zimbabwe emergency power infrastructure rehabilitation ... · african development bank zimbabwe...
TRANSCRIPT
AFRICAN DEVELOPMENT BANK
ZIMBABWE
EMERGENCY POWER INFRASTRUCTURE REHABILITATION
PROJECT - PHASE II STAGE II
RDGS/PGCL DEPARTMENTS
June 2017
Publi
c D
iscl
osu
re A
uth
ori
zed
P
ubli
c D
iscl
osu
re A
uth
ori
zed
TABLE OF CONTENTS
EXECUTIVE SUMMARY v
1. STRATEGIC THRUST & RATIONALE 1
1.1 Project Linkages with Country Strategy and Objectives 1
1.2 Rationale for Bank’s Involvement 2 1.3 Donor Coordination 3
2 THE PROJECT DESCRIPTION AND FINANCING PLAN 3
2.1 Project Background and Origin 3
2.2 Project Objective 4
2.3 Project Components 4
2.4 Project Cost and Financing Arrangements 5
2.5 Bank Group experience, lessons reflected in project design 6
2.6 Key Performance indicators 6
2.7 Project Implementation Status 8
3 PROJECT FEASIBILITY 8
3.1 Economic and financial performance 8
3.2 Environmental and Social Impact 9
4 IMPLEMENTATION 12
4.1 Implementation Arrangements 12
4.2 Financial Management 12
4.3 Disbursements 13
4.4 Procurement Arrangements Phase II Stage II 13
4.5 Monitoring & Evaluation 14
4.6 Risk Management 14
5 JUSTIFICATION FOR FUNDING 15
6 LEGAL INSTRUMENTS AND AUTHORITY 16
6.1 Legal Instrument 16
6.2 Conditions Associated with Bank’s Interventions 16
7 RECOMMENDATION 16
Appendix 1 - Map of the Country and Location of the Project Areas
Appendix 2: Status of Emergency Power Infrastructure Rehabilitation Project – Phase I
Appendix 3 – Status of Zim-Fund Resource Mobilization
Appendix 4 – Status of Active Country Portfolio as at 31 May 2017
Appendix 5 – Project Risk Matrix
i
Grant Information
Client’s Information
Recipient: Republic of Zimbabwe
Executing Agency: Zim-Fund MDTF Management Unit
Financing plan
Source Amount
(Million USD )
Instrument
ZIM-FUND (Phase II-Stage I)
ZIM-FUND (Phase II Stage II)
TOTAL COST
15.42
7.32
22.74
Grant (Approved in 2013)
Grant
Grant
ADB’s key financing information
Loan / grant currency
USD
FIRR, NPV (base case) (13.9%, USD17.30million)
EIRR (base case) (38.0%, USD271.60million)
Timeframe - Main Milestones (expected)
Project approval 19 April 2017
Effectiveness 30 April 2017
Completion (Phase II Stage II) 31 January 2019
Project Closing (Phase II Stage II) 31 March 2019
Project SAP Code:
EPIRP PH II Stage I P-ZW-FA0-002
EPIRP PH II Stage II P-ZW-FA0-014
Currency Equivalents
February 2017
1 UA = 1.358 USD
Fiscal Year
1 Jan – 31 Dec
ii
Weights and Measures
1 metric tonne = 2204 pounds (lbs)
1 kilogramme (kg) = 2.200 lbs
1 metre (m) = 3.28 feet (ft)
1 millimetre (mm) = 0.03937 inch (”)
1 kilometre (km) = 0.62 mile
1 hectare (ha) = 2.471 acres
Acronyms and Abbreviations
AfDB African Development Bank M&E Monitoring and evaluation
ADF African Development Fund MMU MDTF Management Unit
EIRR Economic Internal Rate of Return MOE Ministry of Environment
EOCK MOEPD Ministry of Energy and Power Development
ESMP Environmental and Social Management Plan
MOFED Ministry of Finance and Economic
Development
EPIRP Emergency Power Infrastructure
Rehabilitation Project
POC Programme Oversight Committee
ESIA Environmental and Social Impact Assessment STERP Short Term Emergency Rehabilitation
Program
FIRR Financial Internal Rate of Return T&D Transmission and Distribution
IG Inclusive Government Tx Transformer
I-PRSP Interim-Poverty Reduction Strategy Paper USD United States Dollar
kV Kilovolt (1,000 volts) VAR Volt-Ampere Reactive
MDTF Multi Donor Trust Fund WACC Weighted Average Cost of Capital
MTP Medium Term Plan ZESA Zimbabwe Electricity Supply
Authority
MVA Megavolt ampere (1,000 kVA) ZETDC Zimbabwe Electricity Transmission
and Distribution Company
PA Procurement Agency Zim-Fund Zimbabwe Multi-Donor Trust Fund
PFM Public Finance Management ZPC Zimbabwe Power Company
PMT Project Management Team
iii
Result-based Logical Framework (As agreed with Project Oversight Committee, represented by Government and all contributing Donors)
Country and project name: Zimbabwe, Emergency Power Infrastructure Rehabilitation Project: Phase II Stage II Purpose of the project : Improve availability and reliability of electricity supply to critical social infrastructure facilities and the people of Zimbabwe
RESULTS CHAIN
PERFORMANCE INDICATORS MEANS OF
VERIFICATION RISKS/MITIGATION MEASURES Indicator
(including CSI) Baseline
(year) Target
IMP
AC
T
Improved health of the
people in targeted areas.
Diarrheal morbidity in
children under 5
7.2/1000-2010 <7 (2018) National
statistics, DHS
(Demographic
and Health
Surveys
OU
TC
OM
ES
Re-establishing capacity at Sherwood and Orange Grove to increase available power supply and improve reliability of supply to Gimboki Sewerage works
1.1 Percentage of customers with access to firm transformer capacity at Transmission level
1.2 Number of outages experienced at Gimboki Sewage Treatment Works
43% in 2016 600 hours/ year (2016)
63.5% in 2018 12 hours per year (2018)
ZESA Holdings Quarterly and Annual Progress Reports
Risk 1: Vandalism of rehabilitated facilities Mitigation Measures: Enactment and enforcement of legislation that criminalizes
acts of vandalism and reduction in power outages ensuring that the system is live most of the time. Improve customer communication and feedback options.
OU
TP
UT
S
1. Power infrastructure rehabilitation 1.1 Transmission Transformer capacity increased, Sherwood
1.1 Total Transformer capacity at targeted transmission substations
445MVA in 2016
620 MVA in 2018
EPIRP II Stage II monthly progress reports/ ZETDC reports
Risk 2: Political instability in the run up to the 2018 harmonized elections could lead to
disruption of project implementation. Mitigating Measures: Continued dialogue with Government of Zimbabwe so they ensure a conducive environment and maintain stability during implementation and completion of national project
1.2 Sub-Transmission and
Distribution Capacity Strengthened, Orange Grove
1.2 No. of procured and
installed transformers (with accessories) commissioned.
0 in 2016 2 in 2018
1.3 New 33kV supply line to Gimboki Sewerage works.
1.3 Length of Electricity line constructed
0 km in 2016 2.2km constructed in 2018
INPUTS
KE
Y
AC
TIV
ITIE
S
Component I Installation of 1 x 175MVA, 330/(132)88/11kV Transformer and associated Switchgear at Sherwood substation Installation of 1 x 50/75MVA, 132/33kV Transformer and associated Switchgear at Orange Groove substation Construction of a 2.2 kilometres, 33kV dedicated line to Gimboki Sewerage works
Component II Provide Project Management, engineering design and supervision services Provide Procurement Services Project audit
Components of Phase II Stage II (USD Million)
I. Power infrastructure rehabilitation
$6.30
II. Project Management $0.42
Contingency $0.60
TOTAL $7.32
iv
Project Implementation Schedule
Activity
Project completionProject Disbursement Deadline
1 2 3
2019
8 9 10 11127 8 9 10 11 9 # 11
Preparation of Terms of References for servicesProcurement of Contractors and consultantsStage I Transmission Works (Marvel and Chertsey substations)Stage I Distribution Works Stage I Services (Hwange Power Station)Stage I Goods (Hwange Power Station)
2 38 9 #1 2 3 4 5 6121 2 3 4 5
Project Audit
Board Approval of Additional FinancingSigning of Grant Additional Financing Recruitment of Project Implementing Entity & Procurement AgentProject Management and procurement services Project launchingPreparation of design, specifications and tender document
POC Project Appraisal ApprovalNegotiationTranslation and processing for BoardBoard Approval of ProjectSigning of Grant for Stage IEffectiveness
# 11 #
2016201520142013
111 #121 2 3 4 5 67 8 4 56 77
Schedule for Emergency Power Infrastructure Rehabilitation Project - Phase II
Board Approval
Additional Financing
2017 2018
Stage II Transmission Works (Sherwood & Orange Grove)
7 8 9 10 11 121 2 3 4 5 66 7 8 9
v
EXECUTIVE SUMMARY
In its administrative capacity of the Zimfund, the Bank presented for approval Phase II of the
Emergency Power Infrastructure Rehabilitation Project (EPIRP) on 18 December 2013 with a total
estimated cost of US$32.94 million. The project aims to support of electrical infrastructure
development in Zimbabwe and will contribute to the economic recovery process, improving the
livelihood of general Zimbabweans. However at the time of Board approval, the Donor funds were
inadequate to cover the total project scope. It was therefore agreed to split the overall project scope
into two stages to match the availability of grant funding. Stage I of the program was covered by
US$15.42 million that was available at the time and was approved in 2013. The Board was
informed at the time that management would resubmit the project seeking approval for the
remaining amount (US$ 17.52 million) once more resources became available from the ZimFund
donors.
During the Programme Oversight Committee (POC) meeting held on 29 January 2016, POC
members approved the funding of the US$7.32 million towards EPIRP Phase II Stage II. The
Donors have also confirmed that there will be no further commitments for the Zim-Fund. It is
against this background that management is now seeking approval for the funds to be committed
to EPIRP II Stage II based on the original approved scope.
The objective of the project is to improve the availability and reliability of electricity supply
through the rehabilitation of transmission and distribution facilities in Midlands and Manicaland
provinces. The project was also formulated to further the benefits and impacts of Phase I whose
components included the rehabilitation of the power generation, transmission and distribution
infrastructure throughout the country. The Project target areas are Kwekwe, Gweru and Mutare
with a combined target population of 2 million people.
The Phase II Stage I programme (US$ 15.42 million) focused on the Plant Drain System
Containment and Effluent Treatment Study at Hwange Power Station, rehabilitation of two power
transmission substations in Bulawayo and Gweru and rehabilitation of power distribution facilities
for water supply and waste water treatment plants in Harare. The project was launched in March
2014 and is now under implementation with a planned completion date of November 2018. It
should be noted that the current services of the Procurement Agent and Implementing Entity for
Phase II Stage I already cover Stage II activities.
The processing and implementation of the project will be guided by the Operations Manual
developed for Zim-Fund. The implementation arrangements will remain the same as for EPIRP
Phase II Stage I and the project will receive regular follow up and supervision from the Bank,
Multi-Donor Trust Fund Management Unit (MMU) and other Government of Zimbabwe
structures. The POC will continue to provide policy and strategic guidance.
1
REPORT AND RECOMMENDATION OF THE MANAGEMENT OF THE AFDB GROUP
TO THE BOARD OF DIRECTORS ON A PROPOSED GRANT FUNDING TO ZIMBABWE
FOR THE EMERGENCY POWER INFRASTRUCTURE REHABILITATION PROJECT
(EPIRP) PHASE II STAGE II.
Management hereby submits this report and recommendations for grant funding amounting to US$
7.321 million to the Republic of Zimbabwe from the resources of the Multi-Donor Trust Fund (Zim-
Fund) to finance part of the shortfall on the EPIRP Phase II. When EPIRP II was presented and
subsequently approved by the Board on 18 December 2013, the total budget for the entire project was
US$ 32.94 million. The Board was informed that only USD 15.42 million was available and this would
constitute EPIRP II Stage I and when donors make more commitments, then management would come
back to the Board for approval of the financing towards the scope for EPIRP II Stage II remaining.
1 STRATEGIC THRUST & RATIONALE
1.1 Project Linkages with Country Strategy and Objectives
1.1.1 The project is consistent with the Zimbabwe Agenda for Sustainable Socio-Economic
Transformation (Zim-ASSET), Government’s blue print for development (2013-2018) in which
Infrastructure and Utilities is one of the four pillars of the plan. The project addresses the priority
areas, rehabilitation of electricity infrastructure, emphasized in the National Energy Policy of
Zimbabwe (2012). The Government of Zimbabwe (GoZ) has developed a new Interim Poverty
Reduction Strategy Paper (I-PRSP 2016-2018) which builds on the ZimAsset; the President‘s 10-
Point Plan of August 2015; and sector plans and strategies, and the Sustainable Development Goals
(SDGs), 2016-2030). The I-PRSP focuses on promoting inclusive growth and poverty reduction
through improved policies and interventions, and this is consistent with the ZimAsset Vision of
“Towards an Empowered Society and a Growing Economy”. The proposed project is aligned with the
I-PRSP infrastructure pillar as investment in energy sector is a critical enabler in poverty reduction
and economic development.
1.1.2 The intervention in the sector was entailed in the Updated Country Brief (2014-2016) for
Zimbabwe through the emphasis on rehabilitation of basic infrastructure. The Country Brief (CB)
articulated three focal areas: (i) rehabilitation of basic infrastructure, (ii) governance and institutional
capacity strengthening, and (iii) supporting private sector development. The project is also aligned
with the Bank’s Ten-Year Strategy (TYS) 2013-2022, “High-5s” and the Bank’s Energy Sector Policy.
It is aligned to two of the five TYS operational areas, infrastructure development and private sector
development. The project will also contribute to the achievement of three of the five “High-5s”
objectives; light up and power Africa; industrialize Africa (making electrical power available for the
creation of small and medium-sized industries); and improve the quality of life of Africans. The project
is also in line with the Bank Group’s Strategy on Addressing Fragility and Building Resilience in
Africa. A key focus of the strategy is strengthening state capacity, establishing effective institutions
and promotion of inclusiveness to build resilient societies.
1.1.3 The main vehicles for financing the Bank’s support to Zimbabwe over the last five years have
been the ZimFund, ADF Performance Based Allocation and Transition Support Facility, Private
Sector Window, Fund for Africa Private Sector Assistance (FAPA), and African Water Facility. As of
31st May 2017, the Bank Group’s active portfolio in Zimbabwe consisted of 16 operations (including
one regional operation and 2 private sector operations) with a total commitment of UA 158.7 million.
The portfolio is composed of African Development Fund Grants (59.8 percent), Africa Development
1 Out of USD$ 7.3 million, USD 4.9 million is new resources while the remaining balance is a reallocation from EPIRP Phase I project.
2
Bank loan for Private Sector (14.9 percent) and trust funds administered by the Bank - the Multi-Donor
Trust Fund for Zimbabwe (23.9 percent) and other Trust Funds (1.5 percent). In terms of sectoral
distribution, water supply and sanitation sector accounts for 32.8 percent of the portfolio followed by
the power sector 30.2 percent, the multi-sector (governance and institutional support) 16.6 percent,
financial 11.3 percent, agriculture 4.6 percent, social sector 3.9 percent, and transport sector
accounting at 0.6 percent. The portfolio is relatively young with an average age of 2.3 years.
1.1.4 Currently the overall performance of the portfolio is rated satisfactory at 2.8 on a scale of 1 -
4 based on recent updated supervision rating assessments. This has slightly declined from a level of
3.0 in 2014 and 2015 mainly due to implementation start-up delays due to capacity constraints in
Government amongst others. Out of the rated projects, the portfolio has two problem projects, namely,
(i) Lake Harvest Project which has experienced challenges due to insufficient capital injection from
the sponsor and reduced sales volumes; and (ii) the Capacity Building for Public Finance and
Economic Management (CBPFEM) Project, which was affected by procurement delays particularly
due to extensive contract negotiations for big contracts. The implementation was also affected by weak
capacity in most beneficiary institutions. However, more recently there has been substantive progress
in the procurement process and high valued contracts have been brought to signature Stage in the
CBPFEM, thereby paving the way for payments. On December 16, 2016, the Alaska Karoi Power
Transmission Reinforcement Project was approved and currently is effective for first disbursement.
1.1.5 The overall key portfolio issues include complex stakeholder arrangement, inadequate detailed
design studies at time of project approval; market failure to attract best qualified bidders which
necessitated re-launching of some of the tenders hence delaying procurement process; particularly for
ZimFund projects. Capacity constraints in procurement is also an issue, which the Bank is addressing
by providing capacity building support to the relevant procurement teams at the project level as well
as extending support at the country level through the implementation of the Procurement Roadmap of
the country. The country’s limited experience in project/program implementation in the past several
years, has led to weaknesses in government’s capacity coupled with limited oversight and
accountability, which in return had slowed project implementation, financial management,
procurement, project management, and M&E. To mitigate these issues, the Bank Group together with
Government have in 2016 prepared a Country Portfolio Improvement Plan (CPIP) identifying three
portfolio-wide risks factors which are likely to have adverse impacts on project implementation and
results, namely: (i) inadequate project design and start-up delays, (ii) limited oversight and
implementation capacity and (iii) fiduciary management. The implementation of the agreed CPIP will
be closely monitored by the Bank, Government and Project Implementing Entities.
1.1.6 Since the start-up of Phase II Stage II, the Bank has been closely working with the Zim-Fund
partners to mobilize the additional resources required for the project estimated at US$17.52 million.
Convinced with the progress being made and results demonstrated through the first phase of the Zim-
Fund projects, Denmark, Sweden and Norway committed additional resources amounting to
US$22.74million (including USD4.31 million savings from Phase I) which would be allocated to
EPRIP Phase II. The Program Oversight Committee (POC) of the Zim-Fund endorsed the allocation
of this additional funding to the project on 29 January 2016 to partially complete the initial scope.
1.2 Rationale for Bank’s Involvement
1.2.1 The rationale for the Bank’s involvement in the Project is premised on the commitment the
Bank made to administer the ZIMFUND; and to assist in the economic recovery of Zimbabwe. The
Zim-Fund provides Zimbabwe with much needed resources for revitalizing the economy through
rehabilitation of power and water and sanitation infrastructure. The Project is the last segment of the
on-going power sector infrastructure rehabilitation programme that is financed by the Zim-Fund and
managed through the Zim-Fund Management Unit (MMU) established by the Bank to strengthen staff
presence on the ground to manage the daily operations of the Zim-Fund. The Bank’s continued
3
involvement in the sector through the administration of Zim-Fund therefore remains relevant for
consolidation of the gains made by the country to date and to avoid regression and stagnation in the
power sector infrastructure programme.
1.3 Donor Coordination
1.3.1 Donor support in Zimbabwe has continued despite the restrictive measures and financial
sanctions. To date donor coordination in Zimbabwe has been geared towards the Zim-Asset priority
areas. In June 2014, the Government set up a Cabinet Committee on Aid Coordination to oversee all
aid inflows and to ensure the effective use of such resources in the implementation of Zim-Asset.
Currently the Government is in the process of reviewing the aid architecture for effective development
coordination towards achievement of Zim-Asset objectives. Dialogue and coordination among the
various funding partners is carried out within the context of the ZimFund.
1.3.2 The Bank has deepened its collaboration with all relevant bilateral and multilateral actors on
the ground, including its leadership role in the arrears clearance process. It will continue to participate
in routine joint donor meetings to discuss macroeconomic management and economic governance
issues in Zimbabwe. The Bank constantly engages bilateral and multilateral partners (IMF and World
Bank), United Nations agencies and regional institutions. Thematic group meetings (e.g. on public
financial management) also provide opportunity for coordination and collaboration with other
development partners including the African Capacity Building Foundation, the United States Agency
for International Development, the UK’s Department for International Development (DfID) and the
UN.
1.3.3 In December 2016 the Bank approved a grant facility for Zimbabwe (TSF & PBA) to the value
of US$ 18,762,700 for the construction of a 132kV power line from Alaska Substation to the new
Karoi Substation with associated works including the development of a Network Masterplan. This
project will be the first energy sector project directly funded by the bank and executed by Government.
1.3.4 Direct Government funding by other development partners are however limited due to the
restricted direct investment mandate until the country arrears are cleared. Some support is provided
by the India Export Import Bank for the upgrade of the Bulawayo power station and by the Chinese
Export Import Bank towards the expansion of Hwange Power station, and Kariba South Power Station.
The other development partners such as the World Bank, Power Africa and DFID currently only
provide Technical Assistance within the energy sector or support small pilot projects directly with
civil society. It is anticipated that once the arrears clearance issues have been resolved, this situation
would drastically change, providing opportunity for much more development funds to become
available for the sector.
2 THE PROJECT DESCRIPTION AND FINANCING PLAN
2.1 Project Background and Origin
2.1.1 The Zimbabwe Multi-Donor Trust Fund (ZimFund) was established in 2010 as an emergency
response to a severe humanitarian crisis that manifested itself in the deadly cholera epidemic that
engulfed the country in 2008/9. The outbreak claimed more than 4,000 lives and affected more than
100,000 people. The ZimFund Donor countries responded to the outbreak of cholera by mobilizing
funds for the rehabilitation of water supply and water sanitation infrastructure complimented with the
rehabilitation of power infrastructure through its first phase of projects. The Bank was requested and
accepted to administer the funds in accordance with Bank rules and operational manual that was agreed
between the Donors, the Bank and the Government of Zimbabwe. The first Emergency Power
Infrastructure Rehabilitation Project (EPIRP) under ZimFund was approved in June 2011 and its
execution was completed in April 2016. The project was implemented throughout the country and
4
comprised of the rehabilitation of the power generation, transmission and distribution infrastructure.
The emphasis of the project was on improving the reliability and availability of power supply.
2.1.2 The intervention in the power sector was to be implemented in phases with Phase I utilizing
funds that were immediately available and subsequent phases as donors committed more resources.
As more resources became available and with some savings from Phase I, it was decided to embark
on Phase II which was appraised in March 2013. The total estimated cost of Phase II at appraisal was
USD 32.94 million. However, the committed amount from the donors amounted to only USD 15.42
million. The Phase II intervention was therefore split into Stage I using available resources (USD
15.42 million) and Stage II using resources that would be committed later by Donors. Stage I is
currently under implementation with a planned completion date of November 2018.
2.1.3 The Donors have approved an additional USD7.32 million composed of US$ 4.31 million from
the savings on phase I and US$ 3.01 from additional donors’ contributions for Funding Phase II Stage
II project. They have indicated that no further funding will be made as the ZimFund program is to end
in October 2019. It is against this background that the current project proposal is being submitted for
Board approval.
2.2 Project Objective
2.2.1 The objective of the EPIRP II Stage II is to further improve the availability and reliability of
electricity supply through the rehabilitation of transmission and distribution facilities. The Project
target areas are Kwekwe, Gweru and Mutare with a combined target population of 2 million people.
2.3 Project Components
2.3.1 As appraised in 2013, the EPIRP Phase II scope was prepared through wide consultations with
contributing donors in Zimbabwe and various arms of the government and the power utility. The
project components were split into Stage I which is under implementation and Stage II whose approval
is now being sought from the Board. The original project components for each Stage are described in
table 1 below. Due to limited funding and with the agreement of the contributing donors, most of the
Hwange scope of works was removed as indicated by an “x” symbol. The table below summarises the
retained scope items for Phase II Stage II.
Table 1: Original EPIRP Phase II Stage I and Stage II components
No Item description Stage I scope Stage II scope
1 Rehabilitation works at the Hwange thermal power Station
1.1 Dam dust suppression system for the coal handling plant x x
1.2 Dirty Drainage system (Partial scope)
1.3 Vacuum cleaning plant. x x
2 Power Infrastructure rehabilitation
2.1 Supply and installation of 1 x 175MVA, 330/(132)88/11kV transformer at Marvel Substation
2.2 Supply and installation of 1 x 90MVA, 330/132/11kV
transformer at Chertsey Substation
2.3 Supply and installation of 1 x 50/75MVA, 132/33kV
transformer at Orange Grove substation
5
No Item description Stage I scope Stage II scope
2.4 Supply and installation of 1 x 175MVA,
330/(132)88/11kV transformer at Sherwood substation
2.5 Erect Gimboki Sewage Works 33kV Line
2.6 Supply and installation of 1 x 50MVA, 132/33kV
transformer at Mashava Substation x x
2.7 Rehabilitation of supplies to water and sewerage works in Harare:
2.7.1 Prince Edward Water Treatment Plant
2.7.2 Crowborough Sewage Treatment Plant
2.7.3 Firle Sewage Treatment Works
2.8 Investment plan for power infrastructure x x
2.9 Project Management services 2.9.1 Procurement Agent
2.9.2 Implementation Entity
2.9.3 Audit
2.3.2 It should be noted that the Project Management services for both Stage I and Stage II were
approved under Phase II Stage I financing. Initially it was expected that the project management
services of Stage I and Stage II would overlap but the overlap is now limited. For this reason, provision
has been made for additional resources for project management services under Stage II.
2.4 Project Cost and Financing Arrangements
2.4.1 The revised total project cost of Phase II is estimated at US$ 22.74million. This project cost is
summarized below by component and category of expenditure.
Table.2: Estimated Project Costs
Components Phase II Stage I
Financing approved
(USD million)
Phase II Stage II
Financing
(USD million)
Total Cost (USD million)
1. Power infrastructure
rehabilitation 10,74 6.30 17.04
2. Project Management 2.59 0.42 3.01
Subtotal 13.33 6.72 20.05
Contingency 2.09 0.60 2.69
Total project cost 15.42 7.32 22.74
Table 3: Categories of expenditure
Categories of expenditure Phase II Stage I
Financing approved
(USD million)
Phase II Stage II
Financing
(USD million)
Total Costs
(USD million)
Works 9.29 6.30 15.59
Services 2.87 0.42 3.29
Goods 1.17 0.00 1.17
Sub-total 13.33 6.72 20.05
Contingency 2.09 0.60 2.69
Total 15.42 7.32 22.74
6
2.5 Bank Group experience, lessons reflected in project design
2.5.1 The following key lessons learnt from EPIRP Phase I and Phase II were incorporated in the
design and planning for EPIRP Ph II Stage II:
i) The involvement of the relevant sector ministries is crucial for smooth coordination of project
implementation. In Phase I, the Ministry of Energy and Power Development (MOEPD) did not have
a clear-cut relationship with the existing Project Management Teams (PMTs) within ZPC and ZETDC.
In Phase II, the two Ministries will each identify a coordinator, who will work closely with these
project teams.
ii) The use of country governance structures relevant to the sector to ensure smooth coordination of
project implementation – It is important not only for the implementation of the programme but also
for the sustainability of the solutions that the relevant government and governance structures are
consulted and involved during the design and execution of the programme. ZETDC has been involved
with the project design and approvals and will continue to play a key role during project
implementation.
iii) Technical studies to scope and cost Phase II were carried out to avoid the problems of delay in
implementation experienced and eventual down-sizing of the scope of the Phase I project.
iv) Continuous evaluation of priorities to ensure project intervention is relevant and timely – due to
the emergency nature of interventions, some activities identified at appraisal under phase 1 were
executed by the utilities prior to the implementation of the Project.
v) Procurement processes to take into account the emergency nature of the Project – in phase 1 a lot
of time was spent in the procurement of the Procurement Agent (PA) and Implementing Entity (IE)
before the Project could commence. It is therefore recommended that the PA and IE recruited for
Phase I be retained.
2.5.2 Refer to technical annex B1 for a summary of lessons learned during EPIRP PH I and Phase
II.
2.6 Key Performance Indicators
2.6.1 The project will result in (i) increased electrical network capacity; (ii) contribute to improved
access to electricity; (iii) improve reliability of electricity and (iv) the reduction of outages. The Result
Based Log-frame of the project reflects the performance indicators for the project at input, output and
outcome levels.
2.6.2 The progress during implementation will be monitored by the timely commencement of the
works, regular disbursements, and consultations with the project team, timely submission of quarterly
progress (no later than 45 days after the end of each calendar quarter) and environmental and social
management plan reports as well as annual audit reports. Similarly, the project implementation
schedule and procurement plan provide key indicators for monitoring implementation progress. These
will be updated with actual status for evaluation with planned targets. The detailed project monitoring
plan is attached in the technical annex C1 which provides the timelines, reporting, and responsibility
among the different project stakeholders.
7
2.7 Project Implementation Status
Phase II Stage I
Entry into Force and Conditions for First Disbursement
2.7.1 The project became effective when the Project Protocol of Agreement was signed on 22
January 2014 and became eligible for disbursement on 21 July 2014 after the fulfilment of conditions
precedent for first disbursement. The Agreement provided that the Bank’s obligation to make first
disbursement of the grant was conditioned upon the engagement of the PA and IE.
2.7.2 The Government of the Republic of Zimbabwe (GoZ), acting through the Ministry of Finance
and Economic Development, entered into an agreement with Crown Agents Limited on 19 March
2014, to extend the provision of procurement services to Zim-Fund operations to 30 September 2017.
In addition, a supplementary agreement was concluded on 2 May 2014 for specific procurement
services for the EPIRP Phase II project. Similarly, the GoZ concluded a contract with Parsons
Brinckerhoff Africa Pty (Ltd) which became effective on 21 July 2014 as an Implementing Entity
providing all project management and engineering services.
Technical Progress
2.7.3 The IE mobilized on the 21st of July 2014 to carry out the initial technical assessment and
preparation of detailed scope of works, design, specifications and bill of quantities for the project. All
specifications have been completed for both Stage I and Stage II activities.
2.7.4 There has been a delay in the implementation of the works project components for Phase II
Stage I due to prolonged design, planning and procurement processes. It is now envisaged that
completion of implementation of Stage I will be in the last quarter of 2018. Currently disbursements
are low at sixteen (16) percent because the project has just entered the execution stage. However,
disbursements are expected to rise sharply in the third quarter of 2017 when the equipment for the
works starts arriving on sites.
2.7.5 To ensure timely completion of the phase II project, all stakeholders have been advised that
the end date for the Zim-fund project is October 2019 including defects liability period with no
possibility of extension of funding beyond this date.
2.7.6 To ensure that the project is implemented on time, the MMU will closely monitor the detailed
design approvals and during execution through increase in the number of project monitoring missions
to ensure that all hurdles and bottlenecks between the IE, End-user and the contactor are timeously
cleared.
Procurement
2.7.8 Phase II Stage I project consists of two works packages, one goods package and four services
packages all of which are awarded, as detailed below:
8
Table 4: EPIRP PH II Stage I summary of contracts
Name of Contract Commencement Completion due: Remarks
EPIRP II /001 Implementing Entity
Parsons Brinckerhoff Africa
(Pty) Ltd (PB)
21 July 2014 21 Jan 2019 Contract in progress.
EPIRP II /002
Procurement Agent
(Crown Agents)
12 May 2014 30 Sep 2017
Contract in progress. The contract may
be extended to March 2019 if EPIRP II
Stage II is approved.
EPIRP II /003
External Auditor
(Baker Tilly Gwatidzo, Zimbabwe)
24 July 2015 30 June 2017
Contract in progress. The contract may
be extended to March 2019 if EPIRP II
Stage II is approved.
EPIRP II /004
Transmission Rehabilitation for Marvel and Chertsey Sub-stations.
(Angelique International Ltd.)
14 June 2016 6 Dec 2017 Contract in progress. Design work in advanced stage .
EPIRP II /005
33/11 kV Substations for Prince
Edward Dam, Airport, Mufakose,
and Glenview Substations and 33
kV line from PE Dam to Airport
Substation
(Technofab Engineering Ltd.)
16 Aug 2016. 7 Feb 2018 Contract in progress.
Design work in advanced stage .
EPIRP II /006
Consultancy services for Plant
Drain System containment and
Effluent Treatment Study
(Aqualogus SIRDC Consortium)
24 May 2016 24 Feb 2017
Contract in progress.
Final report findings presented to ZPC in
February 2017
EPIRP II /007
Supply of Mobile Plant Equipment
for Hwange Power Station
Supplier: Barzem Enterprises Ltd.)
19 July 2016 30 April 2017 Contract is in progress.
Phase II Stage II
2.7.9 Under Stage I, considerable time was taken in scoping, design and costing at the commencement
of project which resulted in delays. For the current project, IE for Stage I was asked to scope and cost
the project before finalization of PAR for Stage II and this has been done in advance. In support of the
overall project completion timeline for the Zim-Fund programme, advance contracting procedures
have been approved. This has enabled the MMU to prepare procurement activities for Phase II Stage
II in advance of PAR approval.
3 PROJECT FEASIBILITY
3.1 Economic and financial performance
3.1.1 The financial and economic benefits were determined during the initial project scoping. As
this approval submission is only for the approval of new donor funds towards the completion of the
original scope the pervious determined indicators are still deemed valid.
3.1.2 The Project intervention will result in improved electricity supply as a result of (i) transformer
rehabilitation at the substations, and (ii) provision of dedicated power supplies to water sewerage
9
works. Indirect economic impact will arise from the improved distribution of power which will re-
invigorate the country’s economic activities and boost industrial production and contribute towards
better operations in social institutions through a positive impact on water supply and sewerage services
delivery. Power shortages and network faults have mostly affected manufacturing industries,
agriculture, mining, and social services.
3.1.3 Both the financial and economic benefits from the work at the substations are measured by the
additional revenues from electricity sales and the savings realised by consumers by not using
alternative sources of energy following the rehabilitation, respectively. The alternative cost of supply,
as measured by own generation using diesel engines by household, commercial and industrial
consumers, has been estimated at USD 45 ¢/kWh compared to the current average tariff of USD 9.86
¢/kWh which clearly indicates the magnitude of benefit to be realised from consuming grid energy.
3.1.4 Based on the analysis carried out in 2013 during the original project preparation, the project is
both financially and economically viable as summarised in the table below.
Table 5: EPIRP PH II financial and economic indicators
FIRR; FNPV (WACC of 10%) 13.9%, FNPV USD 17.30 million
EIRR; ENPV (EOCK of 12%) 38.0%, ENPV USD 271.60 million
3.2 Environmental and Social impact
Environment
3.2.1 The Project was validated by ORQR as Category 2 on 23 May 2013. In line with the Bank’s
Environmental and Social Assessment Procedures (ESAP), subsequently two ESMPs have been
prepared by the two sponsoring organizations and the summary of both was disclosed on the Bank’s
website on August 27, 2013. The classification of Category 2 is mainly because the Project’s activities
pertain to medium scale rehabilitation of existing infrastructure and addressing environmental
pollution. The Project is expected to yield more environmental and social benefits than negative
impacts. However, negative impacts are expected to be site specific and temporary such as dust and
noise and will mainly occur during construction. Two other potential impacts are the management of
transformer oil decanted from old transformers which may contain polychlorinated biphenyls (PCB’s);
and contamination of other oils with PCB’s and spillage already observed hence likelihood of soil and
ground water contamination. However, this no longer applies as the transformers have been removed
from the site. The oil from the old transformers has been recycled and reused.
3.2.2 In the ESMP, resettlements were not expected as a result of this project. The works will mainly
comprise urgent repairs of existing infrastructure and O&M capacity building which will not result in
the relocation of beneficiary communities.
3.2.3 EPIRP Phase II Stage I components are under implementation. Prior to the implementation of
these components, detailed ESMPs were prepared for each of the works contracts by the appointed
contractors and reviewed by the Implementing Entity (IE) and ZETDC in accordance with local
legislation and best practices.
3.2.4 The ESMP prepared and disclosed in 2013 included components in EPIRP II Stage I and Stage
II. The Bank and ZETDC staff who visited the sites in October 2016 ascertained that there have been
no environmental changes that warrant intervention. The transformers for the substations in Stage I
and the proposed Stage II have since been removed from site in an environmentally friendly manner.
The sites are clear of any obstructions and are ready to receive the new equipment. The monitoring of
10
Stage II implementation will be done in a similar manner to Stage I. The implementation of Stage I
and II will overlap and therefore the monitoring of both Stage s will be done simultaneously.
3.2.5 ZETDC have an Environmental Management Unit and together with the IE they monitor the
works under the contracts in accordance local legislation and the approved ESMPs. The monitored
environmental aspects among others include compliance with Personal protective clothing, monitoring
and suppressing dust and noise pollution. The Unit also ensures proper handling of transformer oil and
other materials that may be hazardous to health as well as monitoring compliance with the daily safety
toolbox talks that are a prerequisite before work commences. The Unit ensures that the contractors
comply with the requirements of undertaking regular Health and HIV awareness campaigns for the
workers.
3.2.6 The substations sites are all remotely located away from the community residential areas and
their access is restricted to the public and therefore there will be no social impacts as result of the
project.
Climate Change
3.2.7 While the country’s main carbon emissions are from power generation, by and large,
Zimbabwe contributes minimally to global carbon emissions. Expected climate change impacts in
Zimbabwe include excessive or lack of rainfall. However, the current project will not contribute
significant carbon emissions due to its nature of being a rehabilitation project rather than a green field
project.
Gender
3.2.8 The energy sector in Zimbabwe, as in many developing countries, is characterized by both
gender and class dimensions. While high income households rely on more energy efficient and
convenient sources of energy such as electricity and gas, poor people rely largely on wood fuel.
Furthermore, rural communities are estimated to meet 94% of their cooking energy requirements from
traditional fuels, mainly firewood while 20% of urban households use wood as the main cooking fuel.
This situation has led to environmental degradation as families encroach on forests in search of
firewood.
3.2.9 Among rural households, the collection of firewood is largely done by women and girls and in
addition to the time it takes away from productive activities and studying, women and girls are exposed
to the danger of sexual assault when collecting firewood in isolated areas. This risk is exacerbated by
the increasing deforestation that requires people to go farther distances in search of firewood. Among
urban poor households the lack of options has health implications as a consequence of reliance on
petroleum based fuels. Hence, women, girls and young children often suffer the brunt of exposure to
wood smoke and fuel fumes as a result of prolonged exposure when cooking.
3.2.10 Availability of reliable power supply can empower women and contribute significantly to
gender equality at household and institutional level. Institutions of higher learning in Zimbabwe are
experiencing adverse impacts of power outages and this is particularly detrimental to sustaining
competitiveness and gender parity in enrolment. The Zimbabwe Open University (ZOU), due to the
nature of its coverage and target population, is well positioned to improve women’s education and
skills. Open and distance learning (ODL) is a powerful enabler of gender parity in access to higher
education as it allows women particularly adult learners and those who terminated their education
early due to marriage, pregnancy or poverty to catch up. It should thus be noted that the persistent
power outages in Zimbabwe while impacting negatively on the higher education sector overall, has
particularly detrimental effects on gender parity and on the ability of women to fully benefit from
educational opportunities and escape the perpetual poverty trap. In addition, it emerged from anecdotal
reports that there are real concerns about safety for women who may forego study opportunities that
11
require them to commute at night when street lighting may be unavailable. Both the ZOU regional
centres as well as polytechnics have reported a decline in attendance by women when tutorials and
lectures are scheduled at night due to power failures. However, the information emerged from similarly
anecdotal reports, with no supporting baseline data.
Social 3.2.11 For the past decade, Zimbabwe’s energy sector has been in decline resulting in chronic power
outages that have impacted negatively on households, industry, human capital institutions, and
essential basic service delivery. The current power supply continues to be inadequate to meet the needs
of households, industry and key human capital development institutions. In 2012, only 37% of
households in Zimbabwe had access to electricity that is connected to the national grid.
3.2.12 The persistent unscheduled power outages and load shedding have an adverse and sometimes
severe impact on hospitals and higher education and tertiary institutions. Public hospitals by and large
do not have adequate back-up generator capacity to power all operations for extended periods of time.
The largest facilities which predominantly serve poor clients are particularly hard hit as they cannot
generate sufficient income to finance alternative power sources. Such facilities include General
hospitals, in the small urban centres and rural areas are not fed by dedicated power lines and so they
are subjected to the same frequency of power outages as the surrounding communities.
3.2.13 Intermittent power supply is often a direct cause of disruption of clean water supplies in
households as well as essential institutions such as hospitals as power outages affect the water
treatment plants that supply the hospitals. The lack of water for even an hour in such essential
institutions has serious implications for infection control and the health of patients and staff.
3.2.14 Similar to the situation prevailing at most public hospitals, educational institutions including
universities are not spared. ZOU established in1999, is a unique institution of higher learning offering
ODL. ZOU has 10 regional centres in the country where students go for tutorials and examinations.
Some of the negative impacts of frequent power outages on the university include failure to stick to
tutorial and examination schedules, delays in planned work until power supply resumes, the university
printing press failing to meet its production targets resulting in outsourcing of printing jobs work which
entails additional costs. Furthermore, at the ZOU regional centres, study schedules are frequently
disrupted by the unpredictable power supply and this ultimately impacts on study completion rates
with students taking more time than is necessary to complete their studies. This creates additional
barriers to economic participation by the majority rural and adult learners who are expected to benefit
from the ODL institution.
3.2.15 The ZOU also has a Virtual Centre which runs on an e-learning platform. As the centre is run
from Harare, it is affected by power outages which impact on students’ ability to receive tutorials
timeously and to submit assignments online. This is particularly problematic for students in the smaller
urban centres and rural areas.
3.2.16 The key impact of power outages on ZOU is on its operational efficiency, including, (i)
constraints to revenue generation as a result of declining enrolment, (ii) inability to operate its virtual
learning centre efficiently which affects its competitiveness and attractiveness to foreign students, (iii)
increased costs to students as a result of re-scheduling tutorials and (iv) longer duration of studies. The
ZOU which accounts for nearly half of the country’s university enrolments, needs to remain
competitive to take advantage of the increasing free movement of people in the SADC region and
beyond as well as the relaxation of trade barriers. However, there is a striking observation that may be
attributed to a decline in the competitiveness of the institution. The ZOU has experienced a decrease
in overall enrolment between 2005 and 2012. In 2005, ZOU enrolled a total of 20,482 students of
12
whom 71% were female. Enrolment peaked again in 2008 reaching 19,694 students but has since been
on a downward trend year on year with the largest decline between 2010 and 2011.
3.2.17 In addition to the universities, Zimbabwe has 8 Polytechnics, 3 Vocational and Technical
Colleges and 13 Teacher Colleges. All institutions are affected to varying extent by inadequate power
supply which is exacerbated by power outages and load shedding. The hardest hit institutions are those
with power grids linked to suburbs. Rural Institutions have additional challenges. Those connected to
Central Business Districts (CBDs) such as Harare Polytechnic are slightly better off. Load shedding
is currently unscheduled and there is no longer notification to customers about impending power cuts.
3.2.18 The most serious impact of power outages is on the quality of learning, especially at
polytechnics and VTCs. Students at these institutions are expected to spend 90% of their time in
workshops and machines have to be kept running to meet the specified number of contact machine
hours. In the event of power outages, the machine contact hours are reduced which impacts on the
competency of students and readiness for work.
3.2.19 The rating of Zimbabwe’s tertiary institutions have seen a continuing decline against other
African universities especially following the opening up of South African Universities post 1994. The
continuing power shortages are an important contributor to this decline, especially the research output
of the institutions. The restoration of reliable power supply is likely to see a resurgence of the
attractiveness and competitiveness of these institutions in the region.
3.2.20 Addressing fragility and building resilience: The sector and the project area face varying
degrees of fragility. Lack of adequate power supply, dilapidated rural infrastructure, environmental
factors, weak institutions, low accountability and transparency, high public debt and liquidity crisis,
lack of economic opportunities for women etc. are key elements of fragility. The project is designed
to address these challenges and build resilient institutions and societies.
4 IMPLEMENTATION
4.1 Implementation Arrangements
4.1.1 The original institutional and implementation arrangements of the project will continue. The
POC provides an overall strategic and policy oversight for the Zim-Fund. The MMU under the Bank’s
oversight provides portfolio management support. The IE and PA procured through the program
provide project management and procurement services respectively on behalf of the Government of
Zimbabwe. The Project receives guidance from a Project Steering Committee comprising beneficiary
power utilities and key Ministries. The IE concluded an MOU with the two power utilities namely
Zimbabwe Electricity Transmission and Distribution Company (ZETDC) for the transmission and
distribution activities and Zimbabwe Power Company (ZPC) for the generation activities defining the
roles and responsibilities of each party. The coordination is further strengthened through regular
working meetings with the focal points.
4.2 Financial Management
4.2.1 In accordance with the Zim-Fund financial management arrangements, the Project financial
management activities are carried out by the IE. The IE is responsible for ensuring appropriate
financial management arrangements are in place and will prepare quarterly and annual project
financial statements. The financial statements shall be prepared in accordance with the International
Public Sector accounting standards and they shall be audited by an independent external audit firm in
accordance with internationally recognized auditing standards and Bank approved Terms of
Reference. The audit report along with the management letter shall be submitted to the Bank no later
than 180 days after year end. Further details on financial management are disclosed in the technical
annexes.
13
4.2.2 The project financial management activities will be performed by the Project Accounting
division of the Implementing Entity (IE), a division headed by a well-qualified professional with over
three decades of experience. A competent accountant from the Division will be assigned to the Project,
and his/her duties shall be to ensure an appropriate system of bookkeeping, accounting and
documentation to enable timely production of quarterly and annual financial reports in accordance
with the Bank Group’s financial reporting requirements. The IE was responsible for the financial
management of EPIRP Phase I and is currently managing Phase II Stage I. The financial management
responsibilities of the IE were previously not sufficiently and explicitly spelt out in the contracts.
Under Phase II, the financial management responsibilities are contractual obligations of the
implementing entity.
4.2.3 The Project will be audited annually by an external auditing firm in accordance with the
requirements of the Bank Group. An amount has been allocated in the cost of the Project to cover the
cost of the external auditing services. The IE shall provide all financial statements as well as technical
reports to the auditors. The audited accounts and the management will be submitted to the GoZ and
the Zim-Fund MMU once completed, not later than six months after the end of the financial year.
4.3 Disbursements
4.3.1 In accordance with the Zim-Fund Operations Manual, disbursements for all goods, works and
consultancy services for the Project will be undertaken using the Direct Payment method based on
disbursement applications prepared by the PA and approved by the MMU, and shall be in accordance
with the Bank disbursement rules as contained in the Disbursement Handbook. The IE will be
responsible for certification of invoices submitted by other service providers or contractors and
preparation of the disbursement application which will be reviewed and signed off by the PA and
submitted to the Bank, as administrator of the Zim-Fund, for payment. Financial management and
disbursement arrangements are detailed in the technical annex B4.
4.4 Procurement Arrangements Phase II Stage II
4.4.1 Similar to Phase II Stage I, all procurement of Goods and Works and acquisition of consulting
services will be in accordance with the Bank Rules and Procedures for Procurement of Goods and
Works (May 2008, revised July 2012) and Rules and Procedures for the Use of Consultants (May
2008, revised July 2012), as well as in accordance with the Zim-Fund Operations Manual, using the
relevant Bank Standard Bidding Documents. The same procurement arrangement will be utilized for
the final phase of the Emergency Rehabilitation project as used for the first two phases.
4.4.2 The PA, Crown Agents, appointed during Phase I & Phase II Stage I of the programme will
continue to support the procurement activities for Phase II Stage II. The services provided by the PA
include i) preparation of the procurement plan, ii) design of the procurement packages from the
technical specifications prepared by the IE, iii) preparation of prequalification and bidding documents,
iv) advertisement of tender in the relevant publications, v) follow up of the bidding process up to
contract award and including all requisite notifications to the Bidders, vi) monitoring of project
procurement activities, vii) contract amendments and viii) processing of disbursement requests and
submission to the Bank. The current contract Crown Agents is valid until 30th September 2017. It is
anticipated that if EPIRP II Stage II is approved, the contract may be extended to March 2019.
4.4.3 The various items to be procured under respective categories of expenditure and their
procurement methods are summarized below in Table 6. An updated procurement plan of the project
has been included in the technical annex B5. The plan summarizes current status and expected
activities. The Stage II project is expected to be completed by January 2019. The plan provides detail
for each contract to be financed by the grant facility the different procurement methods, the need for
prequalification, estimated costs, prior-review requirements, and time frame are agreed between the
Government and the Bank team.
14
Table 6: Summary of Procurement Arrangement (Amounts in million USD) for Stage II
Procurement Activities/Category Procurement Method Total
ICB SSS LCS
A: Works
Refurbishment of network
infrastructure 6.30 0.00 0.00 6.30
B: Services
Consultancy for Project
Implementation 0.00 0.25 0.00 0.25
Consultancy for Project Audit 0.00 0.04 0.04
Consultancy for Project Procurement 0.00 0.13 0.00 0.13
Total 6.30 0.42 0.00 6.72
4.4.4 The Bank has approved advance contracting to facilitate procurement for the refurbishment of
the network infrastructure package. This procurement package for Works includes three components:
(i) replacement of transformers and related accessories at Sherwood substation; ii) replacement of a
sub transmission transformer and related accessories at the Orange Grove sub-station and iii)
Construction of a 33 kV Overhead Line dedicated to Gimboki Sewage Works.
4.4.5 The IE, appointed for EPIRP Phase II Stage 1, i.e. Parsons Brinckerhoff Africa (Pty) Ltd (PB)
will continue to support Phase II Stage II program. PB is currently responsible for the implementation
of Phase II Stage 1 of the project. The services provided by IE include: (i) the preparation of technical
specifications, (ii) technical evaluation of tenders (bids), (iii) monitoring and tracking project
activities, (iv) coordination of project activities with stakeholders, (v) project supervision and overall
project management services including financial management and the preparation of financial
statements and (vii) reviews of full contract documentation at various Stages of the pre-tender, tender
adjudication and contract negotiation. The current contract with Parsons Brinckerhoff Africa (Pty) Ltd
(PB) is valid until 21st January 2017. It is anticipated that if EPIRP II Stage II is approved, the contract
may be extended to March 2019.
4.4.6 External Project Auditor appointed for EPIRP Phase II Stage I, i.e. Baker Tilly Gwatidzo
Chartered Accountants in association with Baker Tilly France will continue to provide Auditing
services for EPIRP Phase II Stage II. The current contract with Baker Tilly Gwatidzo is valid until
30th July 2017. It is anticipated that if EPIRP II Stage II is approved, the contract may be extended to
March 2019.
4.5 Monitoring & Evaluation
4.5.1 Zim-Fund has developed a monitoring and evaluation (M&E) framework for the Phase II
project. The framework was adopted by the POC on 3rd December 2014 and has been rolled out from
April 2015 starting with the Project Baseline. The Project result matrix has been updated on the basis
of the adopted M&E Framework. It was also prepared in line with the new template approved by the
Bank. The Bank also conducts supervision missions every six (6) months. ZWCO will closely monitor
implementation and dialogue with ZimFund donors, Government and other stakeholders on project
progress performance and improvement.
4.6 Risk Management
4.6.1 Programme risks are regularly reviewed and discussed by the POC. Mitigation factors are
identified and implemented as part of the programme execution. The detail risk matrix for the
programme is notes in Appendix 5. The following key risks are summarised in the table below.
15
Table 7: Summary of Projects Risks EPIRP Phase II Stage II
Actual Risk
Extent of MMU’s
control over the
identified risk
Risk Description and Mitigation Measures
Cost overrun High
Description: Risk of not completing the intended scope
due to cost overrun and limited budget.
Mitigation: Carry out fairly detailed scoping exercise to
meet the project objectives with due allowance for
unforeseen contingencies.
Corruption and
procurement
malpractices.
High
Description: Mis-procurement or the un-authorised
expenditure of project funding.
Mitigation: Adhere to the Bank's procurement of Works,
Goods and Services procedures.
Keep vigil on possible corruption, unethical and
procurement malpractices and investigate, if required.
Political instability could lead to disruption of
project implementation.
High
Description: Project delays experienced due to political
instability. Mitigating: Continued dialogue with Government of
Zimbabwe so they ensure a conducive environment and
maintain stability during implementation and completion
of national project
Vandalism of
rehabilitated facilities High
Description: Risk of not sustaining the programme
outcomes due to vandalism of refurbished infrastructure.
Mitigation: Enactment and enforcement of legislation
that criminalizes acts of vandalism and reduction in power
outages ensuring that the system is live most of the time.
Improve customer communication and feedback options.
5 JUSTIFICATION FOR FUNDING
5.1 The project was originally designed with a full amount of US$32.94 million with funding
arrangement for Stage I (for available resources) and Stage II (for funds to be mobilized) and the Board
was advised that management would come back for the approval of financing for the remaining scope
once grant funding is available. This was therefore expected from the initial approval of the project on
18 December 2013.
5.2 Following commitment of additional resources to ZimFund by Denmark, Sweden and Norway
as well as surplus funds from Phase I identified, the continuation of EPIRP PH II Stage II scope and
the financing for these project activities were approved by the Program Oversight Committee of the
Zim-Fund, which is composed of the Zim-Fund donors and GoZ representatives, on 29 January 2016,
after consideration of the need to move towards achieving the full objectives of the Project as
envisaged at Project Appraisal.
5.3 The project is in alignment with the Bank Group updated Country Brief (2014-2016), the
Bank’s Ten Year Strategy (2013-2022), “High-5s” and Bank’s Energy Sector Policy. The poor state
of power transmission and distribution infrastructure in the country affects the operation of water
16
supply and sanitation plants thus becoming a major constraint and burden to vulnerable and poorer
segment of the residents.
5.4 Stage I is under implementation and front end activities (design, technical specifications) for
Stage II have been completed.
5.5 The Project Appraisal cost estimates, financial and economic outcomes were based on the first
phase of EPIRP and also other works funded by other programs in the country. The estimates included
adequate contingency to cushion for unforeseen circumstances.
5.6 The continuation of EPIRP Phase II Stage II is justified as the expected outcomes will improve
economic recovery and in general contribute to the wellbeing and health of Zimbabweans. This
outcome is aligned to the objectives of the Zim-Fund donor community.
6 LEGAL INSTRUMENTS AND AUTHORITY
6.1 Legal Instrument
6.1.1 The legal instrument to finance the grant will be a Protocol of Agreement between the Republic
of Zimbabwe and the Bank, in its capacity as the administrator of the Zimbabwe Multi-Donor Trust
Fund (ZimFund), for a grant from the resources of the ZimFund.
6.2 Conditions Associated with Bank’s Interventions
6.2.1 Conditions Precedent to Entry into Force of the Grant
The Protocol of Agreement will enter into force on its date of signature by the Recipient and the Bank.
6.2.2 Conditions Precedent to First Disbursement of the Grant
The conditions precedent to first disbursement of the initial grant, which will be extended to the new
grant, have been fulfilled. As such, disbursements may be made from the new phase II stage II grant
upon entry into force of the Protocol of Agreement.
6.2.3 Undertakings
The Government of the Republic of Zimbabwe agree to:
(i) maintain the existence and functioning of the Project Steering Committee from EPIRP, Phase
I & II, in a form and with a composition acceptable to the Bank, with its terms of reference extended
to cover this Project;
(ii) provide a written commitment to the Bank to apply tax and duty exemption for the Project, and
to facilitate work permits and visas for persons working on the Project; and
(iii) implement and report on a bi-annual basis, in a form acceptable to the Bank, on the status of
the implementation of the Environmental and Social Monitoring Plan.
6.2.3 Compliance with Bank Policies
The proposed grant complies with all applicable Bank policies.
7 RECOMMENDATION
7.1 Considering the many socio-economic and environmental benefits of this Project and
objectives of the ZimFund in the recovery and development efforts of Zimbabwe, it is recommended
that the Board of Directors approves this financing from the resources of the ZimFund towards the
completion of the activities for EPIRP Phase II Stage II scope for the amount of US$ 7.32 million.
I
Appendix
Appendix 1 - Map of the Country and Location of the Project Areas
Kariba hydro power station
Mutorashanga
Bindura
Norton
Hwange Thermal
power station Sherwood
Haven
Chertsey
InsukaminiMarvel Tokwe
Plumtree
Triangle
Beitbridge
Dema
Orange Grove
Warren
Harare
Alaska
MOZAMBIQUE
ZAMBIA
BOTSWANA
SOUTH AFRICA
Gweru
Zvishavane
Mashava
Mvuma
Kadoma
Install 50MVA 132/33 kV
Transformer
Horseshoe
Atlanta
Mazowe
Vic Falls
RedcliffInstall 90MVA
330/132 kV
Transformer
Rehabilitation
of Hwange
Power station
Install 175MVA
330/(132)88 kV
Transformer
Install 175MVA
330/(132)88 kV
Transformer
Rehabilitation of Prince Edward
Dam Water works substation and
Crowborough & Firle
Sewerage substations
ZIMBABWE EMERGENCY POWER INFRASTRUCTURE PHASE II
REMOVED FROM
SCOPE
II
Appendix 2: Status of Emergency Power Infrastructure Rehabilitation Project –
Phase I
The Emergency Power Infrastructure Rehabilitation Project Phase I (EPIRP I) was
approved on the 30th June 2011. The approved grant of USD 39,610,000.00 has been
financed by the Zim-Fund. The project had the following components: (i) Rehabilitation of
the Ash Handling Plant at Hwange Thermal Power Station; (ii) Rehabilitation of sub-
transmission and distribution facilities; (iii) Environmental and Social Audit and
implementation of re-designed Environmental and Social Management Plan (ESMP), (iv)
Project Supervision and (v) Project Accounts Audit.
Progress towards Development Objective: The development objective of the project was
to assist in improving the provision of adequate and reliable power supply in an
environmentally sound manner through the rehabilitation of the Ash Plant at Hwange
Power Station and the sub-transmission and distribution facilities in the country. Physical
implementation of the project on the ground started in March 2013 with mobilization of the
first contractor. Most of the packages were completed in 2014 except the rehabilitation of
the Ash Plant at Hwange which was completed during the first quarter of 2016.
Outcome Reporting: Table 7.4.3 below reflects the project outcomes based on the PAR
Results Based Logical Framework (RLF).
Outcome indicators (as per RLF; add more
rows as needed)
Baseline
value
(Year)
Most
recent
value
(A)
End
target (B)
(expected
value at
project
completion
)
Progres
s
towards
target (%
realized)
(A/B)
Comment
Outcome 1:
Electrical energy
production at
Hwange Power
Station
3 133
GWh
3 500
GWh
3 850
GWh
91% The Ash Plant was one of the factors
limiting generation at HPS, the
efficiency and output has increase
beyond the targeted value.
Outcome 2: Number
of customers restored to the network
0 11 382 11 632 98% Implementation of the Sub-transmission
and the Distribution Packages are completed.
Outcome 3:No. of
new customers fed
from supply points
upgraded under
distribution
transformer project.
0 11 888 20 010 59% Implementation of the contracts for the
Distribution is complete. However the
new connection uptake is slow due to
prevailing economic conditions.
Outcome 4:
Population supplied
with water from a
water treatment
source that has a
reliable power supply
0 2 600
000
2 920 73
8 (22%
of
Zimbab
we)
89% Some water points are no longer
functional and in most cases the
transformers were relocated to other
needy areas.
Outcome
5:Population whose
sewerage
reticulation is
0 529 768 529 768
(4% of
Zimbab
we)
100% Sub-transmission and PMTs supplying
sewage works have been installed.
III
powered by a
reliable source of
power
Outcome
6:Customers with
continuous supply of
power due to firm
capacity (Customers)
0 49 605 49 605 100% Seven Sub-transmission transformers
were installed, at the following
Substations: Norton, Atlanta, Mpopoma,
Pomona, Stamford, Criterion and
Mazowe. These will provide firm
capacity to the customers.
Output Reporting:
Table 7.4.4 below reflects progress in achievement of project outputs. The indicators are
based on some of the output indicators reflected in the PAR RLF, but are more refined for
focus and closer to what would be expected in the 2011 RLF. They are as proposed in the
retrofitted RLF.
Output indicators (as specified in the RLF;
add more rows as needed) Most recent
value
(A)
End target (B)
(expected value at project
completion)
Progress towards
target (% realized) (A/B)
Output1: Sub-transmission level
transformers installed (No.)
7 7
100%
Output 2: Sub-transmission level
circuit breakers installed (No.)
16 16
100%
Output 3: 11/0.4kV & 33/0.4kV
distribution transformers installed
(No.)
426 by the
Contractor
81 by ZETDC
507
100%
Output 4: Distribution lines rehabilitated (km)
342 342 100%
Output 5: Distribution cables
rehabilitated (km)
17 17
100%
Output 6: Replace wet ash handling
system
0 1
98%
Output 7: Construct new ash plant
control room
1 1
100%
Output 8: 3.3kV 3-core cables
(metres)
500 500
100%
Output 9: Environmental & Social
Management Plan (1 Report)
1 1 100%
IV
Appendix 3 – Status of Zim-Fund Resource Mobilization The ZimFund contributions as at the end of March 2016 are as indicated in the table below.
Donor Date Pledged Amount Pledged Amount paid in
Currency of the
Donor
Balance in Currency
of the Donor
Amount
Paid in USD
Date of Payment
Australia 12 Oct 2010
AU$ 10,000,000.00 AU$ 5,600,000.00 AU$ 4,400,000.00
AU$ 0.00 USD 5,518,240.00 USD 4,551,800.00
21 Oct 2010 07 Apr 2011
Australia 01 June 2012 AU$ 10,000,000.00 AU$ 10,000,000.00 AU$ 0.00 USD 9,794,000.00 12 June2012
Denmark 04 Oct 2010 DKK 30,000,000.00 DKK 30,000,000.00 DKK 0.00 USD 5,318,081.72 30 Nov 2010
Denmark 21 Nov 2011
09 June 2014
DKK 45,000,000.00
DKK110,400,000.00
DKK 45,000,000.00
DKK 77,000,000.00
DKK 0.00
DKK33,400,000.00
USD 5,158,343.81 USD 2,643,818.03
USD 12,680,502.91
15 Dec 2011 01 Jun 2012
29 Dec 2014
Germany 21 Jan 2011 EUR 5,000,000.00 Euro 5,000,000.00 EUR 0.00 USD 6,857,362.00 01 Apr 2011
Germany 07 Feb 2011 EUR 5,000,000.00 Euro 5,000,000.00 EUR 0.00 USD 6,912,575.00 01 May 2011
Germany 21 Dec 2011 EUR 10,0000,000.00 EUR 10,000,000.00 EUR 0.00 USD 12,957,700.00 13 Dec 2012
Norway 12 Oct 2010
11 Apr 2012
05 Aug 2015
NOK 41,000,000.00
NOK 41,000,000.00
NOK 9,000,000.00
NOK 41,000,000.00
NOK 25,000,000.00
NOK 16,000,000.00
NOK 0.00
NOK 0.00
NOK 0.00 NOK 0.00
USD 7,073,818.03
USD 4,399,084.99
USD 2,697,436.70 USD 1 058 412.62
01 Nov 2010
11 Dec 2012
08 Aug 2013 31 Aug 2015
Sweden 26 Nov 2010
SEK 40,000,000 SEK 10,000,000.00
SEK 30,000,000.00
SEK 0.00
SEK 0.00
USD 1,563,769.91
USD 4,324,470.11
01 May 2011
03 Dec 2010
Sweden 08 June 2012 SEK 50,000,000.00 SEK 30,000,000.00 SEK 20,000,000.00
SEK 0.00 SEK 0.00
USD 4,228,169.89 USD 2,986,970.13
26 June 2012 21 Nov 2012
Sweden 26 Nov 2014 SEK 20,000,00.00 SEK 20,000,00.00 SEK 0.00 USD 2,612,370.15 16 Dec 2014
Switzerland 11 Aug 2011 CHF 4,900,000.00 CHF 4,500,000.00
CHF 400,000.00
CHF 0.00
CHF 0.00
USD 5,699,810.01
USD 412,939.60
06 Sept 2011
27 June 2012
United Kingdom 19 Oct 2010 GBP 10,000,000.00 GBP 10,000,000.00 GBP 0.00 USD 15,865,000.00 28 Mar 2012
United Kingdom 13 Mar 2012 GBP 10,000,000.00 GBP 10,000,000.00 GBP 0.00 USD 15,546,000.00 06 Dec 2010
Total 145,959,285.88 USD 140,860,671.79
Received pledges amount to USD 140,860,671.79. The Contribution Exchange Letter for the remaining Danish pledge was signed between the Bank and
Australia (assigned Danish representative to ZimFund) during the month of August 2016 and disbursement of AU$ 6,589,741.00 to the ZimFund account is
expected in November 2016.
V
Appendix 4 – Status of Active Country Portfolio as at 31 March 2017
# Sector/Operations Funding
Window
Approval
Date
Effective for
1st Disb Date
Completion
Date
Amount App.
(UA)
Amount Dis.
(UA)
Disbursement
RateAge
IP
(Impl.Progress)
DO (Dev.
Objectives)
Overall
Performance
Status
AGRICULTURE SECTOR 7,293,691 5,871,577 80.5% 3.1
1 LAKE HARVEST PROJECT ADB Loan 10/26/2011 1/3/2013 11/26/2020 5,844,023 5,844,023 100.0% 5.6 2 2 PP
ADF Grant 10/19/2015 12/2/2016 19/05/2018 719,165 3,740 0.52% 1.6
FAPA Grant 6/11/2015 11/24/2016 19/05/2018 730,503 23,814 3.3% 2.0
MULTI_SECTOR 26,320,000 17,079,837 64.9% 2.6
3 CAPACITY BUILD. PROJECT FOR PFDEM ADF Grant 12/5/2012 7/4/2013 12/31/2017 16,120,000 12,516,209 77.6% 4.5 3 2 PP
4 GOVERNANCE AND INSTITUTIONAL PROJECT ADF Grant 12/12/2013 4/1/2014 12/31/2017 5,200,000 3,519,769 67.7% 3.5 3 3 PPP
5 STRENGTHENING INSTITUTIONS OF TRANSPARENCY AND ACCOUNTABILIT ADF Grant 7/10/2015 11/23/2015 3/31/2019 2,000,000 1,043,859 52.2% 1.9
6 INST. SUPPORT FOR STATE ENTERPRISE REFORM & DELIVERY PROJECT ADF Grant 1/24/2017 6/30/2020 3,000,000 0.0% 0.3
POWER SECTOR 47,945,403 2,292,909 4.8% 2.1
7 EMERGENCY POWER INFRASTRUCTURE REHAB Phase II ZIMFUND 12/18/2013 7/9/2014 11/30/2018 11,145,403 1,852,709 16.6% 3.5 3 3 NPP
8 ALASKA-KAROI POWER TRANSMISSION REINFORCEMENT PROJECT ADF Grant 12/16/2016 5/18/2017 6/30/2018 13,540,000 0.0% 0.5
9 MULTINATIONAL KARIBA DAM REHABILITATION PROJECT ADF Grant 12/15/2014 11/23/2015 12/31/2025 23,260,000 440,200.00 1.9% 2.5
FINANCIAL SECTOR 17,857,143 - 0.0% 1.1
10 CABS TRADE FINANCE LINE OF CREDIT ADB Loan 4/20/2016 12/28/2018 17,857,143 0.0% 1.1
SOCIAL SECTOR 6,110,000 2,764,526 45.2% 2.0
11 YOUTH AND TOURISM ENHANCEMENT PROJECT ADF Grant 12/18/2013 4/8/2014 6/30/2017 2,700,000 2,483,611 92.0% 3.5 3 3 NPP
12 YOUTH AND WOMEN EMPOWERMENT PROJECT ADF Grant 10/31/2016 5/18/2017 6/30/2022 3,410,000 280,915 8.2% 0.6
TRNASPORT SECTOR 880,000 721,884 82.0% 3.5
13 TRANSPORT SECTOR MASTER PLAN STUDY ADF Grant 12/18/2013 5/20/2014 12/31/2017 880,000 721,884 82.0% 3.5 3 3 NPP
WATER SUPPL/SANIT 51,629,297 6,268,690 12.1% 2.1
14 URGENT WATER SUPPLY AND SANITATION REHAB PHASE II ZIMFUND 10/7/2013 7/10/2014 12/31/2017 14,340,129 3,621,166 25.3% 3.7
ADDITIONAL FINANCINF TO UWSSRP PHASE II ZIMFUND 9/30/2015 11/17/2015 12/20/2018 11,673,039 2,037,566 17.5% 1.7
15 BULAWAYO WATER & SEWARAGE SERVICES IMPROVMENT PROJECT ADF Grant 12/9/2015 5/17/2016 30/12/2021 24,000,000 434,758 1.8% 1.5 3 3 NPP
16 ZIMBABWE INTEGRATED URBAN WATER MANAGEMENT AWF 12/21/2015 8/26/2016 1/2/2019 1,616,129 175,200 10.8% 1.4
158,035,534 34,999,423 22.1% 2.3 2.9 2.8
Note: Ratings (1-4): Highly Unsatisfactory = 1; Unsatisfactory = 2; Satisfactory = 3; Highly Satisfactory = 4 NPP= Non Potentially Problematic Project; PP = Problem Project; and PPP = Potentially Problematic Project
NPP
GRAND TOTAL
SUPPORT TO THE BEEF AND LEATHER VALUE CHAIN2
3 3
VI
Appendix 5 – Project Risk Matrix
Presented below are the perceived risks for the project. From the table below, it can be noticed that all the perceived risks are scored as “Medium” meaning
that the MMU needs to monitor and maintain strict measures as implementation continues.
Risk Category Actual Risk Extent of MMU’s
control over the
identified risk
Risk Assessment
Actual Risk Probability
Rating
Impact
Rating
Score &
Colour
Cost Risks
Cost overrun High 2 3 6
Carry out fairly detailed scoping exercise to meet the
project objectives with due allowance for unforeseen
contingencies.
Liquidity challenges
affecting smooth
payments for services by local service providers
Medium 2 3 6
Ensure financial soundness of winning bidder to ensure
smooth execution.
Hold Regular meetings with Contractor and
Subcontractors to give them a platform to air their liquidity concerns, if any and engage Government for
solution
Contextual risks
Corruption and
procurement
malpractices.
High 2 5 10
Adhere to the Bank's procurement of Works, Goods and
Services procedures
Keep vigil on possible corruption, unethical and
procurement malpractices and investigate, if required.
Disruption of project
implementation High 2 3 6
Political instability in the run up to the 2018 harmonized
elections could lead to disrupted project implementation
and delay in execution.
Continued dialogue with Government of Zimbabwe so
they ensure a conducive environment and maintain stability during implementation and completion of
national project
Local Sub-contractors
being incapacitated by a
troubled financial sector
due to uncertain
economic policies
Low 3 3 9
Engage with the IEs to ensure that the contractor and
subcontractors anticipate changes within the local
financial sector as well as stay ready to institute remedial
measures
Post
implementation
risks
Vandalism of
refurbished installations High 2 3 6
Enactment and enforcement of legislation that
criminalizes acts of vandalism and reduction in power
outages ensuring that the system is live most of the time.
Improve customer communication and feedback options.
VII
Benefits not reaching the
intended beneficiaries Medium 2 4 8
Engage with targeted beneficiaries at project inception
Stage to ensure the design and implementation in line
with the project objectives and outcomes. Carry out post
implementation project verification.
Monitor and ensure continued stakeholder engagement
for any corrective action;
Failure to properly
operate, and maintain the
rehabilitated facilities
Medium 2 4 8
Build Capacity of operating staff within beneficiary
institutions and ensure availability of manuals so that
end users are sufficiently equipped to carry on trouble
shooting.
Engage beneficiary institutions on a //system to ensure
long term sustainability of the project.
Weak institutional
capacity Medium 2 4
Probability Ratings (What is the likelihood of this risk taking place)
1 2 3 4 5
Very unlikely to
happen/ Might not
happen at all.
Unlikely to happen 50-50 chances of happening of
not happening
High likelihood of happening Will definitely happen
Impact Ratings (What is the effect of this risk on project outcomes if it happens and not mitigated)
1 2 3 4 5
Minimum – not much
alteration in any of the key project outcomes
Mild – All or Key outcomes will
be achieved but some outputs will not be achieved
Strong – some key
outcomes might be compromised
Very damaging – significant
reduction in intensity of key outcomes
Catastrophic – complete negation of project
outcomes
Scores and Colour Codes (The score is the product of the Probability Rating and the Impact Rating).
1-5 6-10 11-15 16-25
Low risk, monitor and
manage while
continuing with
implementation
High risk, review and introduce additional
controls to lower risk level. Proceed with
implementation with caution.
Extreme risk, Stop! Immediately introduce further control
measures to lower the risk. Reassess before proceeding.