Welcome IMAC Members !. Report to IMAC Hesheng Chen. Progress of BEPCII Accelerator Status of BESIII Summary. BEPC running ended July 4 2005. SR running finished at 20 June 20, 2005 SR running: 3009 hour. 362 experiments, 1087 users 1751 hours for test beam & slow e+ source - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: Welcome IMAC Members !](https://reader030.vdocuments.net/reader030/viewer/2022033019/568150cf550346895dbef287/html5/thumbnails/1.jpg)
Welcome
IMAC Members !
![Page 2: Welcome IMAC Members !](https://reader030.vdocuments.net/reader030/viewer/2022033019/568150cf550346895dbef287/html5/thumbnails/2.jpg)
Report to IMAC
Hesheng Chen
• Progress of BEPCII Accelerator
• Status of BESIII
• Summary
![Page 3: Welcome IMAC Members !](https://reader030.vdocuments.net/reader030/viewer/2022033019/568150cf550346895dbef287/html5/thumbnails/3.jpg)
BEPC running ended July 4 2005
• SR running finished at 20 June 20, 2005– SR running: 3009 hour.– 362 experiments, 1087 users – 1751 hours for test beam & slow e+ source
• Machine studies: – high beam current, – e+ injection, – transverse feedback,– BPM, – response matrix, – …
![Page 4: Welcome IMAC Members !](https://reader030.vdocuments.net/reader030/viewer/2022033019/568150cf550346895dbef287/html5/thumbnails/4.jpg)
BEPC running finished July 4, 2005
![Page 5: Welcome IMAC Members !](https://reader030.vdocuments.net/reader030/viewer/2022033019/568150cf550346895dbef287/html5/thumbnails/5.jpg)
Milestones in the shutdown
• Pre-alignment of half units started 17 May 2005
• Remove old ring : July 4 – Aug. 5, 2005√• Survey network in tunnel for magnet alignment
Aug. 6 – Sept. 5, 2005 √
• Decoration tunnel: Aug. 25 – Sept. 22, 2005√• Transformer &Electricity upgrade, new water
pipes, cabling: Sept. 23, 2005 – Mar. 2, 2006 √.
• Installation of two rings: started 2 March,
30 units installed until today.
![Page 6: Welcome IMAC Members !](https://reader030.vdocuments.net/reader030/viewer/2022033019/568150cf550346895dbef287/html5/thumbnails/6.jpg)
Delays in delivery and installation of some key devices
• SCQ: – delivery delayed about 6 month – Installation: more delay
• SCQ Valve boxes : – delivery delayed about 4 month– more delay installation
• Power Leads & valve boxes of BESIII SC magnet.
• Antechamber depressed:
![Page 7: Welcome IMAC Members !](https://reader030.vdocuments.net/reader030/viewer/2022033019/568150cf550346895dbef287/html5/thumbnails/7.jpg)
Progress of Linac
• Tuning Phase I:– e+ available at the end of Linac March 19, 2005 – e+ reached 63mA @ 1.3GeV June 1, 2005– e- reaches 1.89 Gev & e+ 1.55 GeV June 17,2005– Repetition rate 12.5Hz →25Hz → 50Hz
• Shutdown July 4, 2005 – Feb. 28, 2006– Phase control system installed– Microwave system improved– Vacuum system improved– Stability of Linac and beam
• Tuning Phase II: March 1 – July 30, 2006
![Page 8: Welcome IMAC Members !](https://reader030.vdocuments.net/reader030/viewer/2022033019/568150cf550346895dbef287/html5/thumbnails/8.jpg)
Linac commissioning (April-06)
Parameters Goal Measured
Beam energy (GeV) 1.89 1.89 (e-); 1.89 (e+)
Beam current (mA) e+ 40 63
e- 500 > 500
Repetition rate (Hz) 50 25-50
Emittance (1σ) ( mmm rad )
e+ 0.53 0.32 ~ 0.20
e- 0.067 0.080 ~ 0.096
Energy spread (%)
e- 0.50< [email protected]
![Page 9: Welcome IMAC Members !](https://reader030.vdocuments.net/reader030/viewer/2022033019/568150cf550346895dbef287/html5/thumbnails/9.jpg)
Linac Tunnel and Klystron Gallery
![Page 10: Welcome IMAC Members !](https://reader030.vdocuments.net/reader030/viewer/2022033019/568150cf550346895dbef287/html5/thumbnails/10.jpg)
Progress of Storage Ring Mass production of most components finished
2 superconducting RF cavities, 2 RF power sources (250kW), 2 superconducting quards, 49 dipoles, 89 quadrupoles, special magnets in IR, 300 power suppliers of magnets, 4 sets of injection magnet system, 80 antechambers. Instrumentations of beam diagnostics and control
in good progress. In progress:
the vacuum chambers of straight sections, photon absorber movable mask …
![Page 11: Welcome IMAC Members !](https://reader030.vdocuments.net/reader030/viewer/2022033019/568150cf550346895dbef287/html5/thumbnails/11.jpg)
Progress of Storage Ring
• Critical path: – superconducting IR magnet, – pre-alignment – cryogenic system/SC devices integrating.
• Most of the hardware are in the stage of installation, testing and commissioning.
• Installation of pre-aligned magnet unit (B,Q,S with one girder) into the tunnel started March 2. 30 units installed
![Page 12: Welcome IMAC Members !](https://reader030.vdocuments.net/reader030/viewer/2022033019/568150cf550346895dbef287/html5/thumbnails/12.jpg)
Simulation of installation
![Page 13: Welcome IMAC Members !](https://reader030.vdocuments.net/reader030/viewer/2022033019/568150cf550346895dbef287/html5/thumbnails/13.jpg)
Installation of half unit (15-17.5 tone)
by air beds
![Page 14: Welcome IMAC Members !](https://reader030.vdocuments.net/reader030/viewer/2022033019/568150cf550346895dbef287/html5/thumbnails/14.jpg)
![Page 15: Welcome IMAC Members !](https://reader030.vdocuments.net/reader030/viewer/2022033019/568150cf550346895dbef287/html5/thumbnails/15.jpg)
Challenges• Cryogenics system: critical path
– Linde compressors and cryogenics arrived – Gas tanks, He gas pipes, N pipes: done – critical path : valve box, system tuning
• SC devices: critical path– SC Magnets production @BNL: small delay – SC cavities: arrived IHEP last week. – BESIII SC magnet: winding to be finished in 10 d
ays. Assembling / testing? reach the specifications ?
– Uncertainty in system tuning
• Field mapping
IMAC May 2005
![Page 16: Welcome IMAC Members !](https://reader030.vdocuments.net/reader030/viewer/2022033019/568150cf550346895dbef287/html5/thumbnails/16.jpg)
IMAC report (May, 205)• There are apparent discrepancies between the schedule used
by the project office and the one used by the group leaders.• The completion of the cryogenic system can not be accurately
predicted due to the delivery of connection box from HIST and completion of transfer lines. So far, there is about 3 months delay.
• The delivery of vacuum chamber and the Ti-N coating also encountered possible delay of about 3 months and with no effective plan of recovery.
• Commissioning of all three SC components, SCQ, SRF, SSM also will be delayed by more than 3 months caused by the delay of completion of the cryogenic system. More `experienced` manpower is needed to complete the design and installation of the cryogenic transfer lines and smooth start up of the cryogenic system.
• The time allowed for combined field measurement with SCQ and SSM in place appears too tight.
![Page 17: Welcome IMAC Members !](https://reader030.vdocuments.net/reader030/viewer/2022033019/568150cf550346895dbef287/html5/thumbnails/17.jpg)
Difficulties• The teams of cryogenics system and SC device
s are limited and shortage of experiences. However, Many helps from experts of DESY and KEK, the teams are shaping.
• Poor performance of HIT Inst. of SCC: delay, bad cooperation and poor management
• BESIII SC magnet: Wang NMR Co. in some troubles
• We could handle other problems, such as mechanics, control, electronics…
![Page 18: Welcome IMAC Members !](https://reader030.vdocuments.net/reader030/viewer/2022033019/568150cf550346895dbef287/html5/thumbnails/18.jpg)
Spare Scheme of IR Delay & uncertainties of IR devices commissioning :
SCQ + Valve boxes: later arrival and delay in installation
BESIII SC magnetPossible further delay in installation,
commissioning and filed mapping A spare scheme of the IR lattice configuration without
SCQ is designed and under preparation . Two normal conducting bending magnets (70B) will
replace the two SCQ IR magnets. With this scheme, the outer ring (SR), the electron
ring and positron ring can be commissioned. The spare scheme is to save the time of about 3
months for the SCQ field measurement with detector solenoid and the field mapping of the detector solenoid itself.
![Page 19: Welcome IMAC Members !](https://reader030.vdocuments.net/reader030/viewer/2022033019/568150cf550346895dbef287/html5/thumbnails/19.jpg)
Quality Control
Quality control system established: Quality control manuals Quality control forms Quality controller Review designs and prototypes Monitor quality and progress in factories
Most of cases are successful, while some cases have problems in quality and schedule for various reasons.
In case of problem, quality is the first. Over design happens some times.
![Page 20: Welcome IMAC Members !](https://reader030.vdocuments.net/reader030/viewer/2022033019/568150cf550346895dbef287/html5/thumbnails/20.jpg)
BEPCII Summary Schedule
![Page 21: Welcome IMAC Members !](https://reader030.vdocuments.net/reader030/viewer/2022033019/568150cf550346895dbef287/html5/thumbnails/21.jpg)
Linac Plan and Installation of Ring
![Page 22: Welcome IMAC Members !](https://reader030.vdocuments.net/reader030/viewer/2022033019/568150cf550346895dbef287/html5/thumbnails/22.jpg)
Schedule• — 9 Oct. 2006:
– Installation of two rings– Tuning and commissioning of devices and
systems, including SCQ commissioning and field mapping
– Alignment • Oct. 06 - July. 07:
– Tuning of machine + SR running – Field mapping of SCQ + BESIII SC magnet – BESIII assembling and tuning
• Aug. 07: BESIII detector moved into beam line• Sept. 07 : Starting machine-detector tuning. • Data taking by Autumn 2007
![Page 23: Welcome IMAC Members !](https://reader030.vdocuments.net/reader030/viewer/2022033019/568150cf550346895dbef287/html5/thumbnails/23.jpg)
The BESIII Detector
Be beam pipe
SC magnet Magnet yoke
MDC
CsI calorimeter
TOF
![Page 24: Welcome IMAC Members !](https://reader030.vdocuments.net/reader030/viewer/2022033019/568150cf550346895dbef287/html5/thumbnails/24.jpg)
Draft Chamber Structure
![Page 25: Welcome IMAC Members !](https://reader030.vdocuments.net/reader030/viewer/2022033019/568150cf550346895dbef287/html5/thumbnails/25.jpg)
![Page 26: Welcome IMAC Members !](https://reader030.vdocuments.net/reader030/viewer/2022033019/568150cf550346895dbef287/html5/thumbnails/26.jpg)
Wiring of Draft chamber
![Page 27: Welcome IMAC Members !](https://reader030.vdocuments.net/reader030/viewer/2022033019/568150cf550346895dbef287/html5/thumbnails/27.jpg)
MDC: inner part outer part
![Page 28: Welcome IMAC Members !](https://reader030.vdocuments.net/reader030/viewer/2022033019/568150cf550346895dbef287/html5/thumbnails/28.jpg)
Wire Tension Distribution
![Page 29: Welcome IMAC Members !](https://reader030.vdocuments.net/reader030/viewer/2022033019/568150cf550346895dbef287/html5/thumbnails/29.jpg)
MDC electronics
• 160 channel prototype system comics ray test and test beam • 512 channel system: final version • Oct. 2005 intl. review• Mass production under way
![Page 30: Welcome IMAC Members !](https://reader030.vdocuments.net/reader030/viewer/2022033019/568150cf550346895dbef287/html5/thumbnails/30.jpg)
CsI crystal CalorimeterFrance
Sanit -Gobain
Shanghai Institute of Ceramics
Beijing
HamamatsuTotal
Order 2040(3000) 1920 1320 5280(6240)
Arrived 1727 1920 1220 4860
Rejected 43+ ? 7+240? ~20 70+ 240?
![Page 31: Welcome IMAC Members !](https://reader030.vdocuments.net/reader030/viewer/2022033019/568150cf550346895dbef287/html5/thumbnails/31.jpg)
Calorimeter electronics
• FE under production • 3 beam test and and 384 channel prototype: re
ach the performance. Noise: 1000 e/crystal 。• Intl. review• On schedule
![Page 32: Welcome IMAC Members !](https://reader030.vdocuments.net/reader030/viewer/2022033019/568150cf550346895dbef287/html5/thumbnails/32.jpg)
-- 32 --
Installation of RPC into endcap
![Page 33: Welcome IMAC Members !](https://reader030.vdocuments.net/reader030/viewer/2022033019/568150cf550346895dbef287/html5/thumbnails/33.jpg)
-- 33 --
![Page 34: Welcome IMAC Members !](https://reader030.vdocuments.net/reader030/viewer/2022033019/568150cf550346895dbef287/html5/thumbnails/34.jpg)
Mass production ---- Module testTest result of an endcap module ——after install
Test result of a barrel module
![Page 35: Welcome IMAC Members !](https://reader030.vdocuments.net/reader030/viewer/2022033019/568150cf550346895dbef287/html5/thumbnails/35.jpg)
BESIII Magnet Progress包绝热膜 组装
运输
绕线
安装
![Page 36: Welcome IMAC Members !](https://reader030.vdocuments.net/reader030/viewer/2022033019/568150cf550346895dbef287/html5/thumbnails/36.jpg)
![Page 37: Welcome IMAC Members !](https://reader030.vdocuments.net/reader030/viewer/2022033019/568150cf550346895dbef287/html5/thumbnails/37.jpg)
Valve box of BESIII SC magnet
Power leads thermal leakage
![Page 38: Welcome IMAC Members !](https://reader030.vdocuments.net/reader030/viewer/2022033019/568150cf550346895dbef287/html5/thumbnails/38.jpg)
-- 38 --
![Page 39: Welcome IMAC Members !](https://reader030.vdocuments.net/reader030/viewer/2022033019/568150cf550346895dbef287/html5/thumbnails/39.jpg)
BESIII: work to be done • Challenge: BESIII SC magnet
– Power Leads – Test of Valve box– Cool down of Magnet– Performance & Stability – Field mapping
• Under construction – Structure of ECAL endcap– Assembling of subdetectors– Assembling BESIII– Tuning – Cosmic ray test
![Page 40: Welcome IMAC Members !](https://reader030.vdocuments.net/reader030/viewer/2022033019/568150cf550346895dbef287/html5/thumbnails/40.jpg)
Cryogenics system
![Page 41: Welcome IMAC Members !](https://reader030.vdocuments.net/reader030/viewer/2022033019/568150cf550346895dbef287/html5/thumbnails/41.jpg)
Gas tanks and pipes
![Page 43: Welcome IMAC Members !](https://reader030.vdocuments.net/reader030/viewer/2022033019/568150cf550346895dbef287/html5/thumbnails/43.jpg)
Cryogenics pipes made in IHEP
各种低温外管道 各种低温内管道
各种 G10支撑件 8通道低温管线
![Page 44: Welcome IMAC Members !](https://reader030.vdocuments.net/reader030/viewer/2022033019/568150cf550346895dbef287/html5/thumbnails/44.jpg)
Summary LINAC tuning goes smoothly with good progress. Manufacture of most of components of Storage
rings and detector goes well. Some delays and technical difficulties in SC components.
So far, no fundamental problem found in the machine and the detector.
We are in a difficult period with many problems in quality and schedule. Great challenges in next 18 month.
About 4 month delay in schedule so far. Thank you for helps from IMAC and many Labs