wsdot perspective on map-21 and pavement … russell...map-21 and pavement management ... •...

20
WSDOT Perspective on MAP - 21 and Pavement Management Mark Russell Pavement Design Engineer Washington State DOT 1

Upload: hoangkhanh

Post on 09-Apr-2018

216 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: WSDOT Perspective on MAP-21 and Pavement … Russell...MAP-21 and Pavement Management ... • Structure (deflection, seismic response) • Remaining Service Life (RSL) ... • Long

WSDOT Perspective on MAP-21 and Pavement Management

Mark RussellPavement Design Engineer

Washington State DOT

1

Page 2: WSDOT Perspective on MAP-21 and Pavement … Russell...MAP-21 and Pavement Management ... • Structure (deflection, seismic response) • Remaining Service Life (RSL) ... • Long

Performance Management in MAP-21Title 23, U.S.C.

2

Page 3: WSDOT Perspective on MAP-21 and Pavement … Russell...MAP-21 and Pavement Management ... • Structure (deflection, seismic response) • Remaining Service Life (RSL) ... • Long

Performance MeasuresFor Decision Making

• Project & Network Level Pavement Management

For Accountability• State Legislature• Governor’s Office• State Auditor’s Office• GASB• MAP-21

3

Page 4: WSDOT Perspective on MAP-21 and Pavement … Russell...MAP-21 and Pavement Management ... • Structure (deflection, seismic response) • Remaining Service Life (RSL) ... • Long

Typical PavementPerformance Measures

• Present Serviceability Index (PSI) - 1958• Roughness (IRI) - 1986• Distress (cracking, rutting, raveling, faulting, etc.)• Friction (Skid Number, macrotexture, IFI)• Structure (deflection, seismic response)• Remaining Service Life (RSL)

What about cost?? Performance at what price??

4

Page 5: WSDOT Perspective on MAP-21 and Pavement … Russell...MAP-21 and Pavement Management ... • Structure (deflection, seismic response) • Remaining Service Life (RSL) ... • Long

Cost-Effectiveness

“…the most efficient investment…”– Annual Cost ($ / lane-mile / year of life)

• Historical Cost of Acceptable Pavement Performance– Actual historical cost ($/LMY)

• Expected Cost of Future Pavement Rehab– Projected LCCA ($ /LMY)

5

Page 6: WSDOT Perspective on MAP-21 and Pavement … Russell...MAP-21 and Pavement Management ... • Structure (deflection, seismic response) • Remaining Service Life (RSL) ... • Long

• Long Term– Evaluating Pavement Design Strategies over

many performance periods– Assumed performance– FHWA RealCost

• Operational (Year-to-Year)– Historical performance is known– Evaluation of single performance period– Decisions involve maintenance/preservation

and rehabilitation/reconstruction

Comparing LCCA

6

Page 7: WSDOT Perspective on MAP-21 and Pavement … Russell...MAP-21 and Pavement Management ... • Structure (deflection, seismic response) • Remaining Service Life (RSL) ... • Long

Maint.(what, when,

where, how, why)

Rehab.(what, when,

where, how, why)

Reconst.(what, when,

where, how, why)

Cost(minimize annual

life-cycle cost)

Performance(achieve minimum

requirement)

Decisions and Outcomes

7

Page 8: WSDOT Perspective on MAP-21 and Pavement … Russell...MAP-21 and Pavement Management ... • Structure (deflection, seismic response) • Remaining Service Life (RSL) ... • Long

• 18,500 lane-miles

• $16 billion pavement replacement cost

The Pavement Management Perspective

Chip Seal6,00032%

Asphalt10,25055%

Concrete2,25013%

Statewide Lane Miles

Page 9: WSDOT Perspective on MAP-21 and Pavement … Russell...MAP-21 and Pavement Management ... • Structure (deflection, seismic response) • Remaining Service Life (RSL) ... • Long

Long-life History by Pavement Type

Structure Life (Years)

5060

9

Page 10: WSDOT Perspective on MAP-21 and Pavement … Russell...MAP-21 and Pavement Management ... • Structure (deflection, seismic response) • Remaining Service Life (RSL) ... • Long

10

Pavement Models: Flexible and RigidFlexible pavements• Asphalt or chip seal• Managed in cycles • Emphasis is to limit scope

of work to only resurfacing

Rigid pavements• Concrete pavements

managed as long-term structures

• Eventually must be reconstructed. Pa

vem

ent C

ondi

tion

Years

Concrete (Rigid)

Pave

men

t Con

ditio

n

Asphalt (Flexible)

Years

Pave

men

t Con

ditio

n

Chip Seal (Flexible)

Years

50-year Pavement Comparison

Page 11: WSDOT Perspective on MAP-21 and Pavement … Russell...MAP-21 and Pavement Management ... • Structure (deflection, seismic response) • Remaining Service Life (RSL) ... • Long

11

LLCC: Asphalt and Chip Seal

Reconstruction ?? ($$$$$$)

Rehab ($$$)??

Years

Cond

ition

Inde

xes

0

100

Optimum time for Rehab

Excessive Vehicle Operating Costs

Excessive Agency Construction Costs

Do Nothing ??

Index value 45 ~ 50

Maintenance ($) ??

Preventive Strategic Reactive

Page 12: WSDOT Perspective on MAP-21 and Pavement … Russell...MAP-21 and Pavement Management ... • Structure (deflection, seismic response) • Remaining Service Life (RSL) ... • Long

12

LLCC: Concrete

TotalReconst.

(index < 25)

Waitfor TotalReconst.

(Replace high risk panels)

Grindand/or

DBRand

SelectiveReconst.

Grind

Years

Cond

ition

Inde

xes

0

100

Risk of Catastrophic Failure:Very Low Low Med. High

Strategy:

Cannot do grind or DBR after this point

MUST do reconstruction after this point

Page 13: WSDOT Perspective on MAP-21 and Pavement … Russell...MAP-21 and Pavement Management ... • Structure (deflection, seismic response) • Remaining Service Life (RSL) ... • Long

Replacement (Strategy) Analysis• Decision Analysis to consider:

– Do Nothing (no replacement)– Maintenance– Rehabilitation– Reconstruction

• If proposed alternative results in lower annual cost, then make decision for (strategy) replacement

13

Page 14: WSDOT Perspective on MAP-21 and Pavement … Russell...MAP-21 and Pavement Management ... • Structure (deflection, seismic response) • Remaining Service Life (RSL) ... • Long

$250 k

12 years 12 years

$26,638/yr=

$250 k

15 years 15 years

$23,538/yr$5 k $15 k

=

10

Calculation of Equivalent Uniform Annual Cost (EUAC) for an asphalt pavement resurfacing ($250k for 12 year period).

Spending additional $5k on maintenance in year 10 and $15k in year 15 results in EUAC that is $3.1k less (12% reduction in annual cost). (Assumed Discount Rate 4%)

Replacement Analysis

14

Page 15: WSDOT Perspective on MAP-21 and Pavement … Russell...MAP-21 and Pavement Management ... • Structure (deflection, seismic response) • Remaining Service Life (RSL) ... • Long

Flexible Cost Effectiveness EvaluationTypical (Avg.) Annual CostConst. LMY $/LMY *

Project Type Cost($/LM) gained (no user $)

Crack Seal $5,000 3 $ 1,800Chip Seal $45,000 7 $ 7,500Rehab (ACP) $250,000 14 $23,000Reconst (ACP) $900,000 20 $66,000

* includes 4% Discount Rate 15

Page 16: WSDOT Perspective on MAP-21 and Pavement … Russell...MAP-21 and Pavement Management ... • Structure (deflection, seismic response) • Remaining Service Life (RSL) ... • Long

Rigid Cost Effectiveness EvaluationTypical (Avg.) Annual CostConst. LMY $/LMY *

Project Type Cost($/LM) gained (no user $)

Grinding $150,000 15 $13,500Rehab. $250,000 15 $22,500Reconst. (CSOL) $900,000 50 $49,000Reconst. (unbonded) $1,600,000 50 $74,000Reconst. (PCC) $2,500,000 50 $116,000

* includes 4% Discount Rate

16

Page 17: WSDOT Perspective on MAP-21 and Pavement … Russell...MAP-21 and Pavement Management ... • Structure (deflection, seismic response) • Remaining Service Life (RSL) ... • Long

17

Page 18: WSDOT Perspective on MAP-21 and Pavement … Russell...MAP-21 and Pavement Management ... • Structure (deflection, seismic response) • Remaining Service Life (RSL) ... • Long

WSDOT 10-Year Concrete Plan

• Maximize opportunities for rehabilitation• Project staging on congested corridors• 515 lane-miles of reconstruction • 366 lane-miles of rehabilitation• $103 million per year

18

Page 19: WSDOT Perspective on MAP-21 and Pavement … Russell...MAP-21 and Pavement Management ... • Structure (deflection, seismic response) • Remaining Service Life (RSL) ... • Long

19

$0

$50

$100

$150

$200

$250

2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020

Projected

Chip Seal

Asphalt

Concrete

Preservation Funding

(2014 $ in Millions)

Page 20: WSDOT Perspective on MAP-21 and Pavement … Russell...MAP-21 and Pavement Management ... • Structure (deflection, seismic response) • Remaining Service Life (RSL) ... • Long

Mark RussellState Pavement Design [email protected](360) 709-5479

20