PCP Progress Report October 2020 PCP QUARTERLY PROGRESS REPORT (Oct – Dec 2020) World Bank Funded Punjab Cities Program Punjab Municipal Development Fund Company Institutional Strengthening Section Email: [email protected] Website: www.pcp.pmdfc.punjab.gov.pk

Upload: others

Post on 04-Feb-2021

7 views

Category:

Documents


0 download

TRANSCRIPT

  • PCP Progress Report

    October 2020

    PCP

    QUARTERLY PROGRESS

    REPORT (Oct – Dec 2020)

    World Bank Funded

    Punjab Cities Program

    Punjab Municipal Development Fund Company

    Institutional Strengthening

    Section

    Email: [email protected]

    Website: www.pcp.pmdfc.punjab.gov.pk

  • PCP Progress Report

    TABLE OF CONTENTS

    1. Executive Summary _______________________________________________ 1

    2. Introduction _____________________________________________________ 2

    3. Summary of Activities /Achievements by Program Component _____________ 3

    3.1 Highlights of Key Accomplishments ________________________________ 3

    3.2 Funds Allocation & Utilization ____________________________________ 5

    3.3 Update – Window – 1 (PBGs – Infrastructure Investments) _______________ 6

    3.4 Update – Window – 2 (IPF) ______________________________________ 11

    4. Assessment of DLRs _____________________________________________ 15

    5. Update – Major Program Components ________________________________ 17

    5.1. Update - Institutional Strengthening ______________________________ 17

    5.2. Update - Environment & Social Management _______________________ 22

    6. Update – Program Steering Committee – Decisions ______________________ 24

    7. Update - Program Action Plan ______________________________________ 26

    Annexures __________________________________________________________ 30

  • PCP Progress Report

    ACRONYMS

    APA Annual Performance Assessment

    ADP Annual Development Program

    CFMS Computerized Financial Management System

    CTS Complaint Tracking System

    DLI Disbursement Linked Indicator

    DLR Disbursement Linked Results

    EHS Environment Health & Safety

    ESFPs Environment & Social Focal Persons

    ESMF Environment and Social Management Framework

    ESSA Environment & Social Systems Assessment

    FABS Financial Accounting & Budgeting System

    FD Finance Department

    FY Financial Year

    GDP Gross Domestic Product

    GIS Geographical Information System

    GoPb Government of Punjab

    IDAMP Integrated Development and Asset Management Plan

    IPC Interim Payment Certificate

    IPF Investment Project Financing

    IS Institutional Strengthening

    LG & CDD Local Government and Community Development Department

    M&R Maintenance & Rehabilitation

    MACs Minimum Access Conditions

    MC Municipal Corporation/Committee

    MO (F) Municipal Officer (Finance)

    MO (I) Municipal Officer (Infrastructure)

    MO (P) Municipal Officer (Planning)

    MO (R) Municipal Officer (Regulation)

    NOC No Objection Certificate

    OSR Own Source Revenue

    O&M Operations & Maintenance

    P for R Program for Results

    PAD Program Appraisal Document

    PBG Performance-Based Grants

    PCP Punjab Cities Program

    PCRs Polymerase Chain Reactions

    PLGB Punjab Local Government Board

    PLGA Punjab Local Government Act

    PM Performance Measure

    PMDFC Punjab Municipal Development Fund Company

    PMS Performance Management System

    PPRA Public Procurement Regulatory Authority

    PURR Punjab Urban Reform Roadmap

    SLG Secretary Local Government

    SOPs Standard Operating Procedures

    TOR Terms of Reference

    ULGs Urban Local Governments

    VO Variation Order

    WB World Bank

  • PCP Progress Report

    Page | 1

    1. EXECUTIVE SUMMARY

    To fulfill DLIs, a comprehensive framework is developed encompassing the process activities, roles &

    responsibilities of the stakeholders and documentation required as per the agreed Means of Verification.

    PMDFC, under the guidance of the World Bank, identified process activities to be implemented to

    achieve desired targets. These activities have been framed, keeping in view the targeted results to be

    achieved for Year – II and the capacity of MCs’ staff against each result area. A comprehensive

    implementation plan is also prepared to schedule the process activities for fulfilling MACs and the

    achievement of PMs according to the prescribed timeline and delegated responsibilities. Contextually,

    the trainings/hands-on sessions are being imparted to the designated/nominated MCs’ staff. Moreover,

    the handholding of MC staff is continuously being ensured not only to achieve the MACs & PMs but

    also to sustain these conditions in the subsequent years.

    Performance Based Grants are being financed through the Bank’s PforR instrument and will be

    provided to 16 MCs in Punjab. Participating MCs will use PBG funds primarily for these financing

    eligible infrastructure investments. PMDFC is continuously monitoring construction activities through

    its field teams and supervision consultants. PMDFC teams are also providing requisite backstopping

    support to MCs staff in building the capacity of MCs to handle such kind of donor-funded projects. This

    report prepared by Institutional Strengthening section will provide a glimpse of efforts accomplished by

    PMDFC Team from time to time.

    The ongoing COVID-19 pandemic in Pakistan has affected businesses far and wide, across the country

    including almost every sector. Decision makers and practitioners at both provincial & grass root levels

    are facing challenges, which are now visible. PMDFC also faced challenges due to this outbreak of

    COVID-19 and day to day Program activities have been constrained due to restrictions in movement

    imposed by Government of Punjab (GoPb).

    Despite of these inevitable COVID-19 related challenges, PMDFC has strived its best efforts to execute

    the PCP operations. Program team is continuously monitoring and overseeing the implementation of

    M&R projects (Year – I) being executed by 16 partner MCs. Moreover, the team is also putting its best

    efforts to accomplish the specific requirements to fulfill DLIs for subsequent releases. The report

    encompasses activities majorly carried out during Oct - Dec 2020.

    PMDFC is coordinating the collection of data and individual reports from partner

    MCs. The report is developed by encompassing both components i.e. IPF

    Component and Performance Based Grants.

  • PCP Progress Report

    Page | 2

    2. INTRODUCTION

    Consequently, it was proposed to launch the ‘Punjab Cities Program” as Program for Results (P for

    R), and WB showed willingness to invest USD 200 million in this Program. It was agreed that through

    the Program, the Bank would support institutional and infrastructure development with particular

    attention on secondary cities, as they provide the most conducive opportunity to pilot a ULG-centric

    model of improving urban governance and service delivery.

    2.1 Program Development Objective

    The development objective of the Program is to strengthen the performance of urban local governments

    participating in urban management and service delivery.

    2.2 Program Cost

    Table 1: Program Cost (1 USD = PKR 152.90)

    Share USD (Million) PKR. (Million)

    Foreign: 200.00 30,580.00

    Local: GoPb /MCs co-financing 36.00 5,504.40

    Total: 236.00 36,084.40

    2.3 Key Features / PCP Components

    The Program is using a hybrid of Investment Project Financing (IPF) and Program for Results (P for R)

    instrument.

    a) Infrastructure Development (Window-I; Program for Result) provides Performance-

    Based Grants (PBGs) based on results achieved by the MCs against the Disbursement-Linked

    Indicators (DLIs).

    b) Institutional Strengthening (Window-2; Investment Project Financing) supports

    provincial government agencies (Finance Department, LG&CD Department, Local

    Government Board, and PMDFC and selected MCs with technical assistance and

    institutional strengthening. (Total Cost; USD 20 Million)

    2.4 Program Cities

    Table 2: 16 cities (Municipal Corporations/ Committees) included in the Program

    North

    Punjab

    Population

    2017

    Centre

    Punjab

    Population

    2017

    South Punjab Population

    2017

    Daska 189,327 Gojra 180,951 Bahawalnagar 199,367

    Hafizabad 269,424 Jarranwala 230,162 Burewala 289,236

    Jhelum 261,711 Jhang 493,108 Khanewal 216,181

    Kamoke 264,217 Kamalia 145,713 Kotaddu 179,730

    Muridke 258,152 Okara 463,302 Vehari 175,042

    Wazirabad 138,433

    Government of Punjab prepared “Punjab Cities Program” with the assistance of the

    World Bank (WB) by analyzing the economic activities in the main cities of Punjab.

    For exploiting the economic growth potential of the cities some policy reforms have

    been proposed in the Punjab Cities Program, which are in line with Vision 2025 &

    Punjab Growth Strategy.

  • PCP Progress Report

    Page | 3

    3. SUMMARY OF ACTIVITIES /ACHIEVEMENTS BY PROGRAM COMPONENT

    3.1 Highlights of Key Accomplishments

    PCP team is striving its best efforts to execute the program operations. Program team is continuously

    monitoring and overseeing the implementation of M&R projects being executed by 16 partner MCs.

    Moreover, the team is also putting its best efforts to accomplish the specific requirements to fulfill DLIs

    for subsequent releases.

    Table 3: Update - DLIs Accomplishment

    Activities Status

    Accomplishment of DLIs (Year – I):

    DLI – 1:

    MCs have achieved Minimum Access

    Conditions (MACs)

    DLI – 2:

    MCs have achieved Performance

    Measures (PMs)

    Completed (Year – I):

    Reduced set of Minimum Access Conditions fulfilled

    and assessed by World Bank Team as prior actions

    for release of USD 9.52 million

    Compliance of DLIs for FY 2019 – 20

    In-time submission of deliverables for 16 cities

    World Bank approved Disbursement Linked Results

    for release of subsequent funds to MCs

    USD 42.64 million released against DLRs achieved

    during FY 2019-20

    Accomplishment of DLIs (Year – II): In Progress:

    Preparatory work / trainings / consultative sessions for

    MCs staff to accomplish DLIs for FY 2020 – 21

    Handholding of MCs staff to ensure functionality of

    systems

    Highlight of key accomplishments is detailed as under:

    Table 4: Progress Summary

    Activities Update

    Update on

    Year-I schemes

    Groups Description No of

    Schemes

    Work

    Commenced

    AA Cost

    (Rs.

    Million)

    Contract

    Cost (Rs.

    Million)

    A Rehabilitation 16 16 1206.80 1127.38

    B Repair 12 11 145.65 126.93

    C Supply Items 16 16 `135.50 129.78

    Total 44 43 1487.95 1384.09

    01 Scheme dropped (for the city of Kamalia)

    Average Progress:

    Physical Progress : 53%

    Expenditure incurred : Rs.437.93 Million

    Financial Progress : 32%

    Rebidding

    MC Name Group Status

    Kamalia B Revised cost estimate under preparation

    Release of PBGs to MCs (Year – II): PKR 7.065 Billion (Sep 14, 2020)

    M&R projects marked on GIS based maps – completed for 16 MCs

    Update on

    SWM Collection of data and requirement from Program MCs (Completed for 16 MCs)

  • PCP Progress Report

    Page | 4

    Activities Update

    Analysis of available data in line with Year-I M&R projects - Completed

    Design Criteria finalized.

    Finalization of specifications of equipment & machinery - Completed

    GIS based design and proposal mapping of SWM – Completed for 10 MCs

    PC-I for MC Muridke, Khanewal, Kamoke & Bahawalnagar – Completed and

    shared with MCs

    PC-I for Jhelum, Burewala, Okara & Jaranwala – In progress

    PCP

    Monitoring

    Dashboard

    Designing of Dashboard – Completed

    Android Application - Developed

    Development completed and dashboard is live now – Test run in progress

    Environment &

    Social

    Management

    Screening & Categorization of Sub-Projects – Completed

    ESMF Development – Completed

    Development of Environment & Social Screening Checklists – Completed

    ESMF Stakeholders Consultation – Completed

    Development of E&S Monitoring Checklist – Completed

    E &S Monitoring of Construction Activities – Completed

    Development of 1st Bi-Annual Progress Report – Completed

    Formulation of Environment, Health and Safety (EHS) SOPs for the Construction

    Labor/Workers (including Women Labor) in English & Urdu both – Completed

    Postings /

    Transfer of

    MCs’ Key Staff

    LG&CD Department is maintaining key staff posting in all 16 MCs.

    PMDFC is providing necessary support to LG&CD Department to make different

    staffing analyses for decision making.

    Revenue

    Generation

    plans

    Benchmarking of OSR for last 03 years - Completed for 08 MCs (Wazirabad,

    Daska, Vehari, Gojra, Kot Addu, Jhang, Hafizabad, Burewala)

    Preparation of Revenue Enhancement Plans:

    Shop rent enhancement plan for 04 MCs (Vehari, Burewala, Hafizabad &

    Gojra) completed

    Action Plans to

    accomplish

    DLIs – FY

    2020-21

    Action Plans for the following activities have been finalized.

    Plan for Minimum Access Conditions (MACs) – FY 2020-21

    Plan for Performance Measures (PMs) – FY 2020-21

    The plan is comprised of a targeted score of 55, specific indicators, process

    activities, resource required and responsibilities, etc.

    Field offices

    establishment

    Establishment of PCP Regional Offices: (Khanewal, Faisalabad & Gujranwala)

    Hiring of Offices - Completed

    Procurement / Delivery of Furniture – Completed

    Procurement of IT equipment – In progress

    Procurement of

    IT & Office

    Equipment

    Advertisement published on Sep 16, 2020 – Opening Date: Oct 22, 2020

    Evaluation completed on Oct 31, 2020

    Letter of acceptance issued on Nov 24, 2020

    Partially Delivered; Expected date of Complete Delivery – Feb 15, 2021

    Hiring of

    Consulting

    Services

    Sectoral Planning, Design & Supervision of Infrastructure Projects

    TORs have been revised and approved by World Bank

    Receipt of EOI on Oct 09, 2020

    RFP issued on Dec 05, 2020

  • PCP Progress Report

    Page | 5

    Activities Update

    Proposal submission from shortlisted consultants by Jan 07, 2021

    PMS, CCTS & MCs’ Websites:

    TORs revised in line with comments received from the World Bank – being

    reviewed by the WB (Finalization in process)

    Own Source Revenue:

    TORs drafted and shared with the World Bank on Sep 30, 2020

    Being reviewed by World Bank.

    Hiring of Audit

    Firm

    RFP issued on Sep 29, 2020

    Contract agreement signed on Nov 14, 2020 – Consultants Mobilized

    Inception report approved

    Field work related to North Region completed

    Field work of central region – in progress

    Assignment is expected to be completed by mid of February, 2021.

    Hiring of APA

    Firm

    Consultant Selection Committee notified by LG&CDD on Oct. 20, 2020

    Advertisement has been published on Oct 30, 2020 (closing date: Nov 16, 2020)

    Shortlisting completed and working paper prepared by LG&CDD to convene

    meeting for evaluation, consultants expected to be on board by end of Feb, 2021

    Designated

    Account for

    PFC unit of FD

    Opening of designated accounts for PFC unit of FD - yet to be opened

    (Account will be opened, as PC – I approves from the competent forum)

    3.2 Funds Allocation & Utilization

    Components’ Allocation Table 5: Program Components & Allocation

    Window # Financing Modality Amount (US $ M) Amount (%)

    1 IDA Allocation for Performance Grants

    (PforR)

    180 90

    2 IDA Allocation for Institutional

    Strengthening (IPF)

    20 10

    Funds Utilization Table 6: Funds Utilization (FY 2019-20)

    Expenditure Releases Utilization

    Area PKR USD PKR USD

    IPF-PMDFC 185.11 1.20 17.47 0.11

    PBG-MCs 1,442.41 9.52 - -

    Total 1,627.53 10.72 17.47 0.11

    Table 7: Funds Utilization (FY 2020-21)

    Expenditure Releases Utilization

    Area PKR USD PKR USD

    IPF-PMDFC 82.99 0.50 147.70 0.96

    PBG-MCs 7,065.05 42.64 290.85 1.92

    Total 7,148.05 43.15 438.55 2.88

  • PCP Progress Report

    Page | 6

    3.3 Update – Window – 1 (PBGs – Infrastructure Investments)

    Participating MCs are using PBG funds primarily for financing eligible infrastructure investments. The

    priority infrastructure investment needs will be determined by infrastructure maps, Integrated

    Development, and Asset Management Plans (IDAMP). The Program MCs contribute 20% of the cost

    of all infrastructure investments financed through PBGs. In the first year of the implementation (FY

    2019-20), Program MCs used PBGs only for servicing the repair and maintenance needs of municipal

    infrastructure. Eligible investments in infrastructure and service delivery have been identified,

    encompassing MC mandates under PLGA 2019. The prioritization and selection of investments will

    ensure (a) citizen participation; (b) social inclusion (including gender and disability considerations); (c)

    climate change and disaster adoption; and (d) economic viability. Annual infrastructure investment

    plans, listing all planned expenditures against PBGs, duly reflected in MC budgets.

    Eligible infrastructure sectors are given as under;

    Table 8: Eligible Infrastructure Sectors

    Functional area Eligible investments

    Waste Management

    (Solid and Liquid) Solid waste: collection equipment, collection bins, transfer stations,

    collection points.

    Construction of new landfills is excluded.

    Liquid waste: construction of wastewater treatment plants with a capacity of less than 50,000 m3/day, sludge ponds, community septic

    tanks, vacuum trucks, vacuum handcarts, and others.

    Water Supply Water supply pumps, overhead reservoirs, mains, and distribution networks.

    Storm Water

    Drainage

    Urban drainage systems; flood control systems

    Connectivity Urban roads, pedestrian walkways and bicycle paths, street and security

    lights, and road signs.

    Social and Livability

    Infrastructure

    Urban greenery and public spaces.

    Fire and Disaster

    Management

    Fire control stations and disaster management equipment (firefighting

    trucks, rehabilitation and/or construction of new firefighting station and

    facilities).

    (a) Investments in the first year are restricted to repair and maintenance priorities; in subsequent

    years, investments may include both rehabilitation and capital investments.

    (b) Proposed investments must be included in list of priority investments identified from updated

    infrastructure maps in the first three years and from IDAMPs in subsequent years.

    (c) To avoid the fragmentation of urban investments (and limit procurement effort), investment

    subprojects are subject to a minimum investment of PKR 50 million (~US$ 500,000) This

    requirement is subject to the following two exceptions:

    i. Municipalities shall be permitted to combine a number of related urban infrastructure items in the

    same geographic area into a single procurement to reach the relevant minimum

    investment/procurement size for a single area-based development initiative.

    ii. If the PBG allocation to an MC is less than PKR 50 million (US$500,000), the minimum

    investment/procurement amount will be correspondingly lowered to the PBG allocation amount.

    (d) At least 80% of the PBG shall be spent on non-movable infrastructure assets.

  • PCP Progress Report

    Page | 7

    The detail progress of infrastructure projects is given as under;

    i.) Progress of schemes of Year-I

    There are total 44 Schemes of M & R of

    infrastructure projects in the first year

    including 03 groups i.e. Group A-

    Rehabilitation Works, Group B- Repair

    Works and Group C – Supply of items.

    Out of these, 43 schemes have been

    awarded and works commenced. One of

    the schemes for the city of Kamalia has

    been dropped. Admin Approval cost for

    all these schemes is 1487.95 Million &

    Works amounting Rs. 1384.09 Million

    have been awarded

    ii.) Progress of Schemes - Group-A Year-I

    Rehabilitation Works

    Contracts have been awarded in all 16

    MCs with Admin approval cost of Rs.

    1206.81 Million. Schemes amounting Rs.

    1127.38 Million have been awarded and

    work Commenced in 16 MCs.

    iii.) Progress of Schemes -Group-B

    Year-I

    Repair Works

    Contracts have been awarded in 11 MCs

    with Admin approval cost of Rs. 145.65

    Million. Schemes amounting Rs. 126.93

    Million have been awarded and work

    commenced in 10 MCs so far.

    iv.) Progress of Schemes of Group-C

    Year-I

    Supply Items

    Contracts have been awarded in all 16

    MCs with Admin approval cost of Rs.

    135.50 Million. Schemes amounting Rs.

    129.78 Million have been awarded and

    work commenced in all 16 MCs.

    Detail of progress schemes and

    beneficiaries of infrastructure schemes are placed at Annex A.

    16 16 16 16 16 16 16 16 16 16

    No

    of S

    ch

    em

    es

    TOTAL= 44 CONTRACTS

    GROUP-A = 16

    AA Cost= Rs. 1206.81 M

    16 16 16 16 16 16 16 16 16 16

    No

    of S

    ch

    em

    es

    TOTAL= 44 CONTRACTS

    GROUP-C = 16

    AA Cost= Rs. 135.50 M

    Work Awarded= Rs. 129.78M

    44 43 43

    1

    TOTAL SCHEMES WORK AWARDED WORK

    COMMENCED

    REBIDDING

    STAGE

    No

    of S

    ch

    em

    es

    TOTAL= 44 CONTRACTS

    AA Cost= Rs. 1487.95M

    Work Awarded= Rs. 1384.09

    12 12 11 11 11 11 11 11 11 11

    No

    of S

    ch

    em

    es

    TOTAL= 44 CONTRACTS

    GROUP-B = 12

    AA Cost= Rs. 145.65 M

    Work Awarded= Rs.126.93M

  • PCP Progress Report

    Page | 8

    Pictorial View – Infrastructure Sub-Projects

    Infrastructure Development Activities - PCP Cities

    Pump House No.2 Mullaha Rasool Nagri Waz.

    W

    azi

    rab

    ad

    Bar Screen

    Before After

  • PCP Progress Report

    Page | 9

    Turbine Pump

    Before After

    Rehabilitation of Sullage Carrier From Social Security Office to 240 More Lahore Road

    Ja

    ran

    wala

    Before During

    Repair Works

    Before During

  • PCP Progress Report

    Page | 10

    Ka

    ma

    lia

    Laying of Tuff Paver approach Road Nawaz Sharif Park

    Before During

    Before start Paint During

    PC

    P M

    on

    ito

    rin

    g D

    ash

    bo

    ard

    Progress Summary View Android App.

  • PCP Progress Report

    Page | 11

    3.4 Update – Window – 2 (IPF) Table: 9 Window2 Interventions

    Result Area Proposed Systems and Activities Status to date

    FD

    Performance-

    Based Grants

    and Financial

    Reporting

    Strengthen FD’s PFC Unit to manage budgeting and release of

    PBGs

    Operationalize MC Financial Monitoring & Reporting System

    (linked to MC CFMS)

    PC-I is under preparation. As PC-I approves from Competent Forum, requisite

    interventions will be executed.

    LG

    &C

    DD

    Policy

    Framework and

    Guidance

    Manage APAs through procuring and managing APA firm

    Establish PPP Unit - develop model contracts, templates, etc.

    Update Level of Service standards

    Develop population-based staffing standards with gender lens

    Update design specifications and standards for municipal

    infrastructure

    LG&CDD has already initiated hiring process for APA Firm to manage annual

    performance assessment of disbursement

    linked indicators for FY 2020-21.

    Consultant selection committee notified by Secretary LG&CD Department.

    Received EOIs being evaluated by LG&CD department

    Three meetings have been convened with LG&CDD and PLGB to discuss the

    capacity building initiatives for LG&CDD

    and PLGB under PCP.

    TORs to hire the consultant to carry out detailed assessment is drafted and shared

    with AS (Dev). LG&CDD has been

    requested to convene meeting on urgent

    basis to finalize the modalities.

    LG

    B

    Human

    Resource

    Management

    Develop and adopt a gender responsive HR Management

    System, including gender based

    provisions such as paid maternity

    leave and harassment free work

    environment

    Develop and operationalize MC Performance Monitoring

    Dashboard (linked to Performance

    Management System in MCs)

    Implement career learning plan, training content, and delivery

    partnerships for staff in Program

    MCs

    PLGB representatives explained that HRMIS is being developed by PITB.

    Certain attributes like gender based

    provisions such as paid maternity leave and

    harassment free work environment are also

    being ensured as per government policy.

    The chair (then Additional Secretary – Dev.) opined that PLGB officers will

    conduct need assessment exercise to chalk

    out the necessary interventions in line with

    PLGA 2019. Following segments will be

    rigorously focused:

    Data collection cell should be more equipped in human resource as well as

    equipment wise.

    Staff capacity building needs should also be chalked out in line with PLGA 2019.

    TORs to hire the consultant to carry out detailed assessment is drafted and shared

    with Secretary PLGB. LG&CDD has been

    requested to convene meeting on urgent

    basis to finalize the modalities.

    PM

    DF

    C

    Update Infrastructure Maps developed under PMSIP

    Amend IDAMP instructions approved by P&DD under PCGIP

    to conform with MC

    M&R Schemes being executed are marked on GIS based maps

    TORs to hire consultant to amend IDAMP framework and to develop and implement

  • PCP Progress Report

    Page | 12

    Integrated

    Development

    and Asset

    Management

    Planning

    organizational structure and staff

    mandates

    LG&CDD instructions to MCs to adopt approved IDAMP

    framework and process for

    municipal infrastructure and

    services.

    Develop asset inventories with age and condition for all municipal

    assets, per approved IDAMP

    Framework.

    Conduct energy audits for electrical equipment, per approved

    IDAMP Framework.

    Conduct fuel audits for mechanical equipment, per

    approved IDAMP Framework.

    Develop training modules for MC staff.

    Train MC Staff on developing IDAMPs.

    Support development of three-year, rolling IDAMPs for each

    participating MC.

    Support implementation of three-year rolling IDAMPs for each

    participating MC.

    three-year, rolling IDAMPs for each

    participating MC drafted - Being reviewed

    Energy & Fuel Audit for electrical & mechanical equipment completed

    Training modules developed and sessions conducted on Energy & Fuel Audit

    Budgeting,

    Financial

    Management

    and Audit

    Ensure Computerized Financial Management System (CFMS)

    developed under PMSIP is fully

    operational, focusing on basic

    financial management functions:

    producing annual budget

    estimates; cash book, automated

    voucher data entry system; annual

    financial statements, etc.

    Assess CFMS to ensure compatibility with FABS (national

    financial management information

    system)

    Rollout additional modules e.g. automated billing system for water

    and shops; challan-based

    collection system for major

    avenues of OSR.

    Develop and operationalize modules for Pension and Payroll.

    Develop Financial Management Manual for MCs.

    Require MCs to assign staff below BPS 14 to operate the system and

    provide training.

    CFMS (developed under PMSIP) is fully operational in 16 PCP partner MCs.

    Upgradation of CFMS is being carried out through an ADP funded scheme, in case any

    additional module is required, it will be

    developed through PCP.

    MCs have assigned the requisite staff to operate the system. Training provided and

    troubleshooting support being provided.

    Field work related to Audit completed by external Audit firm for north region of PCP

  • PCP Progress Report

    Page | 13

    Ensure that DG District Audit can audit CFMS-generated reports

    submitted by MCs.

    Field work of central region – in progress

    Assignment is expected to be completed by mid of February, 2021

    Accountability,

    Transparency,

    and Complaint

    Handling

    Ensure MC websites developed under PMSIP are fully operational

    and updated.

    Develop SOPs and training materials to ensure regular

    updates.

    Ensure that MCs post requisite information on their websites.

    16 PCP MCs’ website (developed under PMSIP) are fully operational and being

    updated as per developed SOPs

    periodically.

    Trainings being imparted as per developed SOPs & training material.

    The requisite information is placed on MCs’ websites

    Ensure Complaint Tracking System (CTS) developed under

    PMSIP is fully operational.

    Develop and implement its upgrade to Grievance Redress

    Mechanism.

    Develop and operationalize CTS/GRM dashboard for MCs

    and LG&CDD.

    Require MCs to assign staff below BPS 14 to operate the system and

    provide training.

    Complaint Tracking System (CTS) (developed under PMSIP) is fully

    operational

    Hiring of consultancy services

    TORs to upgrade CTS into Grievance Redress Mechanism redrafted inline with

    the comments received from the World

    Bank

    Updated version being reviewed by WB MCs have assigned the requisite staff to

    operate the system. Training provided and

    troubleshooting support being provided.

    Monitoring

    Service

    Delivery

    Outcomes

    Ensure Performance Management System (PMS) developed under

    PMSIP is fully operational.

    Add performance indicators and collect requisite data.

    Develop and operationalize monitoring application to replace

    manual reporting forms.

    Update existing PMS dashboards per current MC, PMDFC, and

    LG&CDD structures.

    Formulate Service Improvement Plans based on PMS and CTS

    information.

    Require MCs to assign staff below BPS 14 to operate the system and

    provide training.

    Performance Management System (PMS) (developed under PMSIP) is fully

    operational in 16 PCP MCs.

    Hiring of consultancy services

    TORs to develop & upgrade PMS to meet current requirements of the Program

    redrafted inline with comments received

    from the World Bank

    Updated version being reviewed by WB

    MCs have assigned the requisite staff to operate the system. Training provided and

    troubleshooting support being provided.

    Procurement

    and Contract

    Management

    Amend and adopt for MCs procurement SOPs based on

    PPRA Rules developed under

    PCGIP.

    Update SOPs for Contract Management developed under

    PMSIP, including social and

    environmental management, and

    develop Manual.

    Provide procurement and contract management training to MC staff.

    Being planned

    Training being provided (a session also planned on 27th & 28th Jan, 2021)

    Develop OSR Action Plans for

    OSR sources with highest

    Benchmarking of OSR for last 03 years - Completed for 08 MCs (Wazirabad,

  • PCP Progress Report

    Page | 14

    Own-Source

    Revenue

    Mobilization

    and

    Administration

    potential for revenue

    enhancement.

    Develop training modules.

    Require MCs to assign staff below BPS 14 and provide training.

    Daska, Vehari, Gojra, Kot Addu, Jhang,

    Hafizabad, Burewala)

    Preparation of Revenue Enhancement Plans:

    Shop rent enhancement plan for 04 MCs (Vehari, Burewala, Hafizabad &

    Gojra) completed

    Hiring of consultancy services for OSR mobilization & administration

    TORs drafted and shared with the World

    Bank on Sep 30, 2020

    Being reviewed by World Bank

    MCs have assigned the requisite staff to

    operate the system. Training provided and

    troubleshooting support being provided.

    Infrastructure

    Delivery and

    Maintenance

    Update O&M protocols and manuals for municipal services

    developed under PMSIP.

    Develop training modules on protocols and manuals, including

    social and environmental

    management.

    Train relevant MC staff.

    The updation of protocols and manuals is being planned through hiring an individual

    consultant

    TORs being prepared

    Environmental

    and Social

    Management

    Ensure appointment of social and environment management focal

    persons in each MC.

    Mainstream social and environmental considerations in

    the updating of SOPs, O&M

    manuals, and investment planning

    strategies.

    Develop SOPs, screening checklists, and mitigation

    measures based on ESSA

    recommendations, to put in place

    documented procedures and

    processes for the management of

    environment and social risks.

    Develop training modules and train MC staff.

    Notification has been made for nomination of focal person of Environment & Social

    Management

    Environment and Social Management Framework has been developed

    SOPs and Environmental & Social Screening Checklists have been developed

    as per ESSA recommendations

    Training/ Capacity Enchantment Framework has been developed &

    Training/Briefing sessions with the

    nominated ESFPs are being conducted

    Detail is given in table 12

  • PCP Progress Report

    Page | 15

    4. ASSESSMENT OF DLRs

    MACs & PMs together will enable all 16 MCs to access the full Performance Based Grants (PBGs)

    allocation. Compliance with MACs will be a pre-condition to access the PBGs, and failure to satisfy any

    MAC will disqualify an MC from accessing its PBG for that year. The PMs will build on the foundations

    laid by MACs and will challenge the MCs to raise their performance to achieve incremental targets.

    MCs will be assessed against a set of MACs to access the DLI-1 grants (25% of total PBG envelope) &

    PMs to access the DLI – 2 grants (75% of total PBG envelope).

    Targets for first year has been achieved and DLRs have been confirmed by the WB. Contextually, targets

    for FY 2020-21 have been delineated and requisite backstopping support to MCs’ staff is being provided

    to obtain targeted score for an independent assessment.

    Table 10: Program DLIs

    Areas

    Minimum Access

    Conditions Performance Measures

    MACs PMs Total

    Score

    Scores

    Achieved

    (FY

    2019-20)

    Targeted

    Score

    (FY 2020-

    21)

    Investment

    Planning and

    Budgeting

    1.1 MC has updated

    infrastructure maps

    1.2 MC has an

    approved Annual

    Development Plan

    (ADP)

    1.3 MC Annual Budget

    Estimates, generated

    from the CFMS, have

    been approved by

    Chairman/Council

    1.4 MC has contributed

    20% co-financing for

    PBGs during the FY

    1.1 O&M budgeting and

    planning done for major

    infrastructure services

    3 - 3

    1.2 Infrastructure maps

    used as a planning tool 3 3 -

    1.3 Expenditure control

    of fuel and energy 10 4 6

    1.4 Asset inventory

    prepared and updated 3 - -

    1.5 Three-year rolling

    IDAMP prepared and

    updated

    5 2 2

    Human

    Resources

    2.1 MC has in

    place/assigned core

    locally appointed staff,

    to operate the systems

    -

    Own Source

    Revenue

    2.1 Revenue

    Enhancement Plan

    prepared

    3 - 3

    2.2 Own-Source

    Revenues increased 15 - -

    Procurement 3.1 MC has a

    Procurement Plan for

    current FY

    3.2 MC has functional

    procurement committee

    for relevant level of

    procurement in place

    (per PPRA rules)

    3.1 Adherence to PPRA

    rules

    8 7 8

    Financial

    Management

    and Audit

    4.1MC has functional

    Computerized Financial

    Management System

    (CFMS)

    4.1 Functionality of the

    CFMS 12 9 12

  • PCP Progress Report

    Page | 16

    4.2 MC cash book is

    generated using CFMS

    4.3 MC has submitted

    annual financial

    statements, to the

    satisfaction of auditors

    for the previous FY

    4.4 MC has no adverse

    or disclaimed audit

    opinion for previous

    FY

    Environment

    and Social

    Management

    5.1 MC has designated

    Environmental and

    Social management

    focal persons

    5.2. MC has developed

    an environment and

    social management

    system with gender

    considerations,

    including procedures

    for preparation,

    approval, and

    supervision of

    investments

    5.3 MC has developed

    acceptable capacity to

    prepare, approve, and

    supervise management

    instruments

    5.1 Annual targets set for

    incremental application

    of

    environmental and social

    screening including

    gender

    considerations,

    assessment, and

    mitigation processes on

    all infrastructure

    investments

    2 1 1

    5.2 Eligible investments

    screened for potential

    environmental and social

    safeguard impacts

    3 2 2

    5.3 Environmental and

    Social Assessments,

    Resettlement

    Action Plans and other

    management plans for

    social and

    environmental impacts

    prepared and

    implemented

    5 - -

    Transparency

    and

    Accountability

    6.1 MC has an

    operational website

    6.2 MC has functional

    Complaint Tracking

    System

    6.3 MC has functional

    Performance

    Management System

    (PMS)

    6.1 Information available

    to citizens on MC’s

    website

    4 3 4

    6.2 CTS transformed into

    Grievance Redress

    Management System for

    MC

    2 - -

    6.3 MC responds to

    citizens’ requests per

    Right-to-

    Information Act

    2 2 2

    Operation

    Specific

    7.1 MC Chairman has

    signed Program

    Participation

    Agreement

    Urban

    Infrastructure

    7.1 Urban infrastructure

    targets achieved 20 7 12

    Total 100 40 55

    Minimum 50 numbers are required for each MC in FY 2020 -21 to qualify for PBGs

  • PCP Progress Report

    Page | 17

    5. UPDATE – MAJOR PROGRAM COMPONENTS

    5.1. Update - Institutional Strengthening

    A comprehensive outline is developed encompassing the process activities, roles & responsibilities of

    the stakeholders and documentation required as per agreed Means of Verification. PMDFC under the

    guidance of World Bank, identified process activities to be implemented to achieve desired targets.

    These activities have been framed keeping in view the targeted results to be achieved and the capacity

    of MCs’ staff against each result area, which is detailed in the implementation plan for MACs & PMs.

    The implementation plan has been prepared to schedule the activities for fulfilling MACs and

    achievement of PMs according to the prescribed timeline and delegated responsibilities. Contextually,

    the trainings / hands on sessions are being imparted to the designated/nominated MCs’ staff. This

    handholding of MC staff is ensuring not only to achieve the MACs and PMs but also to sustain these

    conditions in the subsequent years.

    Trainings / Visits/ Follow up Session

    PMDFC Team is providing continuous backstopping support to MCs’ staff for fulfillment of DLIs

    requirements to obtain targeted score for subsequent release of Funds. The Annual Performance

    Assessment will be carried out by an Independent Firm. Moreover, MCs’ staff are also being provided

    necessary backstopping support to make the interventions (i.e. updating of GIS based municipal services

    maps, Computerized Financial Management System, Performance Management System, Computerized

    Complaint Tracking System and MCs’ websites) functional. The following is a brief detail of

    trainings/field visits/ follow up sessions arranged during the time period of Oct - Dec 2020.

    Table 11: Trainings and Visits

    Sr.

    #

    Trainings / Session Topic /

    Field Visits

    Detail of Participants Training / Visit

    Date

    Venue

    A Field Visits for Implementation of Infrastructure Sub Projects under PCP

    1 Field Visits of 03 MCs Daska,

    Kamoke & Muridke for smooth

    implementation of Infrastructure

    sub projects

    Administrator, Chief

    Officer, MO (I&S),

    Sub Engineer &

    Contractors

    November 2020

    MC Offices

    2 Field visit of MC Khanewal to

    brief Public Representatives for

    future projects & budget.

    Deputy

    Commissioner,

    Public Representatives

    November 2020 MC Office

    3 Field Visit of MC Kot Addu for

    orientation session with CO and

    MO (I&S)

    Chief Officer & MO

    (I&S) Team

    November 2020 MC Office

    4 Site Visits of Infrastructure

    projects in MC Okara &

    Khanewal

    SPO- ID, PO-ID &

    DPO- ID

    December 2020 MC Office

    B Field Visits and Refresher Training Sessions on CFMS under PCP

    1 Budget & Cashbook Refresher Training

    Accountant

    CFMS Operator October 2020 PMDFC

    Office Lahore

    2 Visit to MC Jhelum for Pre-Audit Purpose

    CO, MO(Finance),

    Accountant

    CFMS Operator

    December 2020 MC Office

    3 Visit to MC Muridke, Kamoke, Wzirabad, Daska, Jhang &

    Hafizabad to make preparation

    of Audit

    CO, MO(Finance),

    Accountant

    CFMS Operator December 2020 MC Office

  • PCP Progress Report

    Page | 18

    C Refresher Training Sessions on Right To Information (RTI) Act

    1 Refresher Training Sessions on

    Right To Information (RTI) Act

    for partner MCs

    Public Information

    Officers

    (16 PCP MCs)

    Oct - Dec 2020

    (Continuous

    activity)

    PMDFC

    Office

    D Field Visits for Implementation of PMS, CTS, Website Updation

    1 Field Visits of 16 MCs to ensure

    implementation & fulfillment of

    MACs & PMs regarding IS

    interventions

    MC Management &

    Staff

    Oct - Dec 2020

    (Continuous

    activity)

    MC Office

    E Hands on Sessions on Performance Management System (PMS)

    1 Refresher Training sessions on

    data collection for water supply,

    solid waste and streetlight and

    updation in the PMS software

    relating Institutional

    Strengthening (2 sessions)

    Sub Engineer,

    Sanitary Supervisor,

    Light Inspectors,

    Water Supply In-

    charge

    Oct - Dec 2020

    (Continuous

    activity)

    PMDFC

    Office, Lahore

    F Hands on Sessions on Computerized Complaint Tracking System (CCTS)

    1 Refresher Training on CCTS,

    complaint registration, tracking,

    resolving and reports generation

    (daily, monthly, yearly)

    Computer Operators,

    Complaint Cell In-

    charge

    Oct - Dec 2020

    (Continuous

    activity)

    PMDFC

    Office, Lahore

    G Hands on Sessions on MCs Website Updation

    1 Refresher Training on Website

    updation for 16 partner MCs

    Superintendent &

    Computer Operator

    Oct - Dec 2020

    PMDFC

    Office, Lahore

    Note: Personnel are being trained periodically

    Planned Trainings

    Institutional Strengthening section of PCP is planning to organize a series of training sessions

    for 16 PCP MCs’ staff, in order to support PCP partner MCs to fulfil MACs & PMs for FY

    2020-21. The detail of planned sessions is given below;

    Table 11: Trainings and Visits

    Sr.

    No.

    Training Participants Date

    Detail Nos.

    1. Training Session on MC’s Financial

    Management & Audit

    Chief officer, MO (F) &

    Resident Assistant Director

    48 12th – 14th Jan,

    2021

    2. Training Session on Investment

    Planning & Budgeting and Urban

    Infrastructure

    Chief officer, MO (I&S) &

    Sub Engineer

    48 19th – 21st Jan,

    2021

    3. Training Session on Environment &

    Social Management and Procurement

    MO (I&S) & MO (P) 32 27th – 28th Jan,

    2021

    4. Training Session on MC’s

    Transparency & Accountability and

    Monitoring, Evaluation & Reporting

    Chief officer, MO (I&S) &

    PIO

    48 2nd – 4th Feb,

    2021

  • PCP Progress Report

    Page | 19

    Pictorial View - Trainings/Workshops/Visits of 16 PCP Cities

    Training Sessions on Energy and Fuel Audit

  • PCP Progress Report

    Page | 20

    Progress Reviewed by Secretary LG&CDD

    Environment Management Activities

    Trainings of MC Staff at PMDFC

  • PCP Progress Report

    Page | 21

    PCP Team Field Visits

  • PCP Progress Report

    Page | 22

    Update - Human Resource Management (HRM)/ Key Staffing Position

    As a legal covenant of PCP, LG&CDD shall maintain the appointment of provincially appointed staff

    (with acceptable qualification and experience) within the MCs throughout the period of operation

    implementation.

    In this context, LG&CD Department has been maintaining human resource management needs, updating

    and keeping track of postings/ transfer of key staff in 16 PCP partner cities. PMDFC is providing

    necessary support to LG&CD Department to make different staffing analyses time to time for decision-

    making. The data is being gathered/ compiled/ analyzed on major attributes.

    Details developed which highlighted following major attributes:

    Officer having no additional charge = 24

    Officer having one additional charge = 19

    Officer having two additional charges = 10

    Officer having three additional charges = 11

    Officer having four additional charges = 03

    Officer having five or more additional charges = 06

    Posts Vacant = 02

    Additionally, the personnel is grouped into provincially or locally appointed staff to highlight the actual

    gaps. Vacancy position is further trickled to describe the total number of sanctioned, filled and vacant

    positions of 16 PCP cities.

    The detail of current status of officers and vacancy position analysis is placed at Annex – B.

    5.2. Update - Environment & Social Management

    PCP’s IPF Window (technical assistance component) supports the strengthening of social and

    environmental risk management systems in the 16 MCs. It will finance the strengthening of: a) social

    and environmental management focal points in each MC; b) the creation of environmental and social

    management systems at the city level; and c) rolling out a training program by PMDFC for city officials.

    Moreover, environmental and social considerations will be mainstreamed by updating SOPs, O&M

    manuals, and investment planning strategies with a special focus on gender inclusion.

    Development of SOPs for Environment, Health &Safety for workers/Labor (Including

    Women Labor) in Urdu

    The SOPs for Environment, Health & Safety for

    workers/Labor (Including Women Labor) developed in

    Urdu for relevant stakeholders for well understand.

    Key Features of SOPs are:

    SOPs for construction Camp Management

    SOPs for Workers/Labor Health and Safety at

    Construction Site

    SOPs for Environment, social, health & safety of

    Local Residents

    The dissemination of these SOPs to internal & external

    stakeholders will be done after printing as well as the

    training on these SOPs of both internal & external

    stakeholders will also be conducted.

    Title page of SOPs for EHS

  • PCP Progress Report

    Page | 23

    Table 12: ESM progress under Window 2 of Institutional Strengthening

    Proposed Activities as per

    PAD

    Activities Performed by ESM team of CMT

    Ensure appointment of social

    and environment

    management focal persons in

    each MC.

    Notification of MO (I&S) as focal person for Environmental and MO

    (P) as focal person for Social management has been done.

    Mainstream social and

    environmental considerations

    in the updating of SOPs,

    O&M manuals, and

    investment planning

    strategies.

    SOPs for “Environment, Health and Safety of

    Labor/Workers” have been developed and made part of

    ESMF of PCP

    Gender Framework has been developed and made part of

    ESMF of PCP

    Communication Framework has been developed and made

    part of ESMF of PCP

    Monitoring Framework has been developed and made part of

    ESMF of PCP

    Disclosure of Sub-Projects Information has been developed

    and made part of ESMF

    Stakeholders Consultation Framework has been developed

    and made part of ESMF

    Grievance Redress Mechanism has been developed and made

    part of ESMF

    Develop SOPs, screening

    checklists, and mitigation

    measures based on ESSA

    recommendations, to put in

    place documented procedures

    and processes for the

    management of environment

    and social risks.

    SOPs and Environmental and Social Screening Checklists for

    all the sub-projects of PCP have been developed and made

    part of ESMF of PCP

    As per ESSA recommendations, questions related to

    archeological sites and PCRs ,gender and vulnerable groups

    have also been incorporated in the Screening Checklists

    For the Sub-Projects of FY 2019-20,environmental and social

    screening has been carried out by using the Screening

    Checklists

    Develop training modules and

    train MC staff.

    Training/Capacity Enchantment Framework has been

    developed and made part of ESMF

    First Training/Briefing session with the nominated ESFPs has

    been conducted on 11th to 15th May as “ESMF Preliminary

    Consultation & Briefing Session.”

    Consultative Sessions on Environment & Social Management Framework (ESMF)

    Sr.# Session Topic / Detail of Participants Date Venue

    1 Consultative Sessions on

    Environment & Social

    Management Supports the

    strengthening of social and

    environmental risk

    management systems in the

    16 MCs

    Additional Secretary

    (Technical) )

    Forest, Wildlife and

    Fisheries Department,

    (FWFD)

    October 2020 Forest, Wildlife and

    Fisheries

    Department,

    (FWFD)

  • PCP Progress Report

    Page | 24

    6. UPDATE – PROGRAM STEERING COMMITTEE – DECISIONS

    Table 13: Update on Decisions taken in 2nd meeting of Program Steering Committee (PSC)

    Sr. # Agenda Item Decisions Action Plan/ Taken

    1. Update on Punjab Cities Program (PCP)

    i. Opening of designated accounts for PMDFC and

    FD for IPF Funds

    LG&CD Department and PMDFC will coordinate with

    FD to expedite the opening of designated assignment

    account.

    1. Completed: Separate designated accounts to be operated by

    LG&CDD & PMDFC has been opened

    2. In Progress: Designated accounts for PFC unit of FD - yet to be opened (Account will be opened, as PC – I approves from

    the competent forum)

    ii. PC-I for TA under IPF window

    Issuance of administrative approval will be ensured at

    the earliest

    PC-I for Technical Assistance under IPF window approved by

    CDWP on 18th Nov, 2019

    iii. Opening of accounts for Performance Based

    Grants (PBGs)

    If concerned municipalities fail to deposit their

    counterpart funding within week time, then option of at

    source deduction will be applied

    Opening of accounts for Performance Based Grants (PBGs):

    • Accounts opened and 20% counterpart funding have been deposited by partner MCs for FY 2020-21 (For 12 MCs, FD has

    deposited counterpart funding, to meet one of the MAC)

    iv. Priority list of Maintenance & Repair

    Infrastructure Projects

    (Year-1)

    Procurement process will be completed as per timelines • PC-Is approved from competent forum & subsequent Administrative Approvals issued

    • Infrastructure Schemes (M&R) • Total Schemes : 44 in 16 MCs - 03 groups • A: Rehabilitation (16), B: Repair (12), C: Supply (16) • Letter of Award – 43 schemes (Dropped – 01 scheme) • Commencement of work – 43 schemes

    v. PC-IIs for Consultancy (1st Year)

    Instant PC-IIs will be submitted to P&DD by January

    10, 2020 Condition of PC-IIs for consultancy services as mentioned in

    PC-I, have been waived off vide letter dated Feb 10,2020

    Hiring of Annual Performance Assessment Firm o Consultant Selection Committee notified by LG&CDD on

    Oct. 20, 2020

    o Advertisement has been published on Oct 30, 2020 (closing date: Nov 16, 2020)

    o Received EOIs being evaluated by LG&CD department

  • PCP Progress Report

    Page | 25

    Hiring of External Audit Firm o Contract agreement signed on Nov 14, 2020 – Consultants

    Mobilized

    Sectoral Planning, Design & Supervision of Infrastructure Projects

    o TORs have been revised and approved by World Bank o RFP issued on Dec 05, 2020 o Proposal submission from shortlisted consultants by Jan 07,

    2021

    vi. Hiring of Program Staff Hiring of staff will be completed as per timelines Hiring of key staff completed

    Process for hiring of rest of staff being initiated through NTS

    vii. Retroactive Financing Withdrawal application will be submitted to the World Bank

    Amount USD 1.2 Million against Retroactive Financing disbursed by World Bank on Feb 26, 2020

    3. Finalization of Program Operation Manual (POM)

    Draft POM was approved by PSC Program Operational Manual (POM) is approved by PSC on January 02, 2020

    4. Approvals for hiring of Program staff & service

    charges to be paid to

    PMDFC

    After deliberations, the service charges @ 2.92% (PKR

    1,051.924 million) were approved in line with

    recommendations of Program Executive Committee

    and approved PC-I from CDWP.

    The approval of Steering Committee may be regularized to ease out the payment process.

    5. Mode of procurement of goods and works for

    infrastructure projects in

    Municipal Committees

    All goods and works for infrastructure sub projects will

    be procured and managed by MCs. PMDFC may assist

    the MCs for said procurements

    As per decision made in the meeting, PMDFC is assisting in procurement of all goods and works for infrastructure sub

    projects being procured and managed by MCs

    Additional Agenda Items

    1. Social, economic and environmental safeguards

    of foreign-aided projects

    ECA Wing P&D Board will devise a framework in

    consultation with concerned stakeholders to ensure the

    compliance of social, economic and environmental

    safeguards of foreign-aided projects

    • The Environment & Social Management Framework developed for PCP will be reviewed by P&D Department to make it a

    template for upcoming foreign funded projects.

    2. Program Steering Committee Meeting

    ECA Wing P&D Board will get formulated and issue a

    calendar of PSC meetings of all foreign-aided projects

    • PMDFC will ensure to manage the PSC meetings as per the calendar issued by ECA wing of all foreign-aided projects.

  • PCP Progress Report

    Page | 26

    7. UPDATE - PROGRAM ACTION PLAN

    Table 14: Brief on Program Action Plan Issue/risk description Action/completion Timeframe Responsible party Instrument Status

    Provincial level

    16 Municipal Committees

    (MCs) are sensitized to

    the IPF and performance-

    based grant (PBG) system

    PMDFC will conduct workshops to sensitize

    and inform all Program MCs about PCP,

    MACs, PMs, PBGs, and the IPF Window.

    MCs will fully operationalize systems

    developed under PMSIP. No disbursement

    will be made to any defaulting MC against

    the achievement of reduced MACs.

    Within one month

    after effectiveness

    Before the

    assessment of

    reduced MACs

    LG&CDD/PMDFC

    MCs

    DLI/MACs

    MACs

    Completed

    Workshops arranged on 27& 28

    March, 2019 to sensitize and

    inform all Program MCs about

    PCP, MACs, PMs, PBGs, and

    the IPF Window

    Reduced MAC assessed by

    World Bank Team - evidence /

    documentation on the

    achievement of first set of DLRs

    has been shared with the World

    Bank on May 27, 2019 through

    LG&CDD

    Subsequently funds amounting

    USD 9.52 million has been

    released.

    Release of funds from the

    Provincial Consolidated

    Fund to implementing

    agencies is delayed

    because of budgetary

    constraints of GoPunjab

    FD will ensure that PBG disbursements to

    MCs are fully integrated into the provincial

    budget and released to cities within 30 days

    of disbursement by the Bank. Failing this,

    further Program disbursements will be

    suspended.

    Annual FD Legal

    Covenant Completed for FY 2020-21

    Performance Based Grants

    (released against verification of

    DLRs achieved) have been

    released to MCs in the month of

    September 2020.

    MCs reporting on the use

    of grant funds

    MCs will report on grant funds utilization

    through required biannual and annual

    reporting processes, using customized Chart

    of Accounts for new conditional grants in

    budget, and expenditure recording second

    year onwards.1

    After the

    beginning of

    FY18/19 MC

    budget cycle

    LG&CDD and FD Annual

    Reports and

    APA

    On going

    Requisite backstopping support

    being provided to MCs

    Hiring process for APA firm for

    verification of DLRs – FY2019

    20 annulled (in line with WB

    advice) due to lean response

    received as restriction in

    1The POM includes provision for reporting mechanisms for Year1.

  • PCP Progress Report

    Page | 27

    Issue/risk description Action/completion Timeframe Responsible party Instrument Status

    The APA will report on implementation

    status and compliance with environmental

    and social management and investments.

    movement imposed by

    Government of Punjab under

    COVID 19 emergency.

    Process has been re-initiated to

    hire independent firm for

    verification of DLRs (FY 2020-

    21), and consulting firm will be

    on board by Jan 31, 2021.

    Advertisement published on Oct

    30, 2020

    Closing Date: Nov 16, 2020

    Shortlisting completed and

    working paper prepared by

    LG&CDD to convene meeting

    for evaluation, consultants

    expected to be on board by end

    of Feb 2021

    Timeliness of independent

    annual assessment

    LG&CDD will procure an independent

    private firm for APA (annually or on

    multiyear contract), and ensure adherence to

    PBG disbursement cycle.

    Annually LG&CDD Legal

    Covenant

    Process has been re-initiated to

    hire independent firm for

    verification of DLRs (FY 2020-

    21), and consulting firm will be

    on board by Jan 31, 2021.

    Advertisement published on Oct

    30, 2020

    Closing Date: Nov 16, 2020

    Shortlisting completed and

    working paper prepared by

    LG&CDD to convene meeting

    for evaluation, consultants

    expected to be on board by end

    of Feb 2021

    Hiring process for APA firm for

    verification of DLRs – FY2019

    20 annulled (in line with WB

    advice) due to lean response

    received as restriction in

    movement imposed by

  • PCP Progress Report

    Page | 28

    Issue/risk description Action/completion Timeframe Responsible party Instrument Status

    Government of Punjab under

    COVID 19 emergency.

    Potential environmental

    and social impacts of

    infrastructure projects

    are identified, mitigated,

    and monitored

    MCs will seek guidance on environmental

    and social management system as described

    in the POM, which is consistent with

    provincial systems and principles.

    Appointment of Environmental Specialists

    and Social Development Specialists for each

    PMDFC team (Lahore-based team plus three

    regional teams).

    Technical staff in MCs trained on O&M

    Manuals as part of sensitization conducted

    by the LG&CDD/ PMDFC.

    Within one month

    after effectiveness

    Within three

    months after

    effectiveness

    Before first grant

    disbursement

    LG&CDD and

    PMDFC

    PMDFC

    LG&CDD and

    PMDFC

    POM

    POM

    POM

    ESMF has been approved by

    WB

    Environment & Social

    Development Specialists have

    been hired for each PMDFC

    Team (Lahore-based team plus

    three regional teams)

    Ongoing

    Trainings of technical staff are

    being conducted

    Vacant positions of

    provincially appointed

    MC officials compromise

    implementation capacity

    LG&CDD/LGB will appoint qualified

    officials to fill vacancies in provincially

    appointed MC positions.

    Tenure of provincially appointed officials

    will be maintained by LG&CDD/LGB for at

    least 3 years, except for exceptional cases.

    Ongoing

    Ongoing

    LGB and LG&CDD

    LGB and LG&CDD

    Legal

    Covenant

    PAP

    Ongoing

    LG&CD department is

    maintaining requisite staff in

    place in 16 MCs of the project.

    Dual charges still persists

    Updated status is placed at

    Annex A

    No certification /financial

    statement audit is carried

    out by DG District Audit,

    or annual audit is delayed

    DG District Audit, Punjab will ensure that

    the audits of the financial statements of the

    16 MCs are conducted, and reports shared

    with the Bank not later than October 30 each

    year. A private audit firm maybe used in the

    initial years, if DG District Audit does not

    have requisite capacity. Program

    disbursements will be suspended if the audit

    reports are not delivered on time.

    Annual DG District

    Audit/Private Firm

    MAC and

    PAP

    For initial years, A Private Audit

    Firm may be used in place of

    DG District Audit.

    RFP issued on Sep 29, 2020

    Contract Agreement signed on Nov 14, 2020 – Consultants

    mobilized

    Hiring process for Audit firm

    (Year I) annulled due to non-

    receipt of EOIs as restriction in

    movement imposed by

    Government of the Punjab under

    COVID – 19 emergency.

    Municipal Committee level

  • PCP Progress Report

    Page | 29

    Issue/risk description Action/completion Timeframe Responsible party Instrument Status

    Insufficient capacity at

    MCs to implement

    program

    MCs will maintain focal persons for finance,

    planning, internal audit, accounting,

    procurement, and complaint handling

    throughout implementation.

    Over Program

    implementation

    MCs MAC Ongoing Focal Persons complaint

    handling notified.

    Insufficient reporting on

    Program activities

    MCs will provide bi-annual and annual

    reports on financial and Program

    implementation, safeguard management,

    grievance redress, and other relevant

    information.

    Over Program

    implementation

    MCs and PMDFC MAC and

    PM Ongoing

    PMDFC is regularly following

    up and providing backstopping

    support to MCs to accomplish

    MACs and PMs

    Potential environmental

    and social impacts of

    infrastructure projects

    are identified, mitigated,

    and monitored

    MCs will appoint focal persons for

    Environment and Social Management.

    MCs will adopt and implement the updated

    Environmental and Social Management

    Framework (ESMF).

    MCs will update and implement the

    following already developed under PMSIP:

    (a) Communication Strategy (b) Public Consultation Framework

    MCs will develop, notify, and implement

    SOPs for Physical Cultural Resources and

    Health, Safety, and Environment.

    MCs will improve enforcement of labour and

    gender-related laws

    MCs will ensure generation and monitoring

    of environmental data, and coordination with

    relevant agencies

    Institutional strengthening of

    LG&CDD/LGB

    Over Program

    implementation

    Before subproject

    implementation

    Over Program

    implementation

    Over Program

    implementation

    Over Program

    implementation

    Over Program

    implementation

    Before first grant

    disbursement

    MCs

    PMDFC and MCs

    PMDFC and MCs

    PMDFC and MCs

    PMDFC and MCs

    PMDFC and MCs

    PMDFC

    MAC

    ESSA

    ESSA

    ESSA

    ESSA

    Updated

    ESMF

    Updated

    ESMF

    Focal Persons designated for

    Environment and Social

    Management

    ESMF has been approved by

    WB

    SOPs developed & approved by

    WB

    SOPs for health, safety and

    environment have been

    developed and made part of

    ESMF (shared with WB)

    Screening questions for PCRs

    have been incorporated in the

    E&S screening checklist and

    final procedure have been

    included in the ESMF main

    document

    Labour and gender-related

    policies/laws have been made

    part of EHS SOPs

    Completed - reports shared with

    WB

    Training/ capacity building

    manuals have been developed.

  • PCP Progress Report

    Page | 30

    ANNEXURES

    Annex A

    Progress of Schemes

    Table 15: Summary

    Sr.

    No

    Zon

    e

    Nam

    e of

    MC

    Gro

    up

    Contractor

    Name

    Cost

    (million

    Rs)

    Aw

    ard

    Date

    Com

    men

    ce

    men

    t

    Date

    Per

    iod

    (Mon

    ths)

    Scheduled

    date of

    completion

    Time

    Lapsed

    (Month)

    Tim

    e

    Lap

    sed

    /Req

    uir

    ed

    Sch

    edu

    led

    Pro

    gre

    ss

    (%)

    Ph

    ysi

    cal

    pro

    gre

    ss

    (%)

    Exp

    end

    itu

    re

    incu

    rred

    (Mil

    lion

    Rs.

    )

    Fin

    .

    Pro

    gre

    ss

    (%)

    1

    So

    uth

    Pu

    nja

    b

    Khan

    ewal

    A Mohammad Asif 75.03 31-Mar-20 09-May-20 8 08-Jan-21 7.83 96% 64% 28.21 38%

    B Abdul Hameed

    Ghori and Co. 7.41 07-May-20 05-Jun-20 8 04-Feb-21 6.93 85% 70% 4.15 56%

    C M.s Traders 11.49 31-Mar-20 09-May-20 8 08-Jan-21 7.83 96% 96% 11.49 100%

    2

    Veh

    ari A

    Naveed

    Construction Co. 89.08 24-Apr-20 29-Apr-20 8 28-Dec-20 8.17 100% 36% 13.04 15%

    B Faiz e Aam

    Construction 6.74 24-Apr-20 22-Apr-20 8 21-Dec-20 8.40 100% 63% 3.74 55%

    C Sadaqat Builders 4.22 24-Apr-20 22-Apr-20 8 21-Dec-20 8.40 100% 43% 1.50 36%

    3

    Bah

    wal

    nag

    ar

    A Saddaqat

    Builders 86.3 11-May-20

    13-May-

    20 8 17-Jan-21 7.70 93% 62% 46.89 54%

    B Tahir Mehmood 17.67 26-Nov-20 01-Dec-20 4 31-Mar-21 0.97 24% 0% 0.00 0%

    C Superior

    Builders 5.87 11-May-20

    14-May-

    20 5 13-Oct-20 7.67 100% 66% 3.27 56%

    4

    Bu

    rew

    ala

    A Ch. Majeed

    Tahir 81.95 27-Apr-20

    27-Apr-

    20 8

    26-Dec-

    20 8.23 100% 81% 39.36 48%

    C M.S.Traders 10.58 08-Aug-20 27-Aug-20 4 26-Dec-

    20 4.17 100% 81% 6.50 61%

    5

    Ko t

    Ad

    du

    A Abdul Majeed

    Khan 35.75 22-Jul-20 08-Sep-20 6

    07-Mar-

    21 3.77 63% 30% 6.62 19%

  • PCP Progress Report

    Page | 31

    B Muhammad

    Athar 14.14 22-Jul-20 04-Sep-20 6

    03-Mar-

    21 3.90 65% 25% 2.19 15%

    C Javaid & Co. 10.13 27-Apr-20 15-May-20 6 14-Nov-

    20 7.63 100% 52% 0.00 0%

    6

    Cen

    tral

    Pu

    nja

    b

    Jhan

    g

    A Roheela Traders 45.45 18-Jun-20 06-Jul-20 6 05-Jan-21 5.90 97% 83% 5.37 12%

    B Rush

    Construction 38.33 21-Apr-20

    28-Apr-

    20 8

    27-Dec-

    20 8.20 100% 14% 1.76 5%

    C Javaid and

    Company 8.73 21-Apr-20

    28-Apr-

    20 7

    27-Nov-

    20 8.20 100% 78% 2.35 27%

    7

    Gojr

    a

    A Hanif Anjam 61.99 12-May-20 02-Jun-20 8 01-Feb-21 7.03 86% 82% 38.83 63%

    B Liaqat

    Construction 4.84 12-May-20

    21-May-

    20 6

    20-Nov-

    20 7.43 100% 75% 1.90 39%

    C Hanif Anjam 8.15 12-May-20 02-Jun-20 6 01-Dec-

    20 7.03 100% 77% 5.10 63%

    8

    Okar

    a

    A

    Itthad JV

    Mehboob

    Builders

    55.29 07-May-20 15-May-

    20 8 04-Jan-21 7.63 98% 59% 6.21 11%

    B

    Itthad JV

    Mehboob

    Builders

    26.79 07-May-20 15-May-

    20 8 04-Jan-21 7.63 98% 73% 0.00 0%

    C Ittehad Brothers 21.28 26-Oct-20 03-Nov-

    20 5

    26-Mar-

    21 1.90 40% 11% 0.00 0%

    9

    Jara

    nw

    ala

    A Roheela Traders 88.07 24-Apr -20 11-May-

    20 8 10-Jan-21 7.77 95% 72% 30.21 34%

    B M.M Tariq

    Builder 3.41 21-Oct-20

    03-Nov-

    20 3 03-Feb-21 1.90 62% 32% 0.00 0%

    C Suleman

    Engineering 11.24 25-Apr-20

    21-May-

    20 4 20-Sep-20 7.43 100% 72% 2.50 22%

    10

    Kam

    alia

    A

    Muhammad

    Iqbal Javaid &

    Co.

    60.01 16-May-20 17-Jun-20 8 16-Feb-21 6.53 80% 54% 20.75 35%

    B - - 0.00

  • PCP Progress Report

    Page | 32

    C Javed &

    Company 7.44 11-Apr-20

    29-Apr-

    20 6 28-Oct-20 8.17 100% 59% 2.62 35%

    11 N

    ort

    h P

    un

    jab

    Jhel

    um

    A Hashim Ali

    Safdar 45.03 19-May-20 04-Jun-20 7 03-Jan-21 6.97 100% 89% 36.58 81%

    C Hashim Ali

    Safdar 3.35 02-Jul-20 09-Jul-20 4.80

    30-Nov-

    20 5.80 100% 82% 0.94 28%

    12

    Waz

    irab

    ad

    A

    United

    Construction

    Company

    91.66 05-May-20 11-May-

    20 7.80

    31-Dec-

    20 7.77 100% 72% 60.31 66%

    C M/s Qamar U

    Din & Sons 5.207 04-Nov-20

    19-Nov-

    20 4.20

    25-Mar-

    21 1.37 33% 0% 0.00 0%

    13

    Kam

    oke A Imran Sharif 100.09 13-Apr-20

    15-May-

    20 12 30-Apr-21 7.63 65% 30% 12.05 12%

    C Imran Sharif 8.62 22-Aug-20 28-Aug-

    20 3

    27-Nov-

    20 4.13 100% 86% 0.00

    14

    Muri

    dke A

    Choudhary

    Enterprises 82.62 13-Jul-20

    13-Aug-

    20 8 12-Apr-21 4.63 58% 46% 40.00 48%

    B Roheela Traders 5.15 13-Jul-20 10-Aug-20 6 09-Feb-21 4.73 78% 39% 0.00 0%

    C Best Corporation 3.35 13-Jul-20 10-Aug-

    20 6 09-Feb-21 4.73 78% 75% 0.00 0%

    15

    Haf

    izab

    ad

    A Ch. Amjad Ali 58.41 13-Jul-20 09-Sep-20 8 08-May-

    21 3.73 46% 53% 0.00 0%

    B Mian Waqas

    Engineers 0.39 15-Aug-20 29-Sep-20 3 28-Dec-20 3.07 100% 100% 0.39 100%

    C M.S. Traders 7.95 15-Aug-20 15-Sep-20 6 15-Mar-21 3.53 59% 25% 2.15 27%

    16

    Das

    ka

    A Nazeer Ahmad

    & Brother's 70.66 07-Sep-20 24-Sep-20 8

    23-May-

    21 3.23 40% 21% 0.00 0%

    B Nazeer Ahmad

    & Brother's 2.06 07-Sep-20 11-Sep-20 3

    10-Dec-

    20 3.67 100% 72% 0.00 0%

    C Mehboob

    Builders 2.18 01-Jun-20 16-Jun-20 5

    15-Nov-

    20 6.57 100% 44% 0.96 44%

    Total 1384.09 53% 437.93 32%

  • PCP Progress Report

    Page | 33

    Punjab Cities Program - Rehabilitation of Municipal Services Infrastructure Projects

    Table 16: Beneficiaries Detail of Package-I (North Region)

    Sr.No MC Component of Work Beneficiaries

    1 Jhelum

    Water Supply System 55,000

    Sewerage System 95,000

    Street Lights 65,000

    Office Buildings 400

    2 Wazirabad

    Water Supply System 58,000

    Sewerage System 90,000

    Street Lights 62,000

    Office Buildings 425

    3 Kamoke

    Water Supply System 175,000

    Sewerage System 50,000

    Street Lights 40,000

    Parks 50,000

    4 Muridke

    Water Supply System 115,000

    Solid Waste Management 150,000

    Sewerage System 130,000

    Streets Lights 60,000

    Parks 40,000

    5 Hafizabad Water Supply System 150,000

    Sewerage System 120,000

    6 Daska

    Water Supply System 150,000

    Solid Waste Management 115,000

    Sewerage System 200,000

    Streets Lights 45,000

    Table 17: Beneficiaries Detail of Package-II (Central Region)

    Sr.No MC Component of Work Beneficiaries

    1 Kamalia

    Sewerage System 95,000

    Water Supply System 54,000

    Solid Waste Management 50,000

    Street Light 65,000

    Parks 110,000

    Office Building, MC Library & MC Mosque

    Equipment 450

    2 Okara

    Sewerage System 155,000

    Water Supply System 190,000

    Solid Waste Management 340,000

    Street Light 52,000

    Parks 110,000

    Office Building, MC Library & MC Mosque

    Equipment 1,100

    3 Jhang

    Sewerage System 64,000

    Water Supply System 48,000

    Solid Waste Management 280,000

    Street Light 151,000

  • PCP Progress Report

    Page | 34

    Sr.No MC Component of Work Beneficiaries

    Office Building, MC Library & MC Mosque

    Equipment 700

    4 Jaranwala

    Sewerage System 80,000

    Water Supply System 48,000

    Solid Waste Management 182,000

    Street Light 151,000

    Parks 90,000

    Office Building, MC Library & MC Mosque

    Equipment 450

    5 Gojra

    Sewerage System 157,000

    Water Supply System 90,000

    Solid Waste Management 92,000

    Street Light 42,000

    Parks 72,000

    Office Building, MC Library & MC Mosque

    Equipment 350

    Table 18: Beneficiaries Detail of Package-III (South Region)

    Sr.No MC Component of Work Beneficiaries

    1 Bahawalnagar

    Water supply system 138,300

    Sewerage and Drainage system 104,000

    Solid Waste Management 126,720

    Street Light 32,500

    Parks 70,200

    2 Burewala

    Sewerage System 203,722

    Street Light 81,344

    Parks 152,850

    Solid Waste Management 277,500

    Water Supply System 130,680

    3 Vehari

    Water supply system 101,300

    Sewerage and Drainage system 106,000

    Solid Waste Management 120,000

    Street Light 76,000

    Parks 53,000

    4 Khanewal

    Water supply system 182,000

    Sewerage 253,000

    Solid Waste Management 344,000

    Street Light 87,000

    Parks 66,000

    5 Kot Addu

    Solid Waste Management 98,000

    Water supply system 84,000

    Sewerage 147,000

    Street Light 84,000

    Parks 128,000

  • PCP Progress Report

    Page | 35

    Annex - B

    Current Status of Officers Posted at MCs

  • PCP Progress Report

    Page | 36

    Table 19: Vacancy Position Analysis

    MCs having 50% or more vacant posts

    40%

    63%

    55%

    45%

    56%

    36%

    27%

    73%

    40%

    54%54%

    20%

    63%

    56%

    42%

    50%

    Ba

    ha

    wa

    lna

    ga

    r

    Bu

    rew

    ala

    Da

    ska

    Go

    jra

    Ha

    fiza

    ba

    d

    Ja

    rra

    nw

    ala

    Jh

    an

    g

    Jh

    elu

    m

    Ka

    ma

    lia

    Ka

    mo

    ke

    Kh

    an

    ew

    al

    Ko

    t A

    dd

    u

    Mu

    rid

    ke

    Oka

    ra

    Ve

    ha

    ri

    Wa

    zir

    ab

    ad

    Provincially Appointed Staff - % Vacant

    20%

    45%

    40%

    45%

    45%

    71%

    50%

    38%38%

    43%

    25%

    16%

    68%

    39%

    25%25%

    Locally Appointed Staff - % Vacant

    21%

    46%

    40%

    45%46%

    70%

    50%

    39%

    38%44%

    26%

    16%

    67%

    39%

    26%26%

    Total Posts- % Vacant