Page 1: WS1 CP New Connections Registration Process KN (1)

Delivered By: Instructor NameDelivered By: Instructor Name Course Duration: 5.45 HoursCourse Duration: 5.45 Hours

New ConnectionsNew Connections

Classroom PresentationClassroom Presentation

Page 2: WS1 CP New Connections Registration Process KN (1)

Agenda

Day 1

Housekeeping 0900 - 0915

Course Introduction 0915 - 0930

Process Overview 0930 - 1000

New Connections Registration 1000 - 1200

Lunch Break 1200 - 1245

New Connection Cancellation 1245 - 1500

Summary and Assessment 1500 - 1530

2

Page 3: WS1 CP New Connections Registration Process KN (1)

Housekeeping

Ground Rules

• Mobile phones in silent mode

• Punctuality

Fire alarm/Evacuation

Emergencies

Breaks/Lunch

Location of restrooms/cafeteria

Refreshments

3

Page 4: WS1 CP New Connections Registration Process KN (1)

Introduction/Icebreakers

Introduction of trainers

Introduction of participants

Introduction of others present

4

Page 5: WS1 CP New Connections Registration Process KN (1)

Target Audience/Roles

5

KN
gave feedback long time ago that this slide was too cluttered and added little value. change last 2 bullets to just one - NMS, remove operations coordinator and planning and just have one CSA (remove senior). make this the same for all ws1 documents
Page 6: WS1 CP New Connections Registration Process KN (1)

Learning Journey

6

CC&B Introduction (Basic) CC&B Introduction (Advanced – if applicable)

Customer Account Management

Completed

New Connections

Change of Tenancy Change of Supplier Fieldwork Customer Management

Next

Page 7: WS1 CP New Connections Registration Process KN (1)

Course Objectives

After completing this course, you will be able to:

Complete a new connection request

Understand the steps involved in the rejection of a registration process

Cancel registration for a pending new connections request

Understand the steps involved in the rejection of a cancellation request

7

Page 8: WS1 CP New Connections Registration Process KN (1)

Assigned (NB status for meter point – Electricity Only): Assigned is the status that the Network Business (NB) gives the meter point when it is connected to the network for the first time. This is not yet registered to a supplier and hence not energised.

Campaign: A Campaign is a structured effort by Power NI to offer a set of packages (goods and services) to the existing customers or new prospects.

Glossary

8

Page 9: WS1 CP New Connections Registration Process KN (1)

Direct Debit: Direct Debit (or Autopay) is the preferred method of payment within Power NI where customers pay on either a monthly or a quarterly basis.

• Monthly DD is a fixed automatic payment deducted from the customer's account once a month on a date of their choice; while quarterly DD is a variable amount whereby the full amount of the bill is deducted from the account two weeks after the bill date.

Glossary (Contd.)

9

Page 10: WS1 CP New Connections Registration Process KN (1)

• GPRN: A Gas Point Registration Number (GPRN) is a unique reference number assigned to every gas point on the gas network. GPRNs have up to 7 digits. Example: 2354868.

• Log Entry: Log is information captured by the CSA for every customer interaction. The CSA can record log entries at any point in time during the process. The log entry is used for tracking purposes.

Glossary (Contd.)

10

KN
this will be confusing later as it is contacts that primarily will record details of customer interactions. clarify that the log captures details within a case.
Page 11: WS1 CP New Connections Registration Process KN (1)

• Market Messages: Market messages are communication messages exchanged between Power NI and Network Business (NB). For example, it functions like an exchange of emails between two parties. But unlike email, each market message holds information that is processed automatically and appropriate details in the system are updated accordingly.

• MPRN: Meter Point Reference Number (MPRN) is a unique 11-digit number assigned to every single electricity connection and meter in the country. Each MPRN refers to a premise. Example: 10009998888

Glossary (Contd.)

11

Page 12: WS1 CP New Connections Registration Process KN (1)

Order: Orders are created after information is captured for person, account, and premise and these orders are specific to New Connections, Change of Supplier, and Change of Tenancy. Order captures the additional information required to send the market messages besides what has been captured during registration.

Rejection Reason Codes: Whenever NB rejects a new connection request raised by Power NI, it assigns a Rejection Reason Code to indicate the reason for rejection.

Service Agreement: A service agreement (SA) is a contract between Power NI and a customer. The SA contains the terms and conditions controlling how the system will charge the customer for any services they are supplied with.

Glossary (Contd.)

12

Page 13: WS1 CP New Connections Registration Process KN (1)

• Site Works: Site works refers to any physical work performed by NB at the customer’s premise in relation to their gas supply.

• Solicited: Solicited market messages are received from NB as a response to a request from the Supplier/Shipper.

• Unsolicited: Unsolicited market messages are received from the NB on an ad hoc basis and are not in response to a request from the Supplier/Shipper.

Glossary (Contd.)

13

Page 14: WS1 CP New Connections Registration Process KN (1)

New Connections Overview

14

Page 15: WS1 CP New Connections Registration Process KN (1)

Introduction

The customer details captured in the Customer Account Management (CAM) process is the base process for the New Connection (NC), Change of Supplier (CoS), and the Change of Tenancy (CoT) processes. The customer details captured in the CAM process runs into these processes.

Page 16: WS1 CP New Connections Registration Process KN (1)

New Connection Process

16

The New Connection process includes two scenarios:

• New Connection Registration Process - The New Connection Registration process involves registering a customer at a new premise which is being connected to the network for the first time.

• New Connection Cancellation Process - The New Connection Cancellation process involves cancelling the registration before the New Connection Registration process is complete.

o If customer wishes to cancel the process after the new connection has been completed, then Change of Supplier (CoS) process has to be followed.

These processes are facilitated by the transfer of information using market messages between Power NI and the Network Business (NB).

Page 17: WS1 CP New Connections Registration Process KN (1)

After completing this section, you will be able to:

Understand the key steps in the New Connection Registration process

Understand the steps involved in the rejection of a Registration process

Understand the steps involved in the New Connection Cancellation process

Understand the steps involved in the rejection of a Cancellation request

Process Objectives

17

Page 18: WS1 CP New Connections Registration Process KN (1)

New Connection Registration Process - MPRN

18

Customer contacts Power NI for Registration

Check if the customer

exists in the system

Yes

No A new customer record is created

as per CAM

An order is created for the customer and CSA submits the customer registration request

A market message (010) is sent to the NB

The NB returns a market message (101/105) confirming

the registration

Issues Welcome Pack to the customer

Page 19: WS1 CP New Connections Registration Process KN (1)

New Connection Registration Process - GPRN

19

Customer contacts Power NI for Registration

Check if the customer

exists in the system

Yes

NoA new

customer record is created.

An order is created for the customer

A market message (G601RQ) is sent to the NB

The NB returns a market message (G604N) confirming the

registration

Issues Welcome Pack to the customer

CSA books site works appointment and submits the customer registration request.

KN
the orange bubble text is different on this slide than previous slide
Page 20: WS1 CP New Connections Registration Process KN (1)

Rejection of New Connection Registration Process - MPRN

20

NB rejects the registration request sent by Power NI

CSA checks if the

customer needs to be contacted

Yes

No

CSA resolves the rejection and completes

the ToDo

CSA contacts the customer and resolves the rejection

Market Message 101R is sent to Power NI

Based on the rejection reason code, CC&B creates a ToDo for the CSA or

issues an automatic letter.

CSA resubmits the registration request by

resubmitting 010

Yes

End

No

A letter is sent to the customer.

Page 21: WS1 CP New Connections Registration Process KN (1)

Rejection of New Connection Registration Process - GPRN

21

NB rejects the registration request sent by Power NI

CSA checks if the

customer needs to be contacted

Yes

No

CSA resolves the rejection and completes

the ToDo

CSA contacts the customer and resolves the rejection

Market Message G602RJ is sent to Power NI

Based on the rejection reason code, either a To Do is created or

a letter is automatically sent to the customer

CSA resubmits the registration request by resubmitting G601RQ

Yes

End

No

KN
there is no box for sending the letter in this diagram
Page 22: WS1 CP New Connections Registration Process KN (1)

Cancellation of New Connection Registration Process-MPRN

22

The NB returns a market message (111) confirming

the cancellation

A market message (011) is sent to the NB

Customer details are updated and a letter is issued to the customer

Customer contacts Power NI

to cancel the registration

Power NI makes the decision to

cancel the registration

Page 23: WS1 CP New Connections Registration Process KN (1)

Cancellation of New Connection Registration Process-GPRN

23

The NB returns a market message (G607N)

confirming the cancellation

A market message (G605RQ) is sent to the NB

Customer details are updated and a letter is issued to the customer

Customer contacts Power NI

to cancel the registration

Power NI makes the decision to

cancel the registration

Page 24: WS1 CP New Connections Registration Process KN (1)

Rejection of New Connection Cancellation Process - MPRN

24

NB rejects the cancellation request sent by Power NI

Market Message 111R is sent to Power NI

A To Do is created for the CSA to resolve

A letter is automatically sent to the customer

Page 25: WS1 CP New Connections Registration Process KN (1)

Rejection of New Connection Cancellation Process - GPRN

25

NB rejects the cancellation request sent by Power NI.

Market Message G606RJ is sent to Power NI.

Based on the rejection reason code, either a To Do is created or

a letter is automatically sent to the customer.

If a To Do is created, CSA resolves the rejection and

completes the To Do.

After completing the To Do, CSA resubmits the cancellation

request or creates a manual customer contact and letter, if they cannot resolve the To Do

Page 26: WS1 CP New Connections Registration Process KN (1)

You have completed this course, and should now be able to:

Understand the key steps in the new connection registration process

Understand the steps involved in the rejection of a registration process

Understand the steps involved in the new connection cancellation process

Understand the steps involved in the rejection of a cancellation request

Process Review

26

Page 27: WS1 CP New Connections Registration Process KN (1)

Process 1

New Connection Registration

27

Page 28: WS1 CP New Connections Registration Process KN (1)

Business Context

28

The New Connection Registration process is used to register a new premise which is being connected onto the network for the first time for a new, existing or previous customer.

The initial registration process is as described in Customer Account Management, i.e, add/edit person, add/edit account, add premise and add/edit payment details.

After all customer details are recorded, an order is created and sent to the NB for confirmation.

NB processes the request and replies to Power NI through market messages indicating acceptance or rejection of the request.

• If accepted, the details received are updated in the system and a Welcome pack is sent to the customer.

• If rejected, based on the rejection code, either a To Do is created for the CSA or a letter is automatically sent to the customer.

Page 29: WS1 CP New Connections Registration Process KN (1)

After completing this section, you will be able to:

Create an Order

Schedule an appointment (only for Gas customers)

Complete an order

Resubmit an order

Identify the various request and response market message related to New Connection Registration process

Understand the steps involved in the rejection of a registration request

Process Objectives

29

Page 30: WS1 CP New Connections Registration Process KN (1)

Register a Customer for Electricity

30

To register a customer, the following steps must be performed:

• Register customer details (as described in the CAM course)

o If the customer is an existing customer or a previous customer, create a new Service Agreement (SA) against the existing account . This is done only if the customer is in the same CIS division and customer's usage type is same as in the existing account.

o If the customer is new to Power NI, create a new account by collecting all the information like customer details, premise details, and payment details from the customer.

• Create an Order

o Complete the order questions

• Select the eligible package (tariff) for the customer

• Complete the order

At this point a market message is sent to the Network Business (NB) requesting confirmation of the registration of the new customer.

Page 31: WS1 CP New Connections Registration Process KN (1)

Process Steps – New Connection Registration for MPRN

31

Net

wo

rk

Bu

sin

ess

Net

wo

rk

Bu

sin

ess

Page 32: WS1 CP New Connections Registration Process KN (1)

Market Messages for New Connection Registration - MPRN

32

Request sent to NB

by Power NI

Response Received by Power NI from NB

Market Messages

010Registration Request

101P Provisional Acceptance

101R Rejected

101331/332/700 - meter details

Accepted

The following are the different market messages received from NB on the request of 010 by Power NI:

KN
do all staff need to know these last 3 during the classroom presentation - will it lead to confusion?
Page 33: WS1 CP New Connections Registration Process KN (1)

Register a Customer for Gas

33

The registration process for a Gas customer is similar to that for an electricity customer. The key differences to note include:

• At the time of registering the customer’s details, an appointment is required to be booked by the supplier (Power NI).

• The information carried in the market messages is different and is based on the individual requirements set by the NB for electricity and gas respectively. As a result of different information on the market message, the questions on the order will be changed.

Page 34: WS1 CP New Connections Registration Process KN (1)

Process Steps – New Connection Registration for GPRN

34

Page 35: WS1 CP New Connections Registration Process KN (1)

Market Messages for New Connection Registration - GPRN

35

Request sent to NB

by Power NI

Response Received by Power NI from NB

Market Messages

G601RQRegistration Request

G603N Provisional Acceptance

S1501N Rescheduled

101R Rejected

G604N Accepted

The following are the different market messages received from NB on the request of G601RQ by Power NI:

Page 36: WS1 CP New Connections Registration Process KN (1)

Rejection of New Connection Registration Process - Electricity

36

If Network Business (NB) rejects the registration request, the market message 101R is sent to Power NI.

The status of the registration request is set to Rejected and a log entry is added.

Based on the rejection code, either a To Do is created for the CSA to investigate or a letter is automatically issued to the customer advising them that their new connection request was unsuccessful.

A letter is automatically sent, if there is no opportunity for the CSA to resolve the rejection.

If a To Do is created, CSA identifies if the customer needs to be contacted to resolve the rejection.

• If customer contact is required, CSA contacts the customer to get the required information and resolves the rejection.

• If customer contact is not required, CSA resolves the cause of rejection and completes the ToDo.

Page 37: WS1 CP New Connections Registration Process KN (1)

Rejection of New Connection Registration Process - Electricity

(Contd.)

37

On resolving the rejection issue, CSA resubmits the registration request.

• On resubmitting the request, the registration request is initiated.

If the reason for rejection cannot be resolved, the CSA must manually create a Customer Contact to send a letter to the customer informing them that the registration is unsuccessful.

Page 38: WS1 CP New Connections Registration Process KN (1)

Rejection of New Connection Registration Process - Gas

38

If Network Business (NB) rejects the registration request, the market message G602RJ is sent to Power NI.

The status of the registration request is set to Rejected and a log entry is added.

Based on the rejection code, either a To Do is created for the CSA or a letter is automatically issued to the customer advising them that their new connection request was unsuccessful.

A letter is automatically sent, if there is no opportunity for the CSA to resolve the rejection.

If a To Do is created, CSA identifies if the customer needs to be contacted to resolve the rejection.

• If customer contact is required, CSA contacts the customer to get the required information and resolves the rejection.

• If customer contact is not required, CSA resolves the cause of rejection and completes the ToDo.

Page 39: WS1 CP New Connections Registration Process KN (1)

Rejection of New Connection Registration Process – Gas (Contd.)

39

On resolving the rejection issue, CSA resubmits the registration request.

• On resubmitting the request, the cancellation request is initiated.

If the reason for rejection cannot be resolved, the CSA must manually create a Customer Contact to send a letter to the customer informing them that the registration is unsuccessful.

Page 40: WS1 CP New Connections Registration Process KN (1)

Instructor Demo

Demo 1 – Create and complete an order for registering a customer for single premise, single account – electricity (For an existing customer).

Demo 2 – Register a new customer for one account with multiple premises – Keypad.

Demo 3 – Resolve a rejection To Do and resubmit the request (Scenario: MPRN does not exist).

40

Page 41: WS1 CP New Connections Registration Process KN (1)

Exercises

• Exercise 1 – Create and complete an order for registering a customer for single premise, single account – electricity (For an existing customer).

• Exercise 2 – Register a new customer for one account with multiple premises – Keypad.

• Exercise 3 – Resolve a rejection ToDo and resubmit the request (Scenario: MPRN does not exist).

41

Page 42: WS1 CP New Connections Registration Process KN (1)

Review Key Characteristics

42

Register a Customer (Add Account, Add Person, Add Premise)

Create an Order

Note: If the request is for a gas customer, an appointment must be booked by

Power NI for site works.

Rejection of registration request

o Selects the To Do created by the system

o Resolves the To Do

o Resubmits the request

Page 43: WS1 CP New Connections Registration Process KN (1)

You have completed this course, and should now be able to:

Create an Order

Schedule an appointment (only for Gas customers)

Complete an order

Resubmit an order

Identify the various request and response market message

related to New Connection Registration process

Understand the steps involved in the rejection of a registration request

Process Review

43

KN
this is not covered at all?
Page 44: WS1 CP New Connections Registration Process KN (1)

Process 2

New Connection Cancellation

44

Page 45: WS1 CP New Connections Registration Process KN (1)

Business Context

45

The New Connection Cancellation process is triggered under three different scenarios:

• When a customer contacts Power NI to cancel the registration

• When Power NI decides to cancel the registration, and;

• When an unsolicited cancellation message is received from the NB.

The new connection registration process can be cancelled only when the process is pending (not completed); otherwise it follows the Change of Supplier (CoS) process.

Page 46: WS1 CP New Connections Registration Process KN (1)

After completing this section, you will be able to:

Understand the valid reasons for cancelling a new connection registration

Cancel a new connection registration process:

• On request initiated by customer

• Initiated by the business

Understand various request and response market messages related to New Connection cancellation

Understand the steps involved in the rejection of a new connection cancellation request

Understand the concept behind an unsolicited cancellation of a new connection request

Process Objectives

46

Page 47: WS1 CP New Connections Registration Process KN (1)

Cancel a Customer Registration

47

The status of the registration request is set to ‘Pending Cancel’ and a log entry is added.

To cancel a pending registration, the following steps must be performed:

• Power NI sends out a market message informing NB of the cancellation. The CSA needs to select the correct cancellation reason while sending the market message to NB.

• NB responds to the cancellation request with either an acceptance or rejection message:

o If accepted, a cancellation requested acceptance letter is sent to the customer.

o If rejected, depending on the code in the rejection message, either a letter is automatically sent to the customer or a To Do is created for the CSA. A letter is automatically sent, if CSA does not have the opportunity to try and resolve the rejection.

Page 48: WS1 CP New Connections Registration Process KN (1)

Process Steps

48

Page 49: WS1 CP New Connections Registration Process KN (1)

Market Messages for New Connection Cancellation - Electricity

49

Request sent to NB

by Power NI

Response Received by Power NI from NB

Market Messages

011Cancel registration request

111R Rejected

111 Accepted

The following are the different market messages received from NB on the request of 011 by Power NI:

Page 50: WS1 CP New Connections Registration Process KN (1)

Reason Codes for Cancelling a Registration

50

Cancellation Reason Codes Description

CR Customer requests not to proceed with the contract to supply

SE Customer registers the meter point in error but cancellation is not as a result of an objection

The following are the reason codes Power NI use to cancel a registration sent to NB:

KN
clarify if these codes are sent from BN to Power NI OR Power NI to NB?
Page 51: WS1 CP New Connections Registration Process KN (1)

Market Messages for New Connection Cancellation - Gas

51

Request sent to NB

by Power NI

Response Received by Power NI from NB

Market Messages

G605RQCancel registration request

G606RJ Rejected

G607N Accepted

The following are the different market messages received from NB on the request of G605RQ by Power NI:

Page 52: WS1 CP New Connections Registration Process KN (1)

Rejection for New Connection Cancellation - Electricity

52

If Network Business (NB) rejects the cancellation request, the market message 111R is sent to Power NI.

The status of the cancellation request is set to Cancellation Rejected and a log entry is added.

Based on the rejection code, either a To Do is created for the CSA or a letter is automatically sent to the customer.

• A letter is automatically sent, if the CSA does not have the opportunity to try and resolve the rejection.

• If a To Do is created for the CSA and if the CSA cannot resolve the To Do:

o A customer contact is created, and

o The Cancellation Rejection letter is sent to the customer.

• If CSA resolves the To Do, the CSA resubmits the cancellation request.

Page 53: WS1 CP New Connections Registration Process KN (1)

Reason Codes for Rejecting a Cancellation Request - Electricity

53

The following are some of the reason codes that NB sends while rejecting a new connection cancellation request (111R).

Rejection Reason Codes Description

CCC Fieldwork completed and so registration cannot be cancelled.

IMP The MPRN does not exist.

IMS A cancellation request is received for new registration and the MPRN status is energised. A cancellation request can also be received for a terminated meter point.

IRC The cancellation reason code is invalid.

SNR The supplier submitting the cancellation request is not registered to this MPRN or does not have a pending registration.

Page 54: WS1 CP New Connections Registration Process KN (1)

Reason Codes for Rejecting a Cancellation Request - Electricity

54

The following are some of the reason codes that NB sends while rejecting a new connection cancellation request (111R).

Rejection Reason Codes (ROI) Description

IA The 011 received was a duplicate request. MRSO Already have a valid, cancellation for this MPRN.

DIJ Data invalid for jurisdiction.

Page 55: WS1 CP New Connections Registration Process KN (1)

Rejection for New Connection Cancellation - Gas

55

If Network Business (NB) rejects the cancellation request, the market message G606RJ is sent to Power NI.

The status of the cancellation request is set to Cancellation Rejected and a log entry is added.

Based on the rejection code, either a To Do is created for the CSA or a letter is automatically sent to the customer.

• Once the To Do is completed, the CSA resubmits the registration request.

• If CSA is not able to resolve the rejection, a cancellation rejection letter is sent to customer.

Page 56: WS1 CP New Connections Registration Process KN (1)

56

Process Steps

Page 57: WS1 CP New Connections Registration Process KN (1)

Reason Codes for Rejecting a Cancellation Request - Gas

57

Rejection Reason Codes Description

GDNE GPRN does not exist

NNDG Not an NDM GPRN

GPPS GPRN not provisionally registered to Shipper

ISSC Invalid Shipper ID/Supplier ID Combination

SSDS Shipper status does not support this request type

ISRN Site works reference number does not exist

The following are the reason codes that NB sends while rejecting a new connection cancellation request (G606RJ) .

Page 58: WS1 CP New Connections Registration Process KN (1)

Reason Codes for Rejecting a Cancellation Request - Gas(Contd.)

58

Rejection Reason Codes Description

RRBS Original Site Works Reference Number belongs to another shipper

SRBG Original Site Works Reference Number belongs to another GPRN

OSNS Original Site Works Reference Number not set aside for Registration Related Activity

SCCT Site Works cannot be cancelled because of time constraints

SWAC Site Work already complete

ORCR Outstanding Registration cancellation request at this GPRN

Page 59: WS1 CP New Connections Registration Process KN (1)

Unsolicited Cancellation for New Connection

59

Sometimes NB sends an unsolicited request to cancel the customer’s registration.

In such a scenario:

• A To Do is created for the appropriate role to resolve. If the To Do is resolved, the new connection registration process is resubmitted; else the registration process is cancelled.

Example: NB sends an unsolicited cancellation if the request cannot be completed within the permitted timeframes. The reason code for this would be ‘TO’.

Page 60: WS1 CP New Connections Registration Process KN (1)

Instructor Demo

• Demo 1 – Cancel a pending registration on a customer request – Dual-fuel (for only electricity).

• Demo 2 – Identify the reason code for a new connection cancellation rejection (Scenario: New Connection request already completed).

60

Page 61: WS1 CP New Connections Registration Process KN (1)

Exercises

• Exercise 1 – Cancel a pending registration on a customer request – Dual-fuel (for only electricity).

• Exercise 2 – Identify the reason code for a new connection cancellation rejection (Scenario: New Connection request already completed).

61

Page 62: WS1 CP New Connections Registration Process KN (1)

Review Key Characteristics

62

The customer or the business initiates a new connection cancellation process.

Based on the rejection reason code, a To Do is created or a letter is automatically sent to the customer.

Power NI sends out a cancellation rejection letter to the customer when the cancellation request is rejected.

CSA resubmits the cancellation request after resolving the rejection issue.

If the CSA cannot resolve the To Do:

• A customer contact is created, and

• The Cancellation Rejection letter is sent to the customer.

KN
clarify with bullet point above? this is confusing
Page 63: WS1 CP New Connections Registration Process KN (1)

You have completed this course, and should now be able to:

Understand the valid reasons for cancelling a new connection registration

Cancel a new connection registration process:

• On request initiated by customer

• Initiated by the business

Understand various request and response market messages related to New Connection cancellation

Understand the steps involved in the rejection of a new connection cancellation request

Understand the concept behind an unsolicited cancellation of a new connection request

Process Review

63

Page 64: WS1 CP New Connections Registration Process KN (1)

Review Your Knowledge

64

Page 65: WS1 CP New Connections Registration Process KN (1)

You have completed this course, and should now be able to:

Complete a new connection request

Understand the steps involved in the rejection of a new connection registration process

Cancel registration for a pending new connections request

Understand the steps involved in the rejection of a new connection cancellation request

Course Review

65

Page 66: WS1 CP New Connections Registration Process KN (1)

Parking Lot

Have we met the course expectations you stated at the beginning of this course?

Are there any questions in the parking lot that are not answered?

66

Page 67: WS1 CP New Connections Registration Process KN (1)

Course Evaluation

Complete the course evaluation using SurveyMonkey.

Your instructor will provide you with instructions on accessing SurveyMonkey and completing your course evaluation.

It will take you 5 to 10 minutes to complete the course evaluation.

67

KN
is surveymonkey agreed?
Page 68: WS1 CP New Connections Registration Process KN (1)

Course Quiz

A course quiz is provided to all users to assess their understanding of the course.

Your instructor will provide you with instructions on taking the assessment.

68

Page 69: WS1 CP New Connections Registration Process KN (1)

CC&B Help Menu (Alt + F1)

User Guides and Simulations

Super Users

ES Project Team Members

ES Helpdesk (?)

Training Sandbox

Need Help After the Course?

69