2/12/2014 1 Well design & completion www.utp.edu.my By: Dr. Syahrir Ridha WELL CEMENTING Describe the principal functions of cement. Describe the major properties of cement slurry and the additives used in the cement slurries. Calculate the volume of: slurry, cement, mixwater, displacing fluid required for a single stage and two-stage cementing operation. Describe the reasons for setting cement plugs. Describe the principal methods for placing a cement plug in casing or open hole. Describe the principles involved and the tools and techniques used to evaluate the quality of a cementing operation. Well design & completion www.utp.edu.my Lesson Outcome

Upload: angel-ngo

Post on 24-Dec-2015

425 views

Category:

Documents


34 download

DESCRIPTION

Well Cementing

TRANSCRIPT

Page 1: Well Cementing

2/12/2014

1

Well design & completionwww.utp.edu.my

By: Dr. Syahrir Ridha

WELL CEMENTING

Describe the principal functions of cement. Describe the major properties of cement slurry and the

additives used in the cement slurries. Calculate the volume of: slurry, cement, mixwater, displacing

fluid required for a single stage and two-stage cementing operation.

Describe the reasons for setting cement plugs. Describe the principal methods for placing a cement plug in

casing or open hole. Describe the principles involved and the tools and

techniques used to evaluate the quality of a cementing operation.

Well design & completionwww.utp.edu.my

Lesson Outcome

Page 2: Well Cementing

2/12/2014

2

Well design & completionwww.utp.edu.my

Cementing Illustration

Well design & completionwww.utp.edu.my

Objectives

Page 3: Well Cementing

2/12/2014

3

Well design & completionwww.utp.edu.my

Objectives

Well design & completionwww.utp.edu.my

Objectives

Page 4: Well Cementing

2/12/2014

4

Well design & completionwww.utp.edu.my

Cementing Operation

Page 5: Well Cementing

2/12/2014

5

Page 6: Well Cementing

2/12/2014

6

Page 7: Well Cementing

2/12/2014

7

Page 8: Well Cementing

2/12/2014

8

Page 9: Well Cementing

2/12/2014

9

Page 10: Well Cementing

2/12/2014

10

Page 11: Well Cementing

2/12/2014

11

Page 12: Well Cementing

2/12/2014

12

These practices are called single stage cementing

Single-Stage Cementing Operation

Well design & completionwww.utp.edu.my

Page 13: Well Cementing

2/12/2014

13

Multi-Stage Cementing Operation

The idea is to split the cement sheath in the annulus into two, which are:• From the casing shoe to some point above

potentially troublesome formations at the bottom of the hole;

• The cement covering shallower troublesome formations.

Why?1. Long pumping times2. High pump pressures3. Excessive hydrostatic pressure on

weak formations due to the relatively high density of cement slurries.

How its work????

Well design & completionwww.utp.edu.my

Inner String Cementing

It is also known as Stinger Cement Job to cement the casing through a tubing or drillpipestring, rather than trough the casing itself.

Why we need this ???

For LARGE diameter casing, such as conductor and surface casing, conventional cementing techniques result in: The potential for cement contamination during pumping nad

displacement Large displacement volume Long pumping times Large volume of cement left inside the casing between float

collar and shoe.

Well design & completionwww.utp.edu.my

Page 14: Well Cementing

2/12/2014

14

Stinger String Operation

Well design & completionwww.utp.edu.my

A special float shoe is run rather than conventional one.

Once the surface casing (or others) has been run, the string (generally tubing) with the seal adapter attached is run and stabbed into the float shoe.

Drilling mud is then circulated to ensure the annulus clear of any debris.

The cement slurry is pump with spaces ahead and behind.

No plugs are used in this operation since diameter of stinger is so small.

Conventional cementing techniques cannot be used for cementing a liner.

Special equipment must be used for cementing these liners.

The liner has a float collar and shoe installed. There is also a landing collar, positioned about

two joints above the float collar. A wiper plug is held on the end of the tailpipe

of the running string by shear pins. The liner is run on drillpipe and the hanger is set

inside the previous casing string. Mud is circulated to ensure the liner and

annulus free from debris.

Liner Cementing

Well design & completionwww.utp.edu.my

Page 15: Well Cementing

2/12/2014

15

http://www.linertools.com/Publications/how_to_run_and_cement_liners_part_1.pdfFurther reading

1. Pump spacer/wash2. Pump slurry3. Release pump down plug (dart)4. Displace cement down the running string, to the

liner and into the annulus5. Continue pumping until the pump down plug

lands on the wiper plug6. Bleed off pressure and check for back pressure.7. Setting tools release

Procedures as follow:

Liner Cementing

Well design & completionwww.utp.edu.my

QUESTIONS

Well design & completionwww.utp.edu.my

Page 16: Well Cementing

2/12/2014

16

Cementing Equipment Evolution

Well design & completionwww.utp.edu.my

Cementing Equipment Evolution

Well design & completionwww.utp.edu.my

Page 17: Well Cementing

2/12/2014

17

Cementing Equipment Evolution

Well design & completionwww.utp.edu.my

Cementing Equipment Evolution

Well design & completionwww.utp.edu.my

Page 18: Well Cementing

2/12/2014

18

Cementing Equipment Evolution

Well design & completionwww.utp.edu.my

Cementing Equipment Evolution

Well design & completionwww.utp.edu.my

Page 19: Well Cementing

2/12/2014

19

Properties of Cement

Well design & completionwww.utp.edu.my

Properties of Cement

Well design & completionwww.utp.edu.my

API fluid-loss rate less than 50 mL/30 min is often required

Page 20: Well Cementing

2/12/2014

20

Properties of Cement

Well design & completionwww.utp.edu.my

Properties of Cement

Well design & completionwww.utp.edu.my

Page 21: Well Cementing

2/12/2014

21

Properties of Cement

Well design & completionwww.utp.edu.my

Classes of Oilwell Cement

Well design & completionwww.utp.edu.my

Page 22: Well Cementing

2/12/2014

22

Classes of Oilwell Cement

Well design & completionwww.utp.edu.my

Classes of Oilwell Cement

Well design & completionwww.utp.edu.my

Page 23: Well Cementing

2/12/2014

23

API Cement Classification

Classes of Oilwell Cement

Well design & completionwww.utp.edu.my

Cement System

Well design & completionwww.utp.edu.my

Page 24: Well Cementing

2/12/2014

24

Cement Additives

Well design & completionwww.utp.edu.my

Well design & completionwww.utp.edu.my

Cement Additives

A chemical agent used to increase the thickening time of cement slurries to enable proper placement.

Page 25: Well Cementing

2/12/2014

25

Well design & completionwww.utp.edu.my

Cement Additives

Well design & completionwww.utp.edu.my

Cement Additives

Page 26: Well Cementing

2/12/2014

26

Well design & completionwww.utp.edu.my

Cement Additives

Remedial Cementing

Remedial cementing is usually done to correct problems associated with the primary cement job.

The most successful and economical approach to remedial cementing is to avoid it by: thoroughly planning, designing, and executing all

drilling, primary cementing, and completion operations.

Remedial cementing needed to restore a well’s operation indicates that primary operational planning and execution were ineffective resulting in costly repair operations.

Remedial cementing operations consist of two broad categories:1. Squeeze Cementing2. Plug Cementing

Well design & completionwww.utp.edu.my

Page 27: Well Cementing

2/12/2014

27

It is the process by which hydraulic pressure is used to force cement slurry through holes in the casing and into the annulus and/or the formation.

This jobs are often used to carry out remedial operations during a workover on the well.

Squeeze Cementing Application

i. To seal off gas or water producing zones for maximizing oil production;

ii. To repair casing failures by squeezing cement through leaking joints or corrosion hole;

iii. To seal off lost circulation zones;iv. To carry out remedial work on a poor primary cement job;v. To prevent vertical reservoir fluid migration into producing zones;vi. To prevent fluids escaping from abandoned zones.

Squeeze Cementing

Well design & completionwww.utp.edu.my

Methods

High Pressure SqueezeThis method require the formation to be fractured, which then allows the cement slurry to be pumped into the fractured zone.

Low Pressure SqueezeIn this method , the fracture gradient of the formation is not exceeded during squeezing.

Cement slurry is placed against the formation, and when pressure is applied the fluid content (filtrate) of the cement is squeezed into the rock, while the solid cement material (filter cake) builds up on the face of the formation.

Squeeze Cementing

Well design & completionwww.utp.edu.my

Page 28: Well Cementing

2/12/2014

28

Testing the Squeeze JobAfter the cement has hardened it must be pressure test.It should include both positive and negative differential pressure.

Positive pressure test can be performed by closing the BOPs and pressuring up on the casing (Do not exceed formation fracture gradient).

Negative pressure test (inflow test) can be performed by reducing the hydrostatic pressure inside the casing. This can be done using a DST tool. This test is more meaningful since mud filled perforations

may hold pressure from the casing, but may become unblocked when pressure from the formation is applied.

Squeeze Cementing

Well design & completionwww.utp.edu.my

A cement plug is designed to fill a length of casing or open hole to prevent vertical fluid movement.

Cement plugs may be used for:i. Abandoning depleted zonesii. Seal off lost circulation zonesiii. Isolating a zone for formation testingiv. Abandoning an entire well

Plug Cementing

Well design & completionwww.utp.edu.my

Page 29: Well Cementing

2/12/2014

29

Balanced plugThis method is aimed to achieve equal level of cement in the drillpipe and annulus.

Preflush, cement slurry and spacer fluid are pumped down the drillpipe and displaced with mud.

The displacement continues until the level of cement inside and outside the drillpipe is the same (balanced).

If the levels are not the same then a U-tube effect will take place.

The drillpipe can then be retrieved leaving the plug in place.

Plug Cementing

Well design & completionwww.utp.edu.my

Techniques for placing cement plug

Dump bailer This is an electrically operated device which

is run on wireline. A permanent bridge plug is set below the

required plug back depth. A cement bailer containing the slurry is then

lowered down the well on wireline. When the bailer reached the bringe plug the

slurry is released and sits on top of the bridge plug.

Advantages over Balanced PlugHigh accuracy of depth controlReduced risk of contamination of the cement

Plug Cementing

Well design & completionwww.utp.edu.my

Techniques for placing cement plug

Page 30: Well Cementing

2/12/2014

30

Cementing Evaluation

A primary cement job can be considered a failure if the cement does not isolate undesirable zones

Why ?? The cement does not fill the annulus completely; The cement does not provide a good seal between the casing and the

borehole; The cement does not provide a good seal at the casing shoe and a poor

leak off test is achieve.

>>Before these problems are existed, cementing evaluation is performed<<

Temperature survey detecting Top of Cement Cement Bond Log (CBL) detecting the Quality of cement bond

(between casing and cement) Variable Density Log (VDL) detecting the Quality of cement bond

(between casing and cement and also between cement and formation)

Well design & completionwww.utp.edu.my

Temperature surveyInvolves running a thermometer inside the casing just after cement job.It responds to the heat generated by the cement hydration can be used to detect the top of cement

Radioactive surveyRadioactive tracers (carnolite) can be added to the cement slurry before pumped.A logging tool is rub after the cement job is completed.

Cementing Evaluation

Well design & completionwww.utp.edu.my

Detecting Top of Cement

Page 31: Well Cementing

2/12/2014

31

Cement Bond Logs (CBL) This tools become the standard method of evaluating cement jobs,

since they not only detect the top of cement but also indicate how good the cement bond is.

It is a sonic tool which is rub on wireline. The distance between transmitter and receiver is about 3 ft. The logging tool must be centralized in the hole to give accurate results. Both the time taken for the signal and amplitude to reach the receiver

give an indication of the cement bond. The sound speed in casing > that formation or mud, then the first

signals received at receiver are casing. If the applitude is large (strong signal), this indicates that the pipe is

free (poor bond). When cement is firmly bonded to the casing and the formation, the

signal is attenuated.

Measuring quality of cement Bond

Cementing Evaluation

Well design & completionwww.utp.edu.my

“Amplitude” low. Good cement. No

need for squeeze

GOOD CEMENT

“Amplitude” low. Poor cement.

Squeeze cement needed

POOR CEMENT

CBL interpretationCementing Evaluation

Well design & completionwww.utp.edu.my

Page 32: Well Cementing

2/12/2014

32

Variable Density Logs (VDL) CBL only provide bond between casing and cement. VDL can indicate the quality between casing-cement and cement –

formation. A good bond between the casing and cement and cement and

formation is shown by wavy lines to the right of the VDL plot. The wavy lines correspond to those signal which have passed into

formation. If bonding is poor the signal will not reach the formation and parallel

line will be recorded all across the VDL plot.

Cementing Evaluation

Well design & completionwww.utp.edu.my

Measuring quality of cement Bond

Example of VDL

Cementing Evaluation

Well design & completionwww.utp.edu.my

Page 33: Well Cementing

2/12/2014

33

>>Be careful with CEMENT<<

Failure to do so…..

• Data gathering• Lab verification• Cement job simulation

• Cement placement• Flow rate control• Density monitoring• Enough slurry volume

• Hydraulic isolation• Bonding quality• Cement physical properties

Summary

Well design & completionwww.utp.edu.my

Page 34: Well Cementing

2/12/2014

34