wind-related transmission/distribution technologies & needs

31
College of Engineering Discovery with Purpose www.engineering.iastate.edu June 17, 2011 Wind-Related Transmission/Distribu tion Technologies & Needs James McCalley ([email protected] ) REU Short Course on Wind Energy Science, Engineering and Policy

Upload: milly

Post on 20-Mar-2016

35 views

Category:

Documents


1 download

DESCRIPTION

Wind-Related Transmission/Distribution Technologies & Needs. June 17, 2011. James McCalley ( [email protected] ) REU Short Course on Wind Energy Science, Engineering and Policy. Windfarm Electrical System:. LEVEL 2. LEVEL 3. LEVEL 1. LEVEL 2. LEVEL 1. MULTI-FARM COLLECTION NETWORK. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Wind-Related Transmission/Distribution Technologies & Needs

College of Engineering

Discovery with Purpose www.engineering.iastate.edu

June 17, 2011

Wind-Related Transmission/Distribution

Technologies & NeedsJames McCalley ([email protected])

REU Short Course on Wind Energy Science, Engineering and Policy

Page 2: Wind-Related Transmission/Distribution Technologies & Needs

Windfarm Electrical System:

2

Page 3: Wind-Related Transmission/Distribution Technologies & Needs

Three transmission/distribution related issues:

3

Windfarm

Windfarm

Windfarm

Windfarm

Windfarm

Windfarm

Windfarm

Windfarm

MULTI-FARM COLLECTION

NETWORK

MULTI-FARM COLLECTION

NETWORK

LEVEL 1 LEVEL 2 LEVEL 3 LEVEL 2 LEVEL 1

Level 1, Multi-turbine collection network: Interconnect turbines to transmission sub.Level 2, Multi-farm collection network: Interconnect windfarms to backbone trans.Level 3, Backbone transmission: Transport energy from resources to load centers.

Page 4: Wind-Related Transmission/Distribution Technologies & Needs

Multi-turbine collector network• Common voltage levels are 13.8, 25, 34.5 kV• Three-phase, always underground, cable

4

POI or connection to the grid Collector System

Station

Feeders and Laterals (overhead and/or underground)

Individual WTGs

Interconnection Transmission Line

Page 5: Wind-Related Transmission/Distribution Technologies & Needs

Multi-turbine collector network

Page 6: Wind-Related Transmission/Distribution Technologies & Needs

Multi-turbine collector network

In the midwest, cutting drain tiles is a common problem that windfarm developers must contend with.

Page 7: Wind-Related Transmission/Distribution Technologies & Needs

Level 2: Multifarm collection networks

Wind farms site where the wind resources are good, close to existing transmission that has residual capacity. If capacity is insufficient, one of the below happens:•Wind farm is not built;•Special protection schemes are used;•Incremental transmission upgrades are made; •Extensive transmission upgrades are implemented.

7

OK when considering 3.7 GW wind out of 10GW total.Not OK when considering 20 GW wind out of 30GW total.There has not been much intentionality at level 2…. yet.But we need to consider Level 2 Designs, before wind grows much more.

Page 8: Wind-Related Transmission/Distribution Technologies & Needs

Level 2: Multifarm collection networks - Examples

8

• Depends on backbone transmission (may very well change….)

Page 9: Wind-Related Transmission/Distribution Technologies & Needs

The backbone transmission issue: Where are the people?

…But where are the resources?

9

Page 10: Wind-Related Transmission/Distribution Technologies & Needs

NUCLEAR

Long-term National Planning & Resource Integration

GEOTHERMALSOLAR

WindBIOMASS

CLEAN-FOSSIL

Where, when, & how to interconnect?

10

Page 11: Wind-Related Transmission/Distribution Technologies & Needs

Questions on backbone transmission• Is transmission expensive?• Who pays for transmission? Who permits it?• Are there choices for transmission technologies?• Have we ever had a national transmission plan?• Why do many people feel “NIMBY” for transmission?• Why not just put it underground?• Transmission raises cost of energy at sending end and reduces it at receiving end why does sending end generally like it & receiving end often does not?• If a national transmission superhighway lowers average cost of energy for the nation, why not build it?

11

Page 12: Wind-Related Transmission/Distribution Technologies & Needs

Transmission TechnologiesHVAC: 69kV, 115kV, 138kV, 161kV and 230kV

EHVAC: 345kV, 500kV, 765kV Long distance must be overhead due to high line charging.

HVDC: 500kV, 600kV, 800kV, Today, all high-capacity HVDC is thyristor-based

Overhead DC lines less expensive than AC lines but higher termination investment cost. 400 miles is approximate breakover distance. Intermediate terminals (on-off ramps) are expensive. Use of IGBT-based voltage-source converters (lite) alleviates this but only at lower capacities.

Long-distance HVDC underground bulk transmission is possible.

Underground Superconducting Pipe

Regional Transmission: HSIL, GIL, HVDC-lite

12

Page 13: Wind-Related Transmission/Distribution Technologies & Needs

Transmission Technologies

Fig. 4: Cost comparisons between HVDC and EHVAC for 6000 MW of capacity

13

Page 14: Wind-Related Transmission/Distribution Technologies & Needs

Superconducting pipe

14

Page 15: Wind-Related Transmission/Distribution Technologies & Needs

Tres Amigas

15

Page 16: Wind-Related Transmission/Distribution Technologies & Needs

American Superconductor

16

Page 17: Wind-Related Transmission/Distribution Technologies & Needs

AEP Conceptual 765--kV overlay for wind integration

17

Page 18: Wind-Related Transmission/Distribution Technologies & Needs

18

Page 19: Wind-Related Transmission/Distribution Technologies & Needs

20%StrongWest

20%Distributed

20%StrongOffshore

30%

19

Page 20: Wind-Related Transmission/Distribution Technologies & Needs

20

Page 21: Wind-Related Transmission/Distribution Technologies & Needs

30%20%StrongWest

20%Distributed

20%StrongOffshoreMost

Economical+ RPS

21

Page 22: Wind-Related Transmission/Distribution Technologies & Needs

22

Page 23: Wind-Related Transmission/Distribution Technologies & Needs

Criteria for a national overlay design

• Facilitate low-carbon resource development• Move generation to load centers• Low total costs (investment + production)• Reduce overall national energy costs• Avoid “pockets” of high energy costs• Minimal environmental impact• Resilient to large-scale disruptions• Flexible for adaptation to future infrastructure

23

Page 24: Wind-Related Transmission/Distribution Technologies & Needs

Green Power Express

24

Cost: $10 billionVoltage: 765 kVMileage: 3000 milesWho: ITCProposed date: 2020Capacity: 12000 MW

Page 25: Wind-Related Transmission/Distribution Technologies & Needs

SPP EHV Overlay - Ultimate

25

Page 26: Wind-Related Transmission/Distribution Technologies & Needs

ERCOT - CREZ

26

Page 27: Wind-Related Transmission/Distribution Technologies & Needs

PacifiCorp Gateway Project

27

Page 28: Wind-Related Transmission/Distribution Technologies & Needs

NREL’s Eastern Wind Integration and Transmission

28

Page 29: Wind-Related Transmission/Distribution Technologies & Needs

BackgroundA Brief Introduction of Our Proposed Study Process:1. Determine 40 years’ generation and load portfolio using NETPLAN.

Transmission capacities = inf. 2. Identify source/sink nodes under certain criteria3. Obtain an initial transmission candidate topology (graph theory)

Get a min cost spanning tree connect all nodes; Apply “reliability” constraints like N-1 security and rule of 3

4. Optimization. Determine capacities. Discard those arcs with no investment. Can coordinate with the first step

5. Transmission technology selection.6. Production cost simulation7. Power flow, stability studies, etc.

Page 30: Wind-Related Transmission/Distribution Technologies & Needs

Identifying Futures

Key drivers Examples

30

Page 31: Wind-Related Transmission/Distribution Technologies & Needs

ReferencesJ. McCalley, W. Jewell, T. Mount and D. Osborn, “Technologies, Tools, and Procedures for Energy Systems Planning at the National Level,” to appear in Power and Energy Magazine.

Slides from Midwest ISO Engineering Presentations in EE 552 (2008 and 2010).McCalley lecture notes from EE 552.

N. Reddy, “Superconductor Electricity Pipelines: A compelling solution to today’s long-haul transmission challenges,” Right of Way, May/June, 2010, pp. 26-33, available at www.irwaonline.org/EWEB/upload/may_web_SuperConductor.pdf.

R. Dunlop, R. Gutman, and P. Marchenko, “Analytical Development of Loadability Characteristics for EHV and UHV Transmission Lines,” IEEE Transactions on Power Apparatus and Systems, Vol. PAS-98, No. 2, March/April 1979.

R. Gutman, E. Wilcox, 21st Century Transmission Planning: The Intersection of Engineering, Economics, and Environment,” CIGRE, 2009, Calgary.

J. Fleeman, R. Gutman, M. Heyeck, M. Bahrman, and B. Normark, “EHV AC and HVDC Transmission Working Together to Integrate Renewable Power,” CIGRE Paper 978-2-85873-080-3, 2009.

31