when good projects go bad - aacei calgary chinook … · when good projects go bad steve revay...
TRANSCRIPT
Agenda
Warning Signs
Lesson Learnt
Fast Track
Top Causes
Change Management
Communication / Email
Credible Claim Presentation
STRESS
Next step is to deal or cope with stressors in
positive way
•Acceptance
Some things we have no control over so accept
them
e.g. “Someday I’ll laugh about this!”
•Attitude
Try to focus on positive
e.g. “What can I learn from this?”
•Perspective
Ask yourself “How important is this situation?”
Or “Will I even remember this in 5 years?”
What happens when the marketplace is in a downturn
Typically
Contractors tend to be more aggressive in pursing claims – cash flow becomes more important than relationships; and
Owners tend to be more aggressive as they become more concerned with the bottom line – less concerned with keeping contractors happy
What does all this mean
More disputes / claims
AACE International can help
RPs / Technical Products / Certifications /
Education / Annual Seminar.
Warning Signs Owners who:
have unrealistic expectations
fail to properly develop project
cut corners on investigations
and design
inappropriately shift risks to contractor
Warning Signs
Engineers who:
pass on design responsibilities to Contractors
agrees to unrealistic expectations
have vested interest in disputes
produce ambiguous or conflicting documents
Blame for Petro-Canada RCP overrun some $900 million
“The root cause of these problems is poor quality engineering and
sub par site management”
Calgary Herald July 25, 2008 – quoting CEO Ron Brenneman
link
Realistic Schedule
Project Completion Engineering
Overlap
Construction
DELAY
Increased overlap
Failure to move start and end dates notwithstanding initial delays causes unrealistic schedule
Industrial Megaprojects Edward Merrow
It is far more important to be carefully monitoring engineering than construction! When problems start to show up in engineering, it actually may be possible to do something about them. If the problems are not seen until construction, it is usually too late
The Post Mortem You Never Want – How To Determine Findings From a Troubled Project –
Bob Prieto - PM World November 2008
Failing to adequately plan (use of tool)
Plan not sufficiently developed
Critical Path not understood
Schedule does not reflect realities of Project (political / deliverable not tool)
Project execution lacks rigor
Performance metrics not effectively used
Warning Signs Contractors can make the situation worse if
they:
don’t satisfy notice provisions
cut corners to offset bid deficiencies
abuse subcontractors
don’t read the contract or assume it will not
be enforced
fail to keep adequate project records
don’t document claims properly
fail to develop and update schedules
ARTICLES TO READ NOTICE PROVISION
CHANGES/EXTRAS
DISPUTES
AUTHORITY
SOIL SITE CONDITIONS
DELAY
PAYMENT
Words of Wisdom
“ Education is what you get when you read the fine print …
...experience is what you get when you don’t. ”
Scope Creep
Inadequate Change Management
Poor Estimates /PM /Project Teams
Lack of communication
Ineffective Project Controls
Most Common Causes of Overrun ( Linkin discussion)
Unrealistic Expectations
Extensive changes / scope creep
Acceleration – more hours / people
Lack of communication
Ineffective Project Controls
Most Common Causes of Overrun ( SOR experience)
COAA BENCHMARKING STUDY FEBRUARY 2009
RANK COST SCHEDULE PRODUCTIVITY
1 AMOUNT OF UNPLANNED
OVERTIME
% ENGINEERING
COMPLETION PRIOR TO
CONSTRUCTION START
% ENGINEERING
COMPLETION PRIOR TO
CONSTRUCTION START
2 % ENGINEERING
COMPLETION PRIOR TO
CONSTRUCTION START
BUSINESS MARKET
CONDITIONS
AMOUNT OF UNPLANNED
OVERTIME
3 BUSINESS MARKET
CONDITIONS
CRAFT LABOUR SKILL BUSINESS MARKET
CONDITIONS
4 CRAFT LABOUR SKILL QUALITY OF FIELD LEVEL
SUPERVISION
QUALITY OF FIELD LEVEL
SUPERVISION
5 COORDINATION WITH
PLANT SHUTDOWN
WEATHER CONDITIONS CRAFT LABOUR SKILL
FACT OR FICTION
Contractors like changes
Contractors make $$$ (gouge) on changes
Productivity impact (?) can be quantified on each change
Contractors make money on the markup in change orders
CHANGE QUOTATION
The price quoted is only for the direct cost of the change. We
reserve the right to seek compensation for the impact on
contract work and / or the cumulative effect of changes
when these costs (if any) can be quantified.
The Great Debate
Owners
Absolutely refuse to
accept
qualification
Contractors
Need to qualify so as to
preserve their right to discuss
productivity
EXTRA WORK
BREAK-EVEN POINT
0
100
200
300
400
500
0 500 1000 1500 2000
O VERHEAD AND FEE
DIRECT COST VALUE OF CHANGE
?
What is being said - What is happening
Owners say
We want to know early
on when there are problems
Contractors say
Owners become defensive and
more rigid with no give and take
-
becomes war zone
Success
“Success of a project is directly linked to meeting stakeholder expectations, and failure is linked to communication breakdowns”
Dr. Francis T. Hartman “Don’t Park your Brain Outside”
Monitoring
At each and every coordination job site meeting each and every contractor or subcontractor is asked if they are aware of any current or potential situation that is affecting or might affect their time and or cost to complete their work.
Monitoring
The response to this question must be minuted for each and every contractor / subcontractor.
When do we use E-mail?
– 79% checked email in the bathroom
– 77% while driving
– 11% while engaged in intimate behaviour
– 41% while their commercial plane was in the air
– 94% during work nights or weekends
– 96% while on vacation
* Taken from “Mobile Messaging Marketing Trends,”
Opinion from
19 41.30%0 0%
14 30.43%13 28.26%
Totals 46 100%
1.) Make up of Group Do you work for a: Responses
Owner organization – buyer of serviceEngineering organization – design of serviceContractor organization – builderFirm that consults to one or more of the abov...
Inflation
6 13.64%18 40.91%12 27.27%
8 18.18%0 0%
Totals 44 100%
2.) Inflation in Claim What is the general level of
inflation in claims? Responses
10% higher than actual value30% higher than actual value60% higher than actual value100% higher than actual value200% or more than actual value
Inflation Extras
7 15.56%23 51.11%
9 20%6 13.33%0 0%
Totals 45 100%
3.) Inflation in Extras What is the general level of
inflation in extras? Responses
10% higher than actual value30% higher than actual value60% higher than actual value100% higher than actual value200% or more than actual value
Claim Prep
3 6.67%11 24.44%22 48.89%
9 20%Totals 45 100%
4.) Quality of Claim Submission Claim Submissions are
well prepared Responses
AgreeSomewhat AgreeSomewhat DisagreeDisagree
Approach
Provide cause – entitlement-effect;
Maintain credibility;
Amounts should be supportable & auditable; and
No charged language
SOURCES
REVAY WEB PAGE: www.revay.com
AACEI : www.aacei.org
COAA: www.coaa.ab.ca
CII: www.construction-institute.org