wells 4_maersk bop shear ram testing
TRANSCRIPT
11/12/2012 BOP Shear ram testing #1
Wells Process Safety Symposium
Hans Flikkema
What happened:
Master bushings suddenly blew out of
rotary table while jetting wellhead with
seawater.
INCIDENT ALERT
NM - Master Bushings Blown out Out (10.06.10)
What actions taken to prevent recurrence:
Operating practices under total losses
reviewed and recommended changes
have been implemented (next slide) Modified Elevator
What caused it:
Poor accepted practices and procedures!
Well was on total losses since acid stimulation,
over 60 hrs prior, and annulus was
continuously being filled at 8 bbl/min. The
cumulative fill rate was increased to 13
bbl/min to jet wellhead. Evidently, a small
gas bubble at the unknown fluid level
became trapped after pump rate was
increased, then expanded to vertical section
and unloaded seawater exponentially.
What was the result:
Inner bushings and master bushings blew
out of rotary, landing near the AD who was
standing 2 meters away. BOP was closed
and gas bubble bullheaded back to
formation.
MASTER BUSHING
PIN
MASTER
BUSHINGS
BUSHING INSERT
Synergi Case
1542
Changes in operating practises
implemented:
• All post stimulation operations prior to
completion will be carried out with
rotating head installed and activated as
extra barrier
• Post stimulation completions will be
run with sump packer and plug in
tailpipe installed to isolate the reservoir
prior to running the top completion with
multiple control lines.
• In case installation of sump packer is
not possible (multiple zone
completions) the well will be stimulated
after the completion has been installed
through application of QCAJ liners.
• Well designs and relevant operating
procedures have been amended
accordingly.
INCIDENT ALERT
NM - Master Bushings Blown out Out (10.06.10)
Modified Elevator
MASTER BUSHING
PIN
MASTER
BUSHINGS
BUSHING INSERT
Synergi
Case 1542
13-5/8” BOP Shear Ram testing Charles Rowan February and March 2011
OBJECTIVE:
TO VERIFY SHEAR RAM PERFORMANCE WITH THE
BOP’s, RANGE OF TUBULARS (4-1/2”, 5-1/2”, 7”)
AND CONTROL LINE CONFIGURATIONS TYPICALLY
USED IN MAERSK OIL QATAR.
11/12/2012 BOP Shear ram testing #4
11/12/2012 BOP Shear ram testing #5
7” TUBING
11/12/2012 BOP Shear ram testing #6
+/- 6”
Flat pack
squeezed
by side
packers.
As these pictures show then the control lines will not
necessarily be cut 100% and can then cause the rams to
leak on the following pressure tests.
Only 25% (4 out of 16) of the initial
pressure tests were successful. 11/12/2012 BOP Shear ram testing #7
ISR
Body & Blades: 350 deg F / 35% H2S
Elastomers: 250 deg F / 5% H2S & 350 deg F / 35% H2S (Top Packer only)
13-5/8” 10M U max shear OD 7.53”
Calculated shear pressure to shear 7” 23# L-80 w/ Large Bore Bonnets
and Tandem Boosters 2136 psi (No well pressure).
11/12/2012 BOP Shear ram testing #8
Follow up action
• ISR type rams only because they shear/seal more
effectively than SBR type rams .
• 4 ram stack up now standard. –It allows for extra blind
ram on top.
• Completion practises adapted;
• Always us RTH when losses.
• Run sump packer with plug prior to running completion (single
zone stimulated completions)
• Stimulate well after completion has been installed ( multiple
zone completions)
11/12/2012 #9 BOP Shear ram testing
BOP EQUIPMENT changes
CAMERON 13-5/8” 10M TYPE U WITH LARGE BORE
BONNETS AND TANDEM BOOSTER ARRANGEMENT.
CONFIGURATIONS IN TODAY’s OPERATION:
ANNULAR – DOUBLE U – DRILLING SPOOL – SINGLE U
ANNULAR - DOUBLE U – DOUBLE U
CONFIGURATION IN FUTURE OPERATIONS FOLLOWING TEST:
ANNULAR – SINGLE U - DOUBLE U – DRILLING SPOOL – SINGLE U
ANNULAR – DOUBLE U – DOUBLE U
ISR RAMS only
Extra set of blind rams on top of shear rams
11/12/2012 BOP Shear ram testing #10