Work Plan for Model Development at NCTCOG
Arash Mirzaei, P.E.
AMPO Travel Modeling Work GroupSt. Louis, MOJune 11, 2007
2Model Development Group
Outline
Our Current Work • Users• Requests• March 2007 status of modeling system
Our Future Plans• Models• Databases• Tools• Surveys• Schedule and Resources (CompletePlan)
3Model Development Group
Model Development Group (MDG)Current Work
4Model Development Group
Modeling Services UsersInternal Customers
Air Quality Planning and Operations GroupTransportation Planning GroupCongestion Management, Safety and Security GroupDemographics and Goods Management Group Transportation Improvement Program (TIP)Regional Transportation Council and Committees
External CustomersLocal Governments (Cities, Counties)Transportation & Land Use ConsultantsTransit Agencies (DART, T, DCTA)TxDOTNTTA
5Model Development Group
Modeling Services Requests1. Land use/Demographic
Forecast integrated with economic and transportation
2. Sustainable Development/TOD3. Parking Study4. Truck Modeling and Goods
Movement Analyses in Planning
5. HOV Analysis6. Toll Revenue Analysis7. Congestion Pricing8. EJ Analysis9. Emission Analysis
10. MSAT and Noise Analysis11. TCM Credits for Conformity
Analysis12. Transit Planning, Ridership
Forecast 13. Transit Revenue14. New Starts15. Thoroughfare Planning16. Emergency Planning using
Transportation System17. Evacuation Planning18. Ability to Expand Detail
Modeling
Not currently addressed in the model (6)Partially addressed in the model (12)
6Model Development Group
The Travel ModelCovers 5000 sq. mile with 4874 zonesContains 5 full urban counties of 9 non-attainment countiesLevel of roadway coding is up to local streetsAll transit networks are in the modelAll types of facilities are coded in maximum analytical detail that a 4-step model supportsThe goal of the model performance is that no sub-area analysis with the same modeling paradigm can improve the overall results. ONE model for the MPA.Capable of HOV, Toll, managed lane, and transit analysesHas three time periods Has air port and truck componentsSmoothly linked to AQ applicationsSupported by version maintenanceSupported by file management and archiving system
The Travel Model (TM) is multi level, multi class, and multi purpose
7Model Development Group
March 2007 StatusTools
TM is very stable in TransCAD 4.8.Transit Coding Tools are complete and stable.Roadway QA Tools are complete and stable.Traditional Report Writers (Perf, Transit, LOS, ...) are complete.File Management system is complete and reliable.
DocumentationTM Description Document is complete.Validation 1999 Reports are complete.
TrainingTraining for use of TM is complete.Documents and Training presentations are available on Intranet.MUG meetings are regularly scheduled and have high interest.
8Model Development Group
Hours Spent on Projects - Oct ‘06 to March ‘07
Project Type % Hours Spent
Long-Term Projects of MDG 38%
Short Term Projects of MDG 33%
Short Term Projects for Other Groups
12%
Administrative 17%
9Model Development Group
Long-Term Projects of MDG (38%)Training & Model Users Group Workshops (MUG)Model SupportFile ManagementTransCAD Lab HardwareProfessional DevelopmentDesign of Internet and Intranet sitesTeam Management
10Model Development Group
Short Term Projects: MDG (35%)Model Improvements
Model Diagnostic 2004Summit InclusionComparative ReportsAutomated Executive ReportsModeling Area Expansion Sensitivity TestingUE Traffic Assignment StabilityTOD Transit Model Development
Traffic Simulation
Model ImplementationTransition to TransCAD 5.0Re-batching the model
11Model Development Group
Short Term Projects: Other Groups (12%)Transit
DART Model Support DCTA New Start (Transit)DART Onboard Survey Support
Congestion ManagementICM ProjectPOD Locations
Demographics: Skims for Demographic 2040
TIP: Toll Revenue by County
12Model Development Group
Support for Management Activities (17%)AdministrativeCommitteesLeave (Holiday/Vacation/Sick)
13Model Development Group
Model Development Group (MDG)Goal: Models
14Model Development Group
Models NeededLand Use Model
Person Travel Model
Commercial Travel Model
Regional Travel Model to cover 12 counties
15Model Development Group
Land Use Model (LUM): FeaturesModel Features
Accepts control totals and policies for developmentsConsiders effect of Transportation Mode (e.g. Car Ownership)Sensitive to accessibility measures from travel model
Roadway (HOV, Toll, Managed)Transit (Bus, Rail, BRT, PNR)Bike/Pedestrian
Sensitive to Development PoliciesZoningTaxPricing
More TBD
16Model Development Group
Land Use Model: Input & OutputInput
Control Totals for Population and EmploymentTransportation NetworkLand AvailabilityDevelopment Policies
Output (In Large Zone Level)Population Employment# Households# FamiliesMedian IncomeMore TBD
17Model Development Group
Person Travel Model: FeaturesModel Features
Population Synthesis – Generates Households & Family Detail, Worker, Car OwnershipActivity/Trip GeneratorTime and Duration of ActivityMC & DC in individual levelDTA (Signals, Querying, ITS, Toll)Transit AssignmentTrip Data at Individual LevelEffect of accidentsSensitive to Operational DevicesCapable of demand management testingCompatible for traffic micro simulation for any sub-area
18Model Development Group
Person Travel Model: Input & OutputInput
LUM outputSmall Zone StructureTransportation Networks (Roadway, Truck, Rail, Transit, Bike/Ped)
Output Travel Activities of Individual Persons: (Vehicle Ownership, TOD, Mode, Purpose, Activity Duration, More TBD)Traffic Volume by class (income, vehicle class, TOD)LUM Inputs
19Model Development Group
Commercial Travel Model: FeaturesModel Features
Tour-basedGoods and Services DeliveryEffect of hubs and depots at Transfer StationsFleet AllocationsTBD
20Model Development Group
Commercial Travel Model: Input & OutputInput
LUM OutputSmall Zone StructureTransportation NetworksSAM (perhaps)
Output Travel Tours for TrucksTruck Volume (Lightweight, Heavy Truck, TBD)EI, IE, EE Tables
21Model Development Group
Operation of the ModelsFull Feature Model Run will run in order of days and produces the finest detail of the model output.Project level runs will be customized to run in shorter periods based on the required analysis.
For example, 20 class assignment is not needed for # of Lane Determination.
Computer hardware – A lab with distributed capabilities will be built for the model.Storage solution is already designed and scaleable.Sub-Area analysis of model is doable in all steps of the model.The model & network are compatible for sub-area traffic measures.
22Model Development Group
Work Plan for New Model CreationInitial Preparation
MDG conducts user and stakeholder meeting to determine the needs.MDG provides historical perspective of model application for guidance.MDG converts the needs to model features and structure.MDG performs investigation and conducts peer reviews to design the model framework.
Framework:MDG breaks the framework into model components with I/O that can be outsourced for development.Outsourcing of model components happens sequentially with significant overlap to limit the length of development.Different contracts for each component.
23Model Development Group
Work Plan for New Model Creation (con’t)MDG is responsible for connecting the components and creating a functional model.
Timeline (5 years time span)Surveys – 3 yearsModel Development – 4 years Reporting Tools, Application Interface, Diagnostic Reports – 1 year
24Model Development Group
Model Development Group (MDG)Goal: Databases
25Model Development Group
Databases Connected to the ModelRoadway Network – Fully rectified roadway network with signal location and ITS.
Coding process needs to ensure quality assurance.Coding should be done in database as soon as construction project plans are ready (master network).Coding environment should be 100% compatible and convenient to use with other components of Information Systems.
Transit Network – Fully rectified transit network with bus operation and schedule.
Inventory Data for each year needs to be kept in database.Coding System should be simplified in process.Fleet data needs to be kept as well.
26Model Development Group
Databases (con’t)TIP – GIS-based Network
Counts and Surveys – A coordinated effort for data collection and database management is highly needed.
For example, for every project that NCTCOG funds, data format should be already identified in RFP.
27Model Development Group
Model Development Group (MDG)Goal: Tools
28Model Development Group
Modeling Tools NeededRoadway– Coding Tools need major overhaul. Idea of master network seems doable.Transit– Major modification after master network implementation is necessary.Reporting – Models (LUM, PTM, CTM) need extensive reporting capabilities.Comparative – Necessary to capture different model runs’output efficiently.Diagnostic – Necessary to inform the analyst of odd model output and inputs.
29Model Development Group
Model Development Group (MDG)Goal: Surveys
30Model Development Group
Surveys NeededHousehold SurveyTransit Onboard SurveysExternal SurveyAirportWorkplaceParkingTime-of-Day CountsTime-of-Day SpeedsCommercial Vehicles
31Model Development Group
Survey Descriptions Household Survey in 2008 or 2009
It may feature market-based sampling to avoid new surveys for airport, transit, or other markets that the general survey normally under samples.Future model structures and needs are formally determined before the survey is done.How the survey is done is determined based on available technology.We may perform a low budget pilot test to test the new technology.Options are using TxDOT system, adding to NHTS Samples, and conducting our own.
32Model Development Group
Survey Descriptions (pg 2)Transit Onboard Surveys
DART 2007 (funded through UPWP and currently in early stages).FWTA 2008 (funded through UPWP).DCTA.
External SurveyTxDOT 12 County 2006 is done, but needs to be checked for adequacy for mobility.
AirportsDepends on Household survey method.
WorkplaceThe need should be investigated within the new model structure.
Parking Inventory DataSpots available and use by TOD.
33Model Development Group
Surveys Descriptions (pg 3)Time-of-day counts
Same year as Household survey.Locations should be identified as model framework is designed.Classification of Vehicles.After first major data collection, annual surveys need to be scheduled for smaller samples.
Time-of-day SpeedsSame as Counts.
Commercial Vehicles
34Model Development Group
The Future Plan: CompletePlan
35Model Development Group
Future Plan (CompletePlan)CompletePlan is the fastest possible plan.
Duration: 5.5 years (2007 to 2013)
RequirementResources are allocated with no restrictions on budget.
What is IncludedCost and time estimates for major items.A complete working model plan.Documentation
What is Not IncludedTrainingHardware
36Model Development Group
CompletePlan: Cost Summary
Cost (for 5.5 yr) % Total Avg. Annual CostTotal $12,442,000 100% $2,262,000
Staff*Outsource
Do NothingPlan Addition
$5,642,000$6,800,000
$1,026,000
$2,939,000
45%55%
24%
$1,236,000
$9,503,000 76%$534,000
$1,728,000
*Staff cost is based on $67.5/hour including 1.33 OH
37Model Development Group
CompletePlan: Cost Breakdown
(in Thousands) Outsource Staff TotalSurvey $4,550 $809 $5,359Model DevelopmentOngoing ActivitiesTotal
$5,372$3,122$2,250- $1,707
$6,800 $5,638$1,707
$12,438
38Model Development Group
Survey Cost Breakdown
(in Thousands) Outsource Staff TotalHousehold $2,000 $315 $2,315DART Onboard $350 $35 $385FWTA & DCTA Onboard $400 $73 $473Airports $300 $88 $388Workplace $300 $88 $388Parking $200 $70 $270Count & Speed $500 $70 $570Commercial VehicleSurvey Total
$70$500$4,550 $809
$570$5,359
39Model Development Group
Model Development Cost Breakdown
(in Thousands) Outsource Staff TotalShort Term - $1,123 $1,123Land Use $1,000 $597 $1,597Framework - $105 $105Population Synthesis $250 $105 $355Activity Based Model $600 $211 $811Commercial Veh. Model $400 $140 $540Dynamic Traffic Assign. - $281 $281Model IntegrationModel Dev. Total
$560-$2,250 $3,122
$560$5,372
40Model Development Group
Ongoing Activities Cost Breakdown
(in Thousands) Outsource Staff TotalProj. for Other Groups - $290 $290Support & MgmtOngoing Act. Total
$1,417-- $1,707
$1,417$1,707
41Model Development Group
CompletePlan: Staff Manpower Summary
*Staff cost is based on $67.5/hour including 1.33 OH
Cost (5.5 yr)* % Total Avg. Annual Cost
Model Related
Model Support
Outsource QA
OtherTOTAL $5,642,000 100% $1,027,000
$ 451,00041%$2,475,000
$1,716,000 $ 312,000
$1,161,000
29%
20% $ 211,000
10% $ 53,000$ 290,000
Manpower Avg. Annual Manpower
Person Hour
Person Year
83,580
40.1
15,200
7.3