what is just enough test?

47
1 What is Just Enough Test?

Upload: others

Post on 11-Feb-2022

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: What is Just Enough Test?

1

What is Just Enough Test?

Page 2: What is Just Enough Test?

2

TopicsBoard Test TrendsDifferent types of Test

Inspection/StructuralAdvantages/Disadvantages

Big Iron vs Low-CostDistributed TestFalse FailuresSampling

Page 3: What is Just Enough Test?

3

Fault Spectrum and Issues

Solder Paste Height

Solder Missing

Solder BridgeIC Pin Lifted

IC Pin ShortedTrace Short

Trace Open

Not Enough Solder

Board MarkingsReversed Part

Bad Part

Missing Parallel Cap

Part Placement

Part Tolerance

On Power Testing

Wrong Part

Flash Programming

ECO Version

Transistor testing

Boundary Scan

Memory Programming

I2C Programming

GUID Programming

Programming Verification

Test Time

Test Costs

Schedule AOI

X-Ray

MDA

ICT

Flying Probe Functional Test

Page 4: What is Just Enough Test?

4

Board Trends

Higher Speed PartsMore pins per deviceShort life cyclesHigher Reliability Parts

Page 5: What is Just Enough Test?

5

Test TrendsTest is a commodity

Issues are mature – little difference between vendorsHigher density boards -lack of test probe access Verify assembly process not parts

Screened parts don’t fail (normally)Programmable devices (where to program)Designers using standard Test interfaces

Boundary ScanTree-TestingSPI, I2C, ISP (serial interface protocols)

Page 6: What is Just Enough Test?

6

Parts Fail Less

Better Controlled Manufacturing ProcessHigher YieldsLess need for testHigher Reliability

Page 7: What is Just Enough Test?

7

Why Test?

Verification of productBusiness ReputationLow Volumes – less control of processPay Me Now or Pay Me Later

Basic Rule of 10

Page 8: What is Just Enough Test?

8

Test Considerations

TimeVolumeCostQualityThe earlier a fault is found in manufacturing process the cheaper it is to fix (Rule of 10)

Page 9: What is Just Enough Test?

9

Modern SMT line – Quality & Efficiency

AOI MDA/ICT•Defective device•Wrong device•Power-Up•Programming

•Shorts•Opens•Lifted lead•Polarity

•Tombstone•Billboard•Skid/Skew•Marking•Insufficient/excessive solder

Mfg Issues

• Repair after solder is difficult and costly

• Not enough board real estate for ICT test points

Page 10: What is Just Enough Test?

10

Inspection Testing

Solder Paste InspectionAutomated Optical InspectionX-Ray Inspection

Page 11: What is Just Enough Test?

11

SPI Advantages

No fixture costIn-LineNo componentsBeginning of SMT process

Fast program development (less than 1 hr)

Page 12: What is Just Enough Test?

12

SPI Defect Coverage

Solder Defects

• Solder bridge

• Insufficient solder

• Excessive solder

•Volume

Page 13: What is Just Enough Test?

13

SPI Disadvantages

Requires Known Good Board (KGB)Unpopulated board100% success does not guarantee 0% faults

Page 14: What is Just Enough Test?

14

AOI Advantages

No fixture costIn-Line100% Visual coverage vs humanEarly in SMT process

Fast program development (3 -7 hours)

Page 15: What is Just Enough Test?

15

AOI Defect Coverage

Component Defects Solder Joint Defects Surface Defects

• Missing component

• Skid/Skew component

• Extra component

• Tomb-stoned component

• Bill-boarded component

• Alternative/Marking

• Lifted/bent lead

• Broken lead

• Solder bridge

• Insufficient solder

• Excessive solder

• Lifted/bent lead

• Broken lead

• Solder ball

• Through-hole pin

• Gold-finger contamination

• Scratch

Page 16: What is Just Enough Test?

16

AOI Disadvantages

Higher False Failure RatesRequires Known Good Board (KGB)Requires 10-30 board to adjust programOnly Visual (shorts under part not found)BGA pin shorts/opens

Page 17: What is Just Enough Test?

17

X-Ray Advantages

AOI advantages minus markings and polarity

Non-visible assembly faults BGA pin shorts and opensInner layer shorts and opens

Page 18: What is Just Enough Test?

18

X-Ray Coverage

AOI coverageBGA pin coverageInterlayer assembly faults

Page 19: What is Just Enough Test?

19

X-Ray Disadvantages

False Failures More Expensive than “Big Iron” ICT testerRequires KGBProgram development 3-10 days

Page 20: What is Just Enough Test?

20

Structural Testing

Flying ProbeManufacturing Defect AnalyzerBoundary Scan (virtual connections)X-Ray Inspection

Page 21: What is Just Enough Test?

21

Flying Probe Advantages

No fixture Physical verification• Basic shorts and opens• Basic R/L/C testing

1 day program development

Page 22: What is Just Enough Test?

22

Flying Probe Coverage

Shorts & OpensR/L/C testing

Page 23: What is Just Enough Test?

23

Flying Probe Disadvantages

Long test times up to 30 min Limited DiagnosticsLower quality measurementsPossible to miss some shorts

Page 24: What is Just Enough Test?

24

MDA AdvantagesLow CostPhysical testing of board• Shorts• Analog• Open Pins (Vectorless & Clamping Diode)

Short test time1-2 Days to programBetter diagnosticsBetter measurements - guarding

Page 25: What is Just Enough Test?

25

MDA Coverage

Shorts & Opens (Pins and traces)Passive Component Testing• R/L/C , diodes, transistors, fets

Component ValuesVector-less testing (digital presence)

Page 26: What is Just Enough Test?

26

Open IC Pin Detection

Vector-less Testing

Clamping Diode Testing

Both offer low cost analog

measurement to detect an open IC pin

Page 27: What is Just Enough Test?

27

MDA Disadvantages

Requires a fixtureUsually requires mid-high volume to justify fixture costs

Requires nodal access1-2 Days to programRequires 20-50 boards for stable program

Page 28: What is Just Enough Test?

28

ICT Advantages

Most Bang for the Buck Highest Quality TestingMDA test advantagesPowered up testingShort test time (10-60 sec)Digital component testingBest component level diagnostics

Page 29: What is Just Enough Test?

29

ICT Coverage

MDA coverage Powered up testingDevice programmingBoundary Scan and other industry standard interface testing (I2C, SPI)

Page 30: What is Just Enough Test?

30

Easy to Use On Board Programming Software Modules

EEPROM Programming (Mac Address)

ISP Programming

SPI Programming

Page 31: What is Just Enough Test?

31

ICT Disadvantages

Requires a fixtureRequires mid-high volume to justify fixture and program costs

Requires nodal access1-2 weeks to programMore device data requiredRequires 20-50 boards for stable program

Page 32: What is Just Enough Test?

32

Fault Spectrum vs TesterFaultSolder Height X XSolder Quality X X XBd Markings XComp Placement XIC Pin Shorts X X X X XIC Pin Opens X X X X XTrace Shorts X X X XTrace Opens X X X XMissing Part X X X X XBad Part X X XPart Tolerance X X XTransistors X XPower UP X XProgramming X XBoundary Scan X XECO Version X XAt Speed Verfication X

SPI AOI X-Ray Flying Probe MDA ICT Functional100-250K 100-250K 300K-600K 100-200K 20-50K 100K-500K low to high CostLow-High Low-High Low-Mid Low Low-Mid High Low-High VolumeMinute Minute Minutes > 30 Minutes Minute< Minute Minutes-Hours Test Timehours hours days day day week days-weeks* DevelopmentNo No No No Yes Yes Box/Interface Fixture

Page 33: What is Just Enough Test?

33

Traditional Test Choice

Big Iron ICT TesterFastest and largest pin count testerMost bang for the buckAlso costs the most bucksNot cost-effective with smaller volumes

Page 34: What is Just Enough Test?

34

Low Cost Tester Options

MDAMDA with 3rd party (Boundary Scan)Combinational (MDA/ICT/Functional)Stand-alone Boundary ScanUsed Testers

Page 35: What is Just Enough Test?

35

Pin Card Cost700 net board with 200 pin IC

$70,000$10,0008967328:2128Big Iron

$38,500$3,50070411641:164Combo

$12,000$2,00076861281:1128MDA

Pin Card Cost

Bd CostPins req

Bds req

Real Pins/bd

Mux Ratio

Pins/bdTester

Page 36: What is Just Enough Test?

36

Pin Card Costs700 net board with 300 pin IC

$100,000$10,000128010328:2128Big Iron

$38,500$3,50070411641:164Combo

$12,000$2,00076861281:1128MDA

Pin Card Cost

Bd CostPins req

Bds req

Real Pins/bd

Mux Ratio

Pins/bdTester

* 1 drive/1 sense

Page 37: What is Just Enough Test?

37

Software Costs

>$60KAwareMagicShared Wiring

Basic Scan/Scan Pathfinder/ Silicon Nails

Flash 70Opens Xpress/Test Jet

Big Iron

$10KincincFlash libTest JetCombo

$45KNAOption$15K ?

Option$10K ??

Test Jet$10K

MDA

TotalsOtherBScanFlashVector-less

Tester

Page 38: What is Just Enough Test?

38

Tester Costs700 nets with 300 pin IC

Industry Standard

$260K>$60K$100K$100KBig Iron

Integrated Solutions

$99K>$10K$39K$50KCombo

Multi-vendor$77K$45K$12K$20KMDA

NotesTotalSoftwarePinsBaseTester

Page 39: What is Just Enough Test?

39

Boundary Scan Issue

More acceptance than everBut most customers don’t implementPC motherboards don’t (Nand Tree)Cell phones have no test padsStill parts without compliant BSDL

Micro-controllersAutomotive industry likes CAN

Its has many versions

Page 40: What is Just Enough Test?

40

Big Iron vs Low Cost

Big Iron is still the Tried and True standardDo you need 10MHz?Do you need timing sets?

Low Cost is worth investigating if new linesStill need standard driver/sensorsWhat about multiple vendor support

Page 41: What is Just Enough Test?

41

Distributed TestUse strengths of different types of testAOI for presence/bypass & reverse capsPhysical test for shorts and valuesDigital test for program/verificationNo software talks to all vendors (assy/test)Testers need to be able to turn on/off any test

Page 42: What is Just Enough Test?

42

Manufacturing Test

Once process is good little goes wrongWhy Test all partsMaybe test changes in processExample: Replacing a reel of partsWhy Test all parts on the reel

Page 43: What is Just Enough Test?

43

Test SamplingTesters will ability to turn on/off testsRequired for distributed testDrawbacks

QualityCustomer ExpectationsWho takes the blame for a test escape

Could a report even be generated to explain what happened. If its dynamic the conditions changed by the time the fault is found

Page 44: What is Just Enough Test?

44

Functional Failures

How many bad parts are found?Are the failures structural?Is any particular test better at catching these failures and why didn’t it?Did test introduce any failures?

Page 45: What is Just Enough Test?

45

False FailuresWhat do False Failures cost?Rules usually state you must replaceAre the parts really bad?Reasons for False Failures

Marginally testFixtures/ProbesAllow retest and fixture recycling

Page 46: What is Just Enough Test?

46

What will you do?

Same as usualKeep buying “Big Iron”Investigate Low Cost solutionsExplore Distributed Test

Page 47: What is Just Enough Test?

47

Conclusion

Test is mature and is a commodityBoundary Scan only solutions are not viable if there aren’t any boundary scan partsTest can’t be more flexible with current mind sets –not necessarily a bad thingDistributed Test has a long way to go