Work Breakdown Structure
Kathy S. Schwaig
What is a Work Breakdown Structure (WBS)?
A WBS is a logical hierarchy of work packages involved in a projectA WBS is an essential tool in the project planning processOnce the project charter has been created, the project must be scoped out in more detail
Purpose of a WBSA WBS helps to define the work required for the project and to break it into manageable pieces called work packages A good WBS can help in the development of schedules, budgets, and resource requirementsThe WBS is a useful tool for identification of activities and assignment of responsibilities
Possible Ways to Organize Work Breakdown Structures
By project phasesBy project componentsBy functional areasBy types of workBy resource types
Work PackagesA work package is a deliverable or product at the lowest level of the WBSAs a general rule, each work package should represent 80 hours (or less) of effortEach work package should have a clearly identified person who is responsible for it This individual should . . .
Be a member of the project teamBe responsible for the successful completion of the work package
Requirements Definition System Development System Testing DocumentationSystem Design
Equipment History Module
Spare Parts Inventory Control Module
Data Dictionary Development
Screen & Report Design
Logic Diagrams Code Development Module Testing
Work Order Control Module
Development & ImplementationMaintenance Management Information System
Example WBS (Inverted Tree Structure)Example WBS (Inverted Tree Structure)
Example WBS(Indented List Format)
Development & Implementation Maintenance Management Information SystemRequirements DefinitionSystem DesignSystem Development
Equipment History ModuleWork Order Control Module
Data Dictionary DevelopmentScreen & Report DesignLogic DiagramsCode Development
Module TestingSpare Parts Inventory Control Module
System TestingDocumentationImplementation
Identifying Activities
Look for any time-consuming element with identifiable beginning and ending pointsActivities are at the lowest level of the WBSMost activities should produce an identifiable deliverableLong-duration activities (>1 month) should be sub-divided
Guidelines for Developing a WBS
Develop WBS from the top down; not bottom upDon’t exceed about 5 levels in a WBSIdentify work package manager for each WBS itemCheck to make sure that the WBS is consistent with the project charter