Financial Year Project Name Major Activity PROJECT COST Status REMARKS 2013/2014 Contituency Office Administration fund 6% Day to day office operations,staff salaries & general office management 4,709,705 Complete Funds Utilised 2013/2014 Emergency Fund Reserve fund for emergencies and disasters 3,564,466.00 Complete Funds Utilised 2013/2014 Education Bursary Fees Payment for needy students in colleges and universities and activities for enhancement in performance in national examinations. 7,000,000 Complete Funds disbursed to needy students 2013/2014 Monitoring & Evaluation Ensuring sound management and successful completion of projects through through close supervision and evaluation. 2,354,852.00 Complete Funds Utilised 2013/2014 Constituency Sports Committee Sports activities within the constituency 390,000 Complete Complete and In use 2013/2014 Bomorito Primary School Planting of assorted tree varieties in school compound 80,000 Complete Complete and In use 2013/2014 Nyansabakwa Secondary School Planting of assorted tree varieties in school compound 80,000 Complete Complete and In use 2013/2014 Senator Kebaso Secondary School Planting of assorted tree varieties in school compound 80,000 Complete Complete and In use 2013/2014 Kebirigo Secondary School Planting of assorted tree varieties in school compound 80,000 Complete Complete and In use 2013/2014 Kianungu Secondary School Planting of assorted tree varieties in school compound 80,000 Complete Complete and In use WEST MUGIRANGO CONSTITUENCY PROJECTS REPORT TO 31ST MARCH 2016

Upload: others

Post on 23-Mar-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: WEST MUGIRANGO CONSTITUENCY PROJECTS REPORT TO … · for enhancement in performance in national examinations. 7,000,000 Complete Funds disbursed to needy students 2013/2014 Monitoring

Financial Year

Project Name Major Activity PROJECT COST Status REMARKS

2013/2014 Contituency Office Administration fund 6%

Day to day office operations,staff salaries & general office management

4,709,705 Complete Funds Utilised

2013/2014 Emergency Fund Reserve fund for emergencies and disasters

3,564,466.00 Complete Funds Utilised

2013/2014 Education Bursary Fees Payment for needy students in colleges and universities and activities for enhancement in performance in national examinations.

7,000,000 Complete Funds disbursed to needy students

2013/2014 Monitoring & Evaluation

Ensuring sound management and successful completion of projects through through close supervision and evaluation.

2,354,852.00 Complete Funds Utilised

2013/2014 Constituency Sports Committee

Sports activities within the constituency

390,000 Complete Complete and In use

2013/2014 Bomorito Primary School

Planting of assorted tree varieties in school compound

80,000 Complete Complete and In use

2013/2014 Nyansabakwa Secondary School

Planting of assorted tree varieties in school compound

80,000 Complete Complete and In use

2013/2014 Senator Kebaso Secondary School

Planting of assorted tree varieties in school compound

80,000 Complete Complete and In use

2013/2014 Kebirigo Secondary School

Planting of assorted tree varieties in school compound

80,000 Complete Complete and In use

2013/2014 Kianungu Secondary School

Planting of assorted tree varieties in school compound

80,000 Complete Complete and In use

WEST MUGIRANGO CONSTITUENCYPROJECTS REPORT TO 31ST MARCH 2016

Page 2: WEST MUGIRANGO CONSTITUENCY PROJECTS REPORT TO … · for enhancement in performance in national examinations. 7,000,000 Complete Funds disbursed to needy students 2013/2014 Monitoring

2013/2014 Barclays/Nyairicha/Nyanumba/Tai/Nyaswabu/Osugo Road

Clearing side, grading, Drainage, and escavation to level.4.5km

800,000 Complete Complete and In use

2013/2014 Miruka - Bugo Road Bush clearing, and escavation to level. 0.8km

500,000 Complete Complete and In use

2013/2014 Bonyunyu- Onyabanga - Ikonge Road

Bush Clearing, side drainage and escavation to level.3.5 Km

1,000,000 Complete Complete and In use

2013/2014 Bonyunyu-Nyakunguru-Nyabite Road

Bush Clearing,grading, side drainage and escavation to level.4km

1,000,000 Complete Complete and In use

2013/2014 Nyabomite-Rianyagwoka-Marindi Road

Bush Clearing, side drainage and escavation to level.3.5 Km

800,000 Complete Complete and In use

2013/2014 Nyagachi-Kianyabao-Riosiri Road

Bush Clearing, side drainage and escavation to level.4km

800,000 Complete Complete and In use

2013/2014 Nyagachi-Rioindi-Mosobeti Road

Bush Clearing, side drainage and escavation to level.4.5km

800,000 Complete Complete and In use

2013/2014 Gesiaga-Ekerubo-Erami Road

Bush Clearing, side drainage and escavation to level.3.5 Km

800,000 Complete Complete and In use

2013/2014 Kabatia-Nyankongo-Mobamba Road

Bush Clearing, side drainage and Grading.4.6km

1,000,000 Complete Complete and In use

2013/2014 Karantini-Bokimo Road Bush Clearing, side drainage and Grading.3.5km

1,000,000 Complete Complete and In use

2013/2014 Nyaigesa-Kemunguru Road

Bush Clearing, side drainage and Grading.4km

1,000,000 Complete Complete and In use

2013/2014 Nyansabakwa-Mang'ong'o Road

Bush Clearing, side drainage and Grading.4km

1,000,000 Complete Complete and In use

Page 3: WEST MUGIRANGO CONSTITUENCY PROJECTS REPORT TO … · for enhancement in performance in national examinations. 7,000,000 Complete Funds disbursed to needy students 2013/2014 Monitoring

2013/2014 Nyamokenye-Omokonge-Gekomoni Road

Bush Clearing, side drainage and Grading.4km

1,000,000 Complete Complete and In use

2013/2014 Rianyaundi-Kianginda Secondary School Road

Bush Clearing, side drainage and Grading.4km

1,000,000 Complete Complete and In use

2013/2014 Nyamatoki-Egetongo-Nyamotentemi-Erami Road

Grading 4km , and Culvert Installation 28m.

1,500,000 Complete Complete and In use

2013/2014 Bosamaro Chache Water Springs

Fencing Spring area, placing of water points and protection of spring

400,000 Complete Complete and In use

2013/2014 Bosamaro Masaba Water Springs

Fencing Spring area, placing of water points and protection of spring

500,000 Complete Complete and In use

2013/2014 West Mugirango Water Springs

Fencing Spring area, placing of water points and protection of spring

600,000 Complete Complete and In use

2013/2014 Township Water Springs

Fencing Spring area, placing of water points and protection of spring

400,000 Complete Complete and In use

2013/2014 Kenyenya Water Project

Construction of elevated tank and piping

2,000,000 Intending to tender

Intending to tender

2013/2014 Nkora Water Project Gravity water project:Protection of spring, construction of elevated tank and piping

2,800,000 Intending to tender

Intending to tender

2013/2014 Bogichora Water Springs

Fencing Spring area, placing of water points and protection of spring

500,000 Complete Complete and In use

Page 4: WEST MUGIRANGO CONSTITUENCY PROJECTS REPORT TO … · for enhancement in performance in national examinations. 7,000,000 Complete Funds disbursed to needy students 2013/2014 Monitoring

2013/2014 Bonyamatuta Water Springs

Fencing Spring area, placing of water points and protection of spring

400,000 Complete Complete and In use

2013/2014 Keera Water Springs Fencing Spring area, placing of water points and protection of spring

400,000 Complete Complete and In use

2013/2014 West Mugirango Constituency Office

Construction of CDF Office 5,000,000 Intending to tender

Intending to tender

2013/2014 Igena Itambe Health Centre

Construction of Health Facility:Foundation, walling, roofing, painting and electrical works

500,000 Ongoing Works Ongoing

2013/2014 Nyanturago Health Centre

Construction of Maternity Ward and Laboratory:Foundation, walling, roofing, painting and electrical works

400,000 Ongoing Works Ongoing

2013/2014 Motagara Health Centre

Construction of Health Facility:Foundation, walling, roofing, painting and electrical works

400,000 Complete Complete and In use

2013/2014 Geta Health Centre Construction of Health Facility:Foundation, walling, roofing, painting and electrical works

400,000 Ongoing Works Ongoing

2013/2014 Gianchore health centre

Construction of a maternity ward:Foundation, walling, roofing, painting and electrical works

500,000 Complete Complete and In use

2013/2014 Nyansabakwa Health Centre

Construction of Health Facility:Fixing doors and windows, roofing, painting and electrical works

300,000 Complete Complete and In use

Page 5: WEST MUGIRANGO CONSTITUENCY PROJECTS REPORT TO … · for enhancement in performance in national examinations. 7,000,000 Complete Funds disbursed to needy students 2013/2014 Monitoring

2013/2014 Ogango Health Centre Construction of Health Facility:Foundation, walling, roofing, painting and electrical works

300,000.00 Ongoing Works Ongoing

2013/2014 Gianchore Health Centre

Construction of Pre-Fabricated Staff House:Foundation, walling, roofing, plastering and Electrical Works

500,000.00 Ongoing Works Ongoing

2013/2014 Nyansabakwa Health Centre

Construction of Pre-Fabricated Staff House:Foundation, walling, roofing, plastering and Electrical Works

600,000.00 Ongoing Works Ongoing

2013/2014 Kenyambi Health Centre

Construction of Pre-Fabricated Staff House:Foundation, walling, roofing, plastering and Electrical Works

600,000.00 Ongoing Works Ongoing

2013/2014 Mongorisi Health Centre

Construction of Pre-Fabricated Staff House:Foundation, walling, roofing, plastering and Electrical Works

600,000.00 Ongoing Works Ongoing

2013/2014 Nyanturago Health Centre

Construction of Pre-Fabricated Staff House:Foundation, walling, roofing, plastering and Electrical Works

600,000.00 Ongoing Works Ongoing

2013/2014 Kenyerere Health Centre

Construction of Pre-Fabricated Staff House:Foundation, walling, roofing, plastering and Electrical Works

600,000.00 Intending to Tender

Intending to Tender

2013/2014 Ogango Health Centre Construction of Pre-Fabricated Staff House:Foundation, walling, roofing, plastering and Electrical Works

982,769.00 Ongoing Works Ongoing

Page 6: WEST MUGIRANGO CONSTITUENCY PROJECTS REPORT TO … · for enhancement in performance in national examinations. 7,000,000 Complete Funds disbursed to needy students 2013/2014 Monitoring

2013/2014 Masosa Secondary School

Construction of a story building with classrooms and hall:Foundation, walling, plastering, roofing,painting and electrical works

750,000 Ongoing Works Ongoing

2013/2014 Nyamira Technical School

Construction of a multipurpose hall storey building;Foundation, Walling, plastering, roofing, painting and electrical works.

800,000 Ongoing Works Ongoing

2013/2014 Nyamaiya Secondary School

Construction of a hall;Foundation, Walling, plastering, roofing, painting and electrical works.

300,000 Complete Complete and In use

2013/2014 Kenyenya Secondary School

Construction of 3 classrooms;Foundation, Walling, plastering, roofing, painting and electrical works.

400,000 Ongoing Works Ongoing

2013/2014 Rirumi Secondary School

Construction of Storey Building with laboratory and admin block:Foundation, walling, plastering and roofing and electrical works

500,000 Ongoing Works Ongoing

2013/2014 Nyabisimba Secondary School

Construction of a Laboratory :Foundation, walling, roofing, plastering and electrical works.

400,000 Ongoing Works Ongoing

2013/2014 Makairo Secondary School

Construction of storey building containing classrooms, staff offices and Library

700,000 Ongoing Complete and In use

2013/2014 St Tiberious Nyamotentemi Sec School

Construction of classrooms in a storey building:Foundation, walling, roofing, plastering and electrical works.

600,000 Ongoing Works Ongoing

Page 7: WEST MUGIRANGO CONSTITUENCY PROJECTS REPORT TO … · for enhancement in performance in national examinations. 7,000,000 Complete Funds disbursed to needy students 2013/2014 Monitoring

2013/2014 Embonga Secondary School

Construction of 4 classrooms :Foundation, walling, roofing, plastering and electrical works.

400,000 Ongoing Works Ongoing

2013/2014 Nami Secondary School

Construction of storey Building with laboratory:Foundation, walling, plastering and roofing and electrical works

450,000 Complete Complete and In use

2013/2014 Gesore PAG Secondary School

Construction of a Library :Foundation, walling, roofing, plastering and electrical works.

400,000 Ongoing Works Ongoing

2013/2014 St Teresa Secondary School - Bugo

Construction of 3 classrooms:Foundation, walling, roofing, plastering and electrical works.

700,000 Ongoing Works Ongoing

2013/2014 St Josephs Kemasare Secondary School

Construction of 2 classrooms:Foundation, walling, roofing, plastering and electrical works.

400,000 Ongoing Works Ongoing

2013/2014 Bondeka Girls Secondary School

Construction of 3 classrooms:Foundation, walling, roofing, plastering and electrical works.

400,000 Complete Complete and In use

2013/2014 Enchoro Secondary School

Construction of a Laboratory:Foundation, walling, plastering, roofing, installation of equipment and electrical works.

500,000 Ongoing Works Ongoing

2013/2014 Nyagachi Secondary School

Construction of a Twin Laboratory:Foundation, walling, plastering, roofing, installation of equipment and electrical works.

500,000 Ongoing Works Ongoing

Page 8: WEST MUGIRANGO CONSTITUENCY PROJECTS REPORT TO … · for enhancement in performance in national examinations. 7,000,000 Complete Funds disbursed to needy students 2013/2014 Monitoring

2013/2014 Kuura Secondary School

Construction of a Domitory:Foundation, walling, plastering, roofing, installation of equipment and electrical works.

500,000 Ongoing Works Ongoing

2013/2014 Nyachururu Secondary School

Construction of a Laboratory:Foundation, walling, plastering, roofing, installation of equipment and electrical works.

500,000 Ongoing Works Ongoing

2013/2014 Mongorisi Secondary School

Construction of a Laboratory:Foundation, walling, plastering, roofing, installation of equipment and electrical works.

400,000 Complete Complete and In use

2013/2014 Ibucha Primary School Construction of one classrooms from foundation,walling,roofing,fixation of doorsand windows, painting and electrical works.

500,000 Complete Complete and In use

2013/2014 Marindi Primary School

Renovation of three classrooms:walling, roofing (painting,plastering & flooring)

700,000 Ongoing Works Ongoing

2013/2014 Sasati Primary School Construction of 3 classrooms:Foundation, walling,Roofing, painting and electrical works

400,000 Complete Complete and In use

2013/2014 Tonga Pri School Renovation of 2 classrooms:Plastering, roofing and fixing doors and windows

300,000 Complete Complete and In use

2013/2014 Kenyenya Boarding Primary School

Construction of 2 classrooms:Foundation, walling,Roofing, painting and electrical works

300,000 Ongoing Works Ongoing

Page 9: WEST MUGIRANGO CONSTITUENCY PROJECTS REPORT TO … · for enhancement in performance in national examinations. 7,000,000 Complete Funds disbursed to needy students 2013/2014 Monitoring

2013/2014 Kabatia Primary School Renovation of one classrooms:Roofing, fixing doors and windows

250,000 Complete Complete and In use

2013/2014 Nyakeore Special School

Construction of 2 classrooms:Foundation, walling,Roofing, painting and electrical works

350,000 Ongoing Works Ongoing

2013/2014 Bonyunyu Primary School

Renovation of one classrooms:Roofing, plastering, fixing of doors and windows

300,000 Complete Complete and In use

2013/2014 Ekerama Primary School

Construction of 2 classrooms:Foundation, walling,Roofing, painting and electrical works

400,000 Ongoing Works Ongoing

2013/2014 Bobembe Boarding Primary School

Construction of 4 CLASSROOMS:Foundation, walling, roofing and electrical works

400,000 Ongoing Works Ongoing

2013/2014 Nyameru Primary School

Construction of pit a latrine:Foundation, walling, roofing and electrical works

200,000 Complete Complete and In use

2013/2014 Sironga Primary School Renovation of 5 classrooms:Roofing, plastering and fixing doors and windows

600,000 Complete Complete and In use

2013/2014 Nyaisa Primary School Renovation of admin block:Plastering, roofing and windows/doors and electrical works

300,000 Ongoing Works Ongoing

2013/2014 Makairo Primary School

Construction of a hall:Foundation, walling, roofing and electrical works

400,000 Ongoing Works Ongoing

Page 10: WEST MUGIRANGO CONSTITUENCY PROJECTS REPORT TO … · for enhancement in performance in national examinations. 7,000,000 Complete Funds disbursed to needy students 2013/2014 Monitoring

2013/2014 Nyairicha Special School

Construction of storey Building:Foundation, walling, roofing, plastering and electrical works.

500,000 Ongoing Works Ongoing

2013/2014 Bundo Primary School Construction of classrooms:Foundation, walling, roofing and electrical works

300,000 Ongoing Works Ongoing

2013/2014 Matierio Primary School

Renovation of 2 classrooms:Plastering, roofing and fixing doors and windows

300,000 Complete Complete and In use

2013/2014 Marara Primary School Construction of admin block:Foundation, walling, roofing and electrical works

200,000 Ongoing Works Ongoing

2013/2014 Ratandi Primary School Renovation of of 3 classrooms:Flooring, roofing and fixing doors and windows

300,000 Complete Complete and In use

2013/2014 St Josephs Nyamira Primary School

Construction of 3 classrooms:Foundation, walling, roofing and plastering

600,000 Ongoing Works Ongoing

2013/2014 Riamandere Primary School

Construction of classrooms:Foundation, walling, roofing and plastering

200,000 Ongoing Works Ongoing

2013/2014 Nyagachi Primary School

Renovation of 1 classroom:Plastering, roofing and fixing doors and windows

200,000 Complete Complete and In use

2013/2014 Nyantaro Primary School

Renovation of 1 classroom:Plastering, roofing and fixing doors and windows

300,000 Complete Complete and In use

2013/2014 Ting'a Primary School Renovation of 1 classroom:Plastering, roofing and fixing doors and windows

200,000 Complete Complete and In use

Page 11: WEST MUGIRANGO CONSTITUENCY PROJECTS REPORT TO … · for enhancement in performance in national examinations. 7,000,000 Complete Funds disbursed to needy students 2013/2014 Monitoring

2013/2014 Endabu Primary School Construction of 2 classrooms:Foundation, walling, roofing and plastering

300,000 Ongoing Works Ongoing

2013/2014 Bosose Primary School Construction of 2 classrooms:Foundation, walling, roofing and plastering

300,000 Ongoing Works Ongoing

2013/2014 Egesieri Primary School Renovation of one classrooms:Roofing, plastering, fixing doors and windows

200,000 Complete Complete and In use

2013/2014 Kenyambi Primary School

Construction of an administration block:Foundation, walling, roofing and plastering AND Electrical works

300,000 Ongoing Works Ongoing

2013/2014 Bomorito Primary School

Renovation of 6 classrooms:Foundation, walling, roofing and plastering

300,000 Complete Complete and In use

2013/2014 Motagara Primary School

Construction of 2 classrooms:Foundation, walling, roofing and plastering AND Electrical works

300,000 Complete Complete and In use

2013/2014 Kiambere AP Camp Renovation of AP Camp:Roofing, Flooring and windows

200,000 Complete Complete and In use

2013/2014 Etono AP Camp Renovation of AP Camp:Roofing, Flooring and windows

200,000 Complete Complete and In use

2013/2014 Nyagachi Chiefs camp Construction of two pit latrines:Digging of pit, foundation, walling, roofing and plastering

200,000 Complete Complete and In use

2013/2014 Construction and Erection of Constituency Project Sign Posts

Design, construction and erection of 200 project sign posts@ Ksh 10,000 each

500,000.00 Intending to Tender

Intending to Tender

Page 12: WEST MUGIRANGO CONSTITUENCY PROJECTS REPORT TO … · for enhancement in performance in national examinations. 7,000,000 Complete Funds disbursed to needy students 2013/2014 Monitoring

2013/2014 Constituency Motor Vehicle

Purchase of ONE CDF Office Motor Vehicle.

5,000,000.00 Complete Complete and In use

2013/2014 Konate Tea Buying Centre

Construction of Tea Buying Centre:Roofing

150,000 Ongoing Works Ongoing

2013/2014 Omosaria Tea Buying Centre

Construction of Tea Buying Centre:Roofing

150,000 Ongoing Works Ongoing

2013/2014 Kegogi Tea Buying Centre

Construction of Tea Buying Centre:Roofing

150,000 Ongoing Works Ongoing

2013/2014 Bosiango Tea Buying Centre

Construction of Tea Buying Centre:Roofing

150,000 Ongoing Works Ongoing

2013/2014 Ibucha Tea Buying Centre

Construction of Tea Buying Centre:Roofing

150,000 Ongoing Works Ongoing

2013/2014 Mabundu Tea Buying Centre

Construction of Tea Buying Centre:Roofing

150,000 Ongoing Works Ongoing

2013/2014 Gesore Tea Buying Centre

Construction of Tea Buying Centre:Roofing

150,000 Ongoing Works Ongoing

2013/2014 Matierio Tea Buying Centre

Construction of Tea Buying Centre:Roofing

150,000 Ongoing Works Ongoing

2013/2014 Gekomoni Tea Buying Centre

Construction of Tea Buying Centre:Foundation, walling,roofing and electrical works

150,000 Ongoing Works Ongoing

2013/2014 Nyamokenye Tea Buying Centre

Construction of Tea Buying Centre:Roofing

150,000 Ongoing Works Ongoing

2013/2014 Ikobe Tea Buying Centre

Construction of Tea Buying Centre:Roofing

150,000 Ongoing Works Ongoing

2013/2014 Nyanturago Tea Buying Centre

Construction of Tea Buying Centre:Roofing

150,000 Ongoing Works Ongoing

2013/2014 Bosose Tea Buying Centre

Construction of Tea Buying Centre:Roofing

150,000 Ongoing Works Ongoing

2013/2014 Motagara Tea Buying Centre

Construction of Tea Buying Centre:Roofing

150,000 Ongoing Works Ongoing

Page 13: WEST MUGIRANGO CONSTITUENCY PROJECTS REPORT TO … · for enhancement in performance in national examinations. 7,000,000 Complete Funds disbursed to needy students 2013/2014 Monitoring

2013/2014 Riorao Tea Buying Centre

Construction of Tea Buying Centre:Roofing

150,000 Ongoing Works Ongoing

2013/2014 Embonga Tea Buying Centre

Construction of Tea Buying Centre:Roofing

150,000 Ongoing Works Ongoing

2013/2014 FORMULATION OF CONSTITUENCY STRATEGIC PLAN

Formulation and design of 5 Year onstituency Strategic Plan

600,000.00 Ongoing Works Ongoing

2013/2014 Kiambere Polytechnic Construction of 2 pit latrines: Foundation, walling,PLASTERING, roofing and painting and electrical works

300,000 Ongoing Works Ongoing

2013/2014 Bobembe Village Polytechnic

Construction of 2 classrooms: Foundation, walling,PLASTERING, roofing and painting and electrical works

426,055 Ongoing Works Ongoing

2013/2014 Nyainogu Village Polytechnic

Construction of administration block and lecture hall:Foundation , walling, roofing, painting and electrical works

300,000 Ongoing Works Ongoing

2013/2014 Nyaigesa Youth Polytechnic

Construction of 3 classrooms:Foundation , walling, roofing, painting and electrical works

350,000 Ongoing Works Ongoing

Page 14: WEST MUGIRANGO CONSTITUENCY PROJECTS REPORT TO … · for enhancement in performance in national examinations. 7,000,000 Complete Funds disbursed to needy students 2013/2014 Monitoring

2014/2015 Employee Salaries,Goods and Services,Purchase of Furniture and Office Equipments,Purchase of Computers,NSSF,NHIF,Committee Allowances and Expenses

Payment of staff salaries and Gratuity,Purchase of office stationary, fuel, vehicle repairs, telephone expenses and subsistence,Purchase of office furniture and equipment,Purchase of one CDFC laptop and One Computer,Staff NSSF Remmitances,Staff NHIF Remmitances,Committee sitting allowances and expenses

7,176,000 Complete Funds Utilised

2014/2015 Emergency Fund Reserve fund for emergencies and disasters

5,400,259.00 Complete Funds Utilised On Emergencies

2014/2015 Education Bursary 8.0%

Fees Payment for needy students in colleges and universities and activities for enhancement in performance in national examinations.

10,000,000 Ongoing Bursary Disbursement On going

2014/2015 Goods and Services,Committee Expenses,CDFC/PMC Capacity Building

Purchase of stationary, fuel, vehicle repairs, telephone expenses and subsistence in M&E,Committee M&E Expenses,PMC Training and capacity building expenses

3,588,000.00 Complete Funds Utilised

2014/2015 Constituency Sports Committee

Sports activities within the constituency

500,000 Intending to tender

Intending to tender

2014/2015 Nyamira Primary School

Planting of assorted tree varieties in school compound

80,000 Intending to tender

Intending to tender

2014/2015 Nyachogochogo Secondary School

Planting of assorted tree varieties in school compound

80,000 Intending to tender

Intending to tender

2014/2015 Bondeka Girls Secondary School

Planting of assorted tree varieties in school compound

80,000 Intending to tender

Intending to tender

Page 15: WEST MUGIRANGO CONSTITUENCY PROJECTS REPORT TO … · for enhancement in performance in national examinations. 7,000,000 Complete Funds disbursed to needy students 2013/2014 Monitoring

2014/2015 Kianyabongere Primary School

Planting of assorted tree varieties in school compound

80,000 Intending to tender

Intending to tender

2014/2015 Kianungu Secondary School

Planting of assorted tree varieties in school compound

80,000 Intending to tender

Intending to tender

2014/2015 Etibu-Ikobe - Erami Road

Bush Clearing, Opening of road,side drainage and escavation to level.3. Km

900,000 Complete Complete and in use

2014/2015 Motagara Corner- Enchoro Road

Clearing side, grading, Drainage, and escavation to level.3km

900,000 Complete Complete and in use

2014/2015 Bonyunyu- Onyabanga - Ikonge Road

Bush Clearing, side drainage and escavation to level.3.5 Km

800,000 Complete Complete and in use

2014/2015 Bonyunyu-Nyakunguru-Nyabite Road

Heavy Bush Clearing,grading, side drainage and escavation to level.6km

2,000,000 Complete Complete and in use

2014/2015 Nyamokeri-Sironga-Erami Road

Bush Clearing, side drainage and escavation to level.3.0 Km

800,000 Complete Complete and in use

2014/2015 Nyagachi-Kianyabao-Riosiri Road

Bush Clearing, side drainage and escavation to level.4km

900,000 Complete Complete and in use

2014/2015 Nyagachi-Rioindi-Mosobeti Road

Bush Clearing, side drainage and escavation to level.3.5km

900,000 Complete Complete and in use

2014/2015 Riobonyo-Rioigo-Riogao Road

Bush Clearing, side drainage and escavation to level.3.5 Km

1,000,000 Complete Complete and in use

2014/2015 Kabatia-Nyankongo-Mobamba Road

Bush Clearing, side drainage and Grading.4.6km

1,000,000 Complete Complete and in use

2014/2015 Bondeka-Tonga Omunuri Road

Bush Clearing, side drainage and Grading.3.km

900,000 Complete Complete and in use

2014/2015 Nyaigesa-Kemunguru Road

Bush Clearing, side drainage and Grading.4km

1,000,000 Intending to tender

Intending to tender

2014/2015 Nyansabakwa-Mang'ong'o Road

Bush Clearing, side drainage and Grading.4km

900,000 Complete Complete and in use

Page 16: WEST MUGIRANGO CONSTITUENCY PROJECTS REPORT TO … · for enhancement in performance in national examinations. 7,000,000 Complete Funds disbursed to needy students 2013/2014 Monitoring

2014/2015 Gekomoni - Kemasare- Erami Road

Bush Clearing, side drainage and Grading.3km

1,000,000 Complete Complete and in use

2014/2015 Rianyaundi-Kianginda Secondary School Road

Bush Clearing, side drainage and Grading.3km

900,000 Complete Complete and in use

2014/2015 Nyamatoki-Egetongo-Nyamotentemi-Erami Road

Bush Clearing, side drainage and Grading.4km

1,300,000 Complete Complete and in use

2014/2015 BarclaysBank-Nyairicha Road to the River

Bush Clearing, side drainage and Grading.2km

800,000 Complete Complete and in use

2014/2015 Kebirigo - Migingo Road

Bush Clearing, side drainage and Grading.5km

1,100,000 Complete Complete and in use

2014/2015 Bosamaro Water Springs

Fencing Spring area, placing of water points and protection of spring

1,000,000 Ongoing Works Ongoing

2014/2015 Nyamaiya Water Springs

Fencing Spring area, placing of water points and protection of spring

1,000,000 Ongoing Works Ongoing

2014/2015 Township Water Springs

Fencing Spring area, placing of water points and protection of spring

900,000 Ongoing Works Ongoing

2014/2015 Kenyenya Water Project

Completion of elevated tank and piping

1,500,000 Intending to tender

Intending to tender

2014/2015 Nkora Water Project Gravity water project:Protection of spring, construction of elevated tank and piping

2,000,000 Intending to tender

Intending to tender

Page 17: WEST MUGIRANGO CONSTITUENCY PROJECTS REPORT TO … · for enhancement in performance in national examinations. 7,000,000 Complete Funds disbursed to needy students 2013/2014 Monitoring

2014/2015 Bogichora Water Springs

Fencing Spring area, placing of water points and protection of spring

1,200,000 Ongoing Works Ongoing

2014/2015 Bonyamatuta Water Springs

Fencing Spring area, placing of water points and protection of spring

1,100,000 Ongoing Works Ongoing

2014/2015 Ramba Water Project Water Pipiping, Installation of pump and electricity installation

1,100,000 Ongoing Works Ongoing

2014/2015 West Mugirango Constituency Office

Construction of CDF Office 10,500,000 Intending to tender

Intending to tender

2014/2015 Igena Itambe Health Centre

Completion of Health Facility:Construction of 2nd floor slab and firrst floor columns

700,000 Ongoing Works Ongoing

2014/2015 Nyanturago Health Centre

Completion of Health Facility:Flooring, plastering and painting

500,000 Ongoing Works Ongoing

2014/2015 Geta Health Centre Completion of Health Facility:Flooring, plastering and painting

500,000 Ongoing Works Ongoing

2014/2015 Gianchore health centre

Completion of staff house:Flooring,roofing, plastering and painting

700,000 Ongoing Works Ongoing

2014/2015 Ogango Health Centre Completion of health facility:Flooring,roofing, plastering and painting

800,000.00 Ongoing Works Ongoing

2014/2015 Nyamokenye Health Centre

Completion of health facility:Flooring,plastering, windows and painting

500,000.00 Ongoing Works Ongoing

2014/2015 Mongorisi Health Centre

Completion of a staff house:Painting, plastering, roofing and electrical works

600,000.00 Ongoing Works Ongoing

Page 18: WEST MUGIRANGO CONSTITUENCY PROJECTS REPORT TO … · for enhancement in performance in national examinations. 7,000,000 Complete Funds disbursed to needy students 2013/2014 Monitoring

2014/2015 Masosa Secondary School

Completion of a story building with classrooms and hall:Construction of first floor columns and electrical works

1,100,000 Ongoing Works Ongoing

2014/2015 Nyamira Technical School

Completion of a multipurpose hall storey building;Construction of columns, plastering and electrical works.

1,100,000 Ongoing Works Ongoing

2014/2015 Nyamaiya Secondary School

Completion of a hall;plastering, painting and electrical works.

800,000 Complete Complete and in use

2014/2015 Rirumi Secondary School

Completion of Storey Building with laboratory and admin block:Construction of first floor columns and plastering , and electrical works

700,000 Ongoing Works Ongoing

2014/2015 Makairo Secondary School

Completion of Storey Building with laboratory :Construction of first floor columns and plastering , and electrical works

700,000 Ongoing Works Ongoing

2014/2015 St Tiberious Nyamotentemi Sec School

Completion of classrooms in a storey building:First floor walling, plastering and electrical works.

700,000 Ongoing Works Ongoing

2014/2015 Nami Secondary School

Completion of storey Building with laboratory:plastering and painting

300,000 Complete Complete and in use

2014/2015 Gesore PAG Secondary School

Completion of a Library :First floor walling, plastering and electrical works.

700,000 Ongoing Works Ongoing

2014/2015 St Teresa Secondary School - Bugo

Completion of 3 classrooms storied building:plastering, painting and electrical works.

800,000 Ongoing Works Ongoing

Page 19: WEST MUGIRANGO CONSTITUENCY PROJECTS REPORT TO … · for enhancement in performance in national examinations. 7,000,000 Complete Funds disbursed to needy students 2013/2014 Monitoring

2014/2015 Nyagachi Secondary School

Completion of a Twin Laboratory: walling, plastering, roofing and electrical works.

1,000,000 Ongoing Works Ongoing

2014/2015 St Patrice Nyantaro School

Construction of administration block:Walling and electrical works

700,000 Ongoing Works Ongoing

2014/2015 Nyachururu Secondary School

Completion of a Laboratory: plastering and electrical works.

500,000 Ongoing Works Ongoing

2014/2015 Geta Secondary School Completion of a Laboratory:Flooring painting and electrical works.

500,000 Ongoing Works Ongoing

2014/2015 Nyameru Sec School Completion of classrooms in a storey building:2nd floor walling, plastering and electrical works.

800,000 Ongoing Works Ongoing

2014/2015 Rangenyo Girls Secondary School

Completion of dining hall:Flooring,plastering and painting

800,000 Ongoing Works Ongoing

2014/2015 Nyaisa Secondary School

Construction of A multi purpose storey Building :Foundation and part walling

700,000 Ongoing Works Ongoing

2014/2015 Nyakemincha Secondary School

Construction of A multi purpose storey Building :Foundation and part walling

1,000,000 Ongoing Works Ongoing

2014/2015 Nyakeore Secondary School

Completion of Twin Lab: Roofing and plastering and electrical works

800,000 Ongoing Works Ongoing

2014/2015 Gucha Secondary School

Completion of A multi purpose storey Building with laboratory:plastering and painting

800,000 Ongoing Works Ongoing

Page 20: WEST MUGIRANGO CONSTITUENCY PROJECTS REPORT TO … · for enhancement in performance in national examinations. 7,000,000 Complete Funds disbursed to needy students 2013/2014 Monitoring

2014/2015 Gekomoni Secondary School

Construction of one twin pit latrine:Digging of pit, foundation, walling , roofing, plastering and painting

300,000 Ongoing Works Ongoing

2014/2015 Ekenyoro Secondary School

Construction of a computer laboratory :Foundation and walling

1,000,000 Ongoing Works Ongoing

2014/2015 Ibucha Primary School Construction of one classrooms from foundation,walling,roofing,fixation of doorsand windows, painting and electrical works.

500,000 Complete Complete and in use

2014/2015 Marindi Primary School

Renovation of three classrooms:walling, roofing (painting,plastering & flooring)

700,000 Complete Complete and in use

2014/2015 Tonga Pri School Renovation of 2 classrooms:Plastering, roofing and fixing doors and windows

300,000 Complete Complete and in use

2014/2015 Kenyenya Boarding Primary School

Construction of 2 classrooms:Foundation, walling,Roofing, painting and electrical works

300,000 Ongoing Works Ongoing

2014/2015 Kabatia Primary School Renovation of one classrooms:Roofing, fixing doors and windows

250,000 Complete Complete and in use

2014/2015 Nyakeore Special School

Construction of 2 classrooms:Foundation, walling,Roofing, painting and electrical works

350,000 Ongoing Works Ongoing

2014/2015 Bonyunyu Primary School

Renovation of one classrooms:Roofing, plastering, fixing of doors and windows

300,000 Complete Complete and in use

Page 21: WEST MUGIRANGO CONSTITUENCY PROJECTS REPORT TO … · for enhancement in performance in national examinations. 7,000,000 Complete Funds disbursed to needy students 2013/2014 Monitoring

2014/2015 Ekerama Primary School

Construction of 2 classrooms:Foundation, walling,Roofing, painting and electrical works

400,000 Ongoing Works Ongoing

2014/2015 Bobembe Boarding Primary School

Construction of 4 CLASSROOMS:Foundation, walling, roofing and electrical works

400,000 Ongoing Works Ongoing

2014/2015 Sironga Primary School Renovation of 5 classrooms:Roofing, plastering and fixing doors and windows

600,000 Complete Complete and in use

2014/2015 Makairo Primary School

Construction of a hall:Foundation, walling, roofing and electrical works

400,000 Ongoing Works Ongoing

2014/2015 Bundo Primary School Construction of classrooms:Foundation, walling, roofing and electrical works

300,000 Ongoing Works Ongoing

2014/2015 Ratandi Primary School Renovation of of 3 classrooms:Flooring, roofing and fixing doors and windows

250,000 Complete Complete and in use

2014/2015 St Josephs Nyamira Primary School

Construction of 3 classrooms:Foundation, walling, roofing and plastering

600,000 Ongoing Works Ongoing

2014/2015 Nyagachi Primary School

Renovation of 1 classroom:Plastering, roofing and fixing doors and windows

200,000 Complete Complete and in use

2014/2015 Endabu Primary School Construction of 2 classrooms:Foundation, walling, roofing and plastering

300,000 Ongoing Works Ongoing

2014/2015 Bosose Primary School Construction of 2 classrooms:Foundation, walling, roofing and plastering

300,000 Ongoing Works Ongoing

Page 22: WEST MUGIRANGO CONSTITUENCY PROJECTS REPORT TO … · for enhancement in performance in national examinations. 7,000,000 Complete Funds disbursed to needy students 2013/2014 Monitoring

2014/2015 Kenyambi Primary School

Construction of an administration block:Foundation, walling, roofing and plastering AND Electrical works

300,000 Ongoing Works Ongoing

2014/2015 Motagara Primary School

Construction of 2 classrooms:Foundation, walling, roofing and plastering AND Electrical works

300,000 Ongoing Works Ongoing

2014/2015 Riasindani Primary School

Completion of one twin Pit Latrine: walling, roofing, painting, plastering and electrical works

200,000 Complete Complete and in use

2014/2015 Gianchore Primary School

Construction of one twin Pit Latrine:Digging pit, foundation, walling, roofing, painting and electrical works

300,000 Complete Complete and in use

2014/2015 Gianchore Primary School

Construction of 2 classrooms:Roofing, plastering and flooring

400,000 Complete Complete and in use

2014/2015 Etono Primary School Renovation of 3 classrooms:Repair of floor, roof, windows and doors

500,000 Ongoing Works Ongoing

2014/2015 Kiambere Primary School

Renovation of 4 classrooms:Repair of floor, roof, windows and doors

600,000 Ongoing Works Ongoing

2014/2015 Rateti Primary School Completion of two classroom:Plastering, flooring and painting

300,000 Complete Complete and in use

2014/2015 Bondeka Primary School

Renovation of 4 classrooms:Repair of floor, roof, windows and doors

600,000 Complete Complete and in use

Page 23: WEST MUGIRANGO CONSTITUENCY PROJECTS REPORT TO … · for enhancement in performance in national examinations. 7,000,000 Complete Funds disbursed to needy students 2013/2014 Monitoring

2014/2015 Tente Primary School Construction of two class room:Walling of 2nd class, roofing, plastering and painting

400,000 Complete Complete and in use

2014/2015 Omokonge Special Primary School

Construction of 2 twin pit latrines :Digging of pit, foundation, walling,plastering, painting and electrical works

300,000 Complete Complete and in use

2014/2015 Enchoro Primary School

Renovation of 3 classrooms:Repair of floor, roof, windows and doors

500,000 Complete Complete and in use

2014/2015 Rirumi Primary School Construction of 2 twin pit latrines :Digging of pit, foundation, walling,plastering, painting and electrical works

300,000 Complete Complete and in use

2014/2015 Ekoro Primary School Renovation of 2 classrooms:Repair of floor, roof, windows and doors

400,000 Complete Complete and in use

2014/2015 Otanyore Primary School

Construction of Hall:Walling and roofing

900,000 Ongoing Works Ongoing

2014/2015 Bomondo Primary School

Renovation of 3 classrooms:Repair of floor, roof, windows and doors

500,000 Complete Complete and in use

2014/2015 Tonga Omunuri Boarding Primary School

Construction of a storey a Multipurpose building:Filling first floor columns and plastering

800,000 Ongoing Works Ongoing

2014/2015 Omosasa Primary School

Completion of 2 classrooms:Flooring,plastering, fixing doors and windows, painting and electrical works

400,000 Ongoing Works Ongoing

Page 24: WEST MUGIRANGO CONSTITUENCY PROJECTS REPORT TO … · for enhancement in performance in national examinations. 7,000,000 Complete Funds disbursed to needy students 2013/2014 Monitoring

2014/2015 Ikonge Primary School Completion of 2 classrooms:plastering, fixing doors and windows, painting and roofing

200,000 Ongoing Works Ongoing

2014/2015 Kiambere Polytechnic Completion of 2 Classrooms: walling,PLASTERING, roofing and painting and electrical works

400,000 Complete Complete and in use

2014/2015 Bobembe Village Polytechnic

Completion of 2 classrooms: ,plastering, roofing and painting and electrical works

500,000 Ongoing Works Ongoing

2014/2015 Nyaigesa Youth Polytechnic

Completion of a hall: walling, roofing, and electrical works

800,000 Ongoing Works Ongoing

2014/2015 Mariba Village Polytecnic

Completion of two classrooms:flooring, plastering and painting.

300,000 Complete Complete and in use

2014/2015 Ibucha Polytechnic Completion of two classrooms:flooring , plastering, painting, fixing of glass windows/ doors.

500,000 Complete Complete and in use

2014/2015 Kiambere Polytechnic Completion of 2 Classrooms: walling,PLASTERING, roofing and painting and electrical works

400,000 Complete Complete and in use

2014/2015 Bobembe Village Polytechnic

Completion of 2 classrooms: ,plastering, roofing and painting and electrical works

500,000 Ongoing Works Ongoing

2014/2015 Nyaigesa Youth Polytechnic

Completion of a hall: walling, roofing, and electrical works

800,000 Ongoing Works Ongoing

2014/2015 Kebirigo Chiefs Office Completion of chief's office:Roofing, plastering

700,000 ongoing Works Ongoing

2014/2015 Gianchore Chiefs Office

Completion of chief's office:Roofing, plastering

700,000 ongoing Works Ongoing

Page 25: WEST MUGIRANGO CONSTITUENCY PROJECTS REPORT TO … · for enhancement in performance in national examinations. 7,000,000 Complete Funds disbursed to needy students 2013/2014 Monitoring

2014/2015 Constituency Motor Vehicle

Purchase of ONE CDF Office Motor Vehicle.

1,500,000.00 Complete Complete and in use

2014/2015 Electricity Installation of electricity transformers in all wards within the constituency.

4,000,000.00 Complete Complete and in use

2014/2015 Marindi Tea Buying Centre

Completion of Tea Buying Centre:Roofing and plastering

150,000 Ongoing Works Ongoing

2014/2015 Getiesi Tea Buying Centre

Completion of Tea Buying Centre:Completion of Plastering and flooring

150,000 Ongoing Works Ongoing

2014/2015 Rianyaigoti Tea Buying Centre

Completion of Tea Buying Centre:Roofing and plastering

150,000 Ongoing Works Ongoing

2014/2015 Nyankongo Tea Buying Centre

Completion of Tea Buying Centre:completion of Roofing

60,000 Ongoing Works Ongoing

2014/2015 Kemasare Tea Buying Centre

Completion of Tea Buying Centre:completion of Roofing and plastering

100,000 Ongoing Works Ongoing

2014/2015 Kianyabao Tea Buying Centre

Completion of Tea Buying Centre:Roofing and plastering

150,000 Ongoing Works Ongoing

2014/2015 Nyabite Tea Buying Centre

Completion of Tea Buying Centre:Roofing and plastering

60,000 Ongoing Works Ongoing

2014/2015 Bosiango Tea Buying Centre

Completion of Tea Buying Centre:Roofing and plastering

150,000 Ongoing Works Ongoing

2014/2015 Bomondo Tea Buying Centre

Completion of Tea Buying Centre:Roofing

150,000 Ongoing Works Ongoing

2014/2015 Getare Tea Buying Centre

Completion of Tea Buying Centre:Roofing

150,000 Ongoing Works Ongoing

2014/2015 Riosiri Tea Buying Centre

Completion of Tea Buying Centre: Completion of Roofing and flooring

100,000 Ongoing Works Ongoing

Page 26: WEST MUGIRANGO CONSTITUENCY PROJECTS REPORT TO … · for enhancement in performance in national examinations. 7,000,000 Complete Funds disbursed to needy students 2013/2014 Monitoring

2014/2015 Riamisire Tea Buying Centre

Completion of Tea Buying Centre: Completion of Roofing and flooring

150,000 Ongoing Works Ongoing

2014/2015 Sironga Tea Buying Centre

Completion of Tea Buying Centre: Completion of Roofing and flooring

200,000 Ongoing Works Ongoing

2014/2015 Rianyagwoka Tea Buying Centre

Completion of Tea Buying Centre: Completion of Roofing and flooring

100,000 Ongoing Works Ongoing

2014/2015 Nyamaiya Tea Buying Centre

Completion of Tea Buying Centre: Roofing and flooring

150,000 Ongoing Works Ongoing

2014/2015 Rangenyo Tea Buying Centre

Completion of Tea Buying Centre: Completion of Roofing and flooring

60,000 Ongoing Works Ongoing

2014/2015 Karantina Tea Buying Centre

Completion of Tea Buying Centre: Completion of Roofing and flooring

150,000 Ongoing Works Ongoing

2014/2015 Rianyachoti Tea Buying Centre

Completion of Tea Buying Centre: Completion of Roofing and flooring

150,000 Ongoing Works Ongoing

2014/2015 Kebirigo Tea Buying Centre

Completion of Tea Buying Centre: Completion of Roofing and flooring

200,000 Ongoing Works Ongoing

2014/2015 Momoima Tea Buying Centre

Completion of Tea Buying Centre: Completion of Roofing and flooring

130,000 Ongoing Works Ongoing

2014/2015 Nyabomite Tea Buying Centre

Completion of Tea Buying Centre: Completion of Roofing and flooring

100,000 Ongoing Works Ongoing

2014/2015 Gianchore Tea Buying Centre

Completion of Tea Buying Centre: Completion of Roofing and flooring

150,000 Ongoing Works Ongoing

Page 27: WEST MUGIRANGO CONSTITUENCY PROJECTS REPORT TO … · for enhancement in performance in national examinations. 7,000,000 Complete Funds disbursed to needy students 2013/2014 Monitoring

2014/2015 Nyakeore Tea Buying Centre

Completion of Tea Buying Centre: Completion of plastering and flooring and fixing of doors and windows

150,000 Ongoing Works Ongoing

2014/2015 Rianyachani Tea Buying Centre

Construction of Tea Buying Centre:Foundation and walling

200,000 Ongoing Works Ongoing

2014/2015 Kenyenya Tea Buying Centre

Completion of Tea Buying Centre:Flooring and roofing

150,000 Ongoing Works Ongoing

2014/2015 Riamoti Tea Buying Centre

Completion of Tea Buying Centre:Flooring and roofing

150,000 Ongoing Works Ongoing

2014/2015 Bundo KB Tea Buying Centre

Completion of Tea Buying Centre:Flooring and roofing

150,000 Ongoing Works Ongoing

2014/2015 Ibucha Tea Buying Centre

Completion of Tea Buying Centre:Flooring and roofing

65,787 Ongoing Works Ongoing

2014/2015 Bosose Tea Buying Centre

Completion of Tea Buying Centre:Flooring, plastering and roofing

200,000 Ongoing Works Ongoing

2014/2015 Riorao Tea Buying Centre

Completion of Tea Buying Centre:Flooring and roofing

150,000 Ongoing Works Ongoing

2014/2015 Nyamonyo Tea Buying Centre

Renovation of Tea Buying Centre:Flooring and roofing

150,000 Ongoing Works Ongoing

2014/2015 Rianyaundi Tea Buying Centre

Renovation of Tea Buying Centre:Flooring and roofing

150,000 Ongoing Works Ongoing

2014/2015 Omotembe Tea Buying Centre

Renovation of Tea Buying Centre:Flooring and roofing

150,000 Ongoing Works Ongoing

2014/2015 Getaari Tea Buying Centre

Completion of Tea Buying Centre:Flooring and roofing

150,000 Ongoing Works Ongoing

2014/2015 Monga Tea Buying Centre

Completion of Tea Buying Centre:Flooring and roofing

100,000 Ongoing Works Ongoing

2014/2015 Makairo Tea Buying Centre

Renovation of Tea Buying Centre:Flooring and roofing

150,000 Ongoing Works Ongoing

Page 28: WEST MUGIRANGO CONSTITUENCY PROJECTS REPORT TO … · for enhancement in performance in national examinations. 7,000,000 Complete Funds disbursed to needy students 2013/2014 Monitoring

2014/2015 Nyagachi Tea Buying Centre

Completion of Tea Buying Centre:Flooring and roofing

70,000 Ongoing Works Ongoing

2014/2015 Nyaigwa Tea Buying Centre

Renovation of Tea Buying Centre:Flooring, plastering and roofing

150,000 Ongoing Works Ongoing

2014/2015 Miruka Tea Buying Centre

Completion of Tea Buying Centre:Flooring, plastering and roofing

100,000 Ongoing Works Ongoing

2014/2015 Riamaangi Tea Buying Centre

Completion of Tea Buying Centre:Flooring, plastering and roofing

150,000 Ongoing Works Ongoing

2014/2015 Matierio Tea Buying Centre

Renovation of Tea Buying Centre:Flooring, plastering and roofing

150,000 Ongoing Works Ongoing

2014/2015 Mabundu Tea Buying Centre

Completion of Tea Buying Centre:Flooring, plastering and roofing

150,000 Ongoing Works Ongoing

2014/2015 FORMULATION OF CONSTITUENCY STRATEGIC PLAN

Formulation and design of 5 YearC onstituency Strategic Plan

1,200,000.00 Ongoing Works Ongoing

2014/2015 Audit Fees FY 14/15 Constituency Accounts Audit fees

500,000.00 Yet to release funds

NG-CDFC yet to release funds

2014/2015 PURCHASE OF LAND,Purchase of quarry

Purchase of quarry land for generation of constituency road construction materials

2,000,000.00 Not Yet Approved

Project not yet approved by NG-CDF Board

Page 29: WEST MUGIRANGO CONSTITUENCY PROJECTS REPORT TO … · for enhancement in performance in national examinations. 7,000,000 Complete Funds disbursed to needy students 2013/2014 Monitoring

2015/2016 Employee Salaries,Goods and Services,Purchase of Furniture and Office Equipments,Purchase of Computers,NSSF,NHIF,Committee Allowances and Expenses

Payment of staff salaries and Gratuity,Purchase of office stationary, fuel, vehicle repairs, telephone expenses and subsistence,Purchase of office furniture and equipment,Purchase of one CDFC laptop and One Computer,Staff NSSF Remmitances,Staff NHIF Remmittances,Committee sitting allowances and expenses

7,620,754 Ongoing Funds yet to be released by NG-CDF Board

2015/2016 Emergency Fund Reserve fund for emergencies and disasters within the constituency

5,767,647.00 Ongoing Funds yet to be released by NG-CDF Board

2015/2016 Tertiary Institutions Bursary

Fees Payment for needy students in colleges and universities and activities for enhancement in performance in national examinations.

12,000,000 Ongoing Funds yet to be released by NG-CDF Board

2015/2016 Secondary Schools Bursary

Fees Payment for needy students in Secondary Schools

3,500,000 Ongoing Funds yet to be released by NG-CDF Board

2015/2016 Mocks/Cats Payments for mocks and CATS in Primary and secondary schools

500,000 Ongoing Funds yet to be released by NG-CDF Board

2015/2016 Goods and Services Purchase of stationary, fuel, vehicle repairs, telephone expenses and subsistence in M&E

1,000,000.00 Ongoing Funds yet to be released by NG-CDF Board

2015/2016 Committee Expenses Committee M&E Expenses 2,060,377.00 Ongoing Funds yet to be released by NG-CDF Board

Page 30: WEST MUGIRANGO CONSTITUENCY PROJECTS REPORT TO … · for enhancement in performance in national examinations. 7,000,000 Complete Funds disbursed to needy students 2013/2014 Monitoring

2015/2016 CDFC/PMC Capacity Building

PMC Training and capacity building expenses

750,000.00 Ongoing Funds yet to be released by NG-CDF Board

2015/2016 Nyabite - Riamine Soil Conservation

Prevention of Soil Erosion- Building of Culverts and Gabions

1,500,000 New Funds yet to be released by NG-CDF Board

2015/2016 West Mugirango Constituency Sports Committee

Sports activities for men and women within the constituency

500,000 Ongoing Funds yet to be released by NG-CDF Board

2015/2016 Electricity Eletrification and wiring of schools in all wards within the constituency.

4,000,000.00 Ongoing Funds yet to be released by NG-CDF Board

2015/2016 Nyabite-Omonyia-Nyabite Road

Bush Clearing, Side Drainage and Grading of Road .2.5km

1,100,000 New Funds yet to be released by NG-CDF Board

2015/2016 Bonyunyu-Nyakunguru-Nyabite Road

Bush Clearing, Side Drainage and Grading of Road .6km

2,100,000 New Funds yet to be released by NG-CDF Board

2015/2016 Nyamokeri-Ramba-Bosose-Erami Road

Bush Clearing, Side Drainage and Grading of Road .3km

1,200,000 New Funds yet to be released by NG-CDF Board

2015/2016 Nyamatoki-Egetongo-Nyamotentemi-Erami Road

Bush Clearing, Side Drainage and Grading of Road .4km

1,000,000 New Funds yet to be released by NG-CDF Board

2015/2016 Sironga Stage - Kebacha Road

Bush Clearing, Side Drainage and Grading of Road .3km

1,000,000 New Funds yet to be released by NG-CDF Board

2015/2016 Riobonyo-Rioigo-Riogao Road

Bush Clearing, Side Drainage and Grading of Road .3km

1,000,000 New Funds yet to be released by NG-CDF Board

Page 31: WEST MUGIRANGO CONSTITUENCY PROJECTS REPORT TO … · for enhancement in performance in national examinations. 7,000,000 Complete Funds disbursed to needy students 2013/2014 Monitoring

2015/2016 Bondeni-Kianyabongere Road

Bush Clearing, Side Drainage and Grading of Road .3km

1,100,000 New Funds yet to be released by NG-CDF Board

2015/2016 Nyabomite-Bundo-Ombaka Road

Bush Clearing, Side Drainage and Grading of Road .3km

1,100,000 New Funds yet to be released by NG-CDF Board

2015/2016 Nyagachi-Kianyabao-Riosiri Road

Bush Clearing, Side Drainage and Grading of Road .3km

1,100,000 New Funds yet to be released by NG-CDF Board

2015/2016 Rianyaundi-Kianginda Road

Bush Clearing, Side Drainage and Grading of Road .3km

1,000,000 New Funds yet to be released by NG-CDF Board

2015/2016 Bundo Brothers Foot Bridge

Installation of Culverts 1,500,000 New Funds yet to be released by NG-CDF Board

2015/2016 Nyabite - Rangenyo Foot Bridge

Installation of Culverts 1,500,000 New Funds yet to be released by NG-CDF Board

2015/2016 Nyairicha - Bundo Foot Bridge

Installation of Culverts 1,200,000 New Funds yet to be released by NG-CDF Board

2015/2016 Nyabite - Otanyore Foot Bridge

Installation of Culverts 1,800,000 New Funds yet to be released by NG-CDF Board

2015/2016 Nyairosa - Bokimo Foot Bridge

Installation of Culverts 1,500,000 New Funds yet to be released by NG-CDF Board

2015/2016 Kuura - Bosiango Foot Bridge

Installation of Culverts 1,500,000 New Funds yet to be released by NG-CDF Board

Page 32: WEST MUGIRANGO CONSTITUENCY PROJECTS REPORT TO … · for enhancement in performance in national examinations. 7,000,000 Complete Funds disbursed to needy students 2013/2014 Monitoring

2015/2016 Bosamaro Masaba Water Springs

Fencing Spring area, placing of water points and protection of spring

700,000 New Funds yet to be released by NG-CDF Board

2015/2016 Nyamaiya Water Springs

Fencing Spring area, placing of water points and protection of spring

1,000,000 New Funds yet to be released by NG-CDF Board

2015/2016 Mongorisi Bore hole Piping for water supply to community and Installation of Power and other associated Works

2,000,000 On-going Funds yet to be released by NG-CDF Board

2015/2016 Keberigo - Songonga Bore hole

Piping for water supply to community and Installation of Power and other associated Works

2,000,000 On-going Funds yet to be released by NG-CDF Board

2015/2016 Township Water Springs

Fencing Spring area, placing of water points and protection of spring

800,000 New Funds yet to be released by NG-CDF Board

2015/2016 Kionyomo Water Project

Piping for water supply to community from Spring and Installation of Power and other associated Works

1,000,000 On-going Funds yet to be released by NG-CDF Board

2015/2016 Kenyenya Water Project

Piping for water supply to community from Spring and Installation of Power and other associated Works

1,400,000 On-going Funds yet to be released by NG-CDF Board

2015/2016 Ramba Water Project Completion of Pipiping, Installation of pump and electricity installation

600,000 On-going Funds yet to be released by NG-CDF Board

2015/2016 Bogichora Water Springs

Fencing Spring area, placing of water points and protection of spring

1,300,000 New Funds yet to be released by NG-CDF Board

Page 33: WEST MUGIRANGO CONSTITUENCY PROJECTS REPORT TO … · for enhancement in performance in national examinations. 7,000,000 Complete Funds disbursed to needy students 2013/2014 Monitoring

2015/2016 Bonyamatuta Water Springs

Fencing Spring area, placing of water points and protection of spring

1,200,000 New Funds yet to be released by NG-CDF Board

2015/2016 Kemasare Tea Buying Centre

Completion of Tea Buying Centre:completion of Roofing and plastering

100,000 Ongoing Funds yet to be released by NG-CDF Board

2015/2016 Getare Tea Buying Centre

Completion of Tea Buying Centre:Roofing

100,000 Ongoing Funds yet to be released by NG-CDF Board

2015/2016 Riosiri Tea Buying Centre

Completion of Tea Buying Centre: Completion of Roofing and flooring

100,000 Ongoing Funds yet to be released by NG-CDF Board

2015/2016 Nyamaiya Tea Buying Centre

Completion of Tea Buying Centre: Roofing and flooring

100,000 Ongoing Funds yet to be released by NG-CDF Board

2015/2016 Karantina Tea Buying Centre

Completion of Tea Buying Centre: Completion of Roofing and flooring

100,000 Ongoing Funds yet to be released by NG-CDF Board

2015/2016 Rianyachani Tea Buying Centre

Construction of Tea Buying Centre:Foundation and walling

150,000 Ongoing Funds yet to be released by NG-CDF Board

2015/2016 Riamoti Tea Buying Centre

Completion of Tea Buying Centre:Flooring and roofing

100,000 Ongoing Funds yet to be released by NG-CDF Board

2015/2016 Rianyaundi Tea Buying Centre

Renovation of Tea Buying Centre:Flooring and roofing

100,000 New Funds yet to be released by NG-CDF Board

2015/2016 Makairo Tea Buying Centre

Renovation of Tea Buying Centre:Flooring and roofing

100,000 New Funds yet to be released by NG-CDF Board

Page 34: WEST MUGIRANGO CONSTITUENCY PROJECTS REPORT TO … · for enhancement in performance in national examinations. 7,000,000 Complete Funds disbursed to needy students 2013/2014 Monitoring

2015/2016 Miruka Tea Buying Centre

Completion of Tea Buying Centre:Flooring, plastering and roofing

100,000 Ongoing Funds yet to be released by NG-CDF Board

2015/2016 Matierio Tea Buying Centre

Renovation of Tea Buying Centre:Flooring, plastering and roofing

100,000 Ongoing Funds yet to be released by NG-CDF Board

2015/2016 Nyagwakwa Tea Buying Centre

Completion of Tea Buying Centre:Flooring, plastering and roofing

100,000 Ongoing Funds yet to be released by NG-CDF Board

2015/2016 Omosasa Tea Buying Centre

Completion of Tea Buying Centre:Flooring, plastering and roofing

150,000 New Funds yet to be released by NG-CDF Board

2015/2016 Tin'ga Tea Buying Centre

Renovation of Tea Buying Centre:Flooring and roofing

150,000 New Funds yet to be released by NG-CDF Board

2015/2016 Mogumo Tea Buying Centre

Renovation of Tea Buying Centre:Flooring and roofing

150,000 New Funds yet to be released by NG-CDF Board

2015/2016 Riamasi Tea Buying Centre

Renovation of Tea Buying Centre:Flooring and roofing

140,000 New Funds yet to be released by NG-CDF Board

2015/2016 Rionuko Tea Buying Centre

Renovation of Tea Buying Centre:Flooring and roofing

150,000 New Funds yet to be released by NG-CDF Board

2015/2016 Riamicheka Tea Buying Centre

Construction of Tea Buying Centre:Foundation and walling

183,792 New Funds yet to be released by NG-CDF Board

2015/2016 Ramba Tea Buying Centre

Renovation of Tea Buying Centre:Roofing and Flooring

150,000 New Funds yet to be released by NG-CDF Board

Page 35: WEST MUGIRANGO CONSTITUENCY PROJECTS REPORT TO … · for enhancement in performance in national examinations. 7,000,000 Complete Funds disbursed to needy students 2013/2014 Monitoring

2015/2016 Riamocheche Tea Buying Centre

Construction of Tea Buying Centre:Foundation and walling

150,000 New Funds yet to be released by NG-CDF Board

2015/2016 Iranda Tea Buying Tea Centre

Renovation of Tea Buying Centre:Roofing and Flooring

150,000 New Funds yet to be released by NG-CDF Board

2015/2016 Mokwerero Tea Buying Centre

Renovation of Tea Buying Centre:Roofing and Flooring

150,000 New Funds yet to be released by NG-CDF Board

2015/2016 Nyamuronga Tea Buying Centre

Renovation of Tea Buying Centre:Roofing and Flooring

150,000 New Funds yet to be released by NG-CDF Board

2015/2016 Nyachogochogo Tea Buying Centre

Construction of Tea Buying Centre:Foundation and walling

150,000 New Funds yet to be released by NG-CDF Board

2015/2016 Omosocho Tea Buying Centre

Completion of Tea Buying Centre:Fooring, plastering, Installation of doors and windows

100,000 Ongoing Funds yet to be released by NG-CDF Board

2015/2016 Nyabisimba Tea Buying Centre

Renovation of Tea Buying Centre:Flooring and roofing

150,000 New Funds yet to be released by NG-CDF Board

2015/2016 Mageri Tea Buying Centre

Construction of Tea Buying Centre:Foundation and walling

100,000 New Funds yet to be released by NG-CDF Board

2015/2016 Nyankarangania Tea Buying Centre

Renovation of Tea Buying Centre:Flooring and roofing

150,000 New Funds yet to be released by NG-CDF Board

2015/2016 Kiambere Tea Buying Centre

Renovation of Tea Buying Centre:Flooring and roofing

100,000 New Funds yet to be released by NG-CDF Board

Page 36: WEST MUGIRANGO CONSTITUENCY PROJECTS REPORT TO … · for enhancement in performance in national examinations. 7,000,000 Complete Funds disbursed to needy students 2013/2014 Monitoring

2015/2016 Kiabiraa Tea Buying Centre

Renovation of Tea Buying Centre:Flooring and roofing

100,000 New Funds yet to be released by NG-CDF Board

2015/2016 Risa Tea Buying Centre Renovation of Tea Buying Centre:Roofing

150,000 New Funds yet to be released by NG-CDF Board

2015/2016 Igena Itambe Health Centre

Completion of Health Facility:Roofing 400,000 Ongoing Funds yet to be released by NG-CDF Board

2015/2016 Nyanturago Health Centre

Completion of Health Facility: Plastering and painting and Electrical Works

400,000 Ongoing Funds yet to be released by NG-CDF Board

2015/2016 Geta Health Centre Completion of Health Facility:Painting, Land scaping and Purchase of Equipment and Furniture

900,000 Ongoing Funds yet to be released by NG-CDF Board

2015/2016 Ogango Health Centre Completion of health facility:Plastering , Doors and Windows and painting

500,000.00 Ongoing Funds yet to be released by NG-CDF Board

2015/2016 Geta Health Centre Construction Pit Latrine:Digging of Pit, Foundation,Walling,Roofing,Plastering,Painting and Electrical Works

300,000.00 New Funds yet to be released by NG-CDF Board

2015/2016 Nyamokenye Health Centre

Completion of health facility:Land scaping , painting and acquisition equipment/Furniture and Land

600,000.00 Ongoing Funds yet to be released by NG-CDF Board

2015/2016 Motontera Health Centre

Construction of Incenerator:Foundation, walling, plastering and Painting

300,000.00 New Funds yet to be released by NG-CDF Board

Page 37: WEST MUGIRANGO CONSTITUENCY PROJECTS REPORT TO … · for enhancement in performance in national examinations. 7,000,000 Complete Funds disbursed to needy students 2013/2014 Monitoring

2015/2016 Kenyenya Health Centre

Renovation of Health Facility:Repair of sewer system

300,000.00 New Funds yet to be released by NG-CDF Board

2015/2016 Nyamaiya Health Centre

Maternity Wing completion:Plastering, Windows and Doors Painting and Electrical works

400,000.00 Ongoing Funds yet to be released by NG-CDF Board

2015/2016 Ramba Health Centre Completion of Health facility:Purchase of equipment and Furniture, completion of Pit Latrine and Incenerator

700,000.00 Ongoing Funds yet to be released by NG-CDF Board

2015/2016 Etono Health Centre Completion of health facility:Plastering , Doors and Windows, electrical works and painting

500,000.00 Ongoing Funds yet to be released by NG-CDF Board

2015/2016 Masosa Secondary School

Completion of a story building with classrooms and hall:Plastering

500,000 Ongoing Funds yet to be released by NG-CDF Board

2015/2016 Nyamira Technical School

Completion of a multipurpose hall storey building;Plastering, doors and windows

1,200,000 Ongoing Funds yet to be released by NG-CDF Board

2015/2016 Makairo Secondary School

Completion of Storey Building with laboratory :Completion of first floor, roofing,plastering and electrical works

1,200,000 Ongoing Funds yet to be released by NG-CDF Board

2015/2016 Nyagachi Secondary School

Completion of a Twin Laboratory: Completion of first floo columns and plastering

500,000 Ongoing Funds yet to be released by NG-CDF Board

Page 38: WEST MUGIRANGO CONSTITUENCY PROJECTS REPORT TO … · for enhancement in performance in national examinations. 7,000,000 Complete Funds disbursed to needy students 2013/2014 Monitoring

2015/2016 Makairo Secondary School

Construction of Pit Latrine:Digging of pit, foundation,walling,flooring, roofing, painting and electrical works

300,000 New Funds yet to be released by NG-CDF Board

2015/2016 Nyachururu Secondary School

Completion of a Laboratory: Construction of first floor columns and plastering

500,000 Ongoing Funds yet to be released by NG-CDF Board

2015/2016 Geta Secondary School Completion of a Laboratory:Flooring painting and electrical works.

600,000 Ongoing Funds yet to be released by NG-CDF Board

2015/2016 Rangenyo Girls Secondary School

Completion of dining hall:plastering , electrical works and painting

400,000 Ongoing Funds yet to be released by NG-CDF Board

2015/2016 Nyakemincha Secondary School

Construction of A multi purpose storey Building :First floor walling

500,000 New Funds yet to be released by NG-CDF Board

2015/2016 Kebirigo High School Construction of Twin Lab: Foundation and walling and roofing

1,000,000 New Funds yet to be released by NG-CDF Board

2015/2016 Gucha Secondary School

Completion of A multi purpose storey Building with laboratory:Construction of first floor columns and plastering

400,000 Ongoing Funds yet to be released by NG-CDF Board

2015/2016 Kenyenya Secondary School

Construction of Three Class room:Roofing,painting, plastering and electrical works

500,000 Ongoing Funds yet to be released by NG-CDF Board

2015/2016 Marindi Secondary School

Construction of a Storeyed Tuition Block:Foundation and walling

1,000,000 New Funds yet to be released by NG-CDF Board

Page 39: WEST MUGIRANGO CONSTITUENCY PROJECTS REPORT TO … · for enhancement in performance in national examinations. 7,000,000 Complete Funds disbursed to needy students 2013/2014 Monitoring

2015/2016 Bonyunyu Secondary School

Construction of a dormitory:Foundation and walling

500,000 New Funds yet to be released by NG-CDF Board

2015/2016 Nyaigwa Girls Secondary School

Construction of Three Class room:Foundation , walling, electrical works and roofing

1,200,000 New Funds yet to be released by NG-CDF Board

2015/2016 Kebirigo High School Renovation 2 Classrooms:Repair of roof, walls and floor

300,000 New Funds yet to be released by NG-CDF Board

2015/2016 Senator Kebaso Secondary School

Construction of a Multi purpose Hall:Foundation and walling

500,000 New Funds yet to be released by NG-CDF Board

2015/2016 Marani Girls Secondary School

Installation of Lightening Arrestors 300,000 New Funds yet to be released by NG-CDF Board

2015/2016 Kemasare Secondary School

Construction of One Classeroom:Foundation , walling, electrical works, painting and roofing

500,000 New Funds yet to be released by NG-CDF Board

2015/2016 Rateti Secondary School

Renovation 2 Classrooms:Repair of roof, walls and floor

400,000 New Funds yet to be released by NG-CDF Board

2015/2016 Bosiango Sec School Renovation 2 Classrooms:Repair of roof, walls and floor

500,000 Ongoing Funds yet to be released by NG-CDF Board

2015/2016 Nyabisimba Secondary School

Completion of a laboratory:Roofing, plastering, painting and Purchase of equipment and furniture

1,200,000 Ongoing Funds yet to be released by NG-CDF Board

Page 40: WEST MUGIRANGO CONSTITUENCY PROJECTS REPORT TO … · for enhancement in performance in national examinations. 7,000,000 Complete Funds disbursed to needy students 2013/2014 Monitoring

2015/2016 Nyachogochogo Secondary School

Construction of 3 Classrooms:Foundation , Walling,Roofing,Installation of Doors and Windows

1,000,000 New Funds yet to be released by NG-CDF Board

2015/2016 Bomorito Sec School Completion of a hall:Plastering and fixing of doors and windows

500,000 Ongoing Funds yet to be released by NG-CDF Board

2015/2016 Nyachogochogo Secondary School

Construction of Pit Latrine:Digging of pit, foundation,walling,flooring, roofing, painting and electrical works

300,000 New Funds yet to be released by NG-CDF Board

2015/2016 Omosasa Secondary School

Completion of a hall:Plastering and fixing of doors and windows

500,000 Ongoing Funds yet to be released by NG-CDF Board

2015/2016 Nyamira Technical School

Construction of Dormitory:Foundation, walling and roofing

800,000 New Funds yet to be released by NG-CDF Board

2015/2016 Bondeka Girls Secondary School

Construction of an Administration Block:Foundation, walling and roofing

500,000 New Funds yet to be released by NG-CDF Board

2015/2016 Kuura Secondary School

Completion of a laboratory:Purchase of equipment and furniture

400,000 Ongoing Funds yet to be released by NG-CDF Board

2015/2016 Gekomoni Secondary School

Construction of two Classrooms:Digging of pit, foundation,walling,flooring, roofing, painting and electrical works

1,000,000 New Funds yet to be released by NG-CDF Board

2015/2016 Riamandere Secondary School

Completion of two Classrooms:Plastering,painting and electrical works

300,000 Ongoing Funds yet to be released by NG-CDF Board

Page 41: WEST MUGIRANGO CONSTITUENCY PROJECTS REPORT TO … · for enhancement in performance in national examinations. 7,000,000 Complete Funds disbursed to needy students 2013/2014 Monitoring

2015/2016 Nyantaro Secondary School

Completion of an administration block:Roofing and Plastering

300,000 Ongoing Funds yet to be released by NG-CDF Board

2015/2016 Marindi Primary School

Renovation of 4 classrooms and administration block:Replacement of inner wall, plastering and painting and Roofing

400,000 Ongoing Funds yet to be released by NG-CDF Board

2015/2016 Sironga Primary School Completion of administration block.Plastering, flooring and Installation of doors and windows.

400,000 Ongoing Funds yet to be released by NG-CDF Board

2015/2016 Gianchore Primary School

Renovation of 3 classrooms:Repair of roof , wall, doors and windows.

600,000 Ongoing Funds yet to be released by NG-CDF Board

2015/2016 Etono Primary School Renovation of 3 classrooms:Repair of floor, roof, windows and doors

800,000 New Funds yet to be released by NG-CDF Board

2015/2016 Kiambere Primary School

Renovation of 4 classrooms:Repair of floor, roof, windows and doors

1,000,000 New Funds yet to be released by NG-CDF Board

2015/2016 Rateti Primary School Construction of Pit Latrine:Digging of pit, foundation,walling,flooring, roofing, painting and electrical works

300,000 New Funds yet to be released by NG-CDF Board

2015/2016 Bondeka Primary School

Renovation of 2 classrooms:Repair of floor, roof, windows and doors

400,000 New Funds yet to be released by NG-CDF Board

2015/2016 Gekomoni Primary School

Renovation of 2 classrooms:Repair of floor, roof, windows and doors

400,000 New Funds yet to be released by NG-CDF Board

Page 42: WEST MUGIRANGO CONSTITUENCY PROJECTS REPORT TO … · for enhancement in performance in national examinations. 7,000,000 Complete Funds disbursed to needy students 2013/2014 Monitoring

2015/2016 Bomondo Primary School

Renovation of 2 classrooms:Repair of floor, roof, windows and doors

400,000 New Funds yet to be released by NG-CDF Board

2015/2016 Tonga Omunuri Boarding Primary School

Completion of a storey a Multipurpose building:Construction of First Floor Slab

500,000 Ongoing Funds yet to be released by NG-CDF Board

2015/2016 Gesiaga Primary School

Renovation of 3 classrooms:Repair of floor, windows and doors

540,000 New Funds yet to be released by NG-CDF Board

2015/2016 Igena Itambe Primary School

Renovation of 2 classrooms:Repair of Roof, wall, doors, windows and floor

400,000 New Funds yet to be released by NG-CDF Board

2015/2016 Nyakemincha Primary School

Construction of One Class room:Foundation, walling and Roofing, Plastering, painting and electrical works

500,000 New Funds yet to be released by NG-CDF Board

2015/2016 Kianyabongere Primary School

Renovation of 2 classrooms:Repair of Roof, wall, doors, windows and floor

400,000 New Funds yet to be released by NG-CDF Board

2015/2016 Kebirigo Primary School

Construction of Pit Latrine:Digging of pit, foundation,walling,flooring, roofing, painting and electrical works

300,000 New Funds yet to be released by NG-CDF Board

2015/2016 Man'gon'go Primary School

Renovation of 2 classrooms:Repair of Roof, wall, doors, windows and floor

400,000 New Funds yet to be released by NG-CDF Board

2015/2016 Getaari Primary School Renovation of 2 classrooms:Repair of Roof, wall, doors, windows and floor

400,000 New Funds yet to be released by NG-CDF Board

Page 43: WEST MUGIRANGO CONSTITUENCY PROJECTS REPORT TO … · for enhancement in performance in national examinations. 7,000,000 Complete Funds disbursed to needy students 2013/2014 Monitoring

2015/2016 Bugo Primary School Renovation of 2 classrooms:Repair of Roof, wall, doors, windows and floor

400,000 New Funds yet to be released by NG-CDF Board

2015/2016 Tonga Primary School Construction of One Class room:Foundation, walling and Roofing, Plastering, painting and electrical works

500,000 New Funds yet to be released by NG-CDF Board

2015/2016 Nyaisa Primary School Renovation of 2 classrooms:Repair of Roof, wall, doors, windows and floor

500,000 New Funds yet to be released by NG-CDF Board

2015/2016 St Josephs Nyamira Primary School

Construction of a tuition block:Construction of first floor slab

600,000 Ongoing Funds yet to be released by NG-CDF Board

2015/2016 Moruga Primary School

Renovation of 2 classrooms:Repair of Roof, wall, doors, windows and floor

400,000 New Funds yet to be released by NG-CDF Board

2015/2016 Nyairicha Primary School

Renovation of 2 classrooms:Repair of Roof, wall, doors, windows and floor

400,000 New Funds yet to be released by NG-CDF Board

2015/2016 Nyangoso Primary School

Construction of One Class room:Foundation, walling and Roofing

350,000 New Funds yet to be released by NG-CDF Board

2015/2016 Nyairicha Special Primary School

Completion of a tuition block:Plastering, wiring and Roofing

400,000 Ongoing Funds yet to be released by NG-CDF Board

2015/2016 Geta Primary School Construction of Pit Latrine:Digging of pit, foundation,walling,flooring, roofing, painting and electrical works

300,000 New Funds yet to be released by NG-CDF Board

Page 44: WEST MUGIRANGO CONSTITUENCY PROJECTS REPORT TO … · for enhancement in performance in national examinations. 7,000,000 Complete Funds disbursed to needy students 2013/2014 Monitoring

2015/2016 Kenyenya Primary School

Renovation of 2 classrooms:Repair of Roof, wall, doors, windows and floor

400,000 New Funds yet to be released by NG-CDF Board

2015/2016 Ekenyoro Primary School

Renovation of 2 classrooms:Repair of Roof, wall, doors, windows and floor

400,000 New Funds yet to be released by NG-CDF Board

2015/2016 Nyainogu Primary School

Renovation of 2 classrooms:Repair of Roof, wall, doors, windows and floor

400,000 New Funds yet to be released by NG-CDF Board

2015/2016 Nyakeore Primary School

Construction of Pit Latrine:Digging of pit, foundation,walling,flooring, roofing, painting and electrical works

300,000 New Funds yet to be released by NG-CDF Board

2015/2016 Rangenyo Mixed Primary

Renovation of 2 classrooms:Repair of Roof, wall, doors, windows and floor

400,000 New Funds yet to be released by NG-CDF Board

2015/2016 Kegogi Primary School Renovation of 2 classrooms:Repair of Roof, wall, doors, windows and floor

400,000 New Funds yet to be released by NG-CDF Board

2015/2016 Ramba Primary School Renovation of 2 classrooms:Repair of Roof, wall, doors, windows and floor

400,000 New Funds yet to be released by NG-CDF Board

2015/2016 Rirumi Primary School Renovation of 2 classrooms:Repair of Roof, wall, doors, windows and floor

400,000 New Funds yet to be released by NG-CDF Board

2015/2016 Kiambere Primary School

Construction of Pit Latrine:Digging of pit, foundation,walling,flooring, roofing, painting and electrical works

300,000 New Funds yet to be released by NG-CDF Board

Page 45: WEST MUGIRANGO CONSTITUENCY PROJECTS REPORT TO … · for enhancement in performance in national examinations. 7,000,000 Complete Funds disbursed to needy students 2013/2014 Monitoring

2015/2016 Etono Primary School Construction of Pit Latrine:Digging of pit, foundation,walling,flooring, roofing, painting and electrical works

300,000 New Funds yet to be released by NG-CDF Board

2015/2016 Ikurucha Primary School

Renovation of 2 classrooms:Repair of Roof, wall, doors, windows and floor

400,000 New Funds yet to be released by NG-CDF Board

2015/2016 Amatierio Primary School

Renovation of 3 classrooms:Repair of floor, roof, windows and doors

600,000 New Funds yet to be released by NG-CDF Board

2015/2016 Bosiango Primary School

Renovation of 2 classrooms:Repair of floor, roof, windows and doors

400,000 New Funds yet to be released by NG-CDF Board

2015/2016 Bonyunyu Boarding Primary School

Renovation of 2 classrooms:Repair of floor, roof, windows and doors

400,000 New Funds yet to be released by NG-CDF Board

2015/2016 Ibucha Primary School Construction of Pit Latrine:Digging of pit, foundation,walling,flooring, roofing, painting and electrical works

300,000 New Funds yet to be released by NG-CDF Board

2015/2016 Ibucha Primary School Completion of 2 classrooms:walling,Roofing, plastering and electrical works

800,000 Ongoing Funds yet to be released by NG-CDF Board

2015/2016 Makairo Primary School

Renovation of 4 classrooms:Repair of floor, roof, windows and doors

800,000 New Funds yet to be released by NG-CDF Board

2015/2016 Riasindani Primary School

Renovation of 4 classrooms:Repair of floor, roof, windows and doors

700,000 New Funds yet to be released by NG-CDF Board

Page 46: WEST MUGIRANGO CONSTITUENCY PROJECTS REPORT TO … · for enhancement in performance in national examinations. 7,000,000 Complete Funds disbursed to needy students 2013/2014 Monitoring

2015/2016 Geta Primary School Renovation of 3 classrooms:Repair of floor, roof, windows and doors

600,000 New Funds yet to be released by NG-CDF Board

2015/2016 Nyachururu Primary School

Renovation of 2 classrooms:Repair of floor, roof, windows and doors

400,000 New Funds yet to be released by NG-CDF Board

2015/2016 Kianungu Primary School

Renovation of 2 classrooms:Repair of floor, roof, windows and doors

400,000 New Funds yet to be released by NG-CDF Board

2015/2016 Ikobe Primary School Construction of Pit Latrine:Digging of pit, foundation,walling,flooring, roofing, painting and electrical works

300,000 New Funds yet to be released by NG-CDF Board

2015/2016 Nyakoria Primary School

Construction of Pit Latrine:Digging of pit, foundation,walling,flooring, roofing, painting and electrical works

300,000 New Funds yet to be released by NG-CDF Board

2015/2016 Kenyambi Primary School

Renovation of two classrooms:Repair of roof, windows and doors and wall

400,000 New Funds yet to be released by NG-CDF Board

2015/2016 Ekerama Primary School

Completion of 2 classrooms:Roofing,Plastering, doors and Windows

300,000 Ongoing Funds yet to be released by NG-CDF Board

2015/2016 Nyainogu Youth Polytechnic

Construction of a Pit Latrine:Foundation, walling,Roofing,Plastering and Electrical Works

200,000 New Funds yet to be released by NG-CDF Board

2015/2016 Nyaigesa Youth Polytechnic

Completion of a hall: Roofing 500,000 Ongoing Funds yet to be released by NG-CDF Board

Page 47: WEST MUGIRANGO CONSTITUENCY PROJECTS REPORT TO … · for enhancement in performance in national examinations. 7,000,000 Complete Funds disbursed to needy students 2013/2014 Monitoring

2015/2016 Geta Youth Polytechnic

Construction of One Classroom:Foundation, walling,Roofing,Plastering and Electrical Works

500,000 New Funds yet to be released by NG-CDF Board

2015/2016 Kiambere Youth Polytechnic

Construction of One Classroom:Foundation, walling,Roofing,Plastering and Electrical Works

500,000 New Funds yet to be released by NG-CDF Board

2015/2016 Kebirigo Chiefs Office Completion of chief's office:Plastering, Painting and Electrical Works

350,000 ongoing Funds yet to be released by NG-CDF Board

2015/2016 Gianchore Chiefs Office

Completion of chief's office:Plastering , Painting , doors and windows

350,000 ongoing Funds yet to be released by NG-CDF Board

2015/2016 Nyagachi Chiefs Office Renovation of Chiefs Office:Repair of Roof, Floor,windows and doors

200,000 New Funds yet to be released by NG-CDF Board

2015/2016 Etono Chiefs Office Construction of a Pit Latrine:Digging of Pit, Foundation,walling,roofing,Plastering and Painting

200,000 New Funds yet to be released by NG-CDF Board

2015/2016 Kiambere Chiefs Office Renovation of Chiefs Office:Repair of Roof, Floor,windows and doors

200,000 New Funds yet to be released by NG-CDF Board

2015/2016 Audit Fees FY 15/16 Constituency Accounts Audit fees by KENAO

500,000.00 Ongoing Funds yet to be released by NG-CDF Board