world bank documentdocuments.worldbank.org/curated/en/827271468031744717/...2 enhancing capacity...
TRANSCRIPT
Document of
The World Bank
FOR OFFICIAL USE ONLY
Report No: RES21214
RESTRUCTURING PAPER
ON A
PROPOSED PROJECT RESTRUCTURING
OF
GHANA STATISTICS DEVELOPMENT PROJECT
IDA CREDIT NUMBER 50100
AND
SRF CF GRANT TF 10425
AUGUST 25, 2011
TO THE
REPUBLIC OF GHANA
MARCH 22, 2016
Poverty and Equity Global Practice
AFCW1
Africa Region
This document has a restricted distribution and may be used by recipients only in the performance of their
official duties. Its contents may not otherwise be disclosed without World Bank authorization.
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
2
ABBREVIATIONS AND ACRONYMS
CPI Consumer Price Index DP Development Partner or Data Processing F&A Finance and Administration GAS Ghana Audit Service
GDDS General Data Dissemination System GDP Gross Domestic Product GoG Government of Ghana GSDP Ghana Statistics Development Plan GSGDA Ghana Shared Growth and Development Agenda GSS Ghana Statistical Service ICT Information and Communication Technology IDA International Development Association IT Information Technology MDA Ministries, Departments and Agencies M&E Monitoring and Evaluation MESW Ministry of Employment and Social Welfare MMDA Metropolitan/Municipal/District Assemblies MOC Ministry of Communication MOE Ministry of Education MOFEP Ministry of Finance and Economic Planning MOFA Ministry of Food and Agriculture MOH Ministry of Health MLNR Ministry of Lands and Natural Resources MOTI Ministry of Trade, and Industry MOWAC Ministry of Women and Children Affairs NITA NSDS
National Information Technology Agency National Strategy for the Development of Statistics
PAD Project Appraisal Document PDMG Program Development and Management Group PDO Project Development Objectives PIM Project Implementation Manual RRSF Reference Regional Strategic Framework SC Steering Committee SRF-CF Statistics for Results Facility Catalytic Fund
Regional Vice President: Makhtar Diop
Country Director:
Senior Global Practice Director:
Henry G. R. Kerali
Ana L Revenga
Practice Manager/Manager: Pablo Fajnzylber
Task Team Leader
Co-Task Team Leader::
Smile Kwawukume
Abdoullahi Beidou
3
GHANA
Ghana Statistics Development Program
CONTENTS
A. SUMMARY 9
B. PROJECT STATUS 9
C. PROPOSED CHANGES 11
ANNEX 1: RESULTS FRAMEWORK AND MONITORING 16
4
DATA SHEET
Ghana
Ghana Statistics Development Program (P118858)
AFRICA
Poverty and Equity
Report No: RES21214
Basic Information
Project ID: P118858 Lending Instrument: Specific Investment Loan
Regional Vice President: Makhtar Diop Original EA Category: Not Required (C)
Country Director: Henry G. R. Kerali Current EA Category: Not Required (C)
Senior Global Practice
Director: Ana L. Revenga Original Approval Date: 25-Aug-2011
Practice
Manager/Manager: Pablo Fajnzylber Current Closing Date: 31-Aug-2016
Team Leader(s):
Smile
Kwawukume,Abdoullahi
Beidou
Borrower: Ministry of Finance
Responsible
Agency: Ghana Statistical Service,
Restructuring Type
Form Type: Full Restructuring Paper Decision Authority: Country Director Approval
Restructuring
Level:
Level 2
Financing ( as of 18-Mar-2016 )
Key Dates
Project Ln/Cr/TF Status Approval
Date Signing Date
Effectiveness
Date
Original
Closing Date
Revised
Closing Date
P118858 IDA-50100 Effective 25-Aug-2011 27-Feb-2014 28-Apr-2014 31-Aug-2016 31-Aug-2016
P118858 TF-10425 Effective 27-Feb-2014 27-Feb-2014 28-Apr-2014 31-Aug-2016 31-Aug-2016
Disbursements (in Millions)
Project Ln/Cr/TF Status Currency Original Revised Cancelle
d
Disburse
d
Undisbur
sed
%
Disburse
d
P118858 IDA-50100 Effective USD 30.00 30.00 0.00 16.76 10.17 56
P118858 TF-10425 Effective USD 10.00 10.00 0.00 8.94 1.06 89
5
Policy Waivers
Does the project depart from the CAS/CPF in content or in other significant
respects? Yes [ ] No [ X ]
Does the project require any policy waiver(s)? Yes [ ] No [ X ]
A. Summary of Proposed Changes
The project was approved by the Board in August 2011 and to be implemented in 5 years. However, the
project implementation was delayed as a result of a long delay by the Borrower's legislature to approve the
project documents. Legislative approval was later obtained in February 2014 and the project was declared
effective in April 2014. The project thus lost over two years of implementation. The proposed changes are;
(i) to extend the closing date of the IDA Credit from the current August 31, 2016 to June 30, 2018, and
also extend the SRF TF from the current closing date of August 31, 2016 to June 30, 2017 as the parent
SRF TF will close by December 31, 2017, (ii) reallocation of funds within project components, and (iii)
revision of the results framework.
Change in Implementing Agency Yes [ ] No [ X ]
Change in Project's Development Objectives Yes [ ] No [ X ]
Change in Results Framework Yes [ X ] No [ ]
Change in Safeguard Policies Triggered Yes [ ] No [ X ]
Change of EA category Yes [ ] No [ X ]
Other Changes to Safeguards Yes [ ] No [ X ]
Change in Legal Covenants Yes [ ] No [ X ]
Change in Loan Closing Date(s) Yes [ X ] No [ ]
Cancellations Proposed Yes [ ] No [ X ]
Change to Financing Plan Yes [ ] No [ X ]
Change in Disbursement Arrangements Yes [ ] No [ X ]
Reallocation between Disbursement Categories Yes [ X ] No [ ]
Change in Disbursement Estimates Yes [ X ] No [ ]
Change to Components and Cost Yes [ X ] No [ ]
Change in Institutional Arrangements Yes [ ] No [ X ]
Change in Financial Management Yes [ ] No [ X ]
Change in Procurement Yes [ ] No [ X ]
Change in Implementation Schedule Yes [ X ] No [ ]
Other Change(s) Yes [ ] No [ X ]
Appraisal Summary Change in Economic and Financial Analysis Yes [ ] No [ X ]
Appraisal Summary Change in Technical Analysis Yes [ ] No [ X ]
Appraisal Summary Change in Social Analysis Yes [ ] No [ X ]
Appraisal Summary Change in Environmental Analysis Yes [ ] No [ X ]
Appraisal Summary Change in Risk Assessment Yes [ ] No [ X ]
B. Project Status
6
Project implementation is significantly advanced and the project is on track to meet its development
objective if the extension is granted. Implementation progress for the GSDP is rated Satisfactory
following the latest supervision mission in December 2015. A new organizational structure has been
adopted for GSS which seeks to make the GSS leaner, and efficient. Some selected staff have been trained
in research methodology and report writing, survey methods and data management. Other staff members
have been trained in data analysis software SPSS/STATA whilst others had undergone training in different
demographic analysis software programs. Field trainings were also organized for enumerators in labor
force statistics and the integrated business enterprise surveys. A post census cartographic mapping has
been initiated with the aim of updating the enumeration area (EA) information established during the 2010
Population and Housing Census (PHC). The first phase of the Integrated Business Establishment Surveys
(IBES) has been completed and the second phase is currently underway. The Ministry of Education (MoE)
has been supported to carry out the 2014/2015 school census as part of the part project. The report has
since been released. The Ministry of Health (MoH) undertook a survey on the causes of the maternal
mortality rates in the country and a report has been produced. The Births and Deaths Registry has
undertaken the entry of over 200,000 as backlog for the period 2009-2012. A number of statistical reports
have been disseminated.
During the last mission, in December 2015, project implementation progress was rated “Satisfactory”.
C. Proposed Changes
Development Objectives/Results
Project Development Objectives
Original PDO
To strengthen the National Statistical System in the production and dissemination of timely and robust
statistics relevant for evidence-based policy-making and other uses
Change in Project's Development Objectives
Change in Results Framework
Explanation:
The targets of some of the indicators would be changed to accommodate the two year delay in the
implementation of the project. In addition, some of the targets would be changed since the baseline values
that were obtained after the project was prepared are higher than some of the initial targets. One PDO
indicator was dropped since a survey plan was not available. An intermediate indicator has been elevated
to a PDO indicator.
Financing
Change in Loan Closing Date(s)
Explanation:
The Restructuring Paper proposes a change in the closing date from the current August 31, 2016 to a later
date of June 30, 2018 for the IDA Credit and to a later date of June 30, 2017 for the SRF-CF. This request
has been necessitated by the late approval of the project by the legislature and the subsequent late
declaration of effectiveness in April 2014. The proposed new closing date will increase the duration of the
project to four years. The change also involves reallocation of funds within the categories and the revision
of some of the indicators.
Ln/Cr/T
F Status
Original Closing
Date
Current Closing
Date
Proposed Closing
Date
Previous Closing
Date(s)
7
IDA-
50100 Effective 31-Aug-2016 31-Aug-2016 30-Jun-2018 31-Aug-2016
TF-
10425 Effective 31-Aug-2016 31-Aug-2016 30-Jun-2017 31-Aug-2016
Reallocations
Explanation:
The cost of severance payment has gone down significantly because most of the staff were transferred to
sub-national governments. As a result, funds have been added to data production under category 1. With
increased data production to be undertaken, it is foreseen to have more operational expenses hence
Category 3 has increased slightly.
Ln/Cr/TF Currency Current Category of
Expenditure Allocation
Disbursement %
(Type Total)
Current Proposed Current Proposed
TF-10425 USD Gds, CS, NCS, TRNPrts
A.1, B,C & D 10,000,000.00 10,000,000.00 33.00 33.00
Designated Account 0.00 0.00 0.00 0.00
Total: 10,000,000.00 10,000,000.00
IDA-50100 XDR Gds, CS, NCS, TRNPrts
A.1, B,C & D 12,400,000.00 17,017,057.00 67.00 67.00
Severance Pymt under
comp A.2 4,100,000.00 846,943.00 100.00 100.00
Operating Costs under
part D 800,000.00 936,000.00 100.00 100.00
UNALLOCATED 1,500,000.00 0.00 0.00 0.00
Designated Account 0.00 0.00 0.00 0.00
Total: 18,800,000.00 18,800,000.00
Disbursement Estimates
Change in Disbursement Estimates
Explanation:
Annual disbursement estimates have been adjusted to reflect current disbursement status and the extension
of the project closing date. Disbursement is expected to continue in 2017 and 2018 because of the
proposed extension of the closing date.
Fiscal Year Current (USD) Proposed (USD)
2012 5,670,000.00 0.00
2013 12,540,000.00 0.00
2014 3,690,000.00 0.00
2015 4,740,000.00 7,200,000.00
2016 2,960,000.00 7,100,000.00
2017 400,000.00 8,200,000.00
8
2018 0.00 4,850,000.00
Total 30,000,000.00 27,350,0001
Components
Change to Components and Cost
Explanation:
Component 1: The cost for this component will be reduced since the number of staff undergoing the
buyout program has reduced significantly to the originally envisioned up to 300 to about 60.
Component 2. More funds would be allocated to this component to enable the completion of the second
phase of the Integrated Business Enterprise Survey.
Component 3. More data production surveys and activities would be undertaken as part of this component.
These include annual labor force surveys (LFS), High frequency poverty data; Renovation of the
Consumer Price Index, including the definition of a new base year; GDP rebasing exercise to integrate new
improved data sources; Production of Building Cost Index; Two additional annual school censuses;
Production of Births and Deaths Statistics. Subsequently, more funds would be allocated to this
component.
Component 4. There will not be any change to this component.
Current Component
Name
Proposed Component
Name
Current Cost
(US$M)
Proposed
Cost (US$M) Action
1 Institutional reform and
organizational change 9.36 3.20 Revised
2 Enhancing capacity 14.96 16.25 Revised
3 Data development and
dissemination 11.73 16.60 Revised
4 Project Management
and Monitoring and
Evaluation 1.30 1.30 No Change
Total: 37.35 37.35
Other Change(s)
Change in Implementation Schedule
Explanation:
The schedule for implementation now foresees project to be implemented until June 30th, 2018.
1 There was an exchange loss of USD2.65m at the time of the preparation of the Restructuring Paper.
9
GHANA
Ghana Statistics Development Program
RESTRUCTURING PAPER
A. SUMMARY
1. The proposed Level II restructuring aims at successfully completing project
activities and achieving the Project Development Objective (PDO). Project
implementation is progressing satisfactorily and the PDO remains relevant. However,
given the delays in declaring the project effective, there is a need to extend the closing
date to provide sufficient time to implement project activities and adjust the results
framework accordingly. The proposed restructuring also involves the reallocation of
funds partly because the number of staff of the Ghana Statistical Service (GSS) to be
placed on the buyout program was reduced significantly after a policy decision was taken
to redeploy national staff to support data collection efforts at sub-national level. With
more funding available from component one, emphasis would be placed on supporting
GSS and the other Ministries Departments and Agencies (MDAs) to undertake various
surveys to generate data. This approach is also consistent with the capacity strengthening
approach of experiential learning or learning by doing. To this end, the project is
expected to support the production of regular data through annual labor force surveys,
high frequency poverty data, Renovation of the Consumer Price Index, including the
definition of a new base year, GDP rebasing exercise to integrate new improved data
sources; production of Building Cost Index, two additional annual school censuses
among others.
2. In sum, the proposed Level 2 Restructuring to Ghana Statistics Development
Program (CR-50100) includes: (a) twenty month extension of the project closing date
from the current August 31, 2016 to June 30, 2018; (b) a revision of some indicators; and
(c) reallocations of proceeds within project components and disbursement category.
3. This would be the first extension of the project closing date of the IDA Credit
which is expected to be fully disbursed within the proposed closing date extension. This
would also be the first extension of the closing date of SRF-TF. The extension of the
closing dates has been requested by the Borrower on July 4, 2014. The reallocation of
credit and grant proceeds were requested by the Borrower on February 24, 2016. The
other changes were fully discussed and agreed upon.
10
B. PROJECT STATUS
4. The Ghana Statistics Development Project (GSDP), approved by the Board on August
25, 20011, became effective only on April 28, 2014 comprises an IDA Credit (CR/
50100) with an amount of XDR 18m (equivalent to USD30 million at the time of
approval) and SRF TF (TF 10425) with an amount of USD10 million. The original
closing date for both the IDA financing and the SRF TF is August 31, 2016. As of
December 2015, the project had disbursed USD15.34 million from IDA (51 per cent
of project funds) and USD 6.94 million from the SFR-TF (69 percent of grant funds).
5. The Project’s Development Objective (PDO) is to strengthen the National Statistical
System in the production and dissemination of timely and robust statistics relevant for
evidence-based policy making and other uses. Implementation progress for the GSDP
is rated Satisfactory following the latest supervision mission in December, 2015.
6. Component 1 has supported the Government’s reform strategy for the Ghana
Statistical Service (GSS). A new organizational structure has been adopted for GSS
which seeks to make the GSS leaner, and efficient. All new recruits into the GSS are
to have a master’s level degree. As part of the re-organization, GSS no longer
maintains staff at the sub-national level. A total of 28 staff with qualifications up to
Higher National Diploma (HND) have been transferred to the LGS. The staff buyout
program was successfully completed. Two consulting firms provided counselling and
financial management training to the identified staff. Subsequently, the staff buyout
process has been completed. As part of the retraining of staff, a total of 18 staff
members are undergoing a postgraduate degree level courses in statistics, economics,
and population studies in various universities. Existing staff were also trained in
performance management, IT and basic spreadsheet software.
7. Component 2 focuses on enhancing the statistical capacity including the underlying
statistical framework to ensure the production of quality statistics. To this extent, the
project has provided support for the acquisition of equipment and logistics for the
GSS and almost all the MDAs to enhance their capacity in data collection,
processing, and dissemination. These included computers and accessories, projectors,
photocopiers, PDAs, vehicles, etc. In addition, office furniture was also procured for
the implementing agencies. Various training programs were organized for staff of
GSS. Some of the implementing agencies also benefited from training sessions
organized and paid under the project. The trainings are in advance spreadsheet, ICT,
economic modeling, and sampling techniques; 10 staff have been trained in research
methodology and report writing, survey methods and data management, 41 staff
members have been trained in data analysis software SPSS/STATA, and 16 had
undergone training in different demographic analysis software programs. Field
trainings were also organized for enumerators in labor force statistics and the
integrated business enterprise surveys. A post census cartographic mapping has been
initiated with the aim of updating the enumeration area (EA) information established
11
during the 2010 Population and Housing Census (PHC). The updating of the EAs is
being combined with the process of converting all analog maps to digital form in the
urban and semi-urban areas. The field work and the updating and the digitization have
been started for over a year ago. A business census otherwise known as the Integrated
Business Establishment Surveys (IBES) aimed at providing the most comprehensive
list of businesses operating in the country has been initiated. The business register is
aimed at collecting data on the entire population of establishments located in the
country irrespective of whether they are public entity or private, making profits or is a
non-profit institution such as foundations and associations and irrespective of whether
it is involved in a formal or in informal activities. The data-collection-work as well as
the codification and data entry of the census were completed. The Phase I involving
the listing of economic establishments had been completed and three reports; the
Summary Report of the listing exercise, the Job Creation Report and the Business
Register have been drafted and are under review for publication. An international
consultant was hired to design samples for annual business surveys. Based on the
output of the consultancy, the GSS has initiated the field work in November 2015 and
it is expected to be completed in December 2016.
8. Component 3 is aimed at enhancing the quality of statistical data collected by the
GSS and the MDAs, and improving how these data are communicated and
disseminated to users. The Ministry of Education (MoE) carried out the 2014/2015
school census as part of the project. The data processing was completed and the
statistical yearbook was produced. The report has since been released. The Ministry
of Health (MoH) undertook a survey on the causes of the maternal mortality rates in
the country and a report has been produced. The Births and Deaths Registry has
undertaken the entry of over 200,000 as backlog for the period 2009-2012. As part of
activities under the component, a number of statistical reports were disseminated.
These include: the District Census Reports, Ghana Poverty Profile, Ghana Poverty
Mapping Report and the Ghana Demographic and Health Survey Report, Maternal
Deaths Survey Report.
9. Component 4 is aimed at developing and strengthening the institutional capacity of
GSS for project management, coordination, monitoring and evaluation. The
Coordination and Program Management Directorate (CPMD) of GSS coordinated
activities of all the implementing agencies and prepared the necessary reports which
include the Annual Report for 2014, Quarterly and Annual Financial Reports,
Procurement Reports and status reports on the Project. It provided secretariat service
for the National Statistics System Steering Committee (NSSSC) and the Technical
Committee (TC) of the GSDP. The CPMD coordinated the preparation of the 2016
Annual Work Plan and Budget. It supported the Implementation Support Missions
(ISM) since project inception. The CPMD also coordinated the updates of the results
framework of the project.
12
10. The latest implementation support mission conducted in December 2015 concluded
that financial, procurement and project management are satisfactory. As such, there
are no pending audits or legal covenants that are outstanding. The mission also
confirmed that the PDO rating remained Satisfactory to reflect progress of project
activities under implementation.
11. The government has requested for an extension of the closing date to ensure that the
project has enough time for implementation of activities.
C. PROPOSED CHANGES
Extension of the closing Date: The closing date of the project would be extended
from the current August 31, 2016 to June 30, 2018 for the IDA Credit and to June
30, 2017 for the SRF-CF Grant to allow for completion of project activities.
Results framework. The Project Development Objective (PDO) remains relevant.
Some of the indicators have been revised or dropped (See Annex 1).
Reallocations of proceeds within project components and disbursement category.
Credit proceeds would be reallocated from subcomponent 1a, 1b and
subcomponents 2.a, 2c and 3b to sub-components 2b and 3a to ensure that
adequate data production activities are carried out.
Table 1. Breakdown of reallocation within sub-components per funding source
Component IDA (million US$) SRF-CF (million
US$)
TOTAL
revised
(million
US$)
Proposed
change
Budgeted Revised Budgeted Revised
Component 1.
Sub-component
1a:
0 0 2.92 2 2.00 -0.92
Sub-component
1b:
6.44 1.20 0 0 1.20 -5.24
Component 2
Sub-component
2a:
5.73 2.73 0 0 2.73 -3.00
Sub-component
2b
4.18 10.32 0 0 10.32 + 6.14
Sub-component
2c
0 0 5.05 3.20 3.20 -1.85
13
Component 3
Sub-component
3a
9.70 11.80 0.30 4.10 15.90 + 5.9
Sub-component
3b
0 0 1.73 0.70 0.70 -1.03
Component 4 1.30 1.30 0 0 1.30 0
TOTAL 27.35 27.35 10.00 10.00 37.35 0
The proposed changes per component are as follows:
12. Component 1: Institutional Reform and Organizational Change (US$3.20
million: IDA US$1.20 million; SRF US$2.00 million)
Component 1a: Training and re-deployment (SRF US$2.00 million) Staff training at
the GSS Training Center will be intensified to reduce the cost of renting of workshop
venues. In addition, staff participating in short courses are now required to train other
colleagues upon their return from the training workshops.
Component 1b: Staff Buy-out (IDA US$1.20 million)
Due to the decision of government to create statistical units at the sub-national level of
government, a decision was taken, first, to redeploy those staff who have the requisite
basic statistical skills in data collection and have up to Higher National Diploma
qualifications to be redeployed to metropolitan, municipal and district assemblies
(MMDAs). Second due to the late start of the project, some staff also exited the GSS
through natural attrition. Lastly, the number of staff who have less than five years from
the Effective Date of the project to retire increased and could not be redeployed.
Subsequently, the number of staff for the buyout reduced to about 60.
The estimated cost of the staff buy-out is US$1.2 million. This amount was derived based
on the provisions in the Collective Bargaining Agreement.
13. Component 2: Enhancing capacity (US$16.25 million: IDA US$13.05 million;
SRF US$3.20 million)
This component focuses on enhancing statistical capacity including the underlying
statistical framework to ensure the production of quality statistics. It includes three sub-
components: a) Enhancing capacity of GSS and MDA statistical units; b) Improving the
statistical framework; and c) Investing in physical infrastructure and equipment.
Sub-component 2a – Enhancing capacity of GSS and MDA statistical units (IDA
US$2.73 million)
14
Emphasis will now be placed on learning by doing, As a result, formal training
workshops would be reduced whist funds are shifted to data production during which
capacity of officers will be built directly through the development of data production
instruments and on the field data collection, analysis and report writing.
Sub-component 2b – Improving Statistical Framework (IDA US$10.32 million)
More funding has been provided to this sub-component to enable the Business register be
fully developed under the project. The component will ensure the development of a master
sampling framework from the calendar year 2010 population and housing census, and a
central business register and housing census, including census post-enumeration
mapping, cartographic mapping, and business register, through the provision of technical
advisory services and acquisition of goods. Key activities include the following:
Census Post-Enumeration Mapping in 2011;
Creation of Master Sample frame in 2015;
Development of Business Register in 2015 and 2016; and
Cartographic Mapping in 2015 and 2016.
Sub-component 2c – Investing in Physical Infrastructure and Equipment (SRF
US$3.20 million)
There will not be any changes to the activities under this component. However, the
amount allocated for the sub-component would be reduced since most of the physical
infrastructure and equipment needs were already met.
14. Component 3: Data Production and Dissemination (US$16.60 million: IDA
US$11.80 million; SRF US$4.80 million))
This component will support the improvement of data collection, compilation, validation,
management, analysis and dissemination of data in order to improve the quality,
timeliness and use of socio-economic data. It is in line with component (iii) of the
GSDP. It will focus on both enhancing existing statistics and increasing the range of
statistics collected and how these are communicated and disseminated to users. There are
two sub-components: a) data development and management and b) dissemination,
communication and outreach.
Sub-component 3a: Data Development and Management (IDA US$11.80 million;
SRF US$4.10 million)
Additional activities to be undertaken would include: annual labor force surveys (LFS),
High frequency poverty data; Renovation of the Consumer Price Index, including the
definition of a new base year; GDP rebasing exercise to integrate new improved data
sources; Production of Building Cost Index; Two additional annual school censuses;
Production of Births and Deaths Statistics; Preparatory activities of the 2020 census
cartography.
Sub-component 3b: Communication (SRF US$0.70 million) Emphasis would now be laid on the production of soft copies of statistical reports and
loading them on the website of the GSS and the other MDAs in order to reduce the
15
amount spent on hard copies. In addition, GSS would use experienced staff to engage the
media in radio and television talk shows.
15. Component 4: Project Management and Monitoring and Evaluation (M&E) (
IDA US$1.30 million)
Activities will remain the same.
16. Institutional Arrangements
There are no changes to the institutional arrangements. In addition, there will be no
changes to the financial management and procurement arrangements. Project activities
will continue to be implemented according to the Project Implementation Manual (PIM).
The revised Disbursement estimates are as follows:
FY 14 15 16 17 18 19
SRF-CF 0 3.1 3.7 3.2
IDA 0 7.2 7.1 8.2 4.85
Cumulative 0 10.3 21.1 32.5 37.35
The revised Disbursement Categories for the IDA Credit are as follows:
Category Original
Amount (XDR)
Revised Amount
(XDR)
1. Goods, consultants’ services, non-
consulting services and Training under
parts A.1, B, C and D of the project
12,400,000 17,017,057
2. Severance Payments under
Component A.2 of the project
4,100,000 846,943
3. Operating Costs under Part D of the
Project
800,000 936,000
Unallocated 1,500,000 0
Total 18,800,000 18,800,000
There are no changes to the Disbursement Categories of the SRF-TF.
ANNEX 1
RESULTS FRAMEWORK
Project
Name: Ghana Statistics Development Program (P118858)
Project
Stage: Restructuring Status: DRAFT
Team
Leader(s)
:
Smile Kwawukume Requesting
Unit: AFCW1 Created by: Smile Kwawukume on 22-Oct-2015
Product
Line: IBRD/IDA
Responsible
Unit: GPV01 Modified by: Smile Kwawukume on 28-Mar-2016
Country: Ghana Approval FY: 2012
Region: AFRICA Lending
Instrument: Specific Investment Loan
Project Development Objectives
Original Project Development Objective:
To strengthen the National Statistical System in the production and dissemination of timely and robust statistics relevant forevidence-based policy-
making and other uses
Results
Core sector indicators are considered: Yes Results reporting level: Project Level
Project Development Objective Indicators
Status Indicator Name Core Unit of Measure Baseline Actual(Current) End Target
Revised User satisfaction with statistical
products and services of the
Percentage Value 40.00 88.50 90.00
Date 30-Nov-2011 15-Dec-2015 31-Aug-2018
17
NSS Comment A new end
target of 90 has
been established
since the first
survey
established a
satisfaction rate
of 88.5 percent.
User satisfaction with statistical
products and services of the
NSS
Percentage Value 40.00 88.50 60.00
Date 30-Nov-2011 15-Dec-2015 31-Aug-2016
Comment
Revised Ghana Statistical Capacity
overall score
Number Value 64.00 66.00 70.00
Date 30-Nov-2010 15-Dec-2015 31-Aug-2018
Comment End target date
changed to
August 31, 2018
Ghana Statistical Capacity
overall score
Number Value 64.00 66.00 70.00
Date 30-Nov-2010 15-Dec-2015 31-Aug-2016
Comment
Revised Periodicity and Timeliness
Number Value 92.00 87.00 92.00
Sub Type Date 30-Nov-2010 15-Dec-2015 31-Aug-2018
Breakdown Comment End target date
changed to
August 31, 2018
Periodicity and Timeliness
Number Value 92.00 87.00 92.00
Sub Type Date 30-Nov-2010 15-Dec-2015 31-Aug-2016
18
Breakdown Comment
Revised Methodology
Number Value 50.00 60.00 65.00
Sub Type Date 30-Nov-2010 15-Dec-2015 31-Aug-2018
Breakdown Comment End target date
changed to
August 31, 2018
Methodology
Number Value 50.00 60.00 65.00
Sub Type Date 30-Nov-2010 15-Dec-2015 31-Aug-2016
Breakdown Comment
Revised Source data
Number Value 50.00 54.00 65.00
Sub Type Date 30-Nov-2010 15-Dec-2015 31-Aug-2018
Breakdown Comment End target date
changed to
August 31, 2018
Source data
Number Value 50.00 54.00 65.00
Sub Type Date 30-Nov-2010 15-Dec-2015 31-Aug-2016
Breakdown Comment
Marked for
Deletion
Proportion of Surveys and
Censuses implemented by NSS
as per the long-term census and
survey plan
Percentage Value 60.00 90.00 100.00
Date 30-Nov-2011 15-Dec-2015 31-Aug-2016
Comment
No Change Dissemination of Timely and
Robust Statistics
Number Value
Date
Comment
19
Revised Annual School Census
Number Value 3.00 2.00 1.00
Sub Type Date 30-Sep-2010 15-Dec-2015 31-Aug-2018
Breakdown Comment This is a sub
indicator
replacing the
DHS which
the project is
not supporting.
End target date
changed to
August 31, 2018
Demographic and Health
Survey (DHS)
Number Value 12.00 9.00 9.00
Sub Type Date 30-Sep-2010 15-Dec-2015 31-Aug-2016
Breakdown Comment
Revised Ghana Living Standards
Survey (GLSS)
Number Value 18.00 6.00
Sub Type Date 31-Mar-2007 15-Dec-2015 31-Aug-2018
Breakdown Comment The target has
been reduced to
6 months since
field
enumerators are
to use hand held
devices and the
End target date
changed to
August 31, 2018
Ghana Living Standards
Survey (GLSS)
Number Value 18.00 9.00
Sub Type Date 31-Mar-2007 15-Dec-2015 15-Aug-2016
Breakdown Comment
Marked for Multiple Indicator Cluster
Number Value 18.00 18.00 12.00
20
Deletion Survey (MICS) Sub Type Date 31-May-2006 15-Dec-2015 31-Aug-2016
Breakdown Comment
Marked for
Deletion
Integrated Business Enterprise
Survey (IBES)
Number Value 6.00 6.00
Sub Type Date 15-Dec-2015 31-Aug-2016
Breakdown Comment
Revised Labour Force Survey (LFS)
Number Value 3.00
Sub Type Date 15-Dec-2015 31-Aug-2018
Breakdown Comment End target date
changed to
August 31, 2018
Labour Force Survey (LFS)
Number Value 3.00
Sub Type Date 15-Dec-2015 31-Aug-2016
Breakdown Comment
New Economic statistics produced in
accordance with internationally
recommended duration of the
base year (rebased within the
last 5 years) for the Consumer
Price Index (CPI) and for the
GDP
Yes/No Value No No Yes
Date 31-Dec-2002 29-Feb-2016 31-Aug-2018
Comment
Intermediate Results Indicators
Status Indicator Name Core Unit of Measure Baseline Actual(Current) End Target
Revised Proportion of Staff with
professional qualification
Percentage Value
Date 31-Aug-2011 15-Dec-2015 31-Aug-2018
Comment End target date
21
changed to
August 31, 2018
Proportion of Staff with
professional qualification
Percentage Value
Date 31-Aug-2011 15-Dec-2015 31-Aug-2016
Comment
Revised Proportion of GSS staff with
professional qualification
Percentage Value 39.00 48.00 70.00
Sub Type Date 31-Aug-2011 15-Dec-2015 31-Aug-2018
Breakdown Comment End target date
changed to
August 31, 2018
Proportion of GSS staff with
professional qualification
Percentage Value 39.00 48.00 70.00
Sub Type Date 31-Aug-2011 15-Dec-2015 31-Aug-2016
Breakdown Comment
Revised Proportion of MDA statistical
unit staff with professional
qualification
Percentage Value 65.00 65.00 70.00
Sub Type Date 31-Aug-2011 15-Dec-2015 31-Aug-2018
Breakdown Comment End target date
changed to
August 31, 2018
Proportion of MDA statistical
unit staff with professional
qualification
Percentage Value 65.00 65.00 70.00
Sub Type Date 31-Aug-2011 15-Dec-2015 31-Aug-2016
Breakdown Comment
Revised Number of staff (full-time
equivalents) employed by GSS
Number Value 532.00 385.00 350.00
Date 31-Aug-2011 15-Dec-2015 31-Aug-2018
Comment End target date
22
changed to
August 31, 2018
Number of staff (full-time
equivalents) employed by GSS
Number Value 532.00 385.00 350.00
Date 31-Aug-2011 15-Dec-2015 31-Aug-2016
Comment
Revised Number of persons trained
Number Value 50.00 321.00 70.00
Date 31-Aug-2011 15-Dec-2015 31-Aug-2016
Comment End target date
changed to
August 31, 2018
Number of persons trained
Number Value 50.00 321.00 70.00
Date 31-Aug-2011 15-Dec-2015 31-Aug-2016
Comment
Revised Use of master sampling frame
based on updated cartographic
maps for household surveys
Yes/No Value No Yes Yes
Date 31-Aug-2011 15-Dec-2015 31-Aug-2016
Comment End target date
changed to
August 31, 2018
Use of master sampling frame
based on updated cartographic
maps for household surveys
Yes/No Value No Yes Yes
Date 31-Aug-2011 15-Dec-2015 31-Aug-2016
Comment
Revised MDA and regional statistics
offices fully equipped and
operational with computers,
essential equipment and
Number Value 0.00 20.00 20.00
Date 31-Aug-2011 15-Dec-2015 31-Aug-2016
Comment The baseline
23
furniture and ICT connectivity was
erroneously
entered as 10
when it should
be 0.
MDA and regional statistics
offices fully equipped and
operational with computers,
essential equipment and
furniture and ICT connect ivity
Number Value 10.00 20.00 20.00
Date 31-Aug-2011 15-Dec-2015 31-Aug-2016
Comment
No Change Economic statistics produced in
accordance with internationally
accepted standards, including
rebased within the last 5 Years
Yes/No Value
Date
Comment
Revised Supply and Use tables (SUT)
Yes/No Value No No Yes
Sub Type Date 31-Aug-2011 15-Dec-2015 31-Aug-2018
Breakdown Comment End target date
changed to
August 31, 2018
Supply and Use tables (SUT)
Yes/No Value No No Yes
Sub Type Date 31-Aug-2011 15-Dec-2015 31-Aug-2016
Breakdown Comment
Marked for
Deletion
Gross Domestic Product (GDP)
Yes/No Value Yes No Yes
Sub Type Date 31-Aug-2011 15-Dec-2015 31-Aug-2016
Breakdown Comment This indicator
has been
upgraded to
PDO level
24
Marked for
Deletion
Consumer Price Index (CPI)
Yes/No Value No No Yes
Sub Type Date 31-Aug-2011 15-Dec-2015 31-Aug-2016
Breakdown Comment This indicator
has been
upgraded to
the PDO level
Revised Producer Price Index (PPI)
Yes/No Value No No Yes
Sub Type Date 31-Aug-2011 15-Dec-2015 31-Aug-2016
Breakdown Comment End target date
changed to
August 31, 2018
Producer Price Index (PPI)
Yes/No Value No No Yes
Sub Type Date 31-Aug-2011 15-Dec-2015 31-Aug-2016
Breakdown Comment
Marked for
Deletion
Proportion of statistical
products released in accordance
with national statistics release
calendar
Percentage Value 0.00 100.00 70.00
Date 31-Aug-2011 15-Dec-2015 31-Aug-2016
Comment
Revised Communications and
Dissemination Policy Adopted
by NSS
Yes/No Value No No Yes
Date 31-Aug-2011 15-Dec-2015 31-Aug-2018
Comment
Communications and
Dissemination Policy Adopted
by NSS
Yes/No Value No No Yes
Date 31-Aug-2011 15-Dec-2015 31-Aug-2016
Comment
New Production and publication of a
Yes/No Value No No Yes
25
statistics release calendar on
the website of GSS Date 31-Dec-2015 28-Mar-2016 31-Aug-2018
Comment