  • 8/10/2019 WEM - Chapter 3 - Activity Plan for Well Construction Process

    1/8

    Well Engineering Manual Revision 0 OKIOC Doc.no.: 99-03-002

    Chapter 3 Activity Plan for Well Construction Process Page 1 of 8

    OKIOC - CONTROLLING DOCUMENT

    WELL ENGINEERING MANUAL (WEM)

    CHAPTER 3 ACTIVITY PLAN FOR WELL

    CONSTRUCTION PROJECTS

  • 8/10/2019 WEM - Chapter 3 - Activity Plan for Well Construction Process

    2/8

    Well Engineering Manual Revision 0 OKIOC Doc.no.: 99-03-002

    Chapter 3 Activity Plan for Well Construction Process Page 2 of 8

    TABLE OF CONTENTS

    1. INTRODUCTION....................................................................................................................... 3

    2. REQUIREMENTS ..................................................................................................................... 3

    3. PLANNING PHASE................................................................................................................... 3

    4. SCHEDULING PHASE.............................................................................................................. 4

  • 8/10/2019 WEM - Chapter 3 - Activity Plan for Well Construction Process

    3/8

    Well Engineering Manual Revision 0 OKIOC Doc.no.: 99-03-002

    Chapter 3 Activity Plan for Well Construction Process Page 3 of 8

    1. INTRODUCTION

    The following sections contain activity lists for the planning phase and scheduling phase, as described

    in the previous chapter. They should be seen as guidelines that could be used as a starting point for

    setting up a well construction project. Activities not applicable to the specific well construction projectcan be deleted for the specific activity plan.

    The lists can be used to assign staff to activities and thus maintain a project management type of

    control on the progression of the well construction project.

    2. REQUIREMENTS

    In order for these lists to be up to date and to reflect the latest lessons learned, the Drilling

    Superintendent shall ensure that the electronic versions are being updated after conclusion of every

    well construction project.

    3. PLANNING PHASE

    The following activity list is the base case list for the planning phase:

    ID Task Name

    1 Conceptual Plan Report

    2 Outline Well ( from WR [Planning] )

    3 Define welltype

    4 Define total lifecycle of well

    5 Policies, procedures, standards and controls in place?

    6 Review offset data

    7 Obtain offset data: well reports, mudlogs, petrophysical logs, etc.

    8 Analyse offset wells for performance and lessons learned

    9 Identify areas requiring a more detailed follow up

    10 Wellpath Design11 Define wellpath from surface location and target locations/path requirements

    12 Perform torque / drag calculations for optimum path (deviated wells only)

    13 Consider hole cleaning / stability problems

    14 3rd party check / wellpath design

    15 Casing Design

    16 Review formations, pore pressures, formation strengths & temperature gradient

    17 Check offset wells for problems

    18 Obtain well evaluation requirements

    19 Prepare preliminary casing design (incl. alternatives / contingencies)

    20 Check design for shallow gas implications

    21 Completion for development wells

    22 Define completion requirements

    23 Identify long lead time items

    24 Top Hole procedures - anticipated

    25 Mud Programme - requirements in terms of weights, special26 Cement Programme - requirements in terms of weights, gastight, special needs

    27 Formation Evaluation

    28 Coring programme - define requirements

    29 Wireline logging - define requirements

    30 MWD/LWD - define requirements31 Palyno-stratigraphic services - define requirements

  • 8/10/2019 WEM - Chapter 3 - Activity Plan for Well Construction Process

    4/8

    Well Engineering Manual Revision 0 OKIOC Doc.no.: 99-03-002

    Chapter 3 Activity Plan for Well Construction Process Page 4 of 8

    ID Task Name

    32 AFE

    33 Preliminary Time-Depth curve

    34 Costs - spread-rate

    35 Well Test - define requirements

    36 Rig

    37 Identify type and availability

    38 Contract strategy39 Manning / Training

    40 Staff level, resources and budget cover

    41 Specialist training requirements

    42 Logistics & Materials

    43 Logistics

    44 Identify base

    45 Vessels - identify level of activity and availability

    46 Identify heliport

    47 Materials

    48 Identify long lead time items

    49 HSE

    50 Identify environmental sensitivities

    51 Hazard Identification

    52 Well Risk Identification

    53 Well Test Risk Identification

    4. SCHEDULING PHASE

    The following activity list is the base case list for the scheduling phase:

    ID Task Name

    1 Part B (of Drilling Programme)

    2 Prepare Outline Well Programme ( from WR [Scheduling] )

    3 Define welltype

    4 Define total lifecycle of well

    5 Policies, procedures, standards and controls in place?

    6 Review offset data

    7 Obtain offset well reports, mudlogs, petrophysical logs8 Check with contractors for available info

    9 Analyse offset wells for performance and lessons learned

    10 Identify areas requiring a more detailed follow up

    11 Meetings with other Operators to gain info (e.g. Partners)

    12 Wellpath Design

    13 Define wellpath from surface location and target locations/path requirements

    14 Perform torque / drag calculations for optimum path

    15 Consider hole cleaning / stability problems

    16 3rd party check / wellpath design

    17 Internal review

    18 Casing Design

    19 Review outline Well Test proposal for casing size requirements

    20 Review formations, pore pressures & formation strengths

    21 Check offset wells for problems

    22 Obtain well evaluation requirements

    23 Prepare casing design (incl. alternatives / contingencies)

    24 Check kick tolerance acceptance

    25 Present casing design internally

    26 Design landing strings

    27 Design liner running strings

    28 3rd party QA

    29 Implement 3rd party comments

    30 Get results from Site Survey

    31 Check design for shallow gas implications against warning level

    32 Update casing design (conductor & tophole)

    33 Define pressure testing requirements

    34 Internal review casing design report

    35 Issue non conformances as required

    36 Casing Design completed & signed off (proceed with procurement)

  • 8/10/2019 WEM - Chapter 3 - Activity Plan for Well Construction Process

    5/8

    Well Engineering Manual Revision 0 OKIOC Doc.no.: 99-03-002

    Chapter 3 Activity Plan for Well Construction Process Page 5 of 8

    ID Task Name

    37 Completion design for development wells

    38 Completion design, downhole hardware

    39 Flow equipment design: x-mas tree, flowlines, facilities etc.

    40 Packers fluids

    41 Completion fluids

    42 3rd party QA / design

    43 Internal review44 Top Hole procedures

    45 Process shallow seismic survey (through customer)

    46 Receive site survey report (through customer)

    47 Investigate need for pilot hole as per warning level

    48 Define criteria for pilot hole depth

    49 Set-up shallow gas instructions with contractor

    50 Review existing shallow gas procedures

    51 Mud Programme

    52 Receive mud proposal

    53 Environmental assessment of selected mud

    54 Check Parcom data

    55 Verify mud programme

    56 Calculate estimated discharge volumes

    57 Finalise programme

    58 Prepare operational guidelines59 Review of solids control equipment (shakers)

    60 Assess need for using centrifuges with contractor

    61 Assess need for centrifuge contract

    62 Cement Programme

    63 Define required cement properties (density, gastight etc.)

    64 Define required cement heights based on casing design & well proposal

    65 Review cement proposal

    66 Calculate estimated discharge volumes

    67 Check cementing procedures for each string

    68 Finalise programme

    69 Formation Evaluation

    70 Coring programme

    71 Define coring requirements

    72 Assess available technology

    73 Finalise coring requirements

    74 Set-up coring programme

    75 Evaluation of coring method

    76 Prepare effective coring programme

    77 Prepare operational guidance notes

    78 Core Barrels

    79 Define requirements

    80 Order core heads

    81 Order core barrels

    82 Pre-coring meeting

    83 Finalise wireline logging requirements

    84 Agree on EPX requirements

    85 Assess available tool selection

    86 Prepare time effective programme (incl. contingencies)

    87 Finalise MWD/LWD requirements88 Directional drilling requirements

    89 Agree on EPX requirements

    90 Assess use of LWD

    91 Assess available tools

    92 Set up survey / logging programme

    93 Finalise Mudlogging requirements

    94 Agree on EPX requirements

    95 Prepare sampling programme

    96 Agree on Paleo requirements

    97 Challenge duplication of information gathered

  • 8/10/2019 WEM - Chapter 3 - Activity Plan for Well Construction Process

    6/8

    Well Engineering Manual Revision 0 OKIOC Doc.no.: 99-03-002

    Chapter 3 Activity Plan for Well Construction Process Page 6 of 8

    ID Task Name

    98 AFE

    99 Costs

    100 Obtain offset rates

    101 Obtain logging time/cost estimate

    102 Review ledger costs for previous wells for overheads, office manning / timewriting etc.

    103 Determine well specific rates: casing, equipment, rigrate, services etc.

    104 Evaluate transport / supply costs105 Evaluate charter / flight costs

    106 Evaluate extra / special costs and sensitivities

    107 Finalise Time-Depth

    108 Prepare Cost-Depth curve

    109 Compile AFE (10/90 & 90/10)

    110 Present the AFE internally

    111 Present the AFE to Partners

    112 Finalise Well Programme

    113 Define non-conformances and submit to Kazakh Authorities

    114 Assess use of special equipment, e.g. 6 5/8" DP

    115 Prepare Drilling Techniques Note with input from service companies

    116 Initial drill the well on paper exercise

    117 Update Drilling Techniques Notes

    118 Optimise operational sequence

    119 Final drill the well on paper exercise120 Internal review

    121 Review against "lessons learned"

    122 Update well programme

    123 Issue Well Programme

    124 Present programme to partners

    125 Well Abandonment / Suspension (separate programme)

    126 Define strategy and requirements

    127 Identify equipment and resources needed

    128 Prepare programme

    129 Define non-comformances

    130 Internal review

    131 Issue programme

    132 Well Test (separate programme)

    133 Finalise internal requirements ( from WR [Testing] )

    134

    135 Planning meeting with test contractor

    136 Testing Hazid

    137 Follow-up HAZID action points

    138 Assess use of seawater in annulus

    139 Internal presentation

    140 Contractor presentation

    141 Prepare internal HAZOP

    142 HAZOP

    143 Well test planning by test contractor

    144 Well Test Eqt

    145 Define requirements

    146 Audit well testing eqt on rig

    147 Order well testing eqt

    148 Review test programme149 Organise pre-test meeting

    150 Rig Upgrade

    151 Review kick detection system requirements against kick tolerance

    152

    153

    154

    155

    156

    157 Communication

    158 Check reference (position) system

    159 Define telecomms requirements

    160 Drilling office computer hardware / software

    161 Drilling data reporting system

    162 Check available telecomms system

  • 8/10/2019 WEM - Chapter 3 - Activity Plan for Well Construction Process

    7/8

    Well Engineering Manual Revision 0 OKIOC Doc.no.: 99-03-002

    Chapter 3 Activity Plan for Well Construction Process Page 7 of 8

    ID Task Name

    163

    164

    165

    166

    167

    168

    169170

    171 Drilling unit inspection

    172 Review of existing checklists

    173 Review current Operator's action lists

    174 Review maintenance system onboard

    175 Prepare inspection checklist

    176

    177 Document inspection

    178 Review certification status

    179 Training

    180 Define training requirements

    181 Organise training

    182 Wellplan course

    183 DIMS course

    184185

    186

    187 Risk Analysis course

    188

    189 Well Control course / IWCF exam

    190 HPHT course

    191

    192 Logistics & Materials

    193 Logistics

    194 Base

    195 Define supply base

    196 Identify base coordinator

    197 Check experience level at base

    198 Define critical material requirements

    199 Assess coop. with other operators on sharing eqt

    200 Set-up personnel transportation plan

    201 Vessels

    202 Anchor handling requirements

    203 Define supply / standby vessel needs (incl. Nofo requirements)

    204 Set-up rig supply programme

    205 Set-up supply vessel contracts

    206 Set-up standby vessel contracts

    207 Inspect standby & supply vessels

    208 Helicopters

    209 Modify helicopter contracts

    210 Audit heliport facilities

    211 Asses need for Forward Looking Infra Red

    212 Assess need for survival suits with transmitter

    213 Materials214 Casing

    215

    216 Seek & find casing

    217 Order casing

    218 Casing delivery / inspection

    219 Liner Hangers

    220 Define liner hanger requirements

    221 Define PBR requirements

    222 Define liner hanger leadtime

    223 Order liner hangers

    224 Wellhead

    225 Order wellhead

    226

    227 Order 20" surface casing

    228 Order 30" conductor

  • 8/10/2019 WEM - Chapter 3 - Activity Plan for Well Construction Process

    8/8

    Well Engineering Manual Revision 0 OKIOC Doc.no.: 99-03-002

    Chapter 3 Activity Plan for Well Construction Process Page 8 of 8

    ID Task Name

    229 Well hardware

    230

    231 Tubing, tubing hanger, tubing accessories

    232 Wellhead adaptor

    233 X-mas tree

    234

    235236 Bits

    237 Review offset data

    238 Prepare info package to bit vendors

    239 Obtain bit proposals

    240 Select bits

    241 Order bits

    242 Services

    243 Contingency well planning by WfD

    244 Contracts in place for all services needed

    245 Authorities

    246 Prepare discharge documentation

    247 Prepare Permit Application

    248 Submit Permit Application

    249 Obtain Drilling permit

    250 Well testing Permit251 HSE

    252 Hazard Identification

    253 Hazid meeting

    254 Review of Hazid action list

    255 Well Risk Assessment

    256 Risk Assessment meeting

    257 Document RA

    258 Working environment assessment

    259 Well Test Risk Assessment

    260 Risk Assessment meeting

    261 Document RA