Well Engineering Manual Revision 0 OKIOC Doc.no.: 99-03-002
Chapter 3 Activity Plan for Well Construction Process Page 1 of 8
OKIOC - CONTROLLING DOCUMENT
WELL ENGINEERING MANUAL (WEM)
CHAPTER 3 ACTIVITY PLAN FOR WELL
CONSTRUCTION PROJECTS
-
8/10/2019 WEM - Chapter 3 - Activity Plan for Well Construction Process
2/8
Well Engineering Manual Revision 0 OKIOC Doc.no.: 99-03-002
Chapter 3 Activity Plan for Well Construction Process Page 2 of 8
TABLE OF CONTENTS
1. INTRODUCTION....................................................................................................................... 3
2. REQUIREMENTS ..................................................................................................................... 3
3. PLANNING PHASE................................................................................................................... 3
4. SCHEDULING PHASE.............................................................................................................. 4
-
8/10/2019 WEM - Chapter 3 - Activity Plan for Well Construction Process
3/8
Well Engineering Manual Revision 0 OKIOC Doc.no.: 99-03-002
Chapter 3 Activity Plan for Well Construction Process Page 3 of 8
1. INTRODUCTION
The following sections contain activity lists for the planning phase and scheduling phase, as described
in the previous chapter. They should be seen as guidelines that could be used as a starting point for
setting up a well construction project. Activities not applicable to the specific well construction projectcan be deleted for the specific activity plan.
The lists can be used to assign staff to activities and thus maintain a project management type of
control on the progression of the well construction project.
2. REQUIREMENTS
In order for these lists to be up to date and to reflect the latest lessons learned, the Drilling
Superintendent shall ensure that the electronic versions are being updated after conclusion of every
well construction project.
3. PLANNING PHASE
The following activity list is the base case list for the planning phase:
ID Task Name
1 Conceptual Plan Report
2 Outline Well ( from WR [Planning] )
3 Define welltype
4 Define total lifecycle of well
5 Policies, procedures, standards and controls in place?
6 Review offset data
7 Obtain offset data: well reports, mudlogs, petrophysical logs, etc.
8 Analyse offset wells for performance and lessons learned
9 Identify areas requiring a more detailed follow up
10 Wellpath Design11 Define wellpath from surface location and target locations/path requirements
12 Perform torque / drag calculations for optimum path (deviated wells only)
13 Consider hole cleaning / stability problems
14 3rd party check / wellpath design
15 Casing Design
16 Review formations, pore pressures, formation strengths & temperature gradient
17 Check offset wells for problems
18 Obtain well evaluation requirements
19 Prepare preliminary casing design (incl. alternatives / contingencies)
20 Check design for shallow gas implications
21 Completion for development wells
22 Define completion requirements
23 Identify long lead time items
24 Top Hole procedures - anticipated
25 Mud Programme - requirements in terms of weights, special26 Cement Programme - requirements in terms of weights, gastight, special needs
27 Formation Evaluation
28 Coring programme - define requirements
29 Wireline logging - define requirements
30 MWD/LWD - define requirements31 Palyno-stratigraphic services - define requirements
-
8/10/2019 WEM - Chapter 3 - Activity Plan for Well Construction Process
4/8
Well Engineering Manual Revision 0 OKIOC Doc.no.: 99-03-002
Chapter 3 Activity Plan for Well Construction Process Page 4 of 8
ID Task Name
32 AFE
33 Preliminary Time-Depth curve
34 Costs - spread-rate
35 Well Test - define requirements
36 Rig
37 Identify type and availability
38 Contract strategy39 Manning / Training
40 Staff level, resources and budget cover
41 Specialist training requirements
42 Logistics & Materials
43 Logistics
44 Identify base
45 Vessels - identify level of activity and availability
46 Identify heliport
47 Materials
48 Identify long lead time items
49 HSE
50 Identify environmental sensitivities
51 Hazard Identification
52 Well Risk Identification
53 Well Test Risk Identification
4. SCHEDULING PHASE
The following activity list is the base case list for the scheduling phase:
ID Task Name
1 Part B (of Drilling Programme)
2 Prepare Outline Well Programme ( from WR [Scheduling] )
3 Define welltype
4 Define total lifecycle of well
5 Policies, procedures, standards and controls in place?
6 Review offset data
7 Obtain offset well reports, mudlogs, petrophysical logs8 Check with contractors for available info
9 Analyse offset wells for performance and lessons learned
10 Identify areas requiring a more detailed follow up
11 Meetings with other Operators to gain info (e.g. Partners)
12 Wellpath Design
13 Define wellpath from surface location and target locations/path requirements
14 Perform torque / drag calculations for optimum path
15 Consider hole cleaning / stability problems
16 3rd party check / wellpath design
17 Internal review
18 Casing Design
19 Review outline Well Test proposal for casing size requirements
20 Review formations, pore pressures & formation strengths
21 Check offset wells for problems
22 Obtain well evaluation requirements
23 Prepare casing design (incl. alternatives / contingencies)
24 Check kick tolerance acceptance
25 Present casing design internally
26 Design landing strings
27 Design liner running strings
28 3rd party QA
29 Implement 3rd party comments
30 Get results from Site Survey
31 Check design for shallow gas implications against warning level
32 Update casing design (conductor & tophole)
33 Define pressure testing requirements
34 Internal review casing design report
35 Issue non conformances as required
36 Casing Design completed & signed off (proceed with procurement)
-
8/10/2019 WEM - Chapter 3 - Activity Plan for Well Construction Process
5/8
Well Engineering Manual Revision 0 OKIOC Doc.no.: 99-03-002
Chapter 3 Activity Plan for Well Construction Process Page 5 of 8
ID Task Name
37 Completion design for development wells
38 Completion design, downhole hardware
39 Flow equipment design: x-mas tree, flowlines, facilities etc.
40 Packers fluids
41 Completion fluids
42 3rd party QA / design
43 Internal review44 Top Hole procedures
45 Process shallow seismic survey (through customer)
46 Receive site survey report (through customer)
47 Investigate need for pilot hole as per warning level
48 Define criteria for pilot hole depth
49 Set-up shallow gas instructions with contractor
50 Review existing shallow gas procedures
51 Mud Programme
52 Receive mud proposal
53 Environmental assessment of selected mud
54 Check Parcom data
55 Verify mud programme
56 Calculate estimated discharge volumes
57 Finalise programme
58 Prepare operational guidelines59 Review of solids control equipment (shakers)
60 Assess need for using centrifuges with contractor
61 Assess need for centrifuge contract
62 Cement Programme
63 Define required cement properties (density, gastight etc.)
64 Define required cement heights based on casing design & well proposal
65 Review cement proposal
66 Calculate estimated discharge volumes
67 Check cementing procedures for each string
68 Finalise programme
69 Formation Evaluation
70 Coring programme
71 Define coring requirements
72 Assess available technology
73 Finalise coring requirements
74 Set-up coring programme
75 Evaluation of coring method
76 Prepare effective coring programme
77 Prepare operational guidance notes
78 Core Barrels
79 Define requirements
80 Order core heads
81 Order core barrels
82 Pre-coring meeting
83 Finalise wireline logging requirements
84 Agree on EPX requirements
85 Assess available tool selection
86 Prepare time effective programme (incl. contingencies)
87 Finalise MWD/LWD requirements88 Directional drilling requirements
89 Agree on EPX requirements
90 Assess use of LWD
91 Assess available tools
92 Set up survey / logging programme
93 Finalise Mudlogging requirements
94 Agree on EPX requirements
95 Prepare sampling programme
96 Agree on Paleo requirements
97 Challenge duplication of information gathered
-
8/10/2019 WEM - Chapter 3 - Activity Plan for Well Construction Process
6/8
Well Engineering Manual Revision 0 OKIOC Doc.no.: 99-03-002
Chapter 3 Activity Plan for Well Construction Process Page 6 of 8
ID Task Name
98 AFE
99 Costs
100 Obtain offset rates
101 Obtain logging time/cost estimate
102 Review ledger costs for previous wells for overheads, office manning / timewriting etc.
103 Determine well specific rates: casing, equipment, rigrate, services etc.
104 Evaluate transport / supply costs105 Evaluate charter / flight costs
106 Evaluate extra / special costs and sensitivities
107 Finalise Time-Depth
108 Prepare Cost-Depth curve
109 Compile AFE (10/90 & 90/10)
110 Present the AFE internally
111 Present the AFE to Partners
112 Finalise Well Programme
113 Define non-conformances and submit to Kazakh Authorities
114 Assess use of special equipment, e.g. 6 5/8" DP
115 Prepare Drilling Techniques Note with input from service companies
116 Initial drill the well on paper exercise
117 Update Drilling Techniques Notes
118 Optimise operational sequence
119 Final drill the well on paper exercise120 Internal review
121 Review against "lessons learned"
122 Update well programme
123 Issue Well Programme
124 Present programme to partners
125 Well Abandonment / Suspension (separate programme)
126 Define strategy and requirements
127 Identify equipment and resources needed
128 Prepare programme
129 Define non-comformances
130 Internal review
131 Issue programme
132 Well Test (separate programme)
133 Finalise internal requirements ( from WR [Testing] )
134
135 Planning meeting with test contractor
136 Testing Hazid
137 Follow-up HAZID action points
138 Assess use of seawater in annulus
139 Internal presentation
140 Contractor presentation
141 Prepare internal HAZOP
142 HAZOP
143 Well test planning by test contractor
144 Well Test Eqt
145 Define requirements
146 Audit well testing eqt on rig
147 Order well testing eqt
148 Review test programme149 Organise pre-test meeting
150 Rig Upgrade
151 Review kick detection system requirements against kick tolerance
152
153
154
155
156
157 Communication
158 Check reference (position) system
159 Define telecomms requirements
160 Drilling office computer hardware / software
161 Drilling data reporting system
162 Check available telecomms system
-
8/10/2019 WEM - Chapter 3 - Activity Plan for Well Construction Process
7/8
Well Engineering Manual Revision 0 OKIOC Doc.no.: 99-03-002
Chapter 3 Activity Plan for Well Construction Process Page 7 of 8
ID Task Name
163
164
165
166
167
168
169170
171 Drilling unit inspection
172 Review of existing checklists
173 Review current Operator's action lists
174 Review maintenance system onboard
175 Prepare inspection checklist
176
177 Document inspection
178 Review certification status
179 Training
180 Define training requirements
181 Organise training
182 Wellplan course
183 DIMS course
184185
186
187 Risk Analysis course
188
189 Well Control course / IWCF exam
190 HPHT course
191
192 Logistics & Materials
193 Logistics
194 Base
195 Define supply base
196 Identify base coordinator
197 Check experience level at base
198 Define critical material requirements
199 Assess coop. with other operators on sharing eqt
200 Set-up personnel transportation plan
201 Vessels
202 Anchor handling requirements
203 Define supply / standby vessel needs (incl. Nofo requirements)
204 Set-up rig supply programme
205 Set-up supply vessel contracts
206 Set-up standby vessel contracts
207 Inspect standby & supply vessels
208 Helicopters
209 Modify helicopter contracts
210 Audit heliport facilities
211 Asses need for Forward Looking Infra Red
212 Assess need for survival suits with transmitter
213 Materials214 Casing
215
216 Seek & find casing
217 Order casing
218 Casing delivery / inspection
219 Liner Hangers
220 Define liner hanger requirements
221 Define PBR requirements
222 Define liner hanger leadtime
223 Order liner hangers
224 Wellhead
225 Order wellhead
226
227 Order 20" surface casing
228 Order 30" conductor
-
8/10/2019 WEM - Chapter 3 - Activity Plan for Well Construction Process
8/8
Well Engineering Manual Revision 0 OKIOC Doc.no.: 99-03-002
Chapter 3 Activity Plan for Well Construction Process Page 8 of 8
ID Task Name
229 Well hardware
230
231 Tubing, tubing hanger, tubing accessories
232 Wellhead adaptor
233 X-mas tree
234
235236 Bits
237 Review offset data
238 Prepare info package to bit vendors
239 Obtain bit proposals
240 Select bits
241 Order bits
242 Services
243 Contingency well planning by WfD
244 Contracts in place for all services needed
245 Authorities
246 Prepare discharge documentation
247 Prepare Permit Application
248 Submit Permit Application
249 Obtain Drilling permit
250 Well testing Permit251 HSE
252 Hazard Identification
253 Hazid meeting
254 Review of Hazid action list
255 Well Risk Assessment
256 Risk Assessment meeting
257 Document RA
258 Working environment assessment
259 Well Test Risk Assessment
260 Risk Assessment meeting
261 Document RA