Why listen to Cam and Adrienne? LEED Project involvement: –30+ projects to date 2011 –Eastgate Business Park Building, LEED-CS (Edmonton, AB) –South West Police Station, LEED-NC (Edmonton, AB) 2010 –CMEB (University of Alberta), LEED-NC (Edmonton, AB) –Dundee Office Tower, LEED-NC (Yellowknife, NT) –Atlantic Ave Art Block, LEED-CS (Calgary, AB) –Mustard Seed Residence Building, LEED-NC (Calgary, AB) 2009 –Grant MacEwan University Administration Bldg, LEED-NC (Edmonton, AB) –Mother M Mary School, LEED-NC (Edmonton, AB) –Emerald Hills School, LEED-NC (Sherwood Park, AB) –Harvest Ridge School, LEED-NC (Spruce Grove, AB) –Northwest High School, LEED-NC (Calgary, AB) –Yellowknife Fieldhouse, LEED-NC (Yellowknife, NT) –Federal Building Rejuvenation/Restoration, LEED-NC (Edmonton, AB) –Yellowknife Government Office Tower, LEED-NC (Yellowknife, NT) –Ronald McDonald House, LEED-NC (Calgary, AB) –NAIT CAT Building, LEED-NC (Edmonton, AB) –Edmonton Eskimo’s Field House, LEED-NC (Edmonton, AB) 33CCCE –Robbins Health Learning Centre, LEED-NC (Edmonton, AB) –Animal Services Building, LEED-NC (Edmonton, AB) –Grant MacEwan University Student Residence, LEED-NC (Edmonton, AB) –AIMCo Tenant Improvements, LEED-CI (Edmonton, AB) –Athabasca University, LEED-NC (Athabasca, AB) 2008 –Southwest Transit Garage, LEED-NC (Edmonton, AB) –Slave Lake Government Ctre, LEED-NC (Slave Lake, AB) –RCMP Detachment, LEED-NC (Red Deer, AB) –Crop Diversification Greenhouses, LEED-NC (Brooks, AB) –Future Shop, LEED-NC (Edmonton, AB) –Centre in the Park, LEED-NC (Sherwood Park, AB) –Cooling Plant on Campus, LEED-NC (Edmonton, AB) –McKenzie School, LEED-NC (Calgary, AB) 2007 –10830 Jasper Ave Redevelopment, LEED-CS (Edmonton, AB) 2006 –Boreal Centre for Bird Conservation, LEED-NC (Athabasca, AB)

TRANSCRIPT

Page 1: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

Yellowknife Fieldhouse(a LEED® project)

Page 2: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

2CCCE 2011

Page 3: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

Why listen to Cam and Adrienne?

• LEED Project involvement:– 30+ projects to date

• 2011– Eastgate Business Park Building, LEED-CS (Edmonton, AB)– South West Police Station, LEED-NC (Edmonton, AB)

• 2010– CMEB (University of Alberta), LEED-NC (Edmonton, AB)– Dundee Office Tower, LEED-NC (Yellowknife, NT)– Atlantic Ave Art Block, LEED-CS (Calgary, AB)– Mustard Seed Residence Building, LEED-NC (Calgary, AB)

• 2009– Grant MacEwan University Administration Bldg, LEED-NC

(Edmonton, AB)– Mother M Mary School, LEED-NC (Edmonton, AB)– Emerald Hills School, LEED-NC (Sherwood Park, AB)– Harvest Ridge School, LEED-NC (Spruce Grove, AB)– Northwest High School, LEED-NC (Calgary, AB)– Yellowknife Fieldhouse, LEED-NC (Yellowknife, NT)– Federal Building Rejuvenation/Restoration, LEED-NC (Edmonton,

AB) – Yellowknife Government Office Tower, LEED-NC (Yellowknife, NT)– Ronald McDonald House, LEED-NC (Calgary, AB)– NAIT CAT Building, LEED-NC (Edmonton, AB) – Edmonton Eskimo’s Field House, LEED-NC (Edmonton, AB)

33CCCE 2011 3

– Robbins Health Learning Centre, LEED-NC (Edmonton, AB)– Animal Services Building, LEED-NC (Edmonton, AB)– Grant MacEwan University Student Residence, LEED-NC

(Edmonton, AB)– AIMCo Tenant Improvements, LEED-CI (Edmonton, AB)– Athabasca University, LEED-NC (Athabasca, AB)

• 2008– Southwest Transit Garage, LEED-NC (Edmonton, AB)– Slave Lake Government Ctre, LEED-NC (Slave Lake, AB)– RCMP Detachment, LEED-NC (Red Deer, AB)– Crop Diversification Greenhouses, LEED-NC (Brooks, AB)– Future Shop, LEED-NC (Edmonton, AB)– Centre in the Park, LEED-NC (Sherwood Park, AB)– Cooling Plant on Campus, LEED-NC (Edmonton, AB)– McKenzie School, LEED-NC (Calgary, AB)

• 2007– 10830 Jasper Ave Redevelopment, LEED-CS (Edmonton,

AB)• 2006

– Boreal Centre for Bird Conservation, LEED-NC (Athabasca, AB)

Page 4: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

4

The Phases of a Project

CCCE 2011 4

• Design• Tendering• Construction

Page 5: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

5

The Design Phase• Conception:

• What, Where, When

• Project Definition:• What, Where, When

• Budget:• Who• Estimate

• (Ball Park?, Order of Magnitude?, Unit price?)

CCCE 2011 5

Page 6: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

6

The Tendering PhaseHow does the owner want to project to turn out?

Owner to General Contractor Tendering• Who, How

• Construction Management• Design Build• Lump Sum• ????

** Invited or Open Market? **

Where does Tendering fit ?• Before or after the Design Phase.• As part of the Design Phase, or• As part of the Construction Phase

Tendering to Sub-contractors• Who are they, why would the owner need to know?• What difference does a sub-contractor make?

CCCE 2011 6

Page 7: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

7

The Construction Phase

=

CCCE 2011 7

Page 8: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

8

Contractor Involvement

• Responsibilities– The main items that the contractor is responsible for are:

• Review of design information• Shop Drawings• Change orders• Conduit to subs & manufacturers

• The contractor will have to assist on other areas’, mainly in gathering of documentation & participation in meetings

• Oh, yah ….. and to do the building portion!

8CCCE 2011

Page 9: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

Project Management• Tender Period to Sub-contractors

• Include LEED information in tendering information to sub-contractors.• Include LEED information in contracts to sub-contractors.• Invite sub-contractors who have completed LEED projects.

– Choose LEED-aware sub-contractors ????– Name an onsite LEED Champion (General Contractor Individual)

• Continuous monitoring and onsite education.• Tracking whether documentation is being kept up-to-date.• Prevent contractors who may,due to force of habit, revert to conventional

methods,which could compromise LEED credits if not noticed and prevented.• Assemble documentation.

– Educate about LEED (General Contractor’s Responsibility)• Onsite signage explaining LEED.• A job-site meeting with all contractors explaining how LEED relates to the project.

9CCCE 2011 9

Page 10: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

World Saving Time!

CCCE 2011 10

Page 11: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

Research and Green Building Institiutes

ATHENA Sustainable Materials Institute USABuilding Integrated Photovoltaics USACentre for Building Studies USABuilding Research Establishment Europe Institute for Research in Construction Canada Quebec Building Envelope Council CanadaCentre for Sustainable Building Rsearch USABuilding Enclosure Technology and Environment Council USA Center for Maximum Potential Building Systems, Inc. USAInternational Initiative for the Sustainable Built Environment CanadaRocky Mountain Institute USAEcological Building Network USASustainable Architecture Buildings and Culture USACommunity Based Social Marketing CanadaCentre for Resourceful Building Technologies USAInstitute for Local Self Reliance USAAdvanced Buildings USADepartment of Energy Green Building Program USASustainable Building Industry Council USASustainable Building Toolkit CanadaArchitectural Green Solar Network Germany

CCCE 2011 11

Page 12: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

CCCE 2011 12

And then you add LEED!

Page 13: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

LEEDfor Commercial Interiors

LEED-CI

LEEDfor Core & Shell

LEED-CS

LEED - Canada Product Portfolio

Launch 2010

LEEDfor NewConstruction

LEED-NC

LEEDforNeighbourhood Development

LEED-ND

LEEDfor Existing Buildings

LEED-EB

LEEDfor Homes

LEED-H

MURB Application Guide

Campus and Multiple Building Application Guide

Core & Shell and Tenant Space Application Guide

Treated as an application guide under LEED-NC

Launch 2009

CCCE 2011 13

Page 14: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

Contractors, Trades, Suppliers and Manufacturers

• What does all this mean to me?

14CCCE 2011 14

Page 15: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

Contractor Involvement

• Responsibilities– Most of the credits are not the contractors

responsibility.– The main credits that the contractor is

responsible for are:• Prerequisite 1: Erosion Sedimentation Control• MR - C2: Construction Waste Management• EQ - C3:Construction IAQ Management Plan

• The contractor will have to assist on other credits, mainly in gathering of documentation.

15CCCE 2011 15

Page 16: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

Involvement of Contractors and Trades

• Contractor Involvement by Construction Division:

CCCE 2011 16

Page 17: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

Involvement of Contractors and Trades

• Contractor Involvement by Construction Division:

CCCE 2011 17

Page 18: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

Involvement of Contractors and Trades

• Contractor Involvement by Construction Division:

CCCE 2011 18

Page 19: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

Involvement of Contractors and Trades

• Contractor Involvement by Construction Division:

CCCE 2011 19

Page 20: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

Involvement of Contractors and Trades

• Contractor Involvement by Construction Division:

CCCE 2011 20

Page 21: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

Involvement of Contractors and Trades

• Contractor Involvement by Construction Division:

CCCE 2011 21

Page 22: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

Involvement of Contractors and Trades

• Contractor Involvement by Construction Division:

CCCE 2011 22

Page 23: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

Involvement of Contractors and Trades

• Contractor Involvement by Construction Division:

CCCE 2011 23

Page 24: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

Involvement of Contractors and Trades

• Contractor Involvement by Construction Division:

CCCE 2011 24

Page 25: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

Involvement of Contractors and Trades

• Contractor Involvement by Construction Division:

CCCE 2011 25

Page 26: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

Involvement of Contractors and Trades

• Contractor Involvement by Construction Division:

CCCE 2011 26

Page 27: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

Involvement of Contractors and Trades

• Contractor Involvement by Construction Division:

CCCE 2011 27

Page 28: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

Involvement of Contractors and Trades

• Contractor Involvement by Construction Division:

CCCE 2011 28

Page 29: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

Involvement of Contractors and Trades

• Contractor Involvement by Construction Division:

CCCE 2011 29

Page 30: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

Involvement of Contractors and Trades

• Contractor Involvement by Construction Division:

CCCE 2011 30

Page 31: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

Involvement of Contractors and Trades

• Contractor Involvement by Construction Division:

CCCE 2011 31

Page 32: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

Involvement of Contractors and Trades

• Contractor Involvement by Construction Division:

CCCE 2011 32

Page 33: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

Involvement of Contractors and Trades

• Contractor Involvement by Construction Division:

CCCE 2011 33

Page 34: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

Involvement of Contractors and Trades

• Contractor Involvement by Construction Division:

CCCE 2011 34

Page 35: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

Involvement of Contractors and Trades

• Contractor Involvement by Construction Division:

CCCE 2011 35

Page 36: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

Involvement of Contractors and Trades

• Contractor Involvement by Construction Division:

CCCE 2011 36

Page 37: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

Involvement of Contractors and Trades

• Contractor Involvement by Construction Division:

CCCE 2011 37

Page 38: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

LEED Benefit• LEED – HOW DO CONTRACTORS BENEFIT?

– risk mitigation through consistent and accurate documentation which is required to be submitted for third party verification.

– integrated design process reduces the risk of errors, deficiencies and project over-runs.

– closer relationships with clients, subtrades and supplies.– financial savings through on-site recycling, improved supply cost and

management of materials (less waste), preference to local suppliers, efficient construction techniques.

– competitive value through leadership in a rapidly expanding field.– improved business efficiency through required diligent paper work and

record keeping.– future construction opportunities.

38CCCE 2011 38

Page 39: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

Construction in the North

CCCE 2011 39

Page 40: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

Transporting Material up North Can Be Scary

There a few different methods to transport material, equipment, supplies, etc. to sites in YK.

Truck (Ice Roads)FerryHelicopter (Expensive)Plane (Expensive)

CCCE 2011 40

Page 41: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

Ice Roads

The ice crossing is normally open to small vehicles in late December, it opens to larger vehicles in mid-January, and closes in mid-April.

CCCE 2011 41

Page 42: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

Ice Roads & Ferry Transportation

There is about a 3 month period where it may be difficult to transport material, equipment, supplies, etc. to your project because of ice break-up or freeze-up.

CCCE 2011 42

Page 43: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

Ice Break-Up

43

CCCE 2011Mackenzie River, NWT

Page 44: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

Ferry Service in the North

CCCE 2011 44

The Ferry Service begins mid- to late May and ends

mid-January.

Merv Hardie Ferry

Page 45: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

Ferry / Ice Road Crossing

45

CCCE 2011

Page 46: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

Extreme WeatherMust be

Considered

CCCE 2011 46

•Piling•Concrete Pouring•Site Work•Landscaping

Page 47: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

Weather Trending

47

CCCE 2011

Page 48: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

Yellowknife’s New Fieldhouse

48

CCCE 2011

CCCE 2011

Page 49: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

Pre-Engineered Buildings

A large number of the buildings in the North are Pre-Eng because;•Short Construction Season•Lower Construction Cost•Durability & Weather Resistant

CCCE 2011 49

Page 50: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

LEE

D C

heck

list

CCCE 2011

50

Page 51: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

51

LEE

D C

heck

list

CCCE 2011

Page 52: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

Erosion and Sedimentation Control

52CCCE 2011 52

Page 53: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

ESC Onsite

CCCE 2011 53

Page 54: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

54CCCE 2011 54

Page 55: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

55CCCE 2011 55

Page 56: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

CCCE 2011 56

Page 57: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

Construction Waste Management

57CCCE 2011 57

Page 58: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

CCCE 2011 58

Page 59: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

CCCE 2011 59

Page 60: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

Indoor Air Quality

60CCCE 2011 60

Page 61: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

CCCE 2011 61

Page 62: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

CCCE 2011 62

Page 63: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

CCCE 2011 63

Page 64: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

CCCE 2011 64

Page 65: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

Risk Mitigation StrategiesRisks in a project are always present. It is identifying them up front and taking proactive measures to mitigate the negative effects on the project that requires a systematic approach to risk management such as:

•Identify and quantify

•By making them explicit they are easier to manage

•Have a plan to deal with each one, control them and thus minimize potential damage

•Identify risks as part of value management

•Ensure good Health and Safety Management plans are in effect

•Maximize and pre-qualify major subtrades for quality, performance and fiscal responsibility

Page 66: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

Contracts

CCCE 2011 66

Page 67: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

67

IPD

• What is “it”?– Tool?– Methodology?– Management

Structure?– Software? (BIM)

CCCE 2011

Page 68: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

68

Build

ing

with

pur

pose

What is IPD?

“Integrated Project Delivery (IPD), is a collaborative alliance of people,

systems, business structures and practices into a process that harnesses

the talents and insights of all participants to optimize project results,

increase value to the owner, reduce waste, and maximize efficiency through all phases of design,

fabrication, and construction.”

CCCE 2011

Page 69: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

69

Shift the traditional view of design/construction

From this…. DESIGN CONSTRUCTION

To this …… DESIGN / CONSTRUCTIONCCCE 2011

Page 70: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

70

Canadian Construction Documents Committee

CCDC 14 – 2000: Design-Build Stipulated Price ContractCCDC 5B – 2010: Construction Management Contract – For Services and Construction

American Institute of Architects

AIA C191 – 2009: Standard Form Multi-Party Agreement for Integrated project DeliveryAIA E202 – 2008: Building Information Modeling Protocol Exhibit

ConsensusDOCS

ConcencusDOCS 300: Standard Form Tri-Party Agreement for Integrated Project DeliveryConcensusDOCS 301: Building Information Modeling (BIM) Addendum

CCCE 2011

Page 71: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

Manufacturers

• Most of the manufacturers have already put together the required LEED documentation

71CCCE 2011 71

Page 72: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

Associations

72

• Canada Green Building Council (Provincial Chapters and EGB’s)– US Green Building Council (US)

• Construction Specifications Canada– Construction Specifications Institute (US)

• Canadian Construction Association (BCCASSN, ACA, SCA, WCA, etc)– Associated Builders & Contractors (US)

• Canadian Construction Documentation Committee• CanBIM• ASHRAE• Cascadia Green Building Council• CCPE (APEGBC, APEGGA, APEGS, APEGM, etc)

CCCE 2011 72

Page 73: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

The Business Case: Cost benefits of green building:

Hard Numbers

• Operating costs decrease 8-9%• Building value increases 7.5%• Return on investment improves 6.6%• Occupancy ratio increases 3.5%• Rent ratio increases 3%In comparison to the average commercial building:

» Green buildings consume 26% less energy» Green buildings have 13% lower maintenance costs» Green buildings have 27% higher occupant

satisfaction» Green buildings have 33% less greenhouse gas

emissions

CCCE 2011 73

Page 74: Yellowknife Fieldhouse (a LEED ® project). 2CCCE 2011

Resources & Thanks• Lloyd Sadd• Clark Builders• Canadian Green Building Council

(CaGBC)• BuildSmart• Manasc Isaac• Stantec• Cohos Evamy• EcoAmmo• Chandos• IBI Group• Construction Specifications Canada

(CSC)• USGBC• Arndt Tkalcic• ACI • Enermodal

And numerous other companies and people over the years!

74CCCE 2011 74

Thank YouCam Munro, LEED® AP, CTR

Senior Sustainable Innovation SpecialistClark Builders

Director / TreasurerAlberta Chapter, Canada Green Building Council