when the programme is planed or organized there will be some other factors for examples some delays...
TRANSCRIPT
8/3/2019 When the Programme is Planed or Organized There Will Be Some Other Factors for Examples Some Delays and Dis…
http://slidepdf.com/reader/full/when-the-programme-is-planed-or-organized-there-will-be-some-other-factors 1/5
Malta College of Arts & Science & TechnologyBTEC National Diploma – Level 3 2008/2009
Unit 7: Planning, Organisation and Control of Resources in Construction and the Built Environment
17/6/2009
Karl Attard Class: - NDBS1 1 of 5
When the programme is planed or organized there will be some other factors for
examples some delays and disruptions that were not taken into consideration. There are
many factors which may affect the planned program or the organization. To begin with,
these factors refer to the variables unknowns and the unforeseeable.The two general forms consist of: -
Uncertainties due to the adoption of guesswork for example, if is rarely possible to
specify the exact duration of an activity so some amount of estimation is necessary.
Uncertainties associated with rare events of perhaps large consequences for
example, natural disasters, the bankruptcy of a supplier, or the sudden loss of key
personnel.
There are many other types of other disruptions that may effect on planned programme. In
the most general cases, all parameters that define a project schedule may disrupt for
example:-
Activities may be added or removedActivities may be interrupted or their starting dates shifted
The precedence relations of activities may need to be revised for example to see if there is
some design errors The institutional related uncertainties that involve the regulatory,
cultural and the extra-national issues. The regulatory is to keep organization within the
company through the regulations provided.
Every definite project schedule may be disrupted by anything, start off with project
network disruptions. This disruption refers to when an execution of a program is taking
place; activities can either be added or removed which depends on the changes made. Also,
because of these changes, activities may have to be interrupted or else their starting dateswould be shifted for better process. Another thing is that the procedures of activities may
need to be checked to be sure that everything is doing fine as planned. Some examples of
the project network disruptions are the design errors, and the engineering change orders
from the client.
Another type is the activity disruptions. This refers to when an activity is disrupted
because of the duration or the resources that practice diverges from the original planned
project. However, these diverges can be either negative or positive which depends on the
situation. Such that, for duration change in any activity it could be because of delays due to
technical difficulties, resource storages, the need for revise, and unexpected problems that
may occur which forces then to use more resources than originally planned.
The final type is the resource disruptions which consist of shortages of resources.
This is the most common type of disruption in any project development. The variety of
factors may have caused this situation such that these are when a machine breaks down, a
sudden loss of personnel, materials that where overused by other activities or any other
projects, and last of all the late deliveries which are the most important things for the
project to work with.
8/3/2019 When the Programme is Planed or Organized There Will Be Some Other Factors for Examples Some Delays and Dis…
http://slidepdf.com/reader/full/when-the-programme-is-planed-or-organized-there-will-be-some-other-factors 2/5
Malta College of Arts & Science & TechnologyBTEC National Diploma – Level 3 2008/2009
Unit 7: Planning, Organisation and Control of Resources in Construction and the Built Environment
17/6/2009
Karl Attard Class: - NDBS1 2 of 5
Last but not least, we have the variables that are the weather which we have no
control on it so it is very difficult to work with, especially when it is raining. There are also
the labour disputes, confined access, late construction information, the material shortages,
the availability of skilled workers and especially the late design changes.
Disruptions occur when future events do not match expectations and thus they are
closely associated with uncertainties. Uncertainties cannot be predicted because if anything
is planned for the future event, it may never happen, that is no one knows what happens
exactly. The plans can only be reflected when the event is taking place at that very
moment. It could happen the opposite way that has been expected to.
These uncertainties which arise in a construction project management can be divided in
three categories together with two general forms as follows.
Uncertainties can be divided into three categories and two general forms.
The three categories consist of:-Market related uncertainties
Completion related uncertainties
Institutional related uncertainties
The market related uncertainties consists of market demands, competition and supply
chain. The market demands is when a company tries to sell its own products to the
consumers. The competition arises between companies when they try to sell the same
products. One tries to outshine the other by reducing his prices and advertise his products
as best he can. Last of all, the supply chain is when a company has a big business through
the country many materials are transferred to one place to another (under the same
management), however it is still the company’s products but from one shop to another forbusiness.
There is the there is the completion related uncertainties which consists the technical
issues, construction and operational issues. The technical issues are when there is trouble
with the machinery such as they can break down. There is the construction issues which
can cause some problems or any type of material is not constructed well to fit where it is
suppose to be. Then the operational issues that consist of how the operation is controlled
or managed well to continue the process till the end.
The activity disruptions may happen either its duration or resource usage deviates fromthe planned figure. The durations can be either is positive or negative.
8/3/2019 When the Programme is Planed or Organized There Will Be Some Other Factors for Examples Some Delays and Dis…
http://slidepdf.com/reader/full/when-the-programme-is-planed-or-organized-there-will-be-some-other-factors 3/5
Malta College of Arts & Science & TechnologyBTEC National Diploma – Level 3 2008/2009
Unit 7: Planning, Organisation and Control of Resources in Construction and the Built Environment
17/6/2009
Karl Attard Class: - NDBS1 3 of 5
Task 4- D7.2C- Evaluate a range of planning, organisational and control
techniques in terms of utility and efficacy.
Estimate and comment on how useful and efficient certain planning, organisational and
control techniques may be in monitoring and controlling a project, and what affect will they
have on the success of the project when implemented or less.
Once a project is underway and you establish the operating procedures and start working
on perfecting your leadership style, you key responsibility is to keep things going on time
8/3/2019 When the Programme is Planed or Organized There Will Be Some Other Factors for Examples Some Delays and Dis…
http://slidepdf.com/reader/full/when-the-programme-is-planed-or-organized-there-will-be-some-other-factors 4/5
Malta College of Arts & Science & TechnologyBTEC National Diploma – Level 3 2008/2009
Unit 7: Planning, Organisation and Control of Resources in Construction and the Built Environment
17/6/2009
Karl Attard Class: - NDBS1 4 of 5
and within budget. To do this we use the control techniques to have more organized
planned project.
To keep things running smoothly, the following must be monitored for every project,regardless of size or complexity:
The completion of work packages as compared to the plan to check if you are on
schedule
The scope of work being performed to make sure you don’t have scope creep
The quality of work being performed against the requirements for the project
The costs and expenditure as compared to the plan to check your budget
The attitudes of people working on the project or involved with the project
including key stakeholders and management
The cohesiveness and cooperation of team members
Control can imply domination, headstrong authority, or excessive power. Because of thesenegative connotations, people new to project management may be reluctant to implement
project control. The controlling phase is not about domination; however it’s about
gathering information so you can measure, monitor, and adjust progress toward your
project goals. That’s a good thing because, otherwise, you’ll never know if your project is on
the right course.
We use such techniques for example Bar Charts that are used in long and short term
planning, Labour/plant schedule that is used in scheduling of requirements, Time Study
Recording Sheet etc. These are used to control your project and they will directly affect
the end results your project might be.
The concept of earned value is sometimes difficult to grasp, through not because the
concept or the procedure is difficult. The problem is basically twofold: earned value has alanguage of its own and schedule is measured in terms of Euros instead of time. Since
measuring schedule in this fashion goes against intuition and experience, some people
focus on the language rather than on the concepts of earned value. The result is that
learning earned value analysis techniques is harder than it should be. The key to
understanding earned value is in understanding three terms: -
Budgeted cost of work scheduled or the planned value of work.
Actual cost of work performed
Budgeted cost of work actually performed or the “earned” value.
These three terms are used in such techniques like Field Activity Count Record Sheet ,
Synthesis from Element Data, Analytical Estimation Sheet and Daily Report Sheet .
Once these terms and techniques they represent are mastered, all the other terms andcomponents of earned value analysis are easy to remember and use.
In its simplest form, schedule and cost control means:
Comparing planned and actual project progress and costs
Determining a strategy for limiting variation from the schedule and cost baselines
8/3/2019 When the Programme is Planed or Organized There Will Be Some Other Factors for Examples Some Delays and Dis…
http://slidepdf.com/reader/full/when-the-programme-is-planed-or-organized-there-will-be-some-other-factors 5/5
Malta College of Arts & Science & TechnologyBTEC National Diploma – Level 3 2008/2009
Unit 7: Planning, Organisation and Control of Resources in Construction and the Built Environment
17/6/2009
Karl Attard Class: - NDBS1 5 of 5
Managing the activities required to maintain the schedule and costs within
acceptable limits.
Performance control charts come in many forms, but the most common and most useful forschedule and cost control is the one in figure below. The chart has three curves. The middle
curve in the graphic is the cumulative cost curve for the entire project. It is the estimated
cost of all the tasks summed to represent the expected cost over the life of the project. The
very top end of this curve, if measured against the dollar axis, is the budget at completion
or the total cost of the project. The bottom curve in the graphic is a plot of actual costs
spent over time.
Inexperienced project managers may start out full of energy and monitor and control
everything during the first few weeks. Then, when things seem to going okay, the
monitoring falls off. These managers often end up with a big mess at the end of the project
because they’ve failed to keep track of progress and problem. Don’t let this happen!
Maintain your zeal throughout the project.