zebra mussels in a nebraska lake - beaverlakene.org mussels in a nebraska lake ... offutt base lake...
TRANSCRIPT
Timeline
• Date: 3 April 2006• Event: message from the Kansas
ANS Coordinator• Message: they had received a tip on
their web site that someone had seen zebra mussels in the Offutt Air Force Base Lake
Timeline cont.
• I contact Offutt AFB via their public email information system
• Phone call from Karl Morris which leads to setting up site visit
• Early site visit on 25 and 26 April 2006 where zebra mussels are confirmed and the situation is discussed with Base personnel
Offutt Base Lake - dead zebra mussels
Dead shell under rocks
Located on darkened waterline
About 2 feet above 25 April 2006 waterline
Offutt Base Lake - lives up close
Live zebra mussels on
rock collected
about 1foot below 25
April 2006 water
surface
Offutt Base Lake - lake side of discharge
Bottom of discharge
culverts are 3.5’ above
lake level on this date
26 April 2006
Offutt Base Lake - south shore
Note darkened waterline. No zebra
mussels were found above
this line.
Offutt Base Lake Actions to Control Situation
• Since only Base personnel may use lake, there is a higher level of control on use. Base personnel fishing lake must have a fishing permit issued on site.
• Boat docks were closed• Brochures, etc., were made available in
boathouse• The outlet was plugged with concrete in the
Spring of 2007
Offutt Base LakeWater Quality12 June 2006
6 sites
Calcium - 32.3 to 50.6 ppmPotassium - 7.2 to 8.8 ppm
Conductivity - 409 to 414 uS/cmpH - 8.39 to 8.47
Offutt Base Lake - First meeting8 March 2007
• Introductory meeting, statement of problem• General presentation on zebra mussels• Brian Watson, Virginia Coordinator of
Millbrook Quarry eradication• General discussion of problem and options
Millbrook Quarry, Virginia
• 12 acre, 93 feet deep
• Just west of Manassas, VA
• Privately owned and used for sport diving
Millbrook Quarry, Virginia
• Zebra mussel population discovered 2002• Flooding from adjacent creek or dive
operations would have spread zebra mussels to other waters
• Decision made to attempt eradication
Millbrook Quarry, Virginia
• Eradication in Feb. 2006
• Potassium chloride (potash)
• Target concentration of 100 ppm
Millbrook Quarry, Virginia
• Cost was $365,000
• Target concentration of 100 ppm well under EPA level of 250 ppm
• No impact on fishes or groundwater
Offutt Base LakeMeeting participants
• Offutt environmental and legal staff• USFWS• USACOE• USEPA• Iowa DNR• Nebraska Game and Parks• Nebraska Department of Environmental Quality• Nebraska Department of Agriculture• Public Power - Nebraska• MidAmerican Energy - Iowa• Kansas City Board of Public Utilities• State Senator’s office• Local government
Offutt Base Lake - Third meeting3 October 2007
• Another general discussion of treatment options• Concluded that new options were being presented
at each meeting which was slowing process• Decided to cut off discussion at four treatments
and develop spreadsheet with pros and cons of each
• Spectrus CT1300, Endothal, potash, copper sulfate
Offutt Base Lake - Fourth meeting31 January 2008
• Discussed spreadsheet with pros and cons of each of four options
• Deleted Spectrus CT1300 (Clamtrol) due to cost and concerns about efficacy
• Deleted Endothal because available information was that it will be banned by end of year
• Discussed pros and cons of remaining two treatment options: copper sulfate and potash
Potash• Successfully used at Millbrook Quarry• Maintains long-term toxicity• Minimal impact on other species• No impact on public use• Great quantity needed (640 tons)• Concerns about how to get into lake• Cost has risen from $100/ton to $500+/ton (640
tons x $500 = $320,000)
Copper sulfate
• Crystals will sink to bottom and increase toxicity at surface of substrate where ZM live
• Less material needed (32,000 lbs)• Lower cost (@$1.98/lb = $63,360)• Toxicity dissipates quickly• Recommended to treat twice (spring and fall)• EPA concerns about whole lake treatment
Offutt Base Lake - Fifth meeting27 March 2008
• Copper sulfate was selected• DOD will have to pay all costs• Need to move quickly to earmark available
funds for this year• Target date for treatment is before 1 May 2008• Possible second treatment in fall
Offutt Base Lake - Treatment17 September 2008
• Consultant (URS) hired to carry out project planning, obtain permits, write EIS, etc.
• subcontracted actual lake application to Natural Habitats Unlimited
Treatment
• Day of treatment was perfect. No wind, no rain, full sun.
• Boats were guided by GPS• Target was a whole-lake concentration of
1.0 ppm copper
URS personnel picked up all fishWith a major airbase across road, Offutt
required that all fish be picked up to avoid attracting fish-eating birds
to eliminate possibility of
bird-strikes on base
- Results -Copper concentrations in lake
Date Location Range Mean17 Sept Random 1.7 ppm (max) 0.70 ppm
19 Sept Seven sitesTop/mid/bottom
0.00 to 0.73ppm
0.25 ppm
17 Oct Same seven sitesTop/mid/bottom
0.04 to 0.20ppm
0.10 ppm
- Results -Zebra mussel mortality
• Six live colonies placed in minnow pails at six locations prior to treatment
• Examined at 24 and 72 hours and 7 days
• 24 hours - 30% dead• 72 hours - 70% dead• 7 days - 100% dead
- Results -Zebra mussel mortality
• Clean bricks and concrete blocks set out before treatment:
• No new settling found
• >100 rocks, etc. examined at 96 hours:
• No lives found
- Results -Veliger sampling
• Samples collected from three locations post-treatment
• 80 micron net w/ 20 cm opening• 50 meter oblique tow from bottom to
surface• No veligers found
• [too late in year for veligers??]
- Results -Fish Kill: Sport fish, etc.
Species Estimated weight (lb) Duration of kill
Largemouth bass 10 3 to 7
Freshwater drum 600 2 to 10
Crappie 3 Sporadic
Paddlefish 100 Sporadic
Walleye/saugeye 50 5 to 10
Catfish 5 15 to 20
- Results -Fish Kill: Nongame fishes
Bighead carp 6,000 lb. 3 to 25 days
Grass carp 200 lb. Sporadic
Common carp 3,000 lb. 2 to 20 days
Buffalo 28,000 lb. 2 to 40 days
White perch 300 lb. 3 to 7 days
Gizzard shad 200 lb. 1 to 3 days
Gar, bullhead 15 lb. 15 to 20 days
Fish kill summary
• Estimated 39,000 lb. or 320 lb/acre of which 95+% were nongame fishes
• 72% buffalo• 23% carp (bighead,
common, grass)• 0.4% sport fish
Cost?
Actual cost figures are not available but the estimate was ~$100,000 or
$820/surface acre
Double that for the second treatment plus monitoring, etc.
Future plans
• A second treatment is tentatively scheduled for the first week of April, 2009.
• Veliger monitoring, 2009