Where We Are Now. Estimating Projects. Estimating The process of forecasting or approximating the time and cost of completing project (deliverables). The task of balancing expectations of stakeholders and need for control while the project is implemented. Types of Estimates - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: Where We Are Now](https://reader036.vdocuments.net/reader036/viewer/2022062400/56812c55550346895d90dd67/html5/thumbnails/1.jpg)
Estimating Project Times and Costs
CHAPTER FIVE
Student Version
Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved.
McGraw-Hill/Irwin
![Page 2: Where We Are Now](https://reader036.vdocuments.net/reader036/viewer/2022062400/56812c55550346895d90dd67/html5/thumbnails/2.jpg)
5–2
Where We Are NowWhere We Are Now
![Page 3: Where We Are Now](https://reader036.vdocuments.net/reader036/viewer/2022062400/56812c55550346895d90dd67/html5/thumbnails/3.jpg)
5–3
Estimating Projects Estimating Projects
• Estimating–The process of forecasting or approximating the time
and cost of completing project (deliverables).–The task of balancing expectations of stakeholders
and need for control while the project is implemented.• Types of Estimates
–Top-down (macro) estimates: analogy, group consensus, or mathematical relationships
–Bottom-up (micro) estimates: estimates of elements of the work breakdown structure
![Page 4: Where We Are Now](https://reader036.vdocuments.net/reader036/viewer/2022062400/56812c55550346895d90dd67/html5/thumbnails/4.jpg)
5–4
Why Estimating Time and Cost Are ImportantWhy Estimating Time and Cost Are Important
EXHIBIT 5.1
• To support good decisions.
• To schedule work.
• To determine how long the project should take and its cost.
• To determine whether the project is worth doing.
• To develop cash flow needs.
• To determine how well the project is progressing.
• To develop time-phased budgets and establish the project baseline.
![Page 5: Where We Are Now](https://reader036.vdocuments.net/reader036/viewer/2022062400/56812c55550346895d90dd67/html5/thumbnails/5.jpg)
5–5
Factors Influencing the Quality of EstimatesFactors Influencing the Quality of Estimates
Quality of Estimates
ProjectDuration
People
Project Structure and Organization
PaddingEstimates
OrganizationCulture
Other (Nonproject)
Factors
Planning Horizon
![Page 6: Where We Are Now](https://reader036.vdocuments.net/reader036/viewer/2022062400/56812c55550346895d90dd67/html5/thumbnails/6.jpg)
5–6
Estimating Guidelines for Times, Estimating Guidelines for Times, Costs, and ResourcesCosts, and Resources
1. Have people familiar with the tasks make the estimate.
2. Use several people to make estimates.
3. Base estimates on normal conditions, efficient methods, and a normal level of resources.
4. Use consistent time units in estimating task times.
5. Treat each task as independent, don’t aggregate.
6. Don’t make allowances for contingencies.
7. Add a risk assessment to avoid surprises to stakeholders.
![Page 7: Where We Are Now](https://reader036.vdocuments.net/reader036/viewer/2022062400/56812c55550346895d90dd67/html5/thumbnails/7.jpg)
5–7
Top-Down versus Bottom-Up EstimatingTop-Down versus Bottom-Up Estimating
• Top-Down Estimates–Are usually are derived from someone who uses
experience and/or information to determine the project duration and total cost.
–Are made by top managers who have little knowledge of the processes used to complete the project.
• Bottom-Up Approach–Can serve as a check on cost elements in the WBS
by rolling up the work packages and associated cost accounts to major deliverables at the work package level.
![Page 8: Where We Are Now](https://reader036.vdocuments.net/reader036/viewer/2022062400/56812c55550346895d90dd67/html5/thumbnails/8.jpg)
5–8
Top-Down versus Bottom-Up EstimatingTop-Down versus Bottom-Up Estimating
TABLE 5.1
Conditions for Preferring Top-Down or Bottom-up Time and Cost Estimates
Condition Macro Estimates Micro EstimatesStrategic decision making X Cost and time important XHigh uncertainty XInternal, small project XFixed-price contract XCustomer wants details XUnstable scope X
![Page 9: Where We Are Now](https://reader036.vdocuments.net/reader036/viewer/2022062400/56812c55550346895d90dd67/html5/thumbnails/9.jpg)
5–9
Estimating Projects: Preferred ApproachEstimating Projects: Preferred Approach
• Make rough top-down estimates.
• Develop the WBS/OBS.
• Make bottom-up estimates.
• Develop schedules and budgets.
• Reconcile differences between top-down and bottom-up estimates
![Page 10: Where We Are Now](https://reader036.vdocuments.net/reader036/viewer/2022062400/56812c55550346895d90dd67/html5/thumbnails/10.jpg)
5–10
Top-Down Approaches for Estimating Top-Down Approaches for Estimating Project Times and CostsProject Times and Costs
• Consensus methods
• Ratio methods
• Apportion method
• Function point methods for software and system projects
• Learning curves
Project EstimateTimesCosts
![Page 11: Where We Are Now](https://reader036.vdocuments.net/reader036/viewer/2022062400/56812c55550346895d90dd67/html5/thumbnails/11.jpg)
Apportion Method of Allocating Project Apportion Method of Allocating Project Costs Using the Work Breakdown Costs Using the Work Breakdown
StructureStructure
FIGURE 5.1
![Page 12: Where We Are Now](https://reader036.vdocuments.net/reader036/viewer/2022062400/56812c55550346895d90dd67/html5/thumbnails/12.jpg)
Simplified Basic Function Point Count Simplified Basic Function Point Count Process for a Prospective Project or Process for a Prospective Project or
DeliverableDeliverable
TABLE 5.2
![Page 13: Where We Are Now](https://reader036.vdocuments.net/reader036/viewer/2022062400/56812c55550346895d90dd67/html5/thumbnails/13.jpg)
Example:Example:Function Point Count MethodFunction Point Count Method
TABLE 5.3
![Page 14: Where We Are Now](https://reader036.vdocuments.net/reader036/viewer/2022062400/56812c55550346895d90dd67/html5/thumbnails/14.jpg)
5–14
Bottom-Up Approaches for Estimating Bottom-Up Approaches for Estimating Project Times and CostsProject Times and Costs
• Template methods
• Parametric procedures applied to specific tasks
• Range estimates for the WBS work packages
• Phase estimating: A hybrid
![Page 15: Where We Are Now](https://reader036.vdocuments.net/reader036/viewer/2022062400/56812c55550346895d90dd67/html5/thumbnails/15.jpg)
SB45 Support Cost Estimate SB45 Support Cost Estimate WorksheetWorksheet
FIGURE 5.2
![Page 16: Where We Are Now](https://reader036.vdocuments.net/reader036/viewer/2022062400/56812c55550346895d90dd67/html5/thumbnails/16.jpg)
Phase Estimating overPhase Estimating overProduct Life CycleProduct Life Cycle
FIGURE 5.3
![Page 17: Where We Are Now](https://reader036.vdocuments.net/reader036/viewer/2022062400/56812c55550346895d90dd67/html5/thumbnails/17.jpg)
5–17
Level of DetailLevel of Detail
• Level of detail is different for different levels of management.
• Level of detail in the WBS varies with the complexity of the project.
• Excessive detail is costly.–Fosters a focus on departmental outcomes–Creates unproductive paperwork
• Insufficient detail is costly.–Lack of focus on goals–Wasted effort on nonessential activities
![Page 18: Where We Are Now](https://reader036.vdocuments.net/reader036/viewer/2022062400/56812c55550346895d90dd67/html5/thumbnails/18.jpg)
5–18
Types of CostsTypes of Costs
• Direct Costs–Costs that are clearly chargeable
to a specific work package.•Labor, materials, equipment, and other
• Direct (Project) Overhead Costs–Costs incurred that are directly tied to an identifiable
project deliverable or work package.•Salary, rents, supplies, specialized machinery
• General and Administrative Overhead Costs–Organization costs indirectly linked to a specific
package that are apportioned to the project
![Page 19: Where We Are Now](https://reader036.vdocuments.net/reader036/viewer/2022062400/56812c55550346895d90dd67/html5/thumbnails/19.jpg)
Contract Bid Summary CostsContract Bid Summary Costs
FIGURE 5.6
Direct costs $80,000Direct overhead $20,000G&A overhead (20%) $20,000Profit (20%) $24,000Total bid $144,000
![Page 20: Where We Are Now](https://reader036.vdocuments.net/reader036/viewer/2022062400/56812c55550346895d90dd67/html5/thumbnails/20.jpg)
Three Views of CostThree Views of Cost
FIGURE 5.5
![Page 21: Where We Are Now](https://reader036.vdocuments.net/reader036/viewer/2022062400/56812c55550346895d90dd67/html5/thumbnails/21.jpg)
5–21
Refining EstimatesRefining Estimates
• Reasons for Adjusting Estimates–Interaction costs are hidden in estimates.–Normal conditions do not apply.–Things go wrong on projects.–Changes in project scope and plans.
• Adjusting Estimates–Time and cost estimates of specific activities are
adjusted as the risks, resources, and situation particulars become more clearly defined.
![Page 22: Where We Are Now](https://reader036.vdocuments.net/reader036/viewer/2022062400/56812c55550346895d90dd67/html5/thumbnails/22.jpg)
Refining Estimates (cont’d)Refining Estimates (cont’d)
• Contingency Funds and Time Buffers–Are created independently to offset uncertainty–Reduce the likelihood of cost and completion time overruns for a project
–Can be added to the overall project or to specific activities or work packages
–Can be determined from previous similar projects• Changing Baseline Schedule and Budget
–Unforeseen events may dictate a reformulation of the budget and schedule.
![Page 23: Where We Are Now](https://reader036.vdocuments.net/reader036/viewer/2022062400/56812c55550346895d90dd67/html5/thumbnails/23.jpg)
Creating a Database for EstimatingCreating a Database for Estimating
FIGURE 5.7
Estimating Database Templates
![Page 24: Where We Are Now](https://reader036.vdocuments.net/reader036/viewer/2022062400/56812c55550346895d90dd67/html5/thumbnails/24.jpg)
5–24
Key TermsKey Terms
Apportionment methodsBottom-up estimatesContingency fundsDelphi methodDirect costsFunction pointsLearning curves
Overhead costsPadding estimatesPhase estimatingRange estimatingRatio methodsTemplate methodTime and cost databases