wpd connections overview ian sandford primary system design team manager – south wales & south...
TRANSCRIPT
WPD Connections Overview
Ian Sandford
Primary System Design Team Manager – South Wales & South West
February 2015
2
Service Territory
Our distribution services area
WPD operate 4 of the 14 UK electricity licences and distributes electricity to 7.8m customers
Connections in WPD
We deal with approximately 50,000 connection enquiries in a year including 6,000 for generator connections
We connect approximately 36,000 new sites in a year– 35,000 small sites connected at LV – 1000 large sites connected at HV– 60 large sites connected at EHV
A key change has been the increase in the number of generating plants connected to the distribution system
We have connected over 4000MW of generation Much of the electricity network is now constrained or at capacity due
to the amount of DG that has connected
3
Connections – who does what
Customer – apply for the connection and co-ordinate the various parties
DNO – licenced operator who provides the connection from the network to the meter
IDNO – alternate network providers who build, own and operate network assets
ICP – alternate network providers, DNO adopts assets Supplier – provides the bill and arranges meter readings Meter Operator – carries out metering activities for the supplier Ofgem – regulates the gas and electricity distribution and
transmission networks. Sets Guaranteed Standards of performance for connections and agrees charging methodologies
4
The key stages in the process
The process for making an electricity connection varies according to what is being connected and the impact it has on the existing network but the key stages are;
Information
Application
Quotation and Agreements
Construction and Connection
5
6
Information
The WPD website provides information and guidance for customers, developers and connection providers seeking connection services including;
Information on the process of connecting to the network– EREC G83 ‘Recommendations for the connection of small-scale
embedded generators (up to 16A per phase) in parallel with public low voltage distribution networks’
– EREC G59 ‘Recommendations for the connection of generation plant to the distribution systems of licensed distribution network operators
– Competition in Connections guidance and information Information to identify opportunities to connect to the network
Information WPDWebMap – site specific PDF of assets Small Scale Mapping – 1:25,000 PDF of 132kV down to
11kV assets EHV system map – high level map of 132, 66 and 33kV
networks Estimated capacity on 11kV/LV substations Constraint map - highlighted 33kV with voltage or
thermal issues Project underway to implement data extract in KLM
format (viewable with google map) and also containing data attributes
7
• Held 4 times per year in our regional Distribution offices closest to where most participants live
• 26th March 2015• 17th June 2015• 10th September 2015• 10th December 2015
Timetable
Information
Connection Surgeries Following a successful trial last year we
are rolling out an annual schedule of Connection Surgeries
Our Connection Surgeries allow customers to discuss face-to-face with one of our engineers, either the process of applying for a connection in general or specifics about a particular scheme
Particularly aimed at DG connection customers, the surgeries provide assistance with questions on process, timescales, technical requirements and possible constraints in a particular network area
8
9
Application
It is important to contact us in the early stages
Three options– Call our Contact Centre– Apply online - application forms are available on our website– Send an Application Form to our Records Team
1 day contact – internal standard implemented to contact customer to discuss connection after application
10
Application- what information do we need?
The information we require varies depending on what you want to connect but generally we need;– Contact details and site address– Do you need a budget or a formal offer?– A site layout plan showing where the connection is required– The capacity of the connection – The type e.g. demand or generation– Any special equipment characteristics
11
Timescales for providing quotations
The timescales for WPD to provide a quotation for non contestable quotations are– 45 working days for LV generator connections; and– 65 working days for HV and EHV generation connections
The timescales for WPD to provide a quotation for contestable (POC) quotations are– 30 working days for LV generator connections; and– 50 working days for HV and EHV generation connections
Compensation is paid if WPD miss these deadlines There are other standards that apply throughout the connections
process
12
Quotations
Estimates and quotations are produced by local Network Service Teams up to 33kV
Above 33kV design is quotation is by our Primary Systems Design Team
Our Network Services planners are responsible for a section of the network and therefore have valuable local knowledge when discussing and designing connections for customers
Our planners handle both requests for connection by WPD and competition in connection (CiC) requests from connection providers
Our quotation will break our charges down into the areas that are contestable and non contestable
13
Contestable and non contestable
Contestable– work that can be done by an independent connections provider
(ICP) Non contestable
– work that must be done by the DNO If you wish to appoint an ICP to carry out the contestable works they
must be accredited with Lloyds Register
We will adopt the works after completion and require an adoption agreement from you/your ICP
IDNOs also provide networks that they operate and own
14
Minimising your connection charge
Your connection charge will be based on the minimum scheme to make the connection
To smooth the process and keep costs to a minimum we recommend– Provide early details of the full load requirements so that we can
prepare an accurate offer quickly– Legal consents, particularly wayleaves can take time, this is an
area where you may be able to help us– Consider undertaking your own excavation and civil works to
reduce our charge– Shortest route lengths and service positions close to your
equipment minimise the costs
Agreements
For a typical DG connection the following agreements are required: Formal Offer – the contract between you and us to pay for the
specified connection Wayleaves and Consents – depending on the connection there may
be requirements to transfer or lease land to WPD for the connection assets
Local Authority consents and DECC Section 37 consents Connection Agreement – the enduring agreement for the connection
once energised Adoption Agreement – where the connection works are carried out by
an independent connection provider this is the agreement for WPD to adopt the assets constructed
15
16
Construction and Connection
The local team is responsible for the delivery of network activities including connections
These teams handle all competitive and non-competitive connection enquiries up to 11kV for unmetered, metered demand and generation schemes.
At 33kV and above the works are delivered by our locally based major projects teams
Customers will have a named contact and telephone number throughout the process
You will need to appoint a supplier and arrange the metering
17
Connections process summaryCall our Contact
Centre, apply online or send an Application Form to our Records
Team (ensure you enclose a plan)
We will calculate the Connection Charge
and send you an Offer showing Contestable and Non-contestable
costs
Decide whether you want us to do all the work or to appoint an ICP to carry out the Contestable work
If you wish to use an ICP, appoint them and ask them to apply to
us for an Offer
If you want us to carry out all the work, sign and return the Offer
acceptance, together with payment
We will contact you to discuss a date to carry out the work and any other requirements
e.g. obtaining Wayleaves or consents and completing a
Connection Agreement
Register your new supply MPAN with an electricity supplier and arrange your metering
Before we visit, please complete any on- site works which you may
be providing
We will complete the works and energise
your connection
Where to find out more
There is a lot information and advice on the WPD website – simply click on the “connections tab” including
– G59 technical guidance on the requirements that you must meet before the generating plant can be connected to the network
– WPD charging statement
– Connecting Community Energy
Register for one of the UK wide “DG forums”
Sign up for a WPD connections surgery
18
19
Useful websites and telephone numbers
Websites– www.westernpower.co.uk– www.ofgem.gov.uk– www.energynetworks.org– www.decc.gov.uk
Contact us
New Supplies, Records Team
Western Power Distribution
Toll End Road
Tipton
DY4 0HH– Tel: 0845 724 0240– Email: [email protected]