business activities
support you in engineering
prefabrication in our workshop
on-site assembly of the technological systems
industrial activities
nuclearenergy
construction
biotechnologyenvironmental protection
cosmetics chemistrypharmacy
fooddairybrewery
our workshop
gantry frames 2 x 12,5 T1 x 2,0 T
production hall area2.775 m2
height of the production hall
10,06 m
land area6.925 m2
what we manufacture in our workshop
tanks and reactors pipe fences and flow plates service skids – a pump system
elements of process pipelines with diameters from
DN 10 to DN 1200
pilot plants
complete process systems – SKIDs
special process piping(for a nuclear power
station)
piping systems, tunnels, ducts
heat exchangers, evaporators
storage and process tanks
what we manufacture in our workshop
platforms, steelworks
manifolds
ducts mobile process arrangements
what we manufacture in our workshop
what we do at construction sites
pressure tanks complete process installations
process and media piping
pipe bridges
orbital welding supporting structures, platforms, stairs,
railings
heat and cold insulation
GEA TBS / HEINEKEN Sevilla 2005-2007
GEA Tuchenhagen Brewery Systems and GEA HUPMANN AG
Assembly of complete process system and brewery plant. Assembly, welding and thermal insulation of process plants in fermentation cellars, CIP, fermentation and storage stations. Turnkey project. Moving of tanks, equipment into the hall, prefabrication of carrying structures under pipelines, laying and welding of pipelines. Trials, participation in commissioning. 105 000 hours.
Scope of work:
Buyer:
selected projects in the years 2007-2015
TOOTHPASTE FACTORY COLGATEŚwidnica 2006-2013
Building and installation work at the toothpaste site. Process plants and utility media. Construction and as-built documentation.Validation of toothpaste manufacturing plant.
Extension of the piping system.Supply of a complete CIP unit including automation and control systems.
Scope of work:
selected projects in the years 2007-2015
Colgate – Palmolive Mfg (Poland) Sp. z o.o.
Buyer:
UNILEVER POLSKA S.A.Poznań 2007
Unilever Polska S.A.
Process plant for soup manufacture in Unilever Polska S.A. Manufacturing Site in Poznań.
Delivery together with installation and commissioning of the process plant and preparation of thermal insulation on process lines.
Scope of work:
Buyer:
selected projects in the years 2007-2015
PROCESSING OF FRUIT AND VEGETABLES PLANT Mogielnica 2007
Manufacturing and installation of 6 tanks 1000m3
Scope of work:
selected projects in the years 2007-2015
Holvrieka Ido BV
Buyer:
PROCTER&GAMBLE POLSKA SP. Z O.O. Aleksandrów Łódzki 2007-2014
Procter & Gamble Polska Sp. z o.o.
Assembly, welding and installation of pipelines and hook up facilities, process plants and utility media.
CIPs and SKIDs
Scope of work:
Buyer:
selected projects in the years 2007-2015
LECH BROWAR WIELKOPOLSKI S.A.Poznań 2008
Holvrieka Ido BV
Assembly, welding, installation and insulation of 32 fermentation tanks V = 5500 hl
Scope of work:
Buyer:
selected projects in the years 2007-2015
MBEYA BREWERY (SAB MILLER)Tanzania 2009
Krones AG
Assembly, welding, CIP, filtration, fermentation, filling plants; Utility pipelines (steam, condensate, cooling water) thermal insulation. Turnkey project.
Scope of work:
Buyer:
selected projects in the years 2007-2015
MONDELEZ INTERNATIONALSkarbimierz 2009 - 2014
Cadbury WedelLine of: Crunchy, FCCW, Turkish, Double Decker, Picnic
Process hot water; design, manufacture, delivery, installation and commissioning of hot process water system 80°C on Crunchy line including fittings, placed on Skid frame, unloading and assembly of process equipment.
Design, manufacture, delivery, installation and commissioning of low temperature hot water exchangers (LTHW) including pipelines and fittings, supports for LTHW pipelines, access platforms and process media systems; unloading and assembly of process equipment.
Scope of work:
Buyer:
selected projects in the years 2007-2015
WATER TREATMENT STATION Bochnia 2009/2010
Veolia Water Systems Sp. z o.o.
Modernization, extension and installation works.
Scope of work:
Buyer:
selected projects in the years 2007-2015
WASTE WATER TREATMENT PLANT CZAJKAWarszawa 2009-2013
Veolia Water Systems Sp. z o.o.
Assembly of process plant. Prefabrication of the pipelines. Assembly of equipment, participation in commissioning.
STUOŚ-CZAJKA:Thermal Effluent Sediment Disposal Station: Documentation, prefabrication, delivery and assembly of ducts.Thermal protection insulation.
Scope of work:
Buyer:
selected projects in the years 2007-2015
FRUIT JUICES PRODUCTION PLANT WESERGOLD DODOWGermany 2010/2011
Manufacturing and installation of 8 tanks 1500m3
Scope of work:
selected projects in the years 2007-2015
Buyer:
Ziemann International GmbH
selected projects in the years 2007-2015
KASZTELAN BrewerySierpc 2013 - 2014
Buyer:
Krones Sp. z o.o.
Scope of work:
9 CCT Ø6800mm including walkway, ladder, connecting walkwayPremanufacture of elements of the tanksAssembly and welding of the tanksPressure testsDocumentation UDT / TUV
selected projects in the years 2007-2015
KASZTELAN Brewery - BrewhouseSierpc 2013 - 2014
Buyer:
Ziemann International GmbH
Scope of work:
Placing and installation of brewing vesselsAssembly of pumping systems, pipe bridges, piping,Assembly of ”dry part”Tests and start-up
UNILEVER BYDGOSZCZBydgoszcz 2013, 2014
GEA Polska S.A./ GEA PE United Kingdom
Process system for manufacturing and distribution of creams and gels:Skids and valve block prefabrication;Piping system;Prefabrication and assembly of CIP station with piping;Product transfer installation with recovery system (PIG stations).
Scope of work:
Buyer:
selected projects in the years 2007-2015
Catalysts factory BASFŚroda Śląska 2013-2015
MOSTOSTAL ZABRZE S.A.
Process installation for production of catalysts for a mobile NOx reduction systemTechnological and utilities installationsPremanufacture of the valve blocks;Premanufacture and assembly of the pipelinesBuilding and system worksConstruction and as-built documentation Start-up of the system
Project value:6.800.733,08 Euro
Scope of work:
Buyer:
selected projects in the years 2007-2015
Vreugdenhil Dairy Foods NederlandGörinchem 2014 - 2015
GEA Process Engineering Nederland BV & GEA Nu-Con Ltd
Process, technological and utilities installationsPremanufacture and TIG welding of the valve blocksPremanufacture of SKIDsPremanufacture and assembly of the pipelinesBuilding and system worksConstruction and as-built documentation Start-up of the system
Project value:2.488.771,02 Euro
Scope of work:
Buyer:
selected projects in the years 2007-2015
selected projects in the years 2007-2015
Royal Friesland CampinaBorculo 2014 - 2015
Buyer:
GEA Process Engineering Nederland BV, GEA Nu-Con LtdGEA France, GEA Denmark
Scope of work:
Process, technological and utilities installationsPremanufacture and welding of the valve blocksPremanufacture of SKIDsPremanufacture and assembly of the pipelines and service platformsConstruction and as-built documentation Start-up of the system
Project value:3.228.600,00 Euro
Paulaner GermanyMünich 2014 - 2015
KRONES AG
selected projects in the years 2007-2015
Buyer:
Scope of work:
Process, technological and utilities installationsPremanufacture and welding of the valve blocksPremanufacture of SKIDsPremanufacture and assembly of the pipelines and service platformsConstruction and as-built documentation Start-up of the system