 1
4 Grader 1 1 1 1 1 1 1
5 Theodolite 1 1 1 1 1 1 1
6 Water pump 0 0 0 0 0 0 0
7 Bar cropper 1 1 1 1 1 1 1
8 Roller 1 1 1 1 1 1 1
9 Bending machine 1 1 1 1 1 1 1
10 Vibrator 2 2 2 2 2 2 2
11 Road roller 3 3 3 3 3 3 3
12 Backfill compactor 1 1 1 1 1 1 1
13 Crane 0 0 0 0 0 0 0
14 Total 13 14 14 14 14 13 13
V. Tracking progress: Please see attached work tracking.
VI. Others:
-Request the contractor to speech up office finishing work
-Request the contractor to submit detail connection for purlin grid X3 with office area, the drawing
brick wall grid X1/2Y1-2Y3
-Request the contractorto deliver structure frame to site
-Construction work at site is very slow, next week plan of the contractor was delayed in particular :plaster for office area, putty work, concrete of ground slab of factory 02, install anchorbolt for bike park, compacting ground slab of office area.
-Request the contractor to improve and to overcome to catch schedule.
Site pictures
9/17
-
7/29/2019 Weekly Report[2.2013]
10/17
NEW CC CONSTRUCTION CONSULTANTS Co., Ltd.18B Road N.02 Lu Gia Resident Area- Dist 11- HCMC Tel: 08-8641262 fax: 08-8641258
E m a i l : c t t v x d c c @ h c m . v n n . v n
Brick wall & plastering for office area
Putty work
10/17
-
7/29/2019 Weekly Report[2.2013]
11/17
NEW CC CONSTRUCTION CONSULTANTS Co., Ltd.18B Road N.02 Lu Gia Resident Area- Dist 11- HCMC Tel: 08-8641262 fax: 08-8641258
E m a i l : c t t v x d c c @ h c m . v n n . v n
Waterproof & cement mortar work of office roof slab
Leveling for ground slab of office area
Installing support of roof frame of forklift way
11/17
-
7/29/2019 Weekly Report[2.2013]
12/17
NEW CC CONSTRUCTION CONSULTANTS Co., Ltd.18B Road N.02 Lu Gia Resident Area- Dist 11- HCMC Tel: 08-8641262 fax: 08-8641258
E m a i l : c t t v x d c c @ h c m . v n n . v n
Installing wall cladding for factory 02 & factory 03
Compaction crush stone 0x4 for ground slab of the factory 02
12/17
-
7/29/2019 Weekly Report[2.2013]
13/17
NEW CC CONSTRUCTION CONSULTANTS Co., Ltd.18B Road N.02 Lu Gia Resident Area- Dist 11- HCMC Tel: 08-8641262 fax: 08-8641258
E m a i l : c t t v x d c c @ h c m . v n n . v n
Checking level of stone 0x4 of factory 02 Checking level of ground base of factory 03
Testing field density of factory 02 & factory 03
13/17
-
7/29/2019 Weekly Report[2.2013]
14/17
NEW CC CONSTRUCTION CONSULTANTS Co., Ltd.18B Road N.02 Lu Gia Resident Area- Dist 11- HCMC Tel: 08-8641262 fax: 08-8641258
E m a i l : c t t v x d c c @ h c m . v n n . v n
Constructing crush stone 0x4 for ground slab of the factory 03
Fabrication structure frame
14/17
-
7/29/2019 Weekly Report[2.2013]
15/17
NEW CC CONSTRUCTION CONSULTANTS Co., Ltd.18B Road N.02 Lu Gia Resident Area- Dist 11- HCMC Tel: 08-8641262 fax: 08-8641258
E m a i l : c t t v x d c c @ h c m . v n n . v n
Tensile & bending testing of wire mesh
TRANSFORMER
Installing steel bar, formwork for roof floor
Checking slump of concrete
15/17
-
7/29/2019 Weekly Report[2.2013]
16/17
NEW CC CONSTRUCTION CONSULTANTS Co., Ltd.18B Road N.02 Lu Gia Resident Area- Dist 11- HCMC Tel: 08-8641262 fax: 08-8641258
E m a i l : c t t v x d c c @ h c m . v n n . v n
Casting concrete for roof floor
Getting concrete sample
MOTORCYCLE PARKING
Backfilling for foundation
16/17
-
7/29/2019 Weekly Report[2.2013]
17/17
NEW CC CONSTRUCTION CONSULTANTS Co., Ltd.18B Road N.02 Lu Gia Resident Area- Dist 11- HCMC Tel: 08-8641262 fax: 08-8641258
E m a i l : c t t v x d c c @ h c m . v n n . v n
M & E :
Installing pipe Fire Fighting