wp3 status review
DESCRIPTION
G NSS for IN novative R oad A pplications. WP3 Status Review. WP 3.2.2 Trials execution: launch of activities 10 th March Lisbon. Exhaustive trials campaing started 2nd week of March GMV vehicle already performing tests, navteq car will follow soon - PowerPoint PPT PresentationTRANSCRIPT
GNSS for Innovative road Applications
Company’s
logo
WP3 Status Review
WP 3.2.2 Trials execution: launch of activities
10th March
Lisbon
GNSS for INnovative Road Applications
GNSS for Innovative road Applications
Company’s
logo21/04/23 Page 2PRESENTATION TITLE VERDANA (9)
• Exhaustive trials campaing started 2nd week of March
• GMV vehicle already performing tests, navteq car will follow soon
• GMV exhaustive trials expected to be finished by last week of march/first of april.
• Navteq trials conclusion to be discussed yet
• Exhaustive trials routes being tested & evaluated
• Slight modifications and possible changes to be submitted to TRL for approval
• Exhaustive routes data, in GINA format, to be submitted daily to Avego for analysis in GMV case, weekly for Navteq
• Possible changes in geo-object to be discussed with TRL
Exhaustive trials
GNSS for Innovative road Applications
Company’s
logo
End2End Trials
• End2End trials scheduled to be started by last week of march
• OBUs production under course after some delays due to providers related troubles
• All OBUs expected to be installed within March
• End2End core system to be operational by the end of March
• End2End trials volunteers and geo-objects already completed
• OBUs will upload received data in GINA format in a daily basis and stored in the project ftp server
• Possible SW or Data changes to be updated remotely in the OBUs
• Installation and maintenance issues to be deal with by approved installators in the Netherlands.
• Analysis of the data could be performed by Avego once the data begins to be stored in GMV ftp server
GNSS for Innovative road Applications
Company’s
logo21/04/23 Page 4PRESENTATION TITLE VERDANA (9)
Development to start after E2E development ends
Fleet Management– GIS Map with real-time vehicle positioning
Incident Management– Automatic detection of time taken from incident detection to arrival
on site. Contract obligations enforcement
– Provide reports with information regarding specific sites and times monitored per day
Still waiting on AENOR authorization for vehicle usage
AENOR trials
GNSS for Innovative road Applications
Company’s
logo21/04/23 Page 5PRESENTATION TITLE VERDANA (9)
Enforcement trials not succesfully concluded as scheduled
APRN system integration completed
OBU Enforcement Module not integrated
OBU/APRN Communication Integration to be concluded in remote tests between GMV & GMV-SKY
Remote tests to be started by next week, final live test to be performed after remote tests succesfully concluded
Final tests location to be discussed between GMV & GMV-SKY
Enforcement Trials
GNSS for Innovative road Applications
Company’s
logo
The following actions have been undertaken by the project team in order to prepare for trials evaluation and reporting:
Data formats and outputs from test vehicles agreed Sample reference (truth) data provided to Avego Geo-Objects provided to Avego Avego analysis HUB set up to perform the following Exhaustive-
trials data analysis:
21/04/23 Page 6PRESENTATION TITLE VERDANA (9)
Preparation for trials evaluation:
GNSS for Innovative road Applications
Company’s
logo21/04/23 Page 7PRESENTATION TITLE VERDANA (9)
Preparation for trials evaluation:
Agreed Data Format:
- One File per Journey
- Files will be named as per agreed format
routeId-date-starttime-endtime-deviceId.txt
- Files will have the following fields
Field DescriptionWEEK GPS Week
GPS_SECOND GPS Second
LAT OBE Latitude (WGS84 LatLon)
LON OBE Longitude (WGS84 Latlon)
TRUE_LAT Truth Latitude
TRUE_LON Truth Longitude
DIST Distance measured based on OBE positions
TRUE_DIST Distance Measured based on Truth positions
HPL HPL from EGNOS
NSATS Number of Satallites in View
GEO_OBJECTX 1- in geoobject 0-outside geoobjectAs measured by OBE
TRUE_GEO_OBJECTX
1- in geoobject 0-outside geoobjectAs measured by Truth
GNSS for Innovative road Applications
Company’s
logo
For each of the OBU configurations the following will be evaluated and analysed against truth:
Charging Performance – (To be confirmed). – Variation in charge, over Geo-Objects/routes/daily runs/entire data
set– Under/over charging assessment inline with GMAR– Under/over charging inline with Dutch targets
21/04/23 Page 8PRESENTATION TITLE VERDANA (9)
Preparation for trials evaluation: Exhaustive
GNSS for Innovative road Applications
Company’s
logo21/04/23 Page 9PRESENTATION TITLE VERDANA (9)
Preparation for trials evaluation: Exhaustive
Metric Description Calculation Aggregation
Journey Distance Accuracy
Deviation in the overall calculated length of the journey between the truth and test devices.
Truth Distance – OBE Distance
DayRouteOverall
Absolute Journey Distance Accuracy
Absolute value of the distance accuracy.
|Distance Accuracy| DayRouteOverall
Geoobject Distance Accuracy
Deviation in the calculated length of the geoobject usage between the truth and test devices.
(Truth Distance Exit Point – Truth Distance Entry Point) – (OBE Distance Exit point – OBE Distance Entry Point)
DayRouteGeoobjectOverall
Absolute Geoobject Distance Accuracy
Absolute value of the geoobject distance accuracy.
|Geoobject Distance Accuracy|
DayRouteGeoobjectOverall
Each Distance Accuracy metric will be calculated per Journey:
GNSS for Innovative road Applications
Company’s
logo21/04/23 Page 10PRESENTATION TITLE VERDANA (9)
Preparation for trials evaluation: Exhaustive
Metric Description Calculation Aggregation
Position Accuracy Per epoch distance between the Truth and test positions
Dist( (LAT,LON), (TRUE_LAT, TRUE_LON)
DayRouteOverall
Cross Track Accuracy
Per epoch distance between the test position and line struck thru truth positions.
CrossTrack( (LAT, LON), line(TRUE_LAT, TRUE_LON))
DayRouteOverall
Availability Distribution function of accuracy.
Day Route Overall
Continuity Gaps in time (number and length) in OBE position solutions.
DayRouteOverall
Each metric will be calculated per Journey:
GNSS for Innovative road Applications
Company’s
logo21/04/23 Page 11PRESENTATION TITLE VERDANA (9)
Preparation for trials evaluation: Exhaustive
Metric Description Calculation Aggregation
TTFF Time between journey start (from file name) and first position solution of OBE.
Day RouteOverall
Journey Start Distance Accuracy
Take the max time to first fix across all journeys and calculate the positional accuracy within this time for all journeys
Day RouteOverall
Journey Start Position Accuracy
As above for position accuracy between the test and truth device.
Day RouteOverall
Each metric will be calculated per Journey:
GNSS for Innovative road Applications
Company’s
logo21/04/23 Page 12PRESENTATION TITLE VERDANA (9)
Preparation for trials evaluation: ExhaustiveMetric Description Calculation Aggregation
EGNOS Availability
Distribution function of HPL. HPL DayRouteOverall
Integrity Risk Percentage of readings where the distance between the truth and test positions is greater than the HPL.
Position Accuracy > HPL
DayRouteOverall
Satellites in View Distribution of the count of satellites in view
NSAT DayRouteOverall
Incorrect Geoobject Identification
Distance recorded incorrectly in geoobject as % of overall chargable distance for that geoobject.
Where GEOOBJECT_X = 1TRUTH_GEOOBJECT_X = 0
DayRouteOverallGeoobject
Missed geoobject identification
Distance not recorded in geoobject as % of overall chargable distance for that geoobject.
Where GEOOBJECT_X = 0TRUTH_GEOOBJECT_X = 1
DayRouteOverallGeoobject
GNSS for Innovative road Applications
Company’s
logo
For each of the OBU configuration (GPS or GPS and EGNOS) the following will be evaluated and analysed over all participants and Geo-Objects:
Position (AVEGO)– Analysis of impact of size of protection levels on Geo-Object
identification (on EGNOS enabled devices) Distance (AVEGO)
– Distance variations from the “truth”– Analysis of variations in distance through Geo-Objects
Availability of satellites per zone/area (CENIT)– Signal interference (e.g. urban canyons)– Signal Occultation (e.g. tunnels)
For the purpose of End-to-end trials where no reference data is available for comparison, “truth” for lengths of Geo-Objects will be derived from map data.
21/04/23 Page 13PRESENTATION TITLE VERDANA (9)
Preparation for trials evaluation: End-to-End
GNSS for Innovative road Applications
Company’s
logo
For each of the OBU configuration (GPS or GPS and EGNOS) the following will be evaluated and analysed over all participants and Geo-Objects:
Charging (AVEGO)– Analysis of variation in charges for known Geo-Object charges
Driver reaction (Aenor)– Assess driver willingness to change driving habits (questionnaire)– Gather general feedback on charging zones/fees/etc…– For drivers with fixed habits/routes compare data for different days
(e.g. charges, distances) Value Added Services (Aenor)
– Usefulness– Ease of use – Suggested improvements
21/04/23 Page 14PRESENTATION TITLE VERDANA (9)
Preparation for trials evaluation: End-to-End
GNSS for Innovative road Applications
Company’s
logo
For each of the OBU configuration (GPS or GPS and EGNOS) the following will be evaluated and analysed over all participants and Geo-Objects:
SISNeT (CENIT)– Evaluation of SISNeT as a platform for transmitting integrity
information– Analysis of latency of corrections and its potential impact on real-time
VAS. Interference (CENIT)
– Availability of signal during the trial over whole data set Complexity of installation (GMV) Crossing of the Dutch border (CENIT) Lessons learned (CENIT)
21/04/23 Page 15PRESENTATION TITLE VERDANA (9)
Preparation for trials evaluation: End-to-End
GNSS for Innovative road Applications
Company’s
logo
Following analysis of trial data by Avego, TRL will produce trial evaluation report as D3.3-Trials data package, evaluation and results report and D3.4-Market trial report (including technical and user-experience assessment)
Expected delivery for of the report is at T0+21
21/04/23 Page 16PRESENTATION TITLE VERDANA (9)
Preparation for trials reporting:
GNSS for Innovative road Applications
Company’s
logo