WEST PARK HOSPITAL PHASE IIIWeekly Progress Report 0
Period ending September
Weather
Man Power
Subcontractors on Site
Schedule
WEST PARK HOSPITAL PHASE IIIWeekly Progress Report 0
Period ending September
Weather
Average Daily High Temp
Min Low Temp
Average Wind Speed
Man Power
Number or Workers on Site:
Subcontractors on Site
• Basin Mechanical/ NorPac Sheet Metal,
Plaster, Rapid Fire Protection, Yellowstone Electric.
Schedule
•••• Upcoming Meetings
oo
WEST PARK HOSPITAL PHASE IIIWeekly Progress Report 010
Period ending September 19
Average Daily High Temp
Min Low Temp
Average Wind Speed
Number or Workers on Site:
Subcontractors on Site
Basin Mechanical/ NorPac Sheet Metal,
Plaster, Rapid Fire Protection, Yellowstone Electric.
Upcoming Meetings
o Sub Coordination M
o Safety Orientation Meeting, 7am MST Daily
WEST PARK HOSPITAL PHASE III10
9, 2014
Average Daily High Temp 68
51
Average Wind Speed 12
Number or Workers on Site: 32
Basin Mechanical/ NorPac Sheet Metal,
Plaster, Rapid Fire Protection, Yellowstone Electric.
Upcoming Meetings – local time
Sub Coordination Me
Safety Orientation Meeting, 7am MST Daily
WEST PARK HOSPITAL PHASE III
F
F
mph
Basin Mechanical/ NorPac Sheet Metal,
Plaster, Rapid Fire Protection, Yellowstone Electric.
local time
eeting, 9am MST
Safety Orientation Meeting, 7am MST Daily
Basin Mechanical/ NorPac Sheet Metal, Big Horn Enegery,
Plaster, Rapid Fire Protection, Yellowstone Electric.
eting, 9am MST September 16
Safety Orientation Meeting, 7am MST Daily –
Big Horn Enegery, Cowan Construction
Plaster, Rapid Fire Protection, Yellowstone Electric.
September 16 – Conference
– Conference Office
Cowan Construction
Conference Office
Conference Office
Cowan Construction, Empire Lath and
Office
1
Empire Lath and
1
2
Work Progress
Site and Material Prep:
• All patient room soffits on the North side are complete.
• Fire tapping/caulking is ongoing in the Core/East end.
• Drywall is near complete on the West side.
• Tape and finishing of walls on the West end is underway.
Electrical:
• In wall rough in is complete on the North end.
• City inspection on in wall rough in is complete on the North end.
• In wall rough in is underway in the core/East end.
• Cable tray is complete on the West end and underway on the North.
HVAC:
• Exhaust and return duct in the attic is near complete.
• Roof curbs have been set into place.
• VAV’s are being installed on the West end.
• Condenser unit has shown up onsite.
Plumbing
• Insulating of water lines above ceiling continues on the West end.
• Insulating of water lines “in wall” is under way on the North end.
• MedGas rough in is complete on the North end.
• Sanitary lines are complete on the North end.
• Domestic water lines are complete on the North end.
• All plumbing inspections are complete on the North end.
• MedGas rough in is underway in the core/East end.
• Domestic water lines are underway in the core/West end.
Upcoming Activities
• Sheet rock starts on the North end.
• Bathroom tile install starts next week.
• Roofing starts next week around AHU 4.
• Fire Proofing of AHU 4 support beams.
3
Progress Photos
Cable tray and J hooks are complete on the West end. (Yellowstone Electric)
Cable tray and J hooks are underway on the North end. (Yellowstone Electric)
4
Condenser unit arrived on site for AHU 4. (Basin Mechanical/NorPac Sheet Metal)
The curb has been set into place for AHU 4. (Basin Mechanical/NorPac Sheet Metal)
5
All rough in for head walls are complete on the North end.
All in-wall rough in work is complete on the North end.
6
North end Corridor complete with all in wall rough in work. Sheet rock is being stocked for next week.
West end soffits are near complete. (Empire Lath and Plaster)
7
West end Corridor
Drywall is near complete on the West end and finishers are underway. (Empire Lath and Plaster)