wet fgd system overview and operation

62

Click here to load reader

Upload: nguyenquynh

Post on 31-Dec-2016

266 views

Category:

Documents


10 download

TRANSCRIPT

Page 1: Wet FGD System Overview and Operation

Wet FGD SystemOverview and Operation

Ray Gansley

WPCA Wet FGD SeminarPower Gen International

December 1, 2008

Page 2: Wet FGD System Overview and Operation

Agenda

• Introduction

• Major Process Equipment

• Balance of Plant Equipment

• Controls

• Summary

WPCA Wet FGD Seminar - December 1, 2008

Page 3: Wet FGD System Overview and Operation

MAKE-UP WATER TANK

CHLORIDE PURGE

HYDROCLONE

BELT FILTER

SPRAY TOWER ABSORBER

ELECTROSTATIC PRECIPITATOR

STACKWATER

AIR

LIMESTONE

BALL MILL

TO BALL MILL

FROM MW TANK

GYPSUM

REAGENT PREPARATION

ABSORBER

DEWATERING

Process Flow Diagram

WPCA Wet FGD Seminar - December 1, 2008

Page 4: Wet FGD System Overview and Operation

Agenda

• Introduction

• Major Process Equipment

• Balance of Plant Equipment

• Controls

• Summary

WPCA Wet FGD Seminar - December 1, 2008

Page 5: Wet FGD System Overview and Operation

Absorber Island

Absorber

Oxidation Compressors

Spray Pumps

Switchgear

WPCA Wet FGD Seminar - December 1, 2008

Page 6: Wet FGD System Overview and Operation

Jet Bubbling ReactorTray Tower

Fountain TowerOpen Spray Tower

Absorber Designs

WPCA Wet FGD Seminar - December 1, 2008

Page 7: Wet FGD System Overview and Operation

Absorber Unit Operations

Unit Operations

• Inlet – gas distribution, humidification

• Spray zone – gas/liquid contact

• Mist eliminator zone –liquid/gas separation

• Reaction tank – oxidation, dissolution, crystallization

Design Goals

• Lowest lifecycle cost− Capital− O&M

• High reliability

WPCA Wet FGD Seminar - December 1, 2008

Page 8: Wet FGD System Overview and Operation

Absorber Inlet

• Highly corrosive environment− SO3 condensation− Deposits/splash-back

• Design/construction− Solid 3/16” thick C-276− 10º slope toward absorber− Extends 10-15 ft. from shell− Internal overhead deflector

and side shields− Test ports and emergency

quench nozzles− Gas velocity – 3,000-3,600

ft/min

WPCA Wet FGD Seminar - December 1, 2008

Page 9: Wet FGD System Overview and Operation

Absorber Shell

Straight-SideFlared-Side

WPCA Wet FGD Seminar - December 1, 2008

Page 10: Wet FGD System Overview and Operation

• Multiple spray levels with dedicated pumps allows efficient turndown

• Gas velocity – 13-14 ft/sec

Contact Zone

• Spray flow

– Typical afternoon thunderstorm – 1-2 in/hr

– Spray tower – 10 ft/min

WPCA Wet FGD Seminar - December 1, 2008

Page 11: Wet FGD System Overview and Operation

• Design Approach− Intimate gas/liquid contact− No gas sneakage

• Multiple spray stages depending on SO2 inlet and removal efficiency

• Overall spray coverage (>200% at 3-feet) and nozzle distribution to provide even distribution and prevent gas sneakage.

• Wall rings to prevent gas sneakage near side walls.

• Pressure drop vs. pumping power trade-off

Contact Zone

WPCA Wet FGD Seminar - December 1, 2008

Page 12: Wet FGD System Overview and Operation

Spray Nozzles

• Multiple counter-current spray stages

• Nozzle type− Top stage—single orifice hollow

cone− Lower stages—dual orifice

hollow cone• Sauter mean droplet diameter of

~2,000 micron at 8 psig

• Silicon carbide construction

WPCA Wet FGD Seminar - December 1, 2008

Page 13: Wet FGD System Overview and Operation

Spray Zone

Mist Eliminator

Mist Eliminator

Two stages of vertical-flow chevron vanesConstruction

– Polypropylene– Polysulfone– FRP– Alloy/stainless steel

WPCA Wet FGD Seminar - December 1, 2008

Page 14: Wet FGD System Overview and Operation

Gas Flow

5 10 15 20 25C

arry

ove r

Gas Velocity (ft/sec)

Mist Eliminator Operation

WPCA Wet FGD Seminar - December 1, 2008

Page 15: Wet FGD System Overview and Operation

Mist Eliminator Wash System

• Fresh water wash on intermittent basis− First stage washed from

below (1.5 gpm/ft2) and above (0.75 gpm/ft2)

− Second stage washed from below (0.75 gpm/ft2)

• Construction− Piping – FRP, polypropylene,

alloy/SS− Nozzles – polypropylene,

alloy/SS

WPCA Wet FGD Seminar - December 1, 2008

Page 16: Wet FGD System Overview and Operation

Typical size: 50,000-75,000 gpm at 55-85 TDHPump Efficiency: 87-90+%1,000-2,500 hpHorizontal, centrifugalRubber lined casingImpeller

– Hard metal– Rubber-covered

Absorber Recycle Pumps

WPCA Wet FGD Seminar - December 1, 2008

Page 17: Wet FGD System Overview and Operation

Spray Pump Capacity

10,000

20,000

30,000

40,000

50,000

60,000

70,000

1970 1980 1990 2000

Flow

(gpm

)

WPCA Wet FGD Seminar - December 1, 2008

Page 18: Wet FGD System Overview and Operation

Recycle Pump Curve

WPCA Wet FGD Seminar - December 1, 2008

Page 19: Wet FGD System Overview and Operation

• Integral to absorber

• Functions− Limestone dissolution− Oxidation− Gypsum crystallization

• Design considerations− Solids and liquid residence time− Foaming/freeboard

• Side entry agitators with air lances

Reaction Tank

WPCA Wet FGD Seminar - December 1, 2008

Page 20: Wet FGD System Overview and Operation

Materials of Construction

ShellRubber-lined carbon steelFlakeglass-lined carbon steelStainless steel (317LMN)Duplex stainless steel (2205, 255)Nickel-based alloyRoll-clad alloyLined concrete (tile, polypropylene)

External Spray PipingFRPRubber-lined carbon steelSS/alloy

Mist EliminatorsFRPPolypropylenePolysulfoneSS/alloy

HeadersRubber-lined carbon steelFRPStainless steel (317LMN)Duplex stainless steel (2205, 255)Nickel-based alloy

InletC-276

WPCA Wet FGD Seminar - December 1, 2008

Page 21: Wet FGD System Overview and Operation

Reagent Preparation Island

Day Bin

Ball MillFeed Tank

Classifier

WPCA Wet FGD Seminar - December 1, 2008

Page 22: Wet FGD System Overview and Operation

BALL MILL

FROM MW TANK

Limestone Grinding System

WPCA Wet FGD Seminar - December 1, 2008

BALL MILLRECYCLE

TANK

REAGENTFEEDTANK

CLASSIFIER

REAGENT SILO

TOABSORBER

Page 23: Wet FGD System Overview and Operation

• Limestone grinding− Horizontal/vertical

wet ball mills− On-site vs. off-site

preparation• Product ground to

90-95% < 44 μ; 30% solids• Rubber-lined with

hardened steel balls

Limestone Preparation

WPCA Wet FGD Seminar - December 1, 2008

Page 24: Wet FGD System Overview and Operation

Pre-Ground Limestone Injection

• Dry, pre-ground limestone feed options− Pneumatic injection into reaction tank below slurry level− Pre-slurry in small tank

• Advantages− Low capital cost (i.e. no ball mills, auxiliary equipment,

buildings, etc.)− Less equipment to maintain

• Disadvantages− Higher delivered cost

• Lifecycle cost evaluation on case-by-case basis

WPCA Wet FGD Seminar - December 1, 2008

Page 25: Wet FGD System Overview and Operation

Dewatering Island

Hydroclone

Belt Filter

Vacuum Pump

WPCA Wet FGD Seminar - December 1, 2008

Page 26: Wet FGD System Overview and Operation

Primary Dewatering

• Initial solid/liquid separation step− Feed: 15-20% TSS− Underflow: 50-55% TSS− Overflow: 3-5% TSS

• Overflow enriched with CaCO3 due to particle size difference; improved reagent utilization

• Steel casing with rubber, urethane, and ceramic internals

WPCA Wet FGD Seminar - December 1, 2008

Page 27: Wet FGD System Overview and Operation

Secondary Dewatering

• Horizontal belt filter− 8-10% moisture in gypsum− Optimal for cake washing

• Rotary drum filter− 10-15% moisture− Smaller footprint

• Other options− Gypsum stacking− Centrifuge− Thickener

WPCA Wet FGD Seminar - December 1, 2008

Page 28: Wet FGD System Overview and Operation

• Typical specification:− >95% CaSO4•2H2O− <0.5–1.0% CaSO3•½H2O− <100 ppm Cl− <10% moisture− pH 6–8− 30–40µ MMD

• Requires:− High purity limestone (95–

96%)− High efficiency ESP/FF− 99+% oxidation− Belt filter− Cake washing

Wallboard Gypsum

WPCA Wet FGD Seminar - December 1, 2008

Page 29: Wet FGD System Overview and Operation

Agenda

• Introduction

• Major Process Equipment

• Balance of Plant Equipment

• Controls

• Summary

WPCA Wet FGD Seminar - December 1, 2008

Page 30: Wet FGD System Overview and Operation

• Truck, rail, or barge delivery

• ¾” x 0” (20 x 0 mm) crushed limestone

• Outdoor long-term storage feasible in most areas

• Indoor/covered storage in harsh/wet climates

Limestone Delivery/Storage

WPCA Wet FGD Seminar - December 1, 2008

Page 31: Wet FGD System Overview and Operation

Limestone Silo

• Provide buffer between limestone pile and ball mill operation

• 16-24 hr capacity

• Carbon steel construction with polymer or stainless steel hopper lining

• Vibrating bottom/mechanicalactivation

• Vent filter for fugitive dust control

WPCA Wet FGD Seminar - December 1, 2008

Page 32: Wet FGD System Overview and Operation

• Covered storage options− Direct discharge to bunker/

manual reclaim− Convey to dome/manual

reclaim− Convey to building or silo/

automated reclaim• Open pile

− Feasible− Possible issues: moisture,

fugitive dust, leaching• Selection depends on:

− On-site storage requirement− Gypsum contract

Gypsum Storage/Handling

WPCA Wet FGD Seminar - December 1, 2008

Page 33: Wet FGD System Overview and Operation

Fan Arrangement – Retrofit

ELECTROSTATIC PRECIPITATOR

STACK

ID FAN

WPCA Wet FGD Seminar - December 1, 2008

Page 34: Wet FGD System Overview and Operation

Fan Arrangement – Retrofit

ABSORBER

ELECTROSTATIC PRECIPITATOR

STACK

ID FAN

WPCA Wet FGD Seminar - December 1, 2008

Page 35: Wet FGD System Overview and Operation

Fan Arrangement – Retrofit

ABSORBER

ELECTROSTATIC PRECIPITATOR

STACK

ID FAN BOOSTER FAN

WPCA Wet FGD Seminar - December 1, 2008

Page 36: Wet FGD System Overview and Operation

Fan Arrangement – Retrofit

ABSORBER

ELECTROSTATIC PRECIPITATOR

STACK

ID FAN

BOOSTER FAN

WPCA Wet FGD Seminar - December 1, 2008

Page 37: Wet FGD System Overview and Operation

• Purge stream required to control chlorides/inert solid for wallboard gypsum

• Purge stream treatment strategy is site-specific; depends on:− Discharge limits− Receiving body− FGD process design− Fuel, limestone, make-up water

• Treatment options:− Direct discharge− Volume reduction (evaporation,…)− Physical/chemical treatment

• Suspended solids• pH adjustment• Heavy metals removal• COD removal

Wastewater Treatment

WPCA Wet FGD Seminar - December 1, 2008

Page 38: Wet FGD System Overview and Operation

Agenda

• Introduction

• Major Process Equipment

• Balance of Plant Equipment

• Controls

• Summary

WPCA Wet FGD Seminar - December 1, 2008

Page 39: Wet FGD System Overview and Operation

WFGD Controls

• Distributed Control Systems− Overview− Redundancy

• Primary WFGD Control Loops & Instrumentation− Absorber Area− Flue Gas System

WPCA Wet FGD Seminar - December 1, 2008

Page 40: Wet FGD System Overview and Operation

Distributed Control Systems (DCS)– Control and automation of WFGD

processes and components– Interface with remaining power

plant controls– Monitor key process parameters– Process trends, reports, historical

data loggingLocal Control Panels (LCP)Programmable Logic Controllers (PLC)Main FGD Control Area– Dedicated WFGD Control Station– Centralized WFGD Control with

Boiler/Power Plant

WFGD Control Systems

WPCA Wet FGD Seminar - December 1, 2008

Page 41: Wet FGD System Overview and Operation

Redundant Data Highway

OperatorStation Laser Printer

LocalI/O

OperatorStation

RedundantProcessController

EngineeringStation

Line Printer Line Printer

RemoteI/O

SerialDevice

SerialDevice

LocalI/O

RedundantProcessController

RemoteI/O

SerialDevice

SerialDevice

LocalI/O

RedundantProcessController

DCS CONFIGURATION DIAGRAM

Distributed Control System

WPCA Wet FGD Seminar - December 1, 2008

Page 42: Wet FGD System Overview and Operation

Major Control Loops - Absorber

Make-Up Water

L

Solids / Gypsum Bleed

D

pH

Reagent Feed

WPCA Wet FGD Seminar - December 1, 2008

Page 43: Wet FGD System Overview and Operation

Scrubbing Liquor pH– Most important process variable

to be controlled in WFGD →continuous, in-line monitoring, daily lab verification

– Indication of the amount of CaCO3 in scrubbing solution

– Scrubbing liquor below desired range → lower SO2 removal efficiency

– Scrubber liquor above desired range → higher SO2 removal efficiency, excess CaCO3 and reduced gypsum byproduct purity

0 7 14

5.3 – 5.8 Scrubbing Liquor pH

Neutral H2O

acid base

pH / Reagent Feed Control

WPCA Wet FGD Seminar - December 1, 2008

Page 44: Wet FGD System Overview and Operation

Limestone slurry

pH

pH

Reaction Tank

Absorber

FE

pH Controller

LS Flow Controller

SO2 Boiler Load (MW)

pH / Reagent Feed Control

WPCA Wet FGD Seminar - December 1, 2008

Page 45: Wet FGD System Overview and Operation

pH PROBES

TRANSMITTERS

LOCAL DISPLAY PANELS

PROCESS PIPING

pH Instrumentation

WPCA Wet FGD Seminar - December 1, 2008

Page 46: Wet FGD System Overview and Operation

Flue Gas Water Vapor

Mist Eliminator

Wash Water

Limestone Slurry

Oxidation Air Sat. Water

Absorber Bleed Stream

Flue GasWater VaporScrubber Slurry Solids

– Important WFGD process variable, verified daily with laboratory samples

– Scrubber slurry solids: gypsum, limestone, flyash, inerts

– Numerous inputs affecting water balance and solids concentration

– Control solids concentration within narrow range: 14-16 wt.%

Solids Control– Solids too low: potential for

gypsum scaling– Solids too high: increased

potential for wear of equipment– Equipment sizing

Dewatering ReturnMake-up Water

Gypsum Bleed / Solids Control

WPCA Wet FGD Seminar - December 1, 2008

Page 47: Wet FGD System Overview and Operation

Secondary Dewatering

DE

Reaction Tank

Absorber

Return to Absorber

Primary Dewatering Hydroclones

DENSITY

L

LEVEL

L

ABSORBER BLEED PUMPS

Gypsum Solids / Density Control

WPCA Wet FGD Seminar - December 1, 2008

Page 48: Wet FGD System Overview and Operation

Density Measurement

Nuclear Density Meter

• Nuclear Density Meters− Source emits gamma

radiation through process− Detector measures energy

of radiation − Capable of detecting

process variations within desired narrow range

− Safe− Accurate− Simple calibration− Verify with laboratory

analyses

WPCA Wet FGD Seminar - December 1, 2008

Page 49: Wet FGD System Overview and Operation

PROCESS SLURRY

DENSITY METER

LOCAL DISPLAY PANEL

Density Instrumentation

WPCA Wet FGD Seminar - December 1, 2008

Page 50: Wet FGD System Overview and Operation

DE

Reaction Tank

Absorber

L

L

DENSITY

Make-up water

DY

Level Controller

f(x)

f(x)

OX AIR

Level / Make-Up Water Control

WPCA Wet FGD Seminar - December 1, 2008

Page 51: Wet FGD System Overview and Operation

SPRAY TOWER ABSORBER

EXISTING STACK

Booster Fan Control

BOOSTER FANS

ID FANS

P

F

ZY

VANE PITCH CONTROL

NEW STACK

STACK REVERSE FLOW

DUCT PRESSURE

ID Fan Load, Boiler MW

WPCA Wet FGD Seminar - December 1, 2008

Page 52: Wet FGD System Overview and Operation

SPRAY TOWER ABSORBER

EXISTING STACK

Booster Fan Control

BOOSTER FANS

ID FANS

P

ID FAN LOAD, BOILER (MW)

ZY

VANE PITCH CONTROL

UNTREATED FLUE GAS

(BYPASS)

DUCT PRESSURE

SO2TREATED FLUE

GAS

ID FANS

WPCA Wet FGD Seminar - December 1, 2008

Page 53: Wet FGD System Overview and Operation

SPRAY TOWER ABSORBER

Emergency Quench

TY

T

T

INLET FLUE GAS

OUTLET (CLEAN) FLUE GAS

QUENCH WATER

WPCA Wet FGD Seminar - December 1, 2008

Page 54: Wet FGD System Overview and Operation

Agenda

• Introduction

• Major Process Equipment

• Balance of Plant Equipment

• Controls

• Summary

WPCA Wet FGD Seminar - December 1, 2008

Page 55: Wet FGD System Overview and Operation

WFGD Operations Staff

• O&M staffing varies; depends on:− Owner staffing philosophy/

practices− Plant layout/design− Reagent/byproduct− Labor bargaining agreements− Other equipment at plant

WPCA Wet FGD Seminar - December 1, 2008

Page 56: Wet FGD System Overview and Operation

O&M Staff for 2 x 700 MW WFGD

Position Description No. CoverageFGD Supervisor 1 1 shift, 5 days/week FGD Operator 1 3 shifts, 7 days/week FGD Mechanic 1 1 shift, 5 days/week FGD Computer Tech 1 1 shift, 5days/week FGD Specialist 1 1 shift, 5 days/week FGD Material Handling 1 3 shifts, 7 days/week

Page 57: Wet FGD System Overview and Operation

Lifecycle Cost Comparison

WPCA Wet FGD Seminar - December 1, 2008

High Sulfur Low SulfurTotal Plant Capital Cost $ 150,000,000 120,000,000

$/kW 250 200Plant Capacity (per unit) M W e 600 600No. Units 1 1Plant Capacity Factor % 85 85Equivalent Full-Load Hour hr 7,446 7,446Escalation Rate % 3.0 3.0NPV Discount Rate % 10.0 10.0SO2 Removal % 98 98SO2 Production Rate lb/hr 45,000 12,000

lb/M M Btu 7.50 2.00ID Fan Flue Gas Flow acfm 2,100,000 2,220,000

Page 58: Wet FGD System Overview and Operation

Lifecycle Cost Comparison

WPCA Wet FGD Seminar - December 1, 2008

High Sulfur Low SulfurNo. O&M Personnel/Shift 5 5O&M Labor Rate $/hr 50.00 50.00AQCS Power kW 9,000 4,500Fan Power Consumption kW 2,464 1,628Total Power kW 11,464 6,128Power Cost $/kW -hr 0.03 0.03Limestone Consumption lb/hr 74,709 19,922Limestone Cost $/ton 20.00 20.00Gypsum Production lb/hr 138,618 36,965Gypsum Price $/ton (5.00) (5.00)Repair/M aintenance % of TPC 1.5 1.5

Page 59: Wet FGD System Overview and Operation

Lifecycle Cost Comparison

WPCA Wet FGD Seminar - December 1, 2008

Technology High Sulfur Low SulfurO&M Labor $/yr 2,190,000 2,190,000Auxiliary Power $/yr 2,560,776 1,368,838Limestone $/yr 5,562,823 1,483,420W W TS Reagents $/yr 1,500,000 500,000Gypsum $/yr (2,580,382) (688,102)Repair/M aintenance $/yr 2,250,000 1,800,000Total $/yr 11,483,218 6,654,156

$/M W -hr 2.57 1.49

Total Plant Capital Cost $ 150,000,000 120,000,000O&M Cost (25-Yr NPV) $ 138,240,000 69,540,000Lifecycle Cost $ 288,240,000 189,540,000

Page 60: Wet FGD System Overview and Operation

Summary

• WFGD system design is mature; operation is routine

• Major process islands− Absorber− Reagent− Dewatering

• Key balance of plant equipment− Flue gas handling− Material handling− Wastewater treatment− Electrical system

WPCA Wet FGD Seminar - December 1, 2008

Page 61: Wet FGD System Overview and Operation

WPCA Wet FGD Seminar - December 1, 2008

Page 62: Wet FGD System Overview and Operation

www.alstom.com