Working with State and Federal Regulatory and Land Management Agencies Navajo Nation Environmental Protection Agency. Navajo Generating Station (NGS) BART Process. U.S.BOR =24.3%, SRP = 21.7%, LADWP = 21.2% , APS = 14%, NPC = 11.3%, TEP = 7.5%. Unit 1, 2 and 3 = 750 MW each. - PowerPoint PPT PresentationTRANSCRIPT
Working with State and Federal Regulatory and Land Management
Agencies
Navajo Nation Environmental Protection Agency
Navajo Generating Station (NGS) BART Process
Unit 1, 2 and 3 = 750 MW each
U.S.BOR =24.3%, SRP = 21.7%, LADWP = 21.2% , APS = 14%, NPC = 11.3%, TEP = 7.5%
2011
Installation Period Required if SCR is required in this BART
NGS Site LeaseTermination(12/23/19)
3 3 32 2 21 1 1
Lease Negotiations and Approvals
(12/31/11)
NEPA Process(Comp - 12/31/17)
2nd SIP/FIP update for RHR is
due in 2018
SCR Design and installation
Duration
Legal Challenges(2 years ?)
2-04-11 3NGS Owners Initial Proposal - GDReeves
NGS Study
• Evaluate technical, economic and legal feasibility of options • DOI coordinate the study with DOE
– Bureau of Reclamation contract with NREL• Stakeholder Involvement
DOI, NGS Owners, CAWCD, Navajo Nation,Hopi Tribe, CAP water using Indian tribes, Conservation ‐
Groups and other interested NGOs