cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,eb stope pillar destress 1902 e stope...

209
c: ( 'c" . , J, 'f \ f " . ' S'rUOlZS or DZSTRISS BLASTlNG AT CAMPBELL UD LAD MIn .. Michael Cullen Department of Mining and Metallurgical Engineering McGill University, Montreal. e ,July, "1988 A thesis submitted. to the.Faculty of Grpduate Studies and Research in partial of the requirements for the D degree of Master of Engineering. @ Michael Cullen, ,1988. '( - .. ( , . Cl ..

Upload: lamnhu

Post on 04-Aug-2018

234 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

c:

(

'c" . , J,

'f

\

• f

"

. '

S'rUOlZS or DZSTRISS BLASTlNG AT CAMPBELL UD LAD MIn ..

~ Michael Cullen

Department of Mining and Metallurgical Engineering McGill University,

Montreal.e

--~

,July, "1988

A thesis submitted. to the.Faculty of Grpduate Studies and Research in partial ~ulfillment of the requirements for the D

degree of Master of Engineering.

@ Michael Cullen, ,1988.

'( '~.#... -

..

( , .

Cl ..

Page 2: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

. ..

/

ABSTRACT

l1any- "mines are currently experiencing sev'ere rockbursting problems as a result of mining to.deeper depths with ever increasing extraction ratios. ~n recent years renewed interest has been given to destress blasting as a means of rockburst '­control. Destressing involves the blast fracturing of rock to low~r the deformation modulus, peak strength, and residual strength~ If the rock is sufficiently fractured the occurrence of rockbursts may be prevented.

Very little information is available on the amount of fracturi~ required for a successful destress blast, and with what blastlng pattern it can be achieved. This thesis attempts to answer these questions and develop guidelines for destress blasting by means of experimental studies of blast induced fractures. Blasting studies were conducted at Campbell Red Lake Mine in Northern Ontario, canada" The experimental results are site specifie; howe~er, the general conclusions are applicable ta fracturing of any confined rock masse W

RESUME

Plusieurs mines ont présentement des problèmes de coups de terrain intenses dus â 1.' exploi tation en profopdeur de mines avec des taux d'extraction élevé S. Réœemment l'intérêt envers le sautage de décompression à été renouve~lé comme moyen de contrôler les coups de terrain. La dédompression implique la fracturation de la roche au moyen de s~utage pour diminuer le module de déformation, la résistance ulfime e~ la résistance résiduelle. si la roche est suffisamment fracturée, les coups de t~rrain peuvent être évites.

,Très peu d'information est disponible à propos du niveau de fractura~ion~nécessaire pour la réussite d'un sautage de décompression, et avec quel modèle la réussite du sautage peut être ré~lisée. Cette thèse tente de répondre à ces questions et donne les directives pour le sautage de décompression par moyen d'études expérimentales de fracturations induites par le sautage. Les études de sautage ont été réalisées la mine Campbell Red Lake, située au Nord de l'ontario, au Canada. L'emplacement des résultats expérimentaux est spécifique; cependant, les concLusions générales peuvent s'appliquer à n'importe quel fracturation, de massif rocheux confiné •

, ,

f.

Page 3: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

·r \

\

\

.\ --- --~- --~-~--L\-------------:----------~ ..

AClUlOWLEDGMENT

r' am very grate~ul to Campbell Red Lake Mines Limited for financial support and for providing the opportunity to conduct in

situ tests. Special thanks are given to Tony Makuch, Mike Neumann and Brian Lokhorst t mine engiheers, for their advice, an~ assistance with the in situ testing.

Or. B. Mohanty of C.I.L. Limited is thanked for his assistance

with sorne ~f the laboratory testing of rock ~echanical . properties, as well as many useful discussions on explosives and

blasting.

Assistance with laboratory tésting given by Kerry McNamara and Keith ~tani, of Mc~ill University, is' gratefully',

acknowledged. Many colleagues and staff at MCGiil provided

assistance through discussions on~arious aspects of this work,

for which they are thanked. l am particularly gratefu~ to Dr. M. .Scoble~ my thesis advisor, for providing guidance-during the

course of th!s project.

/'

r ..... .-.1

.r ..

-'

;

!

)

1

Page 4: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

1 -6'

/ /

o

/' ,

)

INDBX

1

2 2.1 2.2 2.3

3 3.1 3.2 3.2.1 3.3 3.4 3.4.1 3.4.2 3.4.3 3.5

//4 4.1 4.2 4.3 4.3.1 4.3.2 4.3.3 4.3.4 4.3.5 4.3.6

5 5.1 5.2 5.2.1 5.2.2

6 '5.2.3 5.2.4

5.3 5.4 -

6' 6.1 6.2 6.3 6.4

7 7.1 7.2 7.2.1 7.2.2 7.2.3

! INTRODUCTION Î, CAMPBELL RED LAKE MINE GEOLOGY AND MINE LAYOUT ROCK PROPERTIES AND FIELD STRESSÉS ROCKBURST HISTORY

. DESTRESSING FOR,ROCKBURST CONTRQL MECHANICS OF ROCKBURSTS ' MECHANICS OF DESTRESSING

III •

-

BEHAVIOR OF FRACTURED ROCK I,,;,.~:\;:.,, NUMERICAL MODELING FOR STRESS ANALYSIS ,,'~- -4:,:; THE EXPLOSIVE MECHANISM AND ROCK ERACTURING ... ~'<'I. FRACTURE CREATION '., PREVIOUS STUDIES OF" FRACTURE EXTENSlo'N ~ BLAST HOLE INTERACTION ~ NUMERICAL MODELING FOR FRACTURE ANALY:SrS

REVIEW OF DESTRESS BLASTING PRACTICES INDICATORS'FOR DETERMINING WHEN AND WHERE -TO DESTRESS BENEFITS AND RESULTS OF DESTRESS BLASTING CASE HISTORIES SOUTH AFRICAN GOLD MINES COEUR D'ALENE MINING DISTRICT SUDBURY AREA MINES KERR ADDISON MINE KIRKLAND LAKE MINING CAMP CAMPBELL RED LAKE MINE

PROBEX-l BOREHOLE DILATOMETER -DESCRIPTION OF INSTRUMENT DEFORMATION MODULUS DETERMINATION DILATOMETER CALIBRATION FACTORS DETERMINATION OF HOLE DIAMETER PROBEX-l TESTING CONSIDERATIONS SENSITIVI~Y AND REPEATABILITY OF MODULUS OF DEFORMATION RESULTS IMPRESSION PACKING " SUMMARY AND CONCLUSIONS ON THE PROSEX-1 DlLATOMETER

MICROSEISMIC MONITORING THE MICROSEISMIC WAVE FORM THE CAMPBELL RED LAKE MINE MONITORING SYSTEM MONITORING DESTRESS BLASTING SUMMARY AND· CONCLUSIONS OF MICROSEISMIC MONITORING

FIELD STUDIES OF DESTRESSING NARROW VErN STOPE FACES FRACTURATION AROUND A SINGLE DESTRESS HOLE EFFECTS OF DESTRESSING ON STOPE REACTIONS MICROSEISMIC MONITORING STOPE CONVERGENCE VISUAL INSPECTIONS

i il

-PAGE

l

4'1 4 6

10

i4 14 20 22' 24

- 27 "<.,,31 :-34

36 42

-43 44 45 46 46 48 51 53 -58 66

82 83 85 88 93 94

96 98

I1l6

107 107 110 113 118

119 119 122 124 128 130

1

Page 5: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

c

J;

.1t~-ij ;t :J { , "

"'- • ~ ". J-, .. -

:1'" ~ • ) ,

~ - {

',,1 .-

.~.-. " INDEX 0 COlft'INOlIlD

J ~

(7.2.4. ~ 7.2.5

7.3

8 1 8 .• '1

L

8.2 8.2.1 '8.2.2 ~.3 ~.4

9 9.1 9.2 9.3 9.4

.,-10

, J '. "

1

~ .. ~ . \:\ , OTHER'INSTRUME~JAT~~N DISCONTINUITY SURVEY, SUMMARY AND CONCLUSIONS STUDIES .

; .....,..

OF *REAS,!,' FACE' ~STRE~SINS ,.'

BLAST FRACTURIN~ STUDIES ~FRACTURATION STUD)ES IN THE

PILLAR FRACTURATION STUDIES. IN THE ~OCK,CHARACTERIZATIqN BLAST FRACTURA'.j.fIqN . BLAST VIBRATIO~ STUDIES· SUMMARY ,NND CONCLU,SION$ OK

DESTRESS BLAST DESIGN

\ .

" "-

\~67.0 'w '~T?PE é~~~J . . 1470 STOPE ACCESS DRIFT

, BLAST FRACTURING STUDIES

BLAST HOLE SPACING AND GEOMETRY EXPLOSIVE SELECTION . OTHER BLAST DESIGN CONSIDERATIONS ,-~NUMERICAL MODELING FOR DESTRES5- BLAST DESIGN . .

CONCLUSIONS

APPENDICES

REFE~NCES ,"

1

.\ [.

Il l" , . "

"JI

. .,

, '" .. ,

"

\

1 --~

..

. ,

PAGE , . . 134' .. 135

138

140

140 î47 1'48 151

_ '162 165

1 16-7 171 173

'174 ,

1'76

, 179

196

, Il.

1 Il 11

P il Il

iv

1

,

- "

, . '

Page 6: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

..

..

:iI, . l'" §. 4 , '-

.->;-

. .{/' 4

L'IST QF FIGURES , . ~ .....

F~~~ -.--FIGURE

" ' ... FIGURE , -FIGURE

. \

2-1: 2-2: 2-3: 3-1:

, FIGURE' 3-2: FIGURE 3-4:

--- , . FIGURE:~" -3-4: FIGURE 3-5:

FIGOfΠFIGURE

3-6: 4-1:

Mine Loc,at ion Mqp f

Beological Plan" 1400 Level JIn Situ Stress 1400 Levei Reactions' To Loading In A Stiff And Soft

, Tej:)ting Machine ' , , - The Init.:i"al· Concept '6f Destressing . . t Normalized -Dynamic Stresses: Step Pulse An'd_

, Wave Train . Zones Surrounding Blast Hole' Four Cases Of Initiation Delay Between Charges 'a' And 'b'

" FIGURE ~21-2: FtGURE,:~ 4-3:

Three Dimensional Fracture Development Stope Pillar Destress Blast Pattern Coeur D'Alene Preconditioning Stress Blast patte~

. l'

FIGUtŒ " 4-4: FIGURE 4-5: FIGURE 4-6: FIGURE ·4-7:

F~GURE 4-8: ' fit

FIGURE 4-9: 4-10: 4-11: 4-12:

FIGURE FIGURE FIGURE FIGURE FIGURE FIGURE FIGURE FIGURE FIGURE FIGURE FIGURE FIGURE FIGURE FIGURE F.IGURE FIGURE FIGURE FIGURE .)fIGURE FIGURE FIGURE FIGURE FIGURE

FIGURE FIGURE

- 4-13: 4-14: 4-15: 4-16: 4-17 : 4-18: 4-19: 4-20: 4-21 : 4-22: 4-23: 4-24: 5-1: 5-2: 5-3: 5-4:

'5-5: 5-6: 5-7 : 5-8:

5-9: 5-10:

Stope Pillar Destress Blast Falcon ridge Development Reading Destressing A INCO, Pa~t

~. ." Development Headlng DestreqSlng at INCO . Destress p'attern St ope Backs Kerr Addison Mine Destress Pattern For Raising Up T~ Level, Kerr Addison Mine .

. Destress Pattern For Squarré S~" Stopii1g Kerr Addison Mine Destress Pattern For Pillar Recover~. Destress Pattern For Stope Approach!ng Fault Destress Pattern For Approaching Stopes Destress Pattern For Raises Long Section Macassa Mine Stope Crown pillar Destress Macassa Mine Shaft Sinking Destress Pattern Macassa Mine 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope pillar Destress Thin Section Photograph Of Microfractures SEM Photograph Of Microfractures -1421 Drift Box Hole Pillar Destress Box Hole Pillar Destress CRLM r

Schematic Diagram O( Probex-1 Wireline Attachment. Probex-1 At Underground Test Site Typical Pressure Versus Volume Test Data Idealized Pressure - Volume Deformation Curves Tracin9 Impressions From Dilatometer Fr~cture Impression Maps Inclined Discontinuity Plane Cuttin9 Drill

" Hale Impression Map From Drill Hole-Equal Angle Stèreograph With Example Solution

v

\

PAGE

5 7

12 -

17 21

28 35

38 41

49 49 52 52 52 54

56

57 59 59 60 60 63 64 67 69 70 71 73 74 77 77 7-é ll

80 64..-86 86 91 91

100 101

102 102 104

Page 7: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

c

(ilC

J. -'

LIST or rIGURES CONTlNOBD , ,

. FIGURE FIGURE FIGURE FIGURE FIGURE FIGURE FIGURE

... FIGURE

FIGURE FIGURE FIGURE FIGURE FIGURE FIGURE FIGURE FIGURE FIGURE FIGURE FIGURE FIGURE

FIGURE FIGURE FIGURE

FIGURE FIGURE FIGURE FIGURE FIGURE FIGURE FIGURE FIGURE FIGURE .

FIGURE

6-1: 6-2 : 6-3: 6-4: 7-1: 7-2: 7-3: 7-4:

7-4B: 7-5: 7-6: 7-7: 7-8 :-7-9: 7-10: 7-11: 7-12: 8-1: 8-2 : 8-3:

8-4: 8-5: 8-6:

8-7 :' 8-8: 8-9: 8-10A: 8-10B: 8-11 : 8-12: 8-13: 9-1:

9-2: ,

, Microseismic Event ,-Micr6seismic Monitoring~System Seismic Activity Versus Load Seismiç Survey Layout And Resultjl. Blast Hole Eldngation Blast Hèle Elongation paint Injection Trial 1704 EW~tope, Test Location And Instrumentation ~ Test Blast Sequence Typical Blas~ Rattern Microseismic Activity After Blasting Stope Clos ure ' Stress Fractures Before Scaling Stress Fractures After Scaling Blast B3 Destress Hole Blast C2 Destress' Hole, Discontinuity Map 15 Level Plan. 1p70 W 'A' Stopè

~ , ,

Core Recov~red From 1670 W 'A' Stope' Crown Pillar St reps Strain Curve CRLM Andesite Horizontal Versus Vertical Strain Blast Hole And Diamond Drill Hole Locat~ons 1470 Drift r, D

1470 Drift Destressing Results Hole 3 1470 Drift Destressing Resùlts Hole 4 Core From 1470 Drift Hole 4 1470 Drift Fractures - Impression Packer 1470 Drift Fractures - Drill Core Fractures Versus Blast Hole Spacing Modulus Versus Blast Hole Spacing Modulus Versus Fracture Density Relationship Between Fracture Density And Blast Hole Spacing Relationshlp Between Deformation.Modulus And Fracture Density

,

n

'1 ,

..

vi

PAGE

109 11.2 115 117 121 121 123

125 126 127 129

·129 131 131 133 133 137 141 143

145 146 146

152 154 155 156 158 159 160 160 161

110 •

,170

Page 8: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

.\

.. .. Il

LIS'!' 01' 1ABLBS .~

PAGE'

~ -_ 9, TABLE 2-1 :

, TABLE Û2 - 2 : .

Rock Varieties: Mine Terminology ~d Actuâl Rock Types 8 Mine Levels And Elevations 9

TABLE 2-3: TABLE 2-4 : T,ASLE 4-1:

Rock Properties _ 9 Results Of In Situ 'Stress Measurements .. 11

1 Summary Of Results Of Destress Trials 47 TABLE 4-2 :' Stress Ch~nge And Closure 1604 E Pillar ' 75' TABLE 5-1: Confined Calibration Results 92 TABLE 7-1: TABLE '.8-1 : TABLE ,81-2 :

Discontinuity Ori~~tation 136 1670 W 'A' Stope Crown pVllar Test Resulta J 144 1470 Drift Rock Properties 150

TABLE' 8:"3: Results Of Blasting Tests- 164

r

~,

" , ,

( . <1

'0 ""

--" .

=

. . ,\

.,..

o •

vii

Page 9: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

/

"

C'

... f ,

" 1. INTRODUCTION

The past fort y years has seen very few new ideas for the control ::-r-

of rockbursts with the exce~tion of\the destres~ blasting méthode Review of the literature reveals that the early mine engineer~ were familiar with the i~eas of convergence control and-;ine

, '1),. J

sequencing as preventative measures foY,rockbursts. However, even with modern techniqu~s of convergence control and mine ~equencing, rockbursts continue to occur.

01

,. _ oestressing inv'ol ves al ter-ing the rock mass mechanical properties

---by.creating blast induced fractures. The method has been met with both,skepticism and support. There is limited documented

accounts of the methods success, although it is believed that many, undoccumented, succe~sfull blasts have taken place. Resistançe to the technique js likely the r~sult of unsuccessful

r blasts and limited experiencei many engineers believe'it to be unproven technology. It is the belief of this author that man y unsuccess~ul destress blasts are due t~ poor planning and execution, resulting in the rock mass being either under or over

./ . . fractured. Another drawback of the technique is that once the ground has been destressed, it is not possible to know what the outcome might'have been had destressing not been occurr~d.

Tne preyenti9n_ of ro~kbursts by d~stressing was first practiced in the deep South African gold mines. Initial results in South Africa were very good, however, as mining continued to greâter

c'

, depths and greater extraction ratios,4bursting persisted. In recent years, with more sophisticated design and evaluation

~

tools, destressing has been proven to be an effective method'of rockburst prevention. It is recognized that a greàter , understanding of the mechanics of de~tress~~ and the design destress blasts are still necessary.) _

,of

l'

The term destressing is somewhat a misnomer, a more suitab~e term ~

o. would be rock mass conditioning. Because of its general acceptance \ . within the mining community, the terms destress blasting and

Page 10: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

o

..

destressing will be used throughout this thesis. There are a r

number of o?se~ved and postulated phenomena contributing" to/' _~i~

successfu~ destress blast application. ;

~ a) A' reduction in st-i-ffness due to fracturat'i\;~'. i " • 1

1

b) A. reçiuction ~n }~e/ak, a~Gi residual strength ,d~~. oto f'racturation. c) Contr.olled e'n1'gy dissipation along frac~uFe stirt~ces. d} A reduction in potential energy due to closure. l, e) Non' _violent fai.lure as a result of transition to J.seudC?-

plastic behavior. f) Triggering a controlled rockburst with the blast.

A~l these aspects are covered in general discusss~ons, however, only the reduction in stiffness due to fracturing is\investigated .. expe-rimentally.

v

The term destressing is also used for the tèchnique of degassingc for rockburst prevention in coal rnes, and 'for triggering co~rolled rockbursts,by the infection of wat~ ante joint and faûlt surfaces. These two method~- are not discussed in this paper. ( 1

Campbell Red Lake Mine (CRLM) is a gold mige lbcated in Northern Ontàrio. Gol~ is being ~ined from steeply diPrping, nar~ow vein stopes, by overhand cut and fill tnethods·. The host rocks are andesites and altered chloritic schist. The mine has a history

'of rockbursting starting in the early 1960's. 1 Rockbursta with .1

local Richter-magnitudes up to 3.2-have been recorded. A number

of destress blasts,~ave been conpucted at the mine tith varying . degrees of success. The philosophy at the mine -is ciuse -destressing, for rockburst control in pillars,-as the method of l~st resort. ~his is due to both the high coat of destress blaat!ng and concern over variable reaults. It should be noted that the cost of destressing is below that of placing the required strength an~ modulus backfill necessary for rockburst prevention. Destressing stope breast faces ls carried out routinely at the mine as the need arises. Management and

2

Page 11: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

c

\

(

c

. .

c

J

t

engineering, at the mine, recognized that the destress blast designs, which had developed on a trial and error basis, were in need of improvement. Verification of the methods effectiveness was also .desired. (

1 This thèsis is divided into eight sections starting with a;review of mining and geology at.CRLM and a hlstory ot rockbursting at the mine. Chapter 3 presents the meëhanics of rocfbursting and destressing as well as the theory of blast inducedlfractures. An'extensive literatùre review of des~ress blasting was carried out: this is discussed in Chapter 6. A detaile4 account of_~ .heavily monitored pillar destress bTast at CRLM la included in Chapter 4, along with an analysis of drill core, recovered from . the destressed pillar: this analysis was conducted by this author.Microseismic monitoring and in situ deformation testing

, . were used as the principle tools for the studies/of destress blasting carried out during this project. The borehole dilatometer used for determination of in situ deformation modulus

"was a recently developed ins,trument. . techniques needed to be developed, as

instruments validity. Chapt ers 5 and

As such, operating . weIl as verification of the 6 discuss the two , - ,

moni'toring and testing methods. Details of operating' techniques developed and instrument limitations are given. Chapters ~ and 8 report on the two aspects of destress blasting studied. The tirst study evalua~ed single hole destress blasting ofa stope

-=breast face. An investigation of fracturation around Lthe hole as weIl as a study of the overall effectiveness of the technique,was

carried out~ The second study dealt with blast fracturation. «

Investigations of fracture extension be:twee~blast holes' was carried out as well as monitoring of peak particle velocity.'

/ -

Chapter developes guidelines for destress ~last design at CRLM based on the experimental results and literature review. Chapter 10 presents conclusions and recommendations of this study.

3

Page 12: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

.. \

I~

./

- ,

. C

• ,

2. CAMPBELL RED LA1ΠMID: OVERVIEW

1

CampbeYl Red Lake Mines Limited is a member of the Placer Dome

group. The m~fe is loc~ted in Balmertown within the Red Lake mining district of Northwestern Ontario, Figure' 2-1. Gold with trace silver is mined from thin, steeply dipping ore veins. Mining cornrnenced in 1948 at a rate of 300 t per day. Current

j

production is 1100 t per day .

. Original prOduction was all from shrinkage stoping. Overhand cut and fill stoping is now used almost exclusively below a depth of 200 m. Classified mill tailings, supplemented with sand and -

crushed waste rock, are used for backfill. Cement is added to

sill plugs and stope working surfaces. , Currently, mining is to a - " -depth of 900 m. Access to the mine i5 by a 4 compartment shaft

extending to a depth of 1300 m. It is expected that mining will continue to greater depths in the future. Extraction ratios vary

j

thr~ughout the mine and can be as high as 85 percent in sorne ,areas. 'Hand held,and electric equipment are used in stoping.

,> , The mine has a history of extensive rockbursting which is

ù

generally attributed to the mining method (shrinkage stoping) and ~ .

mine sequencing used in the pasto Geo10gy also has a significant

influence on the occurrence of.~ockbursts. The mine consista of . 5 major ore zones in a comp1ex geologica1 environment. This chapt~r presents an overview of the geolpgy and rockburst history

.;.

of th~e. Details of the mine 1ayout are,given for reference

in subsequent chapters .

2.1

, The mine is ocated in the Red Lake Greenstone Belt which

includes m tavolcan~c and sedimentary rocks. The greenstone belt is part of the B~rch-Uchi lake subprovince,. which in turn 18 part of the Archean Superior Province, Rigg (1980).

4

Page 13: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

(

c

,-----

\

f

Red Lake Min:

i n Map 2-1: Mine l~c_at 0 Figure

\

5

,1

'\ -

Ont ario

/

Page 14: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

..•. , , f

. Hydrothermal intrusions and tectonic deformation have significantly altered the rockmass such that identification of original petrology and deformation seque~ce is not possible. Figure 2-2 shows a simplified geological plan of the 14th level. Rigg (1980) 'suggests that the rock classifications used by the mine are ov~~ simplified. Table 2-1 presents the ~esults of his findings.

The deposit is hydrothermal. Multi~phase intrusions have been noted by Rigg c (1980), although not aIl havé been gold bearing. Subsequent remobilization hasrurther co~plicated the mineralization history. The chloritized schist is believed to be an ultra mafic intrusive, Church (1985). This intrusive ljkely caused deformation in the andesite allowing for inflow of hydrothermal solutions. ,

Ore zones occur in a number of geolog~cal settings but are always

~ubparalle: to cleavage and major structures such as andesite -altered rock contact. The mine:Ls comprised of 5 maiQ. ore zo~s, F, F2, .~, L, and G, as weIl as a number of secondary

zones, S, 0, Al, NL, Figure 2-2. The ore veins are of two distinct types; quartz carbonate fracture filled and replacement type.' Quartz carbonate veins are from 0.25 to 1 m in width,

replacement veins are 0.6 to 9 m wide. The host rocks are andes!te and a chlorite schist. Many ore veins occur along the contact of the two. Rockbursting is only a problem in the stiffer andesitic rock. The less stiff chloritic rock may

, -influence whether failure is violent or non violent.

The mine is divided into 27 levels at approximately 45 m , intervals. Table 2-2 lists level numbers and d~pth below

surface .

6

Page 15: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

l'

':

CI) &al &al t- ~ ...J a: &al u 0 Q z ~ r :x:

"- 0 0

0: ci N

ci ...J W CI)

Cl ...J 0 :::» W ~ \&.1 0

Z Z ID fi) a:: &al Q. W &LI 0

&al W ::1 Cl !:i -' a:: a: oc( z 0 0 0 oc( oc( CI)

lI1~IIID

Figure 2-2: Geoiogical Plan 1400 Level::

c '/

7

Page 16: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

1'L' 41

'l'able 2-1: Mine 'l'erminology and Actual Rock Type •

Mine Terminology

Mdesite

Diorite

Rhyolite

--Altered roçk or Chloritic schist '

Lamprophyre dyke

• J l,

Rock type

P,redominantly basaIt rhyolitic andesite and variolitic andesite'~ith minor i~erflow sedi~ents.

,-

Two massive fractitionated gabbroie bodie~, possibly extrusive. '

Rhyolite

Strongly altered mafiç to ultramafic 'in'trusive rocks, basaIt, andesite, rhyolite and~sediments.

Mafie dyke' , •

after Riggs (1980)

(

, ..

\

..

8

Page 17: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

,~

, .

=-."~-

C

\

C

'l'able 2-2.: Mine Level. and Blevations

'" ~~~~l Elevation (m) L~~~l

b~lQ1t :iil.u;:fa.~~ =

.. 1 53 ' ' 14 ,

2 91 \ 15

3 130 16

4 168 17

5 213 ,18 --~,-

6 259 19

7 305 - 20

B 351 -- -=-21

9 396 22

10 442 23

Il 488 24

12 533 - 25 " 13 579 - " '26

.; 27 '"

'-~

'l'able 2-3: R.oc" Propertiea

Rock no. uni axial Young's type samples strength modulus

(MPa) (GPa)

Andesite+ 8 172 82

Altered rock * 2 116 57.5

Diorite* 7 156 88.7

Ryolites * 5 235 92.5

-

, .. "

Elevation (m)

belQw surface

625

670 716 762

808

853

899

944

991 1036

1082

1128) 1173 \ -

1219

poisson's tensile ratio __ strengt

(MPa)

Cl.2 15.6

~ .15

0.26

0.19

* values from Michigan Technological University, Rock Mechanics Research Facility

+ values from McGill University Rock Mechanics Laboratory

9

-

!?

Page 18: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

-J 2.2 ROCK PROPERTIES AND FIELD STRESSBS

Mechanical properties of the various rock ,types are listed in

Table 2-3. The values are averages from rock samples recovered from throughout the mine.

,~ 'A,,"number of overcoring type stress measurements were conducted by --

CANMET at the mine using triaxial CSIR cells. Table 2-4

summarizes the results and compares them to expected ~alues based

on.calculated stress gradients in the Canadian Shield of Northern - Ontario. Figure 2-3 shows the location and direction of

measurements taken on-the 14th level of the mine. As ls common

in the Canadian Shield, the major principal stress is horizontal,

striking NE-SW. It is almost double the vertical stress, which

is slightly greater than that expected from overburden lo~ding

alone. \)

2.3 ROCKBURS:' BJSTORY

Campbell Red Mines has had a long history of rockbursts. The

first unlocated rockbursts occurred in the vicinity of the mine

before 1961, Morrison (1961). The first located bursts occurred

in remnant boxhole pillars. They were attributed to the removal . ~ ~ ~ ~

of sill and boxhole pillars in shrinkage'stopes. Later, as ,

extraction ratios increased, bursting was triggered by pulling

ore. from shrinkage stopes and mining in their immediate vicinity,

Hedley et al. (1985). Most of the bursts occurred in the boxhole

and sill pillars and around the intersection of raises with

stopes and drifts. Si Il removai iri shrinkage arèas above the

lOth Ievel has been discontinued. As weIl as pillar bursts,

small, strairt energy bursts have occurred regularly around the

periphery of underground openings. A description of the

different burst types is given in Chapter 3.

In 1983 a series of major rockbursts occurred in the 'F' zone.

This is a shrinkage area with a very high extraction ratio.

10

Page 19: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

.... 1» r::r a> 1\)

1 .110>

:0 a> fi)

c -fi) ... 0 ... -:l

Ch -C

Ch -.., a> (/)

(/)

3: l1li a> ... 1» - (/) c»' C .. .., > a> .. 3 l1li CI> :;, :l Ul -... (/)

/t) 0) 0)

?,

~- ~ ~-~

"-

.p

Depth Field Stresses (in MPa), CRL Mine Northern Below Test No. 01 02 a' Ov oRa oHa/av Ontario Data*

Surf~ce Brg./Dip Brg./Dip Brg./Dip % Diff. X % Diff. % Diff. (~Pa)

625 m CRL Tl-2 . 23 lS 10 14 19 1.4 ov=16, oHa-33 . (14 L) CRL Tl-3 060°/40° 214°/33° 134°/33° 12% 42% 6% oHa/ova1.5

combined \

')

.,.

990 m 3 test 53 24 12 25 38 1.5 ,ov=26, 0Ha-44

(22 L) combined 087°/16° 322°/57° 185°/26° 4% 13% 7% oHa/ov-1•4

1220 m CRL T3-2 70 41 31 34 55 1.6 ov~32J 0Ha-47

(27 L) CRL T3-3 230°/10° 020° /76° 140% 7° 6% 17% 14% oRa/"v·,1.4 combined - -_._-_ .... _- _._.~---

x Differences of vertical (ov), averag~ horizontal (ORa) stresses and stress ratio (ORa/Ov) with Northern Ontario data.

* Northern Ontario data, obtained frQm stress gradients in the Canadian Shield

Ov • 0.027 MPa/m (obtained from overburden weight).

ORa • 9.86 MPa + 0.0311 MPa/m (0-900 m depth below sùrface). ,

OHa • 33.41 MPa + 0.0111 MPa/m (900-2200 m depth below surface).

OHa/qv - 251:68 + 1.14 depth m

p'

\..,

~

,.

- 1

Page 20: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

1

\

\

'-,

"

o

o trl

1

--'\

W

~-.J_ W g

.J > -0",' 10

W " -1 -

W .J

o W

sl=major-princjpal stre8~ s2=intermediate stress .J ~ s3=minor principal strestd

~ (/)

see Table 2-••

-- .

al a... ~ « u

Figure 2-3: ln Situ Stress 14,00 Level

after Ma uch 1186

12

...

---,/

Page 21: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

.'

"

c •

L9cal Richter magnituêles up to 3.1 were --recorded. The area is now c10sed off, leaving a large quantity of broken ore within the stopes. A detailed description-and analysis of this bursting activity is presented by Hedley et al. (1985). Rockbursts still o~cur in the zone due to the slow decay of supports and stress transfer from other areas.

More recently, rockhursts have occurred in crown and sill pillars'­of eut and filt stopes. 'Pillars i~ stressed ground are prone to bursting when they reach a critical size, dèpendent upon' stress

'leveis and geology': Under present mining conditions, 10 m is the , '

critical siz~. A fault slip type burst has also been identified in a eut and fill stope, . Neumann (1986).

As weIl as the loss of ore and cleanup costs, rockbursts present . a major threat to life. Fortunately Campbell Red Lake Mipes.has

had no fatalities as a resuit of rockbursts. In order ko quickly and accurately located rockbursts and other sei smic activity the

imine has installed a 64 channel microseismic monitoring system. ,

A description of the system and its uses as weIl as a discussion of microseismic emisaions ls presented in Chapter 6. High energy

microseismic events have been recorded in 16 out of 50 current~y active stopes. Low energy events are recorded from most stopesJ particularly after blasting.

. "

" -'1

13

Page 22: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

)

o

3. DBSTRESSING FOR' ROClœ'ORST OON'l'ROL

The past fo~ty years have seen very few'new ideas for the'control~ of rockbursts with the exce~tion of the destressing rnethod • .. Review of the early literature, ~obson (1946), reveals that the early mine engineers were familiar with the ideas of ,'closure

o contr91 and mini~g sequence for rocthurst con'trol~_. !l'he effects -~= 1 1

of time, 'geology and depth were also recognized. Even tnough modern analysis, and techniques tor contro11ing convergence, are much more sophisticated, and minlng sequence can be planned to minimiie high stress situations, rockbursts still occur.

"

This'chapter discusses sorne of the theoretical considerations of destress blasting. As an introduction ~o the problern a review of rockburst mechanics is presented. This is fo11ow~by the mechanics of destressing. Destressing involves the use of

explosives ~or blast fr~cfuring. An extensive r~view of the explosive mechanism and its relationship to fracturing is 4

presented along with discussions on numerical modiling for stress analysis and fracture prediction. Where applica~le, comparisons are rnad~ between theory and practice at Camp~ell Red Lake Mine , (CRLM) •

. ' 3.1 MECBANICS or ROCKBURSTS

The ~echanics of a rèckburst are not completely understood, although, a numbei of hypotheses haye been présented. The commonly accepted causes are related to the disturbance of the gràvitationa~ and tectonic forces due to excavation of underground openings. The creation of excavations causes stress

and strain energy concentrations about the excavation. If the ;

stress concentrations exceed the strength of the rock, fallure "

will occur, causing closure. A rockburst i8 the result of violent failure. It is interesting to note that rockbursts have occurred in surface quarries although these are not considered in

this work.

14

Page 23: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

c

c

, If the rockmass is assumed to behave in a purel~_elastic manner with no fracturing, formulation of energy b~lance~quations to describe reactions of the rock mass to mining i5 simple. The formulation i5 covered by many authors including Hedley (1987)

\

and Salomon (1984). The general form of the equation follows:

.,.

.,

where Wt = change in potential energy resulting from

Um , ' Uc

Ws Wr

ex"cavation ,.J

= stored strain energy in excavated rock = increa~e in stored strain energy in surrounding

4-

rock = energy absorbed in support deformation = excess energy released

'/" "'. ..

The sei smic energy-' Wk is responsible for damage to the mine; and is a resul t' of c~osure of the excavation if pJ:1_r~ly --elastic • ..

Assuming elastic behavior the se1smic energy can be shown to be:

..

. A number cvenergy relationships'can be d~veloped, from which the

foll~wing statements can be ma~~1 af~er Hedley (1987) •

.. a) Without support, aIl the energy components can be expressed in terms of two parameters Um and Uà (the increase ~n stored strain energy if the stress increase ha occurred on an unstressed specimen). It is relatively easy to calculate these parameters using numerical techniques. b) When mining takes place in very small steps the process is stable and no seismic energy is released. In sorne cases this is contradictory, since many mines employ incremental methods but still experience rockbursts. However, this means that sorne other sources qf energy are being liberated due to non-elastic 90ndition"s, either fracturing of a pillar or slippage along a fault. c) The change in potential energy, Wt is the driving forcé oehind the energy components. If it can be reduced, the other energy components are correspondingly reduced. d) Su~port, su ch as backfill, has two beneficial effects. It

15

Page 24: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

~ >

7 o

will reduce th~change in potential energy by reducing volumétrie cl9sure in the excavations and by absorbing energy, less energy is available to be released as seismic energy.

In reality, the energy released by ruckbursts cannot pe'desc~ibep by elastic reactions, as fracturing and other non elastic behavior occurs.

The seismic energy radiated out is a result of tpe oscillations of the rockmass a~out excavation boundaries , as failure occurs.

,)

Damped oscillations result as the~ock mass closes in on excavations. The amount of seismic energy released is prop~rtional to the size of the failure. ,

J For violent failure to occur, the stiffness of the mine structure must exceed that of the mine loading system. The stored energy of the-mine loàding system ~s imparted into the fai~ing structure 'causing violent failure. An analogy is drawn to a core specimen being loaded in a testing machine. The amount of strain energy

, stored by an object is inversely prop~r:tional to its-stiffness, stiff rnaterials store less strain energy.

~~-

w = stored=-strain energy

fi = stress \ a =_cross-sectional area

l = length-K = stiffness = aE/I E = modulus of deformation

When the stress imposed by the testing machine exceeds the st~ength--?f "the specimen, the relative stiffness oi- each determines whether violent or nonviolent failure occurs. 3~1 shows the stress strain reactions for the two possiçle

J

\

16

Figure

c:a8es.~

Page 25: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

(

. ,

c

. (

Figure 3-1: Reactions To L,oadlng ln A Stlff

Soft Te.tlng Mf chine' -

F

AvoJloble stroin energy, ' ,

DISPLACEMENT CASE A: U nstable: violent "",foilure

17

u

F

w -4 u

cr ~

DISPLACEMENlf 'CASE B: Stable, nonvio.1ent

after B la'ke 1972)

...

\, . ,

Page 26: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

r:: case (a), the specimen stiffness (Ks) is greater than the~· loading mac~ine stiffness (KI). When the load exceeds the specimen st~ength, violent failure will occur. The additional .. (\ -stored strain energy in the loading machine continues to load che specimen as it recoils. For case (b), Kl is greater than Ks. Nonviolent fa~lure will occur as the stored strain energy in the loading machine is not suffiëiênt to further load the sample. Tc cause greater damage, additional l~ad must be applied by the testing machine. ~

Whether or not a mine pillar fail~ vlolently ls a bit more ,-complicated than discussed above. It ls dependent on the post failure 'stiffness of the pillar compared to the stiffness Of the

o

entiFe loading system., The size, number and location of the pillars influences the loading system stiffness.

A rockburst causes instantaneous fracture and dilation of the ground. This causes shocK waves to be propagated through the rock as weIl as d~splacement of rock towards mine,openings. The

shock waves ~ay cause rock to 'burst' off excavatio~ wailS and cause other distortion and movement. An opening close tO a

rockburst may be fille~by ~displaced rock; this is usually in a

violent manner.

Salomon (1983) suggests that the follow~ng conditions are n~cessary -~

for a seismic event, hence rockburst, to occur.

i) A region in the rock mass must be on the brink of unstable equilibrium due to:

a) the presence of an appropriately loaded pre-existing geological weakness, b) changing stress driving a volume of rock towards sudden failure (can be an increase or decrease depending on type of rock burst), ~- ~' c) pillar support systems approach,ing a state in which ' the' unstable collapse is imminent.

i~) Som induced stress changes, regardless of magnitude, must be suffici ntly large to trigger the in~t~bility. iii) sudden stress change of sizablel amplitude must take place at the locus tability to initiate the propagation of seismic iv) Substantial energy must be stored in the loaqing

, 18

Page 27: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

c

c

system, as discussed above. The orïgin of this stored' strain energy is work done by:

a) gravitational forces, t b) tectonic forces, c) stresses induced by mirring.

The three categories, listed in Section (i) of Salomon's ~ criteria, are commonly referred to as fault-siip, strain and

p~llar bursts respect~~ely. Fault-slip t~pe bursts are identical t~ earthquakes and, caf}" pe remote from mine workings, whereas, the

other two occur withln the mine workings. Strain bursts occur near working faces antl are attributed ~o the lowering of the rbck strength ·due to removal of confinement. Pillar bursts are the

result of increas~g stresses beyond the strength of an-isolated

rock structure. The increase in stress 1-s due to stress transfer

from adjacent areas or reduction in pillar size.

A significant stress\change and large quantity of energy is necessary to initiate~ismic waves, originally the energy in

~

rockbursts was attributed only to the stored strain energy. It is noW apparent that changes in the potential energy contribute

significantly to both strain and pillar type bursts. The

different burst types have different seismic effieiencies, this

~~~e percentage of total energy released, released as seismic energy. Much energy is used in the creation of fractures, slip

movement and the generation of heat: Typically, strain bursts

have a 30 to 60 percent seismic efficiency, pillar bursts a 70 to

90 percen~ efficiency, and fault slip bursts alto 10 percent

seismic efficiency. McGarr (1984), has observed that seismic

efficiency decreases with depth.

There are a number of m1n1ng parameters that directly influence

the occurrence of rockbursts. Salomon (1983) has statistically

analysed these parameters, confirming the results for South

African gold mines.

il Excavation size; rockburst incidence increases with size of opening. ii) Abutment size; rockburst incidence increases with decreasing abutment size up to a critical width at which point the incidence

19

c

Page 28: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

1 1

decreases. iii) Depth below -surface; r'ockburst incidence increases with

1 depth. 7-

iv) Dykes; rockburst incidence increases lin the vicinity -of dykes and faults. Mining through dykes and faults at acute angles also increases incidence.

3.2 MECBANICS OF DESTRESSING

The prevention of rockbu~ts by destressing wa~ first introduced by the South Africans i~ 1952, Roux et al. (1957) and Hill et al. (1957), for controlling rockbursts in the deep gold mines. Initî81 results, as discussed in their papers, werê very promising, however, ~s mining continued to greater depths, bursting

persisted. In rece~t years, with more sophisticated design and evaluation tools, destressing has proven to be a very effective r

method for rockburst ~revention. This has generatep much renewed interest in the method.

Figure 3-2 shows the initial theoretical basis behind destressing.

The concept came about from the observation of the natural fracture zone surrounding underground excavations~ Rockbtlrsts

" seldorn occurred in this fractured zone and it appeared to offer a

cushioning effect to any bursts oc~urring beyond it. It was

postulated that increasing the depth of this fractured zone rnight

reduce the occurrence of rockbursts and reduce their violence.

The fracture zone is increased by drilling hales ahead of the face, or into a pillar, and blasting them with explosives. The

hale spacing and explosives loading must be such that the ground

is fractured, but not broken to the extent that mining ia no

longer possible. If blast fracturing is conducted before mining

commences, the practice is termed preconditioning. If the blaat

fracturing is conducted once rniping has cornrnenced,- and the ~a ia

under high stresses, the term destressing is used. This thesis deals primarily with destressing. Both methods alter the rock

~

rnass rnechanical properties in similar ways, although,

preconditioning the rock prior ta it being critically stressed

20

Page 29: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

............... --_ .. _.~----:::---------------:-----------------

Flour. 3-2: The InitiaI Concept Of De.tre •• lng

/

/ /

/

( DIstance from face

.. unfractured rock

After Roux et al. 1--857

c

21

Page 30: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

:)

will result in somewhat different behavior. The d~cision to precondition is usually based on computer modeling or past

experience. The decision to destress is general~y made after

visual confirmation of high stress conditions and proneness to

bursting.

The mech~nics of destressing are not fully understood as yet.

There are a number of observed and postulated phenomena

contributing to the successful application of destressing. ,

i)Reduction in stiffness due to fracturing: \

a) causes redistribution of high stresses; to be effective

the,stresses must be reduced below the strength of the

structure, '

b) reduces stiffness of mine structure below that of mine

loading syst'~.

c) causes convergence.

ii) Energy dissipation by fractured rock:

a) energy is dissipated in closing new fractures, this

reduces energy accumulatton,

b) energy released beyond the fractured zone will be

absorbed by it.

iii) Transition from brittle elastic to pseudo-plastic:

a) fail~re of pseudo-plastic material is non violent.

iv) Reduction of peak and residual strength due to fracturing:

a) causes convergence.

c) causes failure and redistribution of high stresses.

v) Triggering a rockburst:

a) the destress blast may induce the release of energy by

initiating a rockburst.

To be effective, stresses must be transferred to solid rock where

they can be contained, stress transfer that destabilizes an

adjoining area has no benefit. Destressing to date, has been

utilized with success to prevent strain bursts and pillar bursts.

To this author's knowledge it has not been utilized on fault slip

type bursts.

22

Page 31: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

(

(

3.2.1 BEBAVIOR OF FRACTORED ROCK

Cracks and pores have long been recognized to influence modulus

and poisson's ratio, Walsh (1965a, 1965b, 1965c). Increases in

modulus and Poisson's ratio with increasing stress, non linear

stress strain curves and hysteresis have aIl been explain~d by

the presence of pores and cracks.

Uslng the reciprocal theorem of Love (1927), Walsh derived

formulas for the effective modulus, poisson's Ratio and

compressibility of fractured rock. The formulas required

knowledge of average crack length and concentration, values that

are generally not available. The work concluded that modulus and

poisson's ratio are related inversely to crack concentration.

Compressibility is proportional to crack length to the third

power. Under high pressure, when aIl cracks are closed, the

effective modulus is equal to that of uncracked rock. The

effective poisson's ratio may exceed the uncracked poisson's , ratio at high pressure, this is the result of cracks opening

paraI leI to' the direction of maximum stress. Rocks with low

effective modulus exhibit high poisson's Ratio.

Lama (1974) demonstrates in model studies that deformation

modulus and uniaxial strength reduce with increasing nurnber of

joints. The modulus reduction becomes smal-l after the number of

joints exceeds six. For horizontal joints, the maximum strength

reduction was found to be 30 to 40 percent. For vertical joints

the strength reduction was 60 to 70 Bercent of the intact rock

strength. Studies using cubes to simulate orthogonal jointing

resulted in the following relationships.

E = k + ( Lii )B

where k = deformation of model containing more than

150 joints, the limit nurnber beyond which

no further reduction in modulus is observed

fi = constant

23

Page 32: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

1

,. J"

- L = length of model

l = length of element.

~odulus value and uniaxial compressive strength were observed to ~

vary with the orientation of the joints to the loading direction

and joint continuity. Both modulus and strength values decrease

as continuity increased and angle between jointing and loading

direction approached 30 degrees.

Failure of the composite models was progressive. As the number of

individual elements failed, deformation increased. Post failure

curves were flatter for models containing a large number of

.elements and failure was less violent.

3.3 NOMERICAL MODELIN~FOR STRESS ANALYSIS

Numerical modeling to analyze ground stresses and displacernents , is a well recognized and accepted technique. Most modeling 15

now performed utilizing high speed computers. The aécuracy of

any modeling depends upon the sophistication of the computer code

and accuracy of the input parameters. With simple/codes and j

reasonably accurate input parameters (rock properties, geology

and in situ conditions) it is possible to obtain'results within

the correct order of magnitude. This type of model is easy to

use and quick. A more accurate prediction, as is required for

destressing, requires a more sophisticated code and very accurate

knQwledge of the input parameters. Model calibration via back

analysis is very important. Setting up and running these models

ta~es a greater length of time. This section briefly reviews

numerical modeling and its application to destress blasting.

withthe advent of

extremely popular.

of their high cost

computers, numerical methods have become

Physical models are seldom used now because

and time requirements. Likewise, photoelastic

studies are impractical. Multiple analysis of different mining

or destressing scenarios is now possible, in a very short time

24

Page 33: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

\(

(

period, to d~termine the most appropriate course of action.

There are three types of numerical computer methods commonly

useg: differential, integral, and distinct element. A number of

advantages and disadvantages exist for each method.

With the difJerential method the entir~ problem domain is

discretized i~to elements. The outer boundary of the problem

domain is deff~ed arbitrarily allowing discretization errors to

occur throughout the medium. The differ~ntial method can be used

to model non-linear and anisotropie behavior. Rock masses

comprised of units with different mechanical properties can also

be modeled. Examples of differential methods are finite element

and displacement discontinuity. These types of programs are the

ones most commonly,! used 'for destress analysis.

With the ~ntegral-method only the surface of the excavation is ,

discretized; this greatly reduces the magnitude of the probl~m

and increases efficiency. The far field boundary copàitions are

modeled correctly and discretization errors are restricted to the

problem boundary. This ensures fully continuous variation of

stress and displacement throughout the medium. The integral

method is not suitable for analyses of non-linear or

heterogeneous behavior, as these negate the simplicity of the

integral ~ethods solution procedure. The boundary element method

is an example of the integral method. ,~ r

The third computational method is the distinct element method. In

areas of high discontinuity densities such as mine openings it

has been found that rock behaves as an assemblage of rigid blocks

that int~ract along deformable contacts. The model -area is

divided into a set a discrete elements corresponding to the

block pattern. The distinct element method assumes that block

geometry is'unchanged by the acting stresses, any deformation

OCcurs along the joïnt contacts which have definable mechanical

properties. Microscopie discontinuities exist throughout the

rockmass, however, they are disregarded because of their size in

o 2S

Page 34: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

s

"

.. relation to the,area being mo~eled. Destressing introduces sorne

fracturing and enhances any existing near field discontinuities . . Although it may prove applicable, to the authors knowledge,

, simulation of destress blasting with the distinct element method

t has not been carried out.

Numerical models are useful for a nurnber of tasks related to

destress blasting. They are able to determine which areas are

under high stress and in need of destressing; they are able to

determine what reduction in modulus or strength is required, and

the aerial extent that should be affected; they use fuI for

evaluating the potential for creating new areas of instability as

a result of destressing; they are able ta predict _the most

desirable location, ie. hanging wall, foot wall or within the ore

plane. A computer model for analyses of destress blasting must , meet a number of requirements, the most fundamental being that it . accurately predict the rock mass response to mining and destress

blasting. The practice used in most mîning situations is to

first c~librate the model to known rock mass responses via back

analysis. Once the model is calibrated it can be utilized with

confidence to perform the above mentioned tasks.

An i erative approach is best suited to determine what minimum

reduc~'on in modulus of deformation or reduction in rock strength

is requi ed. Blast design to achieve the desired modulus i8

discu8sed in Chapter 8 and Chapter 9. Numerical modeling i8 also

able to predict the optimum destress bl,ast configuration. This . includes the required volume of ground to be blast fractured nnd

-location ie. hangingwall, footwall or within the ore plane.

\J Invariably there is stress transfer from the destressed zone ~nto

thesurrounding mine structure. Numerical models can be used to

;nalyze this transfer. If a new area of instability occurs,

appropriate action such as redesigning the dfstress blast can

take place.

26

Page 35: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

(

(

Destress blasting reduces both the.modulus of deformation and

peak and residual strength. An~lysis at CRLM, Scoble et al.

(1987), indicated that with a finite element program, destressing ,... could be simulated as a reduction in modulus of deformation.

Hansen et al. (1987), reports that reduction in modulus does not

result in good simulation of destress blasting with the computer

program NFOLD, a displaèement discontinuity model. It was found

that convergence prediction with this model wa~ strongly

dependent upon peak aod residual rock strength and only

marginally dependent upon ~lastic modulus.

3 • 4 'l'HI EXPLOSIVE MBCBANI SM AND ROCK fRAC'l'ORING

..

An explosion is the result of the chemical reaction of a thermodynamically unstable material. The reaction i5 divided

into two zones: the reaction head, followed by the reaction zone. 1:1 '

A complete discussion of the chemistry and thermodynamics of the . reaction can be found in Cook (1970). The velocity at which the

reaction occurs, velocity of detonation (VOD) , is the most

important parameter governing the violence of the reaction. Two

.types of reactions are possible: explosive detonation or

explosive deflagration. Explosive detonation is characterized by

h~gh YOD, high explosive pressure, high detonation press~re, and

rapid release of heat. The detonation front travels at a

velocity greater than the seismic velocity of the explosive

material. The explosive reaction occurs in, and in turn supports

a shock front. Explosive deflagration occurs when the YOD is

- lower, resulting in lower pressures. Only detonation is of

interest in the process of fracturing rock.

As the explosive reaction proceeds a quantity of energy is

transferred to the rock. This is knQwn as the dynamic pressure

pulse and is derived from the detonation pressure. In close

proximity to the blast (rIa < 2) this pulse can be approximated

as single spike or step pulse, Figure 3-3. The pulse radiate out

in aIl directions but is,generally only considered in the

27

Page 36: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

" • •

-.

o

Flgur. 3-3: Normallzed Dynamle Str ••••• : Step Pul •• tnd Wav. Train

.4

o

- ·8

: .. ~"""''' ;

... i .-.- \

.... \J ,.../ ...,

:

radial stress

1S

r:: dl.tanc. from bl.at h~'. • :: bl •• l ho'. r.dlua

28

time: ... ec

after Mohanty (1982)

-...,.

Page 37: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

c

c

c

j

f'

tangential and radial directions. With ~me ~d dista~ce the wave separates into frequency components and d~fferent wave bype~. At a large distance,- ria > 10, the wave can.be approximated as a damped sinuso~dal wave train, see Figure 3-3.

Two processes are beli€ved to govern the transfer of the exp~osive pressure to the rock: stress wave transmission and borehole diration. Wave transmission from the detonating

explosive is governed by impedance matching of the explosive and

rock. The impedance relationship as weIl as an estimate of the -

explosion detonation pressure are given by:

where ~t = transmitted st±~ss Pi =--pressure in detonation front

d2C2 = density and -seismic veloci ty of rock -,­

--d1C1 = density and VOD. of explosive

Using an explosive which provides the bes~ impedance match will

~heoretically result in the greatest stress transmission, although achieving even a close match is generally not possible~ due to the vastly different density and seismic~velocity-values.

At CRLM destress blasting is conducted with AN/FO in 45 mm holes,

rock density is 2.5 9 per cc. Assuming an explosive density of 0.9 g per cc, a seismic velocity of 6310 m per sec in rock, and a

VOD of 31QO m per sec, the resulting detonation pressure is 2.2

GPa. The transmitted stress would be 700 MPa.

The second and probably more important method.of stress transfer

is oorehole dilation. As the detonation front travels down the

borehole it causes hole expansion and contraction. Thie

29

Page 38: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

'oscillat~on generates stress waves in the rock. Favreau (1969) _ has shown that the generation of strain waves in the rock is a function of ~ensi~y, Poisson's ratio, Young's modulus, blast hole radius and explosive properties.

At the periphery of the blasthole, energy transfer appears ~o be in the form of a shock wave. The pressures a'r~ not great-enoug~ ~ to create shock waves that travel at·velocities greater than the seismic v~locity, however, the pulses are of very,high energy content. The rock is incapable of transmitting this energy so crushing occurs,-Which causes rapid attenuation of the energy.

Once the wave energy has attenuated sUfficiently, an elastic or 1

seismic wave carries on out into the rockmass, Initially, the t."

strain induced by the elastic wave is still high enough to create fractures. Fracture growth velocity is ~proximately one third that of the seisrnic velocity (speed of the ela.stic wave) , as such fractures can only extend while they are within the stress pulse. This results in discontinuous fractures. The fracture velocity at 'CRLM is estimated to be between 1500 ahd 2100.m per se~ond.

Measurements of the wave energy away from the blasted hole indicate that only 10 "to 20 percent of the total explosive,energy

ois radiated as a seismic wave, the remaining'energy is used in crushing, fracturing, heating and noise. Duvall and Stephenson (1965) have suggested that sorne of this sei smic energy is· attributed to a change in potential energy due to enlarging the borehole. Their calculations indicate the amount to De-small unles~ \mder a very high stress regirne.

,The expldsion aiso ~reates a-Very high temperature and pressure gas. The gas exerts a quasi-static pressure on the surrounding rock. The pressure r~mains until the gas can escape through

, "..--

cracks or out the borehole collar. The gas' pr~ssure is much lower than the detonation pressure, this researchers'to question its significance Although it seems unlikely-that the gas

30

has lead Many -in the blasting process.

pressure is great--enough

Page 39: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

c

c

c

to create new fractures, it is probable that e~isting fractUres may be extended or connected together. Obviously in situ stresses must be exceeded along with t~sile strength of the rock before additional damage can~ccur. Kutter and Fairhurst (1970) analyzed the explosive and gas pressure as two separate components. Their work indicated that gas pressure is important only if the cavity is first pre-conditioned by the exp~osive stress wave.

3.4.1~RACTORE CREATION

Fracturation occurs when the stress exceeds the strength,of the rock. \n the case of blasting~ when the amplitude of the ela-stic ,stress wave exceeds that which the rock can transmit. A single crack advancing at a constant rate is known as stable crack growth. If t~e- amount of strain induced by the stress wave

oQ

exceeds a certain limit, unstable crack growth occurs. Unstable crack growth is characterized by bran ching and multiple crack extensions ."

The stress wave can be resolved into radial and tangential . directions. Both directions have compressive and tensile components. On a theoretical basis it is found that the tensile com~nent o~ the tangential stress is very high, resulting in radia\ fractare$~ With time and distance the radial stress ,

develops a strongir tensile component resulting in tangential of hoop fractures. The compressive component is commonly assumed to have little influence on fracturation due to the high compressive 'strength of rock >'_

Theoretically the radial and tangential stresses can be calculated at any ,point in the rock mass. ' The simplest calculation is that of the classical stress analysis °of a thick wall~d elastic material subject to internaf.and external loading. The equation ~s given below, its theoretical basis' can be found

1

31

Page 40: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

J' i , .' ,

~in most texts·on stress analysis such as Tirnoshenko and Goodier (1970) .

U rr = 2 (P~d2 - Pir2)

-p------------- + ------~-------------1

(d2 - r 2 ) a.? (d2 _1"r2 )

~ (p d 2 - p.r2 ) ee - -0 ~

where urr = radial stress uee = tangential stress

r = intern?l radius of cavity (blasthole radius) d = radial distance to outer boundary of cylinder

Pi = internaI pre-ssure generate by explosive • Po = extern~l pressure (in situ stress)

R = radial distance to point of interest

SolutJon of the above equations for a destress blast at CRLM

suggest that the maximum radial distance for compressive failure to occur is 0 .. 09 m (3 hC!>le diameters). Tensile failu,re should not· extend beyond 0.14 m (6 ho}e diarneters). The analysis -assumed a static pressure was applied and failure is through intact rock, not along the weaker~re-exi~ting discontlnulties. Input parameters were r = 22.5 mm, Pi = 1.6 GPa, tensile strength of rock = 15.6 MPa, compressive strength = 125 MPa.

, An,approximation of,fracturation can also bè determlned by stress and strain determined through peak particle velocity relationships. If the stress wav~ is assumed to be sinùsoldal and plane, the following equatlons can be derived for stress and strain. There derivation can be found in Dowding (1985).

~(f = d cp up up-:cp d Cs Us

32

Page 41: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

(

/

(~

(

where \.

-

, q = compressive or tensile str~ss l ,-.. E = strain T = shear stress v = shear strain

cp = primary (compression) wave seismic ~elocity up = primary wave particle velocity Cs = secondary (shear) w~ve seismic velocity Us ='secondary wav~ particlê velocity

Negative strains are considered compressive. A plane compressive wave produces an equal magnitude s~ear strain, however, for equal particle veloc~ty, shear stress will be greater than longitudinal stress due to the lower seismic speed of t~ shea; wave. This method requires accurate prediction or measurement of peak

particle velocity close to the borehole. . . Prediction of fracturation is made more difficult when

consideration of in situ stresses is necessary~ as is the case .. with destress blast±ng. Most theoretical models do not take

1

conf·inement or in situ stresses into account, as their effect on 'Il' • •

the fracture process is not ëasily quantified. If the rock is considered to be under no confining stress, blast induced failure

will most likely be tensile. The tensile component of a blast

stress wave is less than the compressive component, however, the tensile strength of the rock is typically only 10 percent of the

compressive strength. If the rock has an in situ stress imposed on it, it may not be possible to fracture it in tension.

Assuming the principle of stress supérposition, the ténsile

- component pf the blast wave may not be sufficient to overcome the compressive force and tensile strength of the rock. When the

compressive stress of the blast is added to the compressive in situ stress, it may be sufficient to cause compressive failure of the rock. It is noted that compressive strength increases with increasing in situ stress and confinement. The extent of blast

damage""is depe~t upon the in situ stress conditions; it is

33

Page 42: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

o

conceivable that under certain in situ stress conditions, blast

damage will not occur where it otherwise would be expected.

3.4.2 PREVIOUS STUDIES' OF FRACTURE EXTENSION

D~e to the complex nature of the detonation process and the

cesponse of rock to blasting it is extremely difficult to predict

fracture extension. Experimental and analytical'studies of crack

growth have been undertaken in the past with variable results.

To this· author's ~Owledge"no theoretical method exists that

satisfactorily p~dicts fracturation. Researchers routinely

, conduct small scale tests on laboratory samples, however, scafing results has proved to be very difficult. A number" of in situ:

investigations of blast induced fracturation in confined ground

have been undertaken. The reasons for the investigations and the

type of rock used vary considerably making it extr ely ifficult \

to compare studies. Fracturation is both site speciffic d

dependent upon the explosive and blasting arrangêmen~. The

method of fracture detection may also affect results_

The rock surrounding a blasthole can be divided into three zones,

Figure 3-4. A highly fractured or crushed zone surrounds the '.

hole. This typically extends to one hole diameter. The

shattered rock may be blown out of the hole by the escaping \

detonation gases. The transitional or non linear zone i5'

typified by a distinct drop in the peak stress, however,

extensive radial fractures still persist, Atchison and

Duvall (1963). The elastic or outer zone contains an ever

decreasing number of fractures. It theoretically extends

indefinitely, however, interest is placed only in the area

containing blast induced fractures. The extept of blast induce~

fractures in the linear zone is of primary importance in the .~

design of destress blasts.

Kutter and Fairhurst (1970). analytically determined that crack

extension should be six Qole diameters for a spherical charge and

34

Page 43: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

, Figure 3-4: Zon •• Surroundlng Bla.t Hoi.

• /

\

\

c 1

\

"-

after Du Pont 1977

35

Page 44: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

~'" '" . .,'

nine hole diameters for a cylindrical charge. Their-paper also

concluded that pre-existing fractures grow preferentially to new

ones and create a crack free zone in their immediate vicinity.

Fractures grow preferentially in the direction of maximu~

principal stress, however, in situ stress may suppress iracture

propagation in one direction in favor of crack initiation in

another. The extent of fracturation is dependent upon the , ,

strength of the rock, energy output of the explosive and energy

absorption of the rockmass. Increasing the charge beyond a

certain limit will result in a greater crushed zone but no

increase in the extent of fracturation. This conclusion is based , \

on th~\assumption that there is a limit to the amount of energy

that rock can transfer. If the limit is exceeded, crushing will

occur. Once enough energy has been attenuated, an elastic wave

will travel on outwards.

Olsen et al. (1973) studied fracture extension around confined

blastholes in a competent granite. The studies used a high

strength explosive. Microfractures were observed, in thin

seétions, to extend to ten borehole diameters. Siskind and

Fumant! (1974) observed fracture damage to seven borehole

diameters. Their work was carried out in granite using AN/FO in

165 mm holes. Siskind et al. (1973) studied fracturation around

blastholes in shale pillars of an underground mine. Using AN/FO,

fractures were observed ta extend nine hole diameters, using

dynamite, fractures extended ta twenty four hole diameters.

Steckly et al. (1975) studied confined blasting for the purpose

of in situ leaching. They observed fractures to ten hole

diameters about 230 mm diameter blast holes. Fractures

preferentially occurred along pre-existing discontinuities.

3.4.3 BLAST HOLE INTERACTION

Kutter and Fairhurst (1968) theoretically studied stress wave

reinforcement and interaction. The four possibilities that they

studied were as follows:

36

Page 45: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

(

(

1) The delay betweèn blasts is so long that the pressure -from the first blast i8 negligible by the time the second charge is initiated. i

2) The delay between blasts is such that the quasi static pressure' from the first blast is still significant when the v?~ond charge is initiated.

3) The charge in the secopd hole initiates as the dynamic wave from the first hole passes over it.

4) Simultaneous· initiation.

The four cases are illustrated in Figure 3-5, where two blastholes

are considered.

When the delay between detonation of two charges is,long, no

interaction between stress fields occurs. If the blast holes are ,

sufficiently separated, the situation can be considered as the

explosion of two independent charges. Typical destress blasts

at CRLM use blastholes spaced at 27 to 33 hole diameters. If a

1.6 GPa stress wave is assumed to be generat~d, and attenuation

of the dynamic str~ss is proportional to r-1 . 5 , stress levels ,

on adjacent holes will not be great enough to cause any

modification of the blast hole periphery .

. If the charge in hole 'b' detonates when the quasi static

pressure exerted by hole 'a' is still significant sorne stress

interaction will occur. The pressure from hole 'a' will cause

stress concentrations about 'b'. High tensile stresses will form

at points i and ii, and high compressive stress at points iii and

iv~ Figure 3-5. ~uperposition of the stresses produced as hole

'b' detonates will cause preferential fracturation in the

direction of the plane of the blastholes. Fracturation of this

nature is desired in piliar dest~ess blasts. The fractures in

the plane of the blast holes may also be further extended by the

gas pressure from h9le 'b'.

When the dynamic explosive pressure from hole 'a' passes hole 'b'

as hole 'b' detonates, the results will be similar to case 2.

High tensile stresses are created at points i and ii.

37

Page 46: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

\

Figure 3-5: Four Ca ••• , of Initiation Delay aetw.en Charg •• '.' end 'b'

hol. 'a' hol. 'b'

CASE 1

r 1

... ..1 "- .. r

-"lI-

a 1

1 OU."-lltllle Drn,m'e

* r

CIISf. :5

a

~O l QUOI'·"allc:

-,

r .. .; A

CIISE 4

,Outll·llolle

r -

...

after Kutt.r and hlrhur.t 1887

o

38

Page 47: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

(

,

If the two holes detonate simultaneously, maximum stresses, due to superposition, will occur at mid point between the holes.

Unless the 'ho les are very close, it ~s not likely that the stress

levels will be great enough to create new fractures between the

holes, although, existing fractures may be extended.

~he previous discussion has assumed negligible in situ stress.

If the in situ stress is hydrostatic there is no preferential

stress concentration around hole boundaries. Preferred fracture

direction is unaffected although the extent of fracturation will

change.

When the principal in situ st~ess is perpenditular to the desired

fracture plane, problems are encountered. Tensile stresses are

created which favor the formation of fractures in a direction

parallel to the principal stress. It should be noted that the

actual hole periphery has no stresses acting on it as it is a

free surface; stress concentrations occur a short distance from

this boundary. The problem can be overcome by imposing a stress

field 90 degrees to the in situ stress. This stress field is

conveniently applied by the detonation pressures from an adjacent

hole. The best results would occur if detonation of hole 'b'

occurs as the dynamic pressure wave of hole 'a' is passing over

it. Analysis of the usual destressing practices at CRLM suggest

that the in situ stresses would not be overcome even in the most

Ideal situation. Assuming in situ stresses perpendicular to the'

desired fracture plan are 50 MPa, blasthole spacing is 33 hole

diameters and the stress wave attenuation is proportional to

r-1 . 5, the minimum transmitted detonation pressure required to

overcome the stresses around the adjacent borehole is 543 GPa.

Typical explosive pressures are weIl below this.

In the case of both in situ and no in situ stress it is most

desirable to have the explosives detonate as the dynamic pressure

from the adjoining hole passes over it. As discussed above, in

situ stresses may not be overcome, however, for destressing

purposes it is desirable to create as many fractures as possi%le ~

, 39

Page 48: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

o

o

even if direction can not be controlled. Knowing the seismic

velocity of the rock a delay sequence can be determined to

optimize fracturation. Delay scatter, however, will result in r

inadequate results. Pressure sensitive caps would provide the

most desirable initiation, however, the inherent safety risks

make them unsuitable. Sinee cap timing scatter ls quite

signifieant, particularly in higher delays, the author believes

that blasting aIl holes the same delay will produce satisfactory

results with adequate safety.

A longer duration quasi-static gas pressure will more readily

results in constructive stress interaction. In order to enhance

the effects of the gas pressure on fracturation, it is

recommended that stemming be used to prolong the duration of the

pressure.

An important factor which has not been considered in this

analysis is the influence of pre-existing-discontinuities. The

stress level required to activate fractures along pre-existing

defects is mueh less than that required to initiate new ones. At

CRLM major discontinuities generally run parallel to the

direction of desired fracture propagation. Studies at the mine

have shown that with the exception of the crushed zone around a

blasthole, blast induced fracturation forms along pre-existing

discontinuities, Scoble et al. (1987).

Stress interaction occurs in three dimensions, not just in two as

discussed above. Stress waves originate along the entire length

of the blast hole and radiate out jn aIl directions.Fracture

development is alsO a th~ee dimensional phenomena, not two

dimensional as is commonly assumed for modeling purposes.

Mohanty (1~82) has shown that based on dynamic tensile failure

criterion, 3 orthogonal sets of cracks should occur. Two

orthogonal radial sets, one horizontal, one vertical, arise ~rom

the tangential stresses. The third set is circumferential and iB

the result of the tensile portion of the radial stress component . .. ,

'The circumferential cracks do not occur until the tensile

40

Page 49: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

j

Plgur. 3-8: Thr •• Dlm.n.Jona' Fracture Development. ,

BOREHOLE

( .fter Mohanty 1982

i

, ;

"

c

Page 50: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

\

o

cornponent of the radial_stress is sufficiently large. Figure 3-5 illustrates this predicted fracture scherne. As discussed above, in situ stress and pre""existing discontinuities will signif~antly alter this idealized pattern .

. 3.5 NOMERlCAL MODELING FOR l'RACTORlI: ANALYSIS -,

MOQeling of blast induced fracture extension is still in the

development stages. The response ot rock to blasting is very - difficult to predict due to the êomplex_interaction between rock

and explosives, as well as the complex behavior of the rock and _ e~plosive individually. As with aIl numerical rnodeling, the

accuracy of the results ls dependent upon the sophistication of the model and.accuracy of the input parameters (explosive properties, rock properties, blast hole configuration, etc.).

Most avai~able codes for nurnerical modeling of fracture extension

use established elastic theory and static loading conditions.

These codes make a number of assurnptions such as linear elastic

behavior and a homogeneous, isotropie matérial. Usually, only

tensile failure is considered. Because of greater explosive use,

and less complicated environments, most blasting simulators are

designed for use in surface operations. As such, the influence

of in situ stress is not considered. This severely lirnit~ the

confidence placed on results obtained from these models for

ponfined blasts. It is hoped that more sophisticated codes,

suitable for modeling confined blasts in high stress regimes will

bec orne available in the near future.

(;,)

42

Page 51: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

c

4 REVIEW OF DESTRBSS BLASTING PRACTICES

The prevention of rockbursts by destress blasting was conceived in South Africa in the 1950'5. The concept came from the observation of the natural fracture zone surrounding underground

ex~avations. Rockbursts seldom occurred in this fractured zone which also appeared to form a protective cushion against bursts

occurring beyond it. It was postulated that increasing the depth

of th!.s fractured zone Iflight reduce rockburst frequency and

intensitYi the high stress region wouid be shifted farther away . from the stope opening and the extent of the protective cushion

zone would be increased.

~

FOllowing the South African initiative, man y m1n1ng camps with

rockburst problems initiated destress blast programs. It was

quickly realized that the technique could aiso be used in

development headings such as drifts, raises and shafts, and aiso

for destressing large areas of groupd such as sill pillars and

entire stopes. The techniques used have varied greatly, depending

on stope geometry and engineering approach. Although much

destress blasting has been perforrned, documentation on the

practice is sparse. An unpublished study by the Ontario Ministry

of Labour, Frantzos (1980), reported that 18 Ontario mines had

used or were using destress blasting for ground control. Most of

the available literature reports on successful destress blasting,

however, not aIl destress blasts have achieved the desired

results, Quesnel (1987), Oliver et al. (1987).

'During the course of study for this thesis, site visits were made

by the author to Kerr Addison and Macassa mines where destress

blasting has been used extensively. These mines have geological

environments similar to Campbell Red Lake Mine (CRLM). This

chapter presents detailed case studies of destress blasting at

CRLM, Macassa and Kerr Addison mi~s. Indicators llsed in the past

to determine when to destress as weIl as sorne of the reported

benefits of destressing are discussed. A review of case studies

found in the literature is also included.

43 .

Page 52: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

o

4.1 INDlCATORS l'OR DBTERMINING WHBN AND WHBRB TO DB1JTUSS

Many--different techniques have been~used at mines to determine when ~estressing is ~ecessary. The decision-to des~ress is made once conditions indicate the onset or expected onset of higb stresses.

1 -./

Present day numerical modeling methods can accurately predict 'u

stress conditions, which in turn can be used to determi~e when and where to destress. In the past, stress prediction was not readily determined. A number of indicators and criteria used previously to determine when and where to destress are listed below along with referénces to the available literature. P~st

experience was often used as a guide; engineers would decide to' destress knowing that similar conditions had resulted in rockbursts on c:ither occasions. The occurrence of seisffiic' activity and small rockbursts also indicated the need to destress an area. Rock appearance has been used to identify ,over-stressect rock, however, the method is not weIl defined or easily quantified. Deform~tion of openings such as drill holes incticates high stressés; an estimate of magnitude and direction can ,. also he determined. In most cases more than one indicator is reviewed prior to making the decision to~destress.

Preyious experience; Hill et al. (lES7), Jianyun and Jiayou . (1987), Karwoski et al. (1979), Cook and Bruce (1987),

Makuch et al. (1987), Blake (1979).'

~ occurrence Qf seismic actiyity, ~ rockbursting:

Quesnel and Hong (1986) 1 Morrison '(1964), Moruzi aI)d Pasieka (1964), Oliver et al. (1987), Dickhout (1963),le Bel et~al. (1987), Slade (1968).

~ appearancej Issaccson (1962) reports a pillar hav~n9 a monolithic appearance, Roux et al. (1957) reports overstressed xock having a glassy appearance.

44

Page 53: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

t

L ~ \

(

, , , ,

l

\

c

r

Tunnel deformation ~ drill ~ closurej Lama (1972).

~ mgàeJlng: Makuch et al. (1987), Karwoski et al.

(1979), Blake (1972):

..

, 4'.2 BZNZI'ITS AND RESULTS OF DIlSTRBSS BLASTING i,

• Successrul destress blasting causes a number of eff.ects on the rockmass. The following list of ,reported beneÏits is derived'

l' from the references sited in the above"'section.

- 'reduction in the frequency and magnitude of seismic activity 'i

, and rockbursts in the destressed zone. J ~h~ occurrence of seismic act:ivity and rockbursts in adjacent lt

, 1 1

. blocks of solid ground. -,closure.

- reduced deformation. reduction in stress.

- overall improvements in ground conditions. -_reduced scaling.

l ' - :reduced overbreak. ~

,1 >1

,- ,\reduced rockbolt tension. -- ~ncrea'sed fract~ring-. '

J 1

:

In sorne cases c'ontradicting results have beenQ reported. Lama (1972), reports reduced deformation in a tunnel after fi ring radial destress holes; most authors report an increase in closure after destressirig. This-discrepancy i~~elY due to differences in application and geol6gidalr~nvironment, however, an accurate .-. interpretation ls not possible because of limited information. Both reduced overbreak and scaling as weIl as increased fracturing have been reported in the s~me paper,' Dickhout (1963).

This author provides no explanation for 'this apparen~ , '

contradiction. Fracturing has been reported to increase by as _. muc~ aS 100 percent, Dickhout (1963), Moruzi and Pasieka (1964)

report a more modest 15 percent increase in fractures. Destress

45

Page 54: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

· holes are generally observed to have enlarged after blasting. Collars are often bell shaped. Harling '(1'962), reports a 75

'" percent increase in diameter along the length of the hole. t

4.3 CASE HISTORIES 4.3.1 SOUTH AFRICAN GOLO MINES

,

The first destress trials were conducted at 'the East Rand . Proprietary Mines in South Africa. The mine is typical of Soùth African .gold mines in that the gently dipping reef deposit was being mined by a longwall method.

œhe procedure ·used was to drill 51 mm diameter holes on 1.5 m centers, 3 m deep. The bottom half of the 'hole was charged with 60 percent strength Ammon Gelignite or Dynagel. The remainder ~f the hole was sternmed with sand. Holes were blasted routinely to

ensure a fractured zone extended at least 1 to 1.5 m ahead of the 'stope face. Holes were collared 0.3 m above the footwall and angled down 8 degrees# resulting in the toe penetrating 0.6 m into the footwall: In dyke material the hole spacing was reduced to 1 m and charging increased to 70 percent of the hole length.

-- . Table 4-1 summarizes the initial resu1ts. As discussed by Roux et

al. (1956) and Hill et al. (1957), the initial results were very promising. As mining continued to greater depths, however, bursting pérsisted and the destress program was abandoned.

Blake (1982') concludect that the early South African destressing did not provide a large enough fracture zone for the long stope faces and high stress levels at which mining was being conducted.

\.

Cook et al. (1964) report on the_ results of seismic monitoring of o

conventional and destressed production blasts in South Africa .. It was believed that in order for destressing to be successful

there must be a reduction in stored strain energy which would result in the creation of seismic energy. Monitored blasts' indicated no difference in the seismic energy"released by the two blast types; all energy was attributed to the explosives alone.

46

Page 55: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

(

(

\

_ .. --,

T-able 4-1: Summary of Results of Destress Trials

Befor.e Destress~ng

No. of stopes_

Fathorns stoped 16,600 (j

Incidence no. of bursts 44 bursts per 1000

fathorns ,stoped 2.64

Sever!ty no. of severe bursts 22 %. severe bursts to

total bursts --.50 incidence of severe

bursts 1.32

Time '-bursts during day

shift % during day shift severe bursts day'

shift % severe day shift

Casualties killed

. injured total

Il / 25

5 110

5 24 29

/

After Destressing

17

17,300

29

1. 68

6

20.6

0.35

o o

o 1 1

Percent Improvernent

34

36

73

73

81

100

100 9"6 97

after Hill et al. (1957) .

..

t

47

\ '. .

Page 56: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

J l

~

-4.3.2 COEUR~'ALENE NcrNIN~ DISTRICT

The Galena Mine, as weIl as many other mines in the Coeur d'Alene

mining district of Idaho, have successfully used pillar

destressing for a number of years, Blake (1982). Steeply

dipping, narrow, veins are being mined by overhand cul and fill

methods. Once ~he crown pillar is reduced below a 15 m thickness \ -

the ground becomes burst-prone. The procedure has been to

destress using 38 to 51 mm holes drilled from within the stope on

1.5 to 3 m centers, as shown in Figure 4-1. Blasting is with

high velocity explosives and milli-second delays. The blasts _

have resulted in substantial stope closure, reduced seismic

velocity and reduction in stress around the stopes. The degree

~f fracturing has not been such as to cause subsequent mining

problems.

Destressing a large block of ground, such as a pillar, has been

~--- ~xtended to entire stoping areas. Karwoski et al. (1979) report

on what they calI ground preconditioning at the Hecla mine in the

Coeur d'Alene district of Idaho. Large ,blocks of ground were

preconditioned or blast frac ured during level development, prior

to commencement of pro uction mining or the creation of highly

stressed, rockburst prone pillars. The object was to fracture

the ground sufficiently to prevent the creation of ~ighf.Y

stressed ground right from the start. Mining would begin and end

in fractured rock. Mining between leve1s, in areas outside the

preconditioned.zones still required conventional destressing. The

destress holes were fan drilled from crosscuts with maximum toe

sepa~ation of 2.3 m, Figure 4-2. Hole diameter was 92 to 102 mm,

the prima~y explosive was a high velocity water gel, charging as

indicated in Figure 4-2, aIl collars were stemmed with sand and

clay. Holes were toe and collar primed and traced with

detonating cord. Milli-second delays were used to reduce the risk

of air blast damage.

Preconditioning trials were conducted in both the vein and wall

rock. In both cases destressing was considered to have been

48

Page 57: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

C ------.-

C'

c

\ l'

1 . ,

'1 '--------... J'/OO t...1 f .... ,.. .... r

1 i T r T 1'1 T 1 -T

"" .. 1 1 l ,1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

0

.--1 • .. .. JO

! l g -. ....

!I S ltrnCIII A-A

Figure 4-1: Stope pmar Oestress Blast Pattern, Coeur O'Alene (

è

{ after" Blake 1972

Pounds of explosives

Tola/= 337

225 ~14

crosscut

o 10 20 1 l ,

.. ~. Seole ft Figur. 4-2: Pr.condltlonlng Bla.t Pattern Coeur D'Alene 1

after Karwoakl et al. 1979

49

Page 58: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

l

~ f r -

effec~ive in reducing the anticipated high stress and burst prone

oondition. Based on drilling. costs, mineability'and results of

computer simulations, the on-vein preconditioning was considered

preferable to off vein preconditioning. u~

The preconditioning was monitored and evaluated with stress

gauges, convergence stations, seismic velocity surveys and a

microseismic monitoring system. A 28 percent reduction in the

seismic velocity and a red\ction in the stress level were

recorded in the blasted arra; this indicated that the ground was

successfully fractured by the blast. Stress and convergence

measurements during the course of mining agreed well with those

of linear elastic finite element computer modeling. The

microseismic monitoring continued to register activity in the

vicinity of the preconditioned ytopes as they'were mined,

although frequency and intensity were less than usual. Only

minor activity'was recorded within the preconditioned or shielded

ground. Mining between the destressed zones resulted in

increas~d seismic activity and the reoccurrence of rockbursts.

This confirmed the need to precondition the entire stope block.

As a result of the success of the first preconditioning trial, a

second, larger, preconditioning blast was cortducted at Hecla

Mine, Blake (1980). The block destressed was 137 rn long and 27 m

on dip. The drilling pattern and explosive loading was siroil~ to

the first trial. Drilling was exclusively in the more easily ~

drilled vein rock. Holes were 82 ,mm diameter, loaded to a 6 m

collar with Tovex 5000 cartfidge.' The holes were traced with

detonating cord. In order to minimize stress transfer rate and

air blast, the holes were blasted in groups of 5 or 6 at a time.

Raising up through the preconditioned rock resulted in only minor

microseismic activity. A second phase of this destress project

was planned to destress pillars on the over lying level. As

drilling was being conducted a major rockburst occurred,

destressing the area in question.

50

Page 59: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

c

c

4 • 3 • 3 SODBORI APJ!.A MINES:

At the Falconbridge mine in Sudbur~, destressing has successfully t'

been used t~ alleviate rockburst prone conditions in steeply

dipping cut and fill stopes, Slade (1968). After a number of

rockbursts occurred in the stope hangingwall it was decided to use destress blasting. Initially 3 m long d8stress holes were

J

dri1led from within the stope out into the hangingwall and blasted with the advancing face.( As the pillar thickness was

reduced, 21 m long destress holes were drilled from the upper

level into the hangingwall ~s shown in Figure 4-3. The holes

were spaced at 6 m centers. Induced fracturing and loose were

observed i~the drift and stope. The stope closure rate

decreased after destressing and no problems were encountered when mining the pillar. 4

~oruzi and Pasieka (1964) report on a similar destress blast at

the Falconbridge Mine. The blast was monitored to\evaluate the

effectiveness of destressing. Blast holes were aga'in drilled

from the upper level into the hangingwall. Holes were 48 mm

diameter at 9 m centers. Drill core fractures, closure and

photoelastic shear strain were analyzed pefore and after the

blast. The closure rate was not affected by the destress blast. "

·There was a lS percent increase in the number of fractures

observed. The strain rate was obser~ed te increase slightly,

although only marginally above the accuracy of the measuring

technique.

f7 The Creighton mine in Sudbury has been destressing development

headings since the 1960's, Dickhout (1963). After the evaluation

of a number of blast designs the accepted practice became to

drill two 50 m,57 mm diameter, holes in the face as shown in

Figure 4-4. A 2 m overlap of subsequent destress holes was

always ensured. Blasting was performed with AN/FO. A 3 m collar

was left unloaded. Destressing caused a mark~à reduction in

overbreak as weIl as reducing the frequency of microseismic

activity. A 100 percent increase in the number of fractures

51

Page 60: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

T."tSA" OfiSTR(S$ t!.QU

Figure 4-3: Stope Pillar Oestress Blast Falconbrldge

" PREVIOUS

OEST~ESS HOlE " OESTRESS HOlES " 6' 1:

-~~'!~-----~-----------_:~---------2S'± •

after Siade 1968

DRIFT

Figure 4-4: Development Headlng Destresslng At INCO

LOADED

I...-~----I

0AIWt1C \MTS / PLAN VlEW fOR HEXT ROUI4D \

+8 f LONGITUDINAl VlEW

52

efter Dlckhout 1963

Figure 4-5 Oév'elopement Headlng Oeatresslng At INCO

aUer Oliver et al. 1887 ~

Page 61: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

(

c

c

visible in the drifts was reported. In one case a rockburst

occurred at the drift face when the overlap of destress holes was reduced to zero, Oliver et al. (1987). Destressing techniques

used at the mine have changed over the years. Drifts are now driven with jumbos: four destress holes are used as shown in Figure .4-5. The holes are drilled to twice the round depth, two

of the holes are angled up and out into the wall rock. Review of

the destressing practice revealed that the need to destress

depended on drift orientation and proximity to the orebody.

4.3.4 KERR ADDISON MINE

Kerr Addison Mine is located 40 km east of Kirkland Lake Ontario.

The mine has a long history of rockbursting and has used destres­

sing extensively in the pa st to control the problem. Regrettably­

very little documentation exists on the practices used at the

mine. The following section is based on a mine site visit and

personal correspondence with Mr. M. Plaunt, the chief mine

engineer.

In 1962 thé loss of the mine was feared due to rockbursting. Dr.

R. Morrison proposed a mining sequence and destressing program to

reduce the frequency and magnitude of the rockburst incidence,

Morisson, (1962). The. new sequence resulted in a 50 percent

reduction in production rate although the number of rockbursts

also necreased. Destressing was never scientifically qualified

~lthouqh it was believed to have been an important tool for

ground control.

Initial destressing at the mine was performe~-in overhand cut and

fill stop~s as indicated in Figure 4-6. There is little record of

the effectiveness of this method, it is likely that any benefits·

gained were outweighed by the creation of a fractured back under'

which miners had to work.

53

Page 62: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

e ... CIl

dealreaa holea

1

1 t -

Figur e 4-6: 0 es tres sPa tt ern St.ope Ba oks, Kerr A d dl s on MI" e

atler Frantzoa 1980

1

54

Page 63: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

(~

c

Due to prodùction demands, a 46 m thick by 305 m long pillar was

created below 3100 level. The pillar contained long fIat backs

t in man y areas and was th~ location of extensive rockbursting.

Following Morrison's advlce a slot was mined through the pillar

with the aid of destressing. Destress holes up to 37 m long were

drilled from the stope and from 3100 level, Figure 4-7. The

holes generally followed the d~p of the ore although sorne were

drilled into the hangingwall. No explanation exists for the the

hangingwall destress holes except that they were reported to be

effective. This technique for bringing raises up to a level was

used ext~nsively throughout the mine after its initial success.

After the slot was mined through, square set stoping commenced in

an inverted "V" sequence moving away from the slot. Stopes ran

the full width of the ore zone but were restricted.to 15 m in

length. Destressing was performed routinely every second lift,

the pattern used is shown in Figure 4-8. Destress holes were

drilled with bar and arm type drills, 38 to 57 mm diameter. The

remainder of the ~re body was also mined with an inverted "V"

pattern between levels and an overall regular "V" pattern

throughout the mine. Destressing continued on a regular basis

every second lift. Rockbursts still occurred, however they were

less frequent and r~stricted to locations remote from working

areas.

No engineering studies were conducted into the effectiveness of

destressing. The opinion at the mine is that the method was •

successful and would be used again if a similar situation arosè.

The ground being destressed was blocky, and under high stress,

requiring the use of square set stoping. Any additional

fracturing caused by the destress blasting was not a concern. It ~)

is apparent that the blocks were tightly interlocked and only

loosened at excavation boundaries. Destress blasting would have

caused block loosening to a greater depth. The mining methods,

sequencing and destressing used at Kerr Addison were extremely

labour intensive and costly, however, they did prove effective in

combating the rockburst problem.

55

Page 64: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

o

o

flll

o

hanglngwall ore zone

de .. tresa holea 1 1

.1 1·

3.100 level

tootwall

3250 level

. , ' Figure 4-7: Destre88 Pattern Ratslng Up To Level. Kerr Ad/dlson Mine

56

Page 65: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

Figure 4-8: Destress Pattern Square Set St oplng, Kerr" Addison Mine

-

lead l .; -stope q) -

1 1

- ~-1 "1

>- 1 1 -"

1 < -

1 1" 1

,

.... 1 1 1

1

1 1

\ 1 1 1

-\

-. , 0;1 -~

SECTION V(EW

c l'

l -~ / hanglngwal

. 1 1

1 1 > 1 1

1 1

1; ~ '"

1 "

~~~

>"

l

1 1 - 1

\

L - -" ~

-"-l

footwall

PLAN VIE""

57

1

Page 66: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

--

o

..... , ..,

1

!

4.3.5 KIRKLAND LAKE MINING CAMP

, Maeassa and Lake Shore mines have used destressing as a means of alleviating high stress conditions sinee the 1950's. the' fol­lowing section is based on work by Harling (1965), Cook and Bruce (1983), Quesnel and Hong (1986) and te Bel et al. (1987), as weIl as a sit~Dvisit. The site visit was made to Macassa mine-and included-discussions with R. Hon~! ground control eng~neer for Macassa mine and W. Quesnel, chief ground control engineer for Lac Minerals.

Both mines are located ~n-Kirkland Lake Ontario. They,are Gwned by Lac MineraIs Ltd. At present only Macassa is operating. The entire Kirkland La~e mining,camp has a long history of severe rockbursting associated with areas of geological weakness, stiff rocks and high extraction ratios.

Longhole and short hole Q~stressing were practiced -at the mines in the pasto Harling (1965) reports short hole destressing to ~ave been eftéctive in reducing the bursting incidence"in breast faces and backs put gives no details. Quesnel (1987) reports that successful results are currently being achieved with short hole (10 rn) destressing used during driving of conventional

, --raises. Suecess is g~eatest ~hen holes are drilled in the plane of the rai se rather than angled outwards. Destress héle location~ is planned aecording to geological structure.

Longhole destressing was used as a st ope approached a mined out are~_or fault, in pillar recovery and to bring raises up to the leve:l-. Examples of actual destress blast hole ayouts are shown in Figures 4-9 to 4-12. In all these exampl he mine waa of the opinion that the blâsting was successfu shifting-high stresses away from the area. This was such_~yidenc~ as

reduced burst incidence and intensity, and the occurrence of . rockbursts in areas adjacent ta but not witnin the destressed ground. A more in-depth account of this work ia presented by Harling (1965).

f.

58

Page 67: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

(

(--

fil "

fil 1

F.lgure 4-9:, Destress Panern For Plllar Recovery

\ destre88 holes

1

v-

\ \

after Harllng

\ Flgur,e 4-10:0estre8s Pattèrn For"Stop..a Approachlng Fault .,

~9 aUer Harllng

--

u

1

Page 68: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

)

o deatress holes

fil 1

f "f.

Flgur~ 4-11: Destress Pattern For Approachlng Stopes

after Harllng

"" -=

Figure 4-12: Destress Pattern For Ralaes , ,

after Harllng

-

o . ~

Page 69: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

,

c

Oéstress hole~ were usually diamond drilled 38 to 57 mm diameter. Percussive holes were used on occasion although deviation and

general_ho~~ quality were not as good. Holes were loaded with

AN/FO and collar primed. A 3 m collar was found desirable to

reduce cratering. In broken ground the hole -was traced with

Primacord to ensure complete detonation. Hole spacing was 7 to - 8.5 rn centers. This was believed to be.the maximum hale to hole

distance for successful dest-ressing. It has been reported, , , Harling (1965)'-, that a sign of successful destressing was 1;0

observe deformation due to rock movement in th~blasted hole.

The authors experience is that deformation and enlargernent is

~~mmon in most hol~s' afte'r blasting, particularly ~here many geological discontinuities and high in situ stresses existe Hole

deforrnation is not considered a suitable indication of successful '

7 destress blasting. 'When possible, the holes were drilled in the

vein: where not possible, duê to badly broken ground, holes were

·~led at 10 to 15 degrees into the hangingwall. Hole collars

were lined up êo as to minirnize damage to timber support. When /' '\

blasting, water Blowers were used to reduce the fire hazard and

bulkheads were used to prevent blockage of any travel ways.

Holes were blasted simultaneously. Ground conditions gen~rally

deteriorated, necessitating'further de~tressing, after advancing

two thirds of khe distance covered by the destress zone. In sorne

instances the mining of remnants had to be discounted dué to their low tonnage and grade

destressing. No rockbursts

'by longhole destres~ing ..

and the relatively high cost of

were reported to have been triggered

Although reports suggest the destressing was successful, this

author's e~perience suggests that the blast designs used in the

Kirkland Lake Camp in the past would only cause local fracturing

and modulus reduction in the,vicinity of the blastholes. Hole

spacing was too great to effect the rockmass between the holes.

61

\

1

Page 70: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

1 Ma~assa mine is now working to depths of over 2000 m.

--Mineralization has become less scattered than in the past,

t'

resulting in higher area extraction ratios. Tne greater --. ~

extraction and greater depth is resulting in more frequent and

higher intensity rockbursts at the mine.

, .. In June 1986 a destress blast' was initiated at the mine in the

,58-40 stope crown pillar. The pillar is shown in long section in

Figure 4-13, a 55 percent extrac'tion rati.o had been reached. The

\ de<?ision to destress was based on a high incidence of seismic . '

, \ activity in the stope back as ~ell as indication of high pressure

by squeeze blocks. Numerical modeling later confirmed the high '"

stresses.

The vein material in this stope is a silicified basic syenite and }

tuff. The fqot wall is a less silicified basic syenite and tuff.

vThe hangingwall is basic syenit~ and syenite porphry. The vein

rock is the stiffest material. A major fault forms the

hangingwall in the w~stern section and swings over to the

footwall in the eastern~section. The fauit is tightly closed

with up to 2 cm chlorite gouge infilling. A sec~nd fault is

located 1 to 2 m in the 'hangingwall" parallcl to the vein . •

Diamond drill holes revealed a 3 to 4 m thic~ fracture zone

around the perirnater of the pillar. High stresses in the center ,

of the pillar were indicated by core discing.

The destress hole 'pattern is shown in Figpre 4-14. The blast was

designed with a powder factor of 0.045 kg/t. Due to hole

squeezing the final loaded powder factor was only 0.029 kg/t.

,Hole number 1, shown on Figure 7, could not be loaded due to a

break through. Hole number 14 was eut off and did not fire. To ( 1

, avoid vibration damage to nearby mine structures, blasting was

l~mited to 42 kg per delay. Collars were 3.5 m, stemmed with

C.I.L Inert Gel ànd barite. A high degree of eratering still

oeeurred around the blasted holes, this was due to the fraetured

-p~rimeter zone around the stope. Convergence points and à microseismie monitoring system were used to monitor the blast.

62

Page 71: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

(

ri

, -' -

#3 shaft

58-40

r----' L-...-JI

J _ JO

5725 level

Figure 4-13: Long Section Macassa Mine

efte.,. Quesnel and Hong 1 sa6

63

Page 72: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

.,

..,.

~

Ch ~

o •

":', ! ••••••• • f ••••••••••

:·~~mitmm . :~1~~n1HHH~

l~l~·i{tl: :~.::II.~.i·.'I·: \}f;l;(rl~i~iiji)l:~ \ll~,\;,r •. , ••• " ...... ' ...... t .... ' .••• ;>~ •• , ....... 1 ...... .: :.::,~.~.~.:.::. :.: .. ;.:: .• : t·:-: :." "." '/ " ~.?:::'.'~ ~'. 3 .:::::.:.:.:

, 1 1

\ 1 \

" \ \ \ 1 \

\

\ 58-40 Stope\

\

\ \

1 1 :::.:~

:.:·:·:V:·~lI~"\\".'~\.\.'.":':.:':':':',:':':':\';': ,

14

.f!

~j~~~~~tî~*~~~t~~~~:~}~~lf;~J~i ."::;:::~~~~:~~~,*~f:::~~:~~~:~ ~~;~:: ...... .

~1g~.~W~\j:: . ~t:!i~r{i;;l

13 12 11

L,~J .~. '\~

~i~;i:\~'~';~f11' ! fj'i:i'i,'~~~;;'~~:~f.~~;!!i~ii!·, t\ltll\l:ii:l~~;:,I·ll!~ft.~;i~~;I r:::::i}:;··:::·::.t:::!j::·:~:!~\!;::::i!::. 10 9 8 7 6 5 4 3 2

~

~ ... " ~' ... '.' ' ..

"

-/-J

Figure 4-14: Destress M,cassa

1 Stope

1 Crown Pillar Mine

after Q'uesnel and Hong 1986

Page 73: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

c

(

Low and intermediate energy microseismic events occurred for

several hours after the destress blast. No events occurred within the solid block below the stope, suggesting it was capable

of sustaining any transferred stresses.

Convergence was recorded at aIl stations, the maximum was 28 mm.

The minimum convergence was 5.8 mm occurring adjacent to hole 1.

After a subsequent production blast a small rockburst occurred in

this area, displacing 25 'tons of rock. The convergence jumped to

33 mm. It is believed that the ground in this area was not

adequately destressed as a result of being unable to fire number

1 hole.

Drill core recovered from between destress holes 12 ~nd 13 was

not disced, indicating a stress reduction. Fracturing was

greatest at the location between the destress holes indicating

the creation of a continuous fracture zone between holes.

, Although only a ~ow powder factor was used, the ~nergy input was

sufficient to induce failure and interconnecting fractures in t~e

plane of the destress holes, this indicates that the stress on

the pillar was approaching the rock peak strength.

To date, no more major seismic activity has occu~ed in or around

the stope. The destress blast appears to have be~n successful in

transferring stress ta adjacent ground. The fact tiat one burst

occut-red in the vicinity of low convergence suggests that

convergence is a necessary effect of destressing.

!

During sinking of the No. 3(shaft at Macassa mine, rockbursting

becarne a continuous probleml after 1120 m; a number of remedial

measures were taken, including des-tressing. The following expert

from Le Bel et al. (1987) sumrn~rizés the methods and experience.

nA variety of blastholes drilling patterns was used to achieve destressi~g during shaft sinking. These included holes drilled into the sidewalls and loaded to their full length, inclined holes drilled downward into the corners of the excavation, and perimeter holes loaded with Xactex. Both sideholes aud corner holes tended to cause excessive blast-

65

Page 74: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

--

induced fracturing and 100sening of the rock, subsequent rockbursts. successful in reducing

f

overbreak and, because of genera1 increased the amount of damage caused by Xactex loaded perimeter holes were not

bursts.

Below 5000 feet (1524 ml,' a systematic pattern of destress blasting was used. At the shaft stations (every 150 feet, 45.7 ml, four 2 inch (50 mm) diameter holes were drilled, using a longhole machine; for 90 feet vertically from the corners of the excavation (holes l, 3, 4 and 6 in Figure 4-15). In locations where bursting had been experienced above the station, an additional two holes (no's 2 and 5) were drilled. These holes were blasted with 3 taped lengths of Primaflex and were initiated with the first bench blast after the station.

Once excavation had passed the 90 ft. (27.4 m) longhole destress holes, a series of short, 12 ft. long, small diameter (1 3/8 inch, 35 mm) destress holes were drilled with each bench. The holes were located in the ben ch as weIl the end walls. Four short holes would be drilled per bench, i.e. holes 1, 2, 3 and 7 from o~e bench to the next.

H\tes \ and 8 had a collar of 5 ft. (1.5 m) of commercial stemming and ehe remaining 7 ft. (2.1 m) was loaded with Powermex. Of the various destress blasting methods used, the longhole destressing coupled with short holes proved to be least damaging,/, although it ls difficult to demonstrate any substantial

.. reduction in rockburst frequency." . ~

, 4.3 . 6 CAMPBELL RED LAKE MINE "vi'

-l. Destressing at CRLM'has included crown pillars in cut and fill

stopes, remnant boxhole pillars in shrinkage stopes, and face

destressing in horizontal cut and fill stopes. In general ,

destress blasting is deemed to have been successful. In order to

gain a better understanding bf the mechanics of destressing the

most recent crown pillar destress blast was heavily instrumented

and monitored. This section is based on mine site visits during

destress blasts and discussions with the following: T. Makuch,

N. Neumann and B. Lokhorst - mine engineers, Dr. W. Blake - rock

mechanics consultant, Dr. D. Hedley - research Scientist at

CANMET. Information on the geology, layout and rockburst history

of the mine can be found in Chapter 3.

66

\

Page 75: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

~

c

c

c

~ .;

)

r

..

12 ft

• 1

4 •

- -.... 8

• 2

5 •

7

• 3

7 •

~--,

~;;. ......

-\ .,

Figure 4-15: Shaft Slnklng Destress Pattern, Macassa Mine

-7

after le Bel et al 1987

67

..

.,

Page 76: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

., , r ..

\

The first cut and fill pillar destressed was in 1102 E. 'B'

séope, located in the 'A' ore zone on the 10 level. The area ~ad a very high extraction ratio and was subject to considerable

bursting and spalling. Destress holes were drilled in a fashion

similar to that used in the Coeur d'Alene district of Idaho. ,Holes were 45 mm diameter, at 1.8 m centers, drilled from within

the stope in the plane of the ore. The pattern, location of , ,

" convergencè points and measured closure are shown in Figure 4-16.

The holes were loaded with AN/FO and fired simultaneous1y. Three

rockbursts occurred 65 hours after the destress at the location

shown in Figure 4-16. The bursts occurred at a point where, . following the destress blast, little closure was measured. After

the rockburst greater closure wàs measured. Much damage resulted

from the bursts and to_date no further mining has been undertaken

in the area.

The next pillar destressed was the 1902 E crown pillar, located

in the 'A' zone on the 18 levél. As a result of an increase in

the microseismic activity and visual observation of the pillar it

was decided to destress' both the 1902 E crown pillar and 1802 E

sill pillar. The destress blast hole pattern is shown in

Figure 4-17. Holes were 45 mm diameter, drilled at 1.8 m

centers. The holes were loaded with AN/FO and traced with 't , 1 detonating cord, 1.5 m unstemmed collars were 1eft. Mi1lisecond

de1ays were used for initiation. Much micréseismic activity as

weIl as one rockburst occurred immediately after the destress

blast. Another burst followed a later production blast in the

pillar. No other incidents occurred as the pillar was

successfully mined out. During mining the pillar was observed to

be highly fractured, creating sorne drilling problems.

The most recent pillar destress was in 1604 E stope, located in

the 'A2' zone on the 15 level. The extraction ratio was much

l~ss than in the previous examples, as shown in Figure 4-18.

Based on previous experience and computer modeling it was felt

that the pillar would be burst prone once reduced to a 10 m

thickness. Spalling and 'fracturing were observed wlthin the

68

Page 77: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

~

:!! ID C .. CD

.... 1 .... œ .... .... 0 1\)

m CJ (JJ -0

en '0 CD CD

~ II) ..

• 0 -.. CD ca .. (1) -3:: .. • CD ~ en c: en

". ()

"\ =r

• .. ~ ... ~

CD 01 ...

u

:

~ --S'ë) & ~~~BUètY~98Cl2 Tlmber:d

c..r~ ~'L-J' , 37 38 39 4 41 4 ~4~"-~~..J 1002 E DRI

1102 E STOPE

45mm Holes

~ , . . ~. pQW6ÉR'.:'IFi,CTO~ .;.p.e.6kQ/m •.•. '. .,." . ':.' .. '" (l.-(,,25 ·,6'lri3 . : .. " ~'. ': .. '. :. " : . -' . ': •. : .: 'Li' 0 'N"

.. .... :., .. '.:. :- :e{<PIO:Sf\f-e.s;;;-: Anfo ... ..... : .... ~ ... : :b~.IaY'.: :': < .... 25ms/hole

,. 12

10

• • ca C • • I! u •

mm 2

0

.. ;. ~"I .. t ).... ........ '( .. <' ......... "'''\ .... \'\ .... , .. .. : ......... -::-.... :.. '?'........ ::: .. .... ;~.~ .. ::f "$h .. :-:.<"::- :..... ...... ....:-

............. /$ .. :;;: ........ -:.-:- .. 1>-:......... .. .... .(':

, , .

Vay 3 J '1982

..\-: ..... ....... (>,\

" , -:. -:..... ... . ,

, .••.... .':OQ·l:Jb~e'Tru Llne

"

y _ EX1ensometer b Station

46

Closure From Extensometer Stations -

; .. " ::0 • ID •

k ~ ~ 10-1

.. 11 ,a 25

April

Il Il 23 30 • 13 20 27 M., June 1 9 82

'" 12

ta

& • c • • I! u •

mm 2

0

, \

-:! ::0 al

.. " Il 25 2

Apt Il

.. •

10-2

9 18 23 30 1 13 20 27

MI, June 198 2

1.

Il

l'

& 12

: 10

6 $ mm 2

o

~I . 1" J

.. ,t" ,. 25 2

~prlJ

10-3

-------• Il 23 30 6 '3 20 21

May June

".~ 1

Page 78: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

..... CI

-~

ID --CD ... 1: ID 7t' c 0 :r

• -• , -ID C» -of

,1

::!! (Q c: ... CD .,.. 1 .... ...., ..

.... CO 0 fi)

m Cf) -0 '0 CD

'"tI

II) ... 0 CD (1) -... en CI)

en

~ ~~ .... '", .... ,t~ ....... : ~

tt'fACrOÂ' , '

~~'\,~>~~,,~,\, ,~~-- <,

~:: ... ~ç:::"~'" ~::- ...... tr ,~.. ... ':... .. ....

,~'.E~PJo,~f\tes, '.;. Antô 'l' "OëlOoa10{$ ,- 25

<~Oôtib là ,'t,unk f..' ~~ ,~~ .... ..;: .....

...... :: ... :.~ .. ~~' ..... .. .'" .. ~ '\ .... .~.. .. ..

( y ~"'", ~

.,/

: "= : .... " .. " . .,,' ........... • .. l " : ',',.' .. " ..

: ••• ~ ,," ~ .. " .. ,. • •• "" ". :. ' .. l " " " ..

, : ~ ....... :: ' , '! :... '. ': ' ; ',.' :,' . ': -: .-:: '.':: :. .: -:. ~ ::. '. : ' .. : ~ :: , : l .. ' : ,:,' ·1 8-0~: E: : Q .. ~:r~.E: ....... , .... : .. ~, . ..:".' t. .. " .......... 0" .' '..... ...0 ,",', ... "

'. ':. . '.' ..... ,:. 'I:t '1." .' •• , .... .' ••• '.: ... :. ::'J::'::" :.:.'; ::: :'; ': .: ,. .:: .:.: . ::, :.: . .' ;':: .:. ':,'. ~ ':: :.:'. ..,..... LF :, '" i __ .................... ,........... .. Jo "",,*,-,. ;:: A..-

" ... - - - .. ::. ".' 10 .... ....... .. ".. ...'. ...""

ni;&( 'l~1P':~E'tAEiNT" ~ ,"Ii,:::' ... ~ .. :'!':". ~ .. :': 'l'" ." .. .. • • • .." • .,., .. " .". ", , .. :" ~ ." .......... : " : .,.~. "

" 0' " '. "1 ... '.. :'0" .... ' ..... 0 •• : ~ • ". :" _::: •• ~ .:". ·E·· :C·· ·S'tOPE::.·· 's<';:"è: '7:. I:O':N : ........ : .... '._ .. .. .. . '.. ............. .. :........ .

, . • _. ~ "a •

0 ...... :.,

; ..

.. ,

., END

SECTION

.. ;: ... ~ ....... «1' .... ..-.. J'Y<;> ..... ; ... y ~ ,,<;- --- ------.,.,---- -------1802 E O,STOPE #-_ ... ~_ .. ---_ .........

.. ..,' ~1~..d +<"T· "~&l-4' ........ ".. ' .. d0 ~ ,':y 9. --~.'>~ " .... ".,",j., ~ ;;.-::.-:"" -_ >,,' ' ... ",~;.ti{lli. g",ç.J~.&il,- , "',, ". " " . '

" ~ ~ ~", ",.t;~,.,. ~ '" ' " -' ",' '45~ "DE .... ~ ~~"~'" ",,' '''',~~~. ~~..,..: ~..., , ~."" '.. -':::~-M.~",~Sn~.' ~.",. '!;"-<!J.~f,.,..J!lf(l" STRESS HaL ES

p N

y A

Extensometer StatIon

/'

Page 79: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

c

,

(

c

· · . 1 \

, ' .' -. ' ..

, .' • .. . ,. "

Q) 1 •

-Q.;I­O~ ....... \'

~ft.' • VI .'t4

.. ··~o-:" , , . .' , .. ..t" : ~.' -'-

'. , ., p ••

: . . ' '.

Figure 4-18: Long Sectlon A 1 Zone

after Makuch et al. 1987

Page 80: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

stope but no unusual rnicroseismic,activity was noted. ln order to gain a better insight into ,the effects of ~estressing the stope -was heavilY:" instrumented in cooperation with the'-Canada Center for Mineral and Ènergy Technology' (CANMET) u~ing vibrating wire stress gauges, tape extensometer points, backfill pressure cell, blast vibration monitors, and a wave form analyzer'linked to the mine MP250 microseismic monitoring system, Figure 4-19. Disp1acernent discontinuity comPMter mode1ing suggested that rock­bursting would occur in the ~entral portion of the pillar. The destress pattern used is shown in ,Figur~ 4-20. Holes were 44 mm diarneter, dri}led at 1.6 m centers from within the stope. The hales w~re angled into the footwall to avoid damage to the c,ernent

; ~ 1

~plug in the drift above. It was decided to destress no. 3 vein crown pillar, which was no longer econornic. This created a stress shadow for sub~~quent stoping of nos. 1 and 2 ,vein~, and avoided working through b1asted ground. It was also, necessary to blast a section o~ no. 1 vein to complete the destressing.

The destress blast was followed by only minor microseismic activ­ity and no bursting. Measured ground vibration was within 20

percent of what was predicted. Backfill was not observed to carry any increased pressure. Few stress related problems were encountered as the no. "2 vein was rnined to the level suggesting "

that the blast was eff~ctive in Shiftcj~ng the stresses away.from the area: 'Sample closure and stress c nge data arising after the blast was compareato correspondi data predicted by a two

" dimensional, linear, finite element computer model, Table 4-2. The compari~on suggests that the blast resulted in a rnodulus

, \

reduction approaching 50 percent. One stress gaug~, located in the destress zone, recorded an increase in stièss suggesting tha~ the fracture plane did not extend between the destress ho les in

- ,

this area. Contrary to this, the nearest extensometer indicated average closure. The reliability of monitoring at this proximity to blasts is -questionable. The blasting may cause loca~

sloughing and incorrect closure m~~surem~nt~. Blastt~ration may cause 100sening of the wedge pinning the stress ~auges in place.

, 72

Page 81: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

.~

C

~. ~

c

,e

""

'(

. -

, '

"

..J

\

\.

'.

--..,

o .

• Q. Q --0

~ W

~ fD ....

.. ... -.. Q

W

~, 1ft

"'"

"

....

~~------~---~~I •

Q

.. _L ____ !.

&----01 ':'"

........... ~. ,-,', 1 ", J" '0'.::: :.:. -':," .' ' . ," .. ...,.' .,'; ........ Q.

;/::::.::':.::::':-.i'.~ • : '~",t "I": ," •• : ,""".:.

...tJ'N', • 1

• , 1 \ , 1

c o :;:: Il U o ... " o ~ > e

1 1 1 1

1 . el 1 Z· , 1

~ 1 l' -' 1 L a. , ,

.. -• ~ ,. e o • c • ~ M W

, ,

-'

\ "

• .. l:I • • .. Go

. ~

Flqure 4-19: 1604 EW Stope',PlUar Instrumentation

/ a fter Scoble ~t al. 1987

73

_A'

Page 82: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

'.

l,'

\

, '1-

Z : ' ..

w .. ,~ ..

w

•• CJ'

~-

c. ut C c(

o ..J

,ro .. . ,

'10. '

"

, ' . f

' .. • '. -1 ~ . . , .

.:.

, l';, 't.

.C;:) • . • Co.

'.

. r .'

OGlGl -cS C:O-J <z

VI W ...J o J:

...J

...J oC(

Figure 4-20; 1604 EW Stope Pillar .O~8tre88

. alter Scoble et al. 1987 (

..

w a.. o t­en

w

M,

ê,.; CI': .x~ '11';; ~~ '0 o_

u a: o ~

u < u..

a: w Q ~ o a..

Page 83: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

Table 4-2: Stress ehange ana Closure, 1~04E Pillar

StatioI) Measured Change 'Predicted Change 25% Modulus 50% Modulus Reduction Re~uction

Ex-2 -2.89 mm -0.7 mm -2.1 mm

Ex-4 -0.51 mm +0.1 mm +0.5 mm

E~-5 --1.41 mm -1.0 mm -1. 9 mm

Stress-3 -0.77 mPa -0.7 mPa .. -2.1 mPa

Stre"Ss-5 -5.50 mpa -1. 8 mPa -5.6' mPa \

Stress-6 +5.60 mPa +1. 8 mPa +7.6 mPa

after Scoble et al. 1987 .• -' ....

...

.. 1

c

. .. ..,.

) /-

M ,

C· " ~ --

fi'

"\ "- <" 0

t 75 ",

Il "

Page 84: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

1

J

Core was recovered from the destressed pillars in holes drilled

between no's 3 and 4 and no's 15 and 16 destress holes. The exact

position of the diamond~rill holes between the destress holes i8 not known. Core analysi~ by the author revealed no difference ... in

the fracture density along the length of the core with the

exception of the collars. In order to asses microfracturing scanning electron (SEM) and opticai microscope studies were

conducted. Anastimosing microfractures were observed in calcite

crystals of one sample recovered from the destressed area, Figure

4-21' and 4-22. Quarhz crystals exhibited undulose extinction

while sorne mica crystals were highly deformed, both these

features are related to high stresses, but not shock stress. No microfractures were observed in samples from outside the

destressed zone. The samples outside the destress zone were' of a different mineralogical composition: less silicified and with no

large calcite crystals. It is thereforè no~ possible to confirm

whether the microfractures were due to the destressing or other o

stress related phenomena. No samples showed sflgns of fracture /

along grain boundaries which is a feature associated with blast

induced stresses. Descriptions of the thin section studies are

located in Appendix 1. "

Two Boxhole pillar destress operations ,have been carried out at

the mine. Boxhole piIIars are created between ore shoots in

stopes being mined by shrinkage methods. These pillars are found

to be the most burst prone structures at Campbell Red Lake Mine.

Destressing was conducted in piIIars showing signs of high stress

such as fracturing, spalling and squeeze on ore shoot structures.

On the 14 level in the 'F' zone the boxhole pillar.s were

located in a fault block area; it is believed that this resulted

in higher than usual stress concentrations. The pattern and

loading arrangement used is shown in Figure 4-23. There was no

bursting immediately following the destress blast, ,however, the ~-...",,,,,

followin week there was sorne bursting on the leveis above. Four

months l

area.

after

severe rockbursting throughout the stoping

observed to Qave increased significantly

Figure 4-23.

76

Page 85: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

• ".

\'

'C

,

Figure 4-21: Thin Section Photograph of Anastimosing Microfractures in Calcite Crystals

\ --!igure 4-22: Scanning Electron Microscope Photograph of '-~-~~. Microfractures

~, 77 \

/ -

Page 86: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

~ "TI co C .. tn

~ 1

ri,) ~

.... ~ ri,) .... 0 ~ ---Dl 0 .... )(

CO :x: 0 -CD

" -II) .., 0 (1) (1) -.., CD

DI (1) - (1) .. CD ... 3: III 1':' c: t)

:r CD

!!. ... 10 CD ...

o

~~ LJ9 1 ::le =.- , ~ 24

POWDER

.::,.,

"'~\:~\'{:\.'''''' ~ .. ,,\ .... ~~, ... ,," ..... ,\\",,~ ,~,~ .. -< " , ~ .. ,:: .. \"'~,\'.": ," \., ...... .... .. ,'.. ..

"

':::: ....... , .. ' .. ~'"\. ~ \: r '~)}jÇ:'---..-" ~\";"~\,~ _. ---- ~, \. .. .., .... \,'\" ,~'~ ... '~ ... \. ... ~' ....... ~~~\., ... , ... \ ..... , .. ' ~f"""" .. ~\" , .... 1 ..... ' .. \... -::,' + :::,~\ ... ~, ..... " .... '.. ...':: '\. .. "''':-''~~\~''\'''''' .. " ........

\' \ .... ~,~"'\, \. ","

t~

1 N A L

~ ~

<C

45mm Holes

:o"D 0 ~~~ 16 1,

ExplosIves - Anlo Delay -25ms/hole

SECTION Double Trunk Llne

"

..... .. .... ,,', '/

/'­--- /14A: .17-,

.....t

Holes

Closure From Extensomete r Stat i,P n s • 5 DI C ..

• ti :&

mm 2

o

• 1

:. • li :&

mlll2

14 E

s •

14-2

• • < • ..

t~ p

• • ~

u

_--l--V /?

5 • 01 e • • 14 0 ti 3

mm 2

01

148·

01

• 5 DI .. ~ 41 14 C ..

• U l ~

.~ mm 21 è

0

5 • p 12 S • P 12

• 5

• ~ .. 14A ..

• •

l~ •

..c l • u !

'\ V 0

w

\)

Page 87: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

c

(

«

<,

The second boxhole pillar blast was located on the 1500 level in

the 'G' zone. Single holes 3.6 m long, 44 mm diam~er were drilled into the centei of 18 pillars. ~The holes were loaded

, with Magnafrac 5000 cartridge explosives, a 0.6 m collar was

stemmed with çement grout cartridges. The holes were double

primed with Nonel caps and blasted simultaneously. A rockburst

occurr~d 2.5 hours after the blast in an inaccessible subdrift as shown in Figure 4-24. The burst a~peared to be located on an

andesite - altered rock contact. It is probable that the blast

was succe9sful ln destressing the pillars, however, stress

transfer caused a non-destressed pillar to burst. Vibrating wire Il

stre"ss gauges, located as shown on Figur~ 4-24, showed no changes

after the blast.

In addition to these relatively large destress blasts, the mine . ,

has also destressed_breas~ faces in narrow eut and fill stopes.

The technique has been to drill a single hole into the horizontal

face. The hole typically extends 1.2 to 1.5 m beyond the length

of the production round. The destr1ss hole is blasted along with

the round. The hypothesis is that of the original South African

work: an increased fracture zone would push high stresses further

ahead' of the face and provide cushioning for any burst that does

occur. The position of the destress hole was ~eft up to the

driller but is usually located in the upper center portion of the

face. Destressing has only been initiated when ~opes have shown

signs of high stress s'uch as bursting, increased microseismic

activity, spalling and stress cracks. It has further been

observed that the high stress concentrations are restricted to

specifie areas in the stope such as around geologic contacts, and /

near to raises, although reasons for local, stress perturbations

are not always obvi?us. Brief histories of two stopes in which

breast face destressing was conducted concludes this section.

The 1702 lE 'B' stope is located on the 17 level in the 'A' ore

zone. After one year with no mining activity stoping was re­

initiated. In order to achieve high producti~n'the miner took . double lifts using vertical breasting. Very few rockbolts or ,

79

Page 88: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

,

CD r----.:-.-l. 10 10 -

altered rock

holes

o VWSt:4

hole.

\ ,

, (

Figure 4-24: Box Hole PlIIar Destres8 CRLM ( ~

80

1 .

, -

1

Page 89: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

(

c

other support were installed. The stope became seismically

active abd high energy events were recorded by the rnicroseismic

monitoring system; eventually a burst occurred. In order to

bring the situation ufider control the stope was tight filled. \ ,

Horizontal breasting is now used with extensive rock support and

breast face destressing. The destress hales are drilled 4.8 m

while the round is 3 m, 32 mm hales are used in bath cases. Much A

seismic activity still occurs after blasting, however the energy

released is low magnitude and no more rockbursts have occurred.

This example has demonstrated effective stress control measures,

however, it is not possible to isolate the contribution of

destress~ng to the control measures.

The 1704 EW stope is located on the 17 level in the 'Al' ore

zone. The stope was experiencing high frequency and intensity

sei smic activity part{cularly after blasting. A number.of small

bursts occurred in the vicinity of a raise and at a dyke. The

problem was particularly bad where raise and dyke intersected. -

Destressing was initiated as a control measure. A 32 mm diameter

hole was drilled 1 to 1.8 m beyond the round depth and fired with

the round. Shorter rounds and heavy support were used in the . vicinity of the raise and dyke. A study conducted by the author,

Chapter 7, was unable to verify the effectiveness of destressing,

by this method, in this particular situation, however, as a safety

precaution the mine is continuing to destress this stope. (

81

Page 90: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

/

o

5 PROBEX-l BOREHOLE DlLATOMETER

In order to complete this research project it was deemed necessary to be able to determine both in situ modulus of deformation and fracture density. After consideration of a

number of instruments, the Probex-l Borehole Dilatometer was

selected. This chapter discusses the operation, data reduction and problerns encountered with the instrument. Results and

Interpretation of data are presented in Chapter 8.

The limitations of laboratory derived Young's modulus for rock

mass evaluation are weIl recognized. Laboratory testing is

limited in representing the rock mass in question due to the size

of samples. Duplicating in situ environmental conditions is also

difficult in laboratory testing. Accurate measurement of modulus

of deformation is required for a complete understanding of r0ck

mass behavior. Coupled with the need for accurate mOduli values

is the need to detect and orientate fractures at remote

locations.

Several instruments have recently been developed for the in situ

measurement of rock mass modulus in diamond drill holes. The

instruments measure the response of the rock to an applied load.

If the load is applied in a uniform, radial, manner then the

instrument is termed a dilatometer or pressuremeter. It is

generally accepted that a dilatometer is for measurement in rock

'while a pressuremeter is for measurement in soils or soft rock.

An advantage of borehole dilatometers is their ability to obtain

measurements in locations accessible only by drill hole.

Continuous in situ measurements along the length of a borehole

allow rapid testing through a large volume of rock. The instrument is particularly valuable where core recovery i8 poer,

provided that the boreh~le walls are not too irregular.

Dilatometer rneasurements are preferable to laboratory tests as

the volume of rock tested is greater and dilatometer tests can be

conducted in moderately fractu,red and jointed rocks.

82

Page 91: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

c.

c

oilatometers can determine variation in deformation modulus as a

reBult of changes in lithology, 'joint frequency and areas of 1

weakness such as fractured and weatherea zones. Dilatometers have been used ta outlined zones of excavation damage, Koopmans

nnd Hughes (1985, 1984), measure the deformability of dam site

foundations, Rocha et al. (1970), measure short term creep in t

potash, Ladanyi and Gill (1983), and evaluate stability in .

underground hard rock mines Scoble et al. (1988).

5.1 DESCRIPTION-OF INSTRUMENT

The Roctést Probex-1 is a flexible dilatometer with a

cylindrical, radially expandable adiprene membrane. A schematic

diagram of the instrument is shawn in Figure 5-1. Pressurilàtion

is achieved by injecting fluid from the water cylinder into the

membrane cavity. The downstream piston in the water cylinder iB

actuate? by the hydraulic pump situated outside the borehole.

The piston is instrumente~with a linear variable displacment transducer (LVDT) to measure injected volume; this arrangement

eliminates errors caused by the parasitic expansion of the tubing and pumping system. The LVDT digital read-out unit is located on

surfàce. An initdal calibration determines the digital units per

injected volu~. Pressure is measured from the dial gauge

situated on the hydraulic pump. This measurement method requires . correction factors for the inert~a of the expanding m~mbrane and

dilation / compression (stiffness) uf the testing system. The

membrane inertia proves to be negligible when testing in ha rd

rocks. Other dilatometer systems incorporate LVDTs within the

expanding membrane to measure volume expansion directly. This

arrangement has the advantage of not requiring a correction Jor

system stiffness, and of being able to detect anisotropy_within the rock rnass.

~he Probex-l is 3 m long and weighs 40 kg. Operation of the

instrument requires two people." Both drill casing and wire 1ine " ,

rnethods have been us@d fo~.insertion of the instrument into the

83

Page 92: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

o

Inflation Une

Deflation Line _--f--t-t---t Pressure Gauge (1 nflation Circuit)

Pump

LVDT ~~.uL1

READOUT UNIT

1 Dilatable Membrane

Il

Pressure Gauge (Deflation Circuit)

MEASURING MODULE

Upstream Piston (Oil)

DUAL-ACTION HYDRAULIC MODULE

Dual Piston Rod

i!~h- Downstream Piston (Water)

a: llJ

h ~_ Cylinder ~ ~

EXPANOABLE DILATOMETER PROBE

Steel Core , (Mounting for DiJatometer Probe)

Saturation Plug __ -"("

Figure 5-1: .Schematlc Diagram Of Probex-1

.p 1

1

after ROCTEST (1986)

84

Page 93: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

c

c 1 1

hole. The instrument attaches to !BX' size'drill casing. An

attaehmént for wire line operation was constructed at McGill University, Figure-S-2. Figure 5-3 shows the instrument at an

underground test site. ~

"

5'.2 DEFORMA'l'ION MODULUS DE'l'ERMINATION

, The standard analysis of dilatometer data pssum~s the rock mass

to be a linear elastic, homogeneous and isotropie continuum.' The

effeets of anisotropy on modulus of deformation'can, however, be

substantial. Amadei (1985) has published a theoretical solution . "-for determination of deformation modulus in anisotropie rock.

The effect of in situ stresses on dilatometer results is also of

&oncern, Ladanyi (1975) diseusses this problem. The ISRM (1986)

suggest a method of analysis for regular jointed rock masses and

also recommend adjusting fo~ scale. In most situations the,

standard analysis is still used as in situ stresses and

discontinuity properties are very eomplex or unknown. rhe cv

limitations of the testing method and method analysis must be

recognizedi results must not be confused with other modulus

values. In this text, results are referred to as dilatometer moduli of deformation.

If the loaded length of borehole is large eompared to the

diameter, the·stress regime is considered to be plane strain.

Assuming an elastic medium the stress at any point is given by:

~

where

6rr = Pi R2 /r2 for compression

for tension e = -Pi R2/r2 "

ôrr= radial stress

r = radius of borehole d' 'b ('d Pi = pressure, uniformly l.strl. ute

R = distance from center of borehole

85

Page 94: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

-,

)

. ,

National Library of Canada,

canadian Theses Service

NOTICE

o

THE cjU~LITY OF THIS MICROFICHE 15 HEAVILY DEPENDEN" UPON THE OUAL~TY OF THE THESIS SUBMITTeo' FOR MICROYILMING.

UNFORTUNATELY THE COLOUREO ILLUSTRATIONS OF THIS THESIS CAN ONLY YIELD DIFFERENT TONES OF GREY.

'\

l' 1 :

( .

o 1

"

1 :

Bibliothlque nationale 4u Ca~ada~

Service des th'ses canadienne. "'"

--~ AVIS

"

o

LA QUALITE DE' CE"TTE MICROFICHE bEPEND, GRANDEMENT DE LA OUALIT.E DE LA THESE SOUMISE AU MICROFILMAGE.

"

• MALHEUREUSEMENT, LES DIFFERENTES

, ,

ILLUSTRATIONS EN COULEURS DE CETTE 0

TBESE NE PEUVENT DONNER OUE- DES TEINTES DE GRIS.

• <>

"

u •

. -.

..

Page 95: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

a-

~\ \

• ,

1

Figure 5-2: Wireline Attachment for Probex-l Dilatometer

Figure 5-3: probex-l At Underground Test Site

86

Page 96: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

c

,

c

(

·. --ri~·- --------r------------__ -r '

p

The volume involved in a single test'~pènds ~p.n. the pressure '" used. Using the above equations it is possible to estimate this ,

volume. Theoretically the dilatometer induces.stresse~ in the rock out to an infini te distance (r). The minimum stress, beyond which the rock is no longer influencing test results, is not,as yet defined. Exam~nation of"a pressure volume curve indicates

that the rock behaves in a linear fashion after being str€ssed­beyond 10 MPa. If 10 MPa is considered to be the stress below .

t which the rbck ~s no longer influential of test results, then the volume of rock 'affecting the test is calculated to be 0.005 m3 .

The dilatometer measures the diametral deformation of a borehole subjected to a uniformly distributéd radial pressure. Using ..,

- thick wall cylinder theory and assuming an infin~te elastic medium, the rock modulus can be deteFmined.

The deformation of the diameter of the borehole is given by:

or dr/r = (l+v) dP/E

E = (l+v) r dP/dr

where v = Poisson's ratio

E = modulus of elasticity P = pressure in probe

\

dr = change in radius of borehole

, <

dP = change in probe pressure between

= Pb - Pa

Pa = pressure at first measurement

Pb = pressure at second measurement

readings

When expressed in terms of volume instead of radius, the equàtion becomè-s:

E • 2(1+v) V dP/dV

87

Page 97: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

J

.. . in volume between readings

, "",

• 'h.

' .

V = volume of cavity when dP and dV are 'mèasured '- = Vo + Vm

Vo = initial volumë of deflated probe Vm = mean' additional volume injected

= (Va + Vb) / 2 Va = volumè at first m~asurement

-

Vb = volume at second measurément

" The pressure and volume change must be corrected for membrane inertia and syst'Em.-dilation / compression. The equation becomes:

tE = 2, (1 + v) V

dV - c

(dP-dP i)

.. where dP· = change in pre$sure due to inertia &f membrane

1 ~

cOFresponding to increment dP c = volume correction factor due to system __ dilation /

compression.

\.

5.2.1 DlLATOMETER CALIBRATION FACTORS

• The Probex-~must be corrected for membrand inertia and . . dilation. Membrane inertia is established by inflating

system the ~

unconfined probe and plotting a pressure versus volume curve from . , which the correction factor is 09tained, Roctest (1986). During , tests it was noted that sorne of the membranes did not inflate symmetrically due·to variable ,embrane rubber thicknes~ (12-16 mm).~ Modulus deterrnination is \ot affected by this. Best fit curve for the membrane inertia data was of the form:

y =, m Xn

88

Page 98: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

Je

(

f,

- where y = pressure X = volume m and n are dependent upon -the membrane used.

Regr~ssion coefficients (r2) of 0.99 were obtained. The maximum pressure required to overcome membrane inertia was 1~2 MPa, this

I(Y 1" __

'is insignificant when testing in ha rd rook. Repetition of the inertia correction curve was good, however, tpe maximum pressure

~; , 1

required to overcome me~rane ,inertia decr~ases slowly with us,e.

The volume correction is determined by inflating the probe in a calibration cylinder of known stiffness and plotting a pressure versus volume curve. The slope of the lipear portion of the curve is the stiffness of the combined 'testing system plus calibration cylinder. Compression occurs in the inflating water and rubper membrane while dilation occurs in the steel core, reaervoir casing and piston. The volume correction calibration .. factor 'c' is determined by the following equation:

\ c = a - b \

\ where a = inverse of testing system and cylinder stiffne~s, ,

b = inverse of calibration cylinder stiffness

b = 2Vc (r+t (l+vct)

. '

--.. ftJ

where Vc = inside volume.qf cylirder'affeeted by test .:>

r = inside radius of test cylinder •

t = cylinder thickness~ Vc = Poisson's ratio for cylinder material

.1 Ec = Young' s modulus for cylinder material

The factor 'e' is the inverse of the testing system stiffness. Stiffness, in this text, is defined as the stress deformation ratio (kPa/cc)~ The accuracy of the factor c is crucial to the

89

,\ ,

Page 99: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

1

..

o

, modulus determination. A difference of- .00001 cc/kPa can significantly alter results.

)

A typical calibration curve is shown in Figure 5-4. Data

analysis reveals the slope to be hi9?ly variable, depending on the portion of the curve over which the slope is taken. At high pressures, i.e. over' 25 MPa, there is an increase in slope and. non linearity of the curve. This is due to the non linear , deformation of the instrument. Results are-al~~ dependent on the

/

method and accuracy of the instr~~ent readings. Table 5-1

presents a listing of calibration results obtained for three

membranes. Even when tests were performed under identical conditions, the reproducibility was not good. All data was . ( ,

analyzed over a 13 to 26 MPa pressure interval by'linear " \

regression. During calibration tests the system was slow to

stabilize, at high pressures stability could take ~s long as 10

minutes. This is due to time depen~ent system dilation and heat loss of the compressed fluid (this component is small). The

slope of the curve decreases with time which resflts in a higher_ calibration factor. Our procedure h~ been to ufe an average of

ma~y results ~btained after readings stabilize. ~

Other authors have reported leakage problems with their

respective ditatometer systems; this would create reading

instability. Leakage has occurred in the McGill instrument,

although, it has not caused any significant problem. Ruman error­

in reading the pressure gauge i8 believed to be the great~st source of error. A pressure transducer and digital read-out are

recommended to overcome this Pfoblem (now availablé through RocTest).' The calibration curve waa observed to ahift to the

',---left when testèd underground.' Thi~ did not appear to affect the ,

calibration factor. ft

The calibration factor 'a' ia dependent upon the diameter of the

testing cylinder. Membrane end effects and thinning are

influenced by the hole diaméter. Calibration factors should be determined over a range of different sized cylindersl the value

\ \ \

\ \

90

Page 100: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

c

. o

c

~f('f'.

28

21

2.

22

20 ..... ~ ,- t8 Go :1 ..... ta • ~

t. :t

• • • t2 .. Q.

- 10

1

a

• 2

0

y)

a Clonflned calibration

• 'In .It u te .'t"

~ -. J 1

!-~

Q InJected volume (cc)

..

\ \

200

figure 5-4:Typlcal Pressure Versus Volume Test Data

• ~ :1

• • • .. . Q.

" • --ca. ca. •

\ ,

'C curv"e curv. urve 2 curv. 4 1 3

Figure 5-5: Idealized

Pressure-Volume

Deformation Curve

/ InJ.ct.d volu ...

a fter Scoble et al. (1988)

91

..

Page 101: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

.. . TABLE 5-1: CONFINED CALIBRA~ION..RESULTS

Q PROBE 1 LOCATION DATE CALIBRATION COMMENTS

FACTOR 'a' (cc/kPa)

114 McGill 8/12/86 .00114 first calibration 114 mine 8/12/86 .00118 114 mine 8/13/86 .00117 under ground 114 mine 8/18/86 .00119 under ground 114 mine 8/18/86 .00117 under ground 114 mine 9/14/86 .00119 under ground 114 mine 9/14/86 .00121 under ground 114 mine 9/14/~,6, . ~0119

125 RocTest 5/2:t/8~6 .0012ii , first calibration

125 Roc Test 5/21/86 .00118 125 RocTest 5/21/86 .00123 125 Roc Test 5/21/86 .00122 125 RocTest 5/21/86 .00125 125 RocTest 5/21/86 .00115 125 RocTest 6/2/86 .00119

3 125 RocTést 6/2/86 .00121 125 RocTest 6/3/86 .00120 c~~~

125 RocTest 6/3/86 .00120 ~

125 RocTest 6/3/86 . 00120 .. ">

125 RocTest 6/3/86 .00122 ~ ... 1.

125 RopTest 6/3/86 .00118 125 McGill Il}4/86 .001228 125 McGill 11/4/86 .001237 t • .. , 125 McGill 1/30/87 .001377 readings after 5 mfn>': .~

125 McGill 1/30/87 .001360 rea(iings after 5 min. ": 125 McGill 1/30/87 .001273 readings after 10 min.':' 125 McGill 2/13/87 .001328 readings after 6 min 125 McGill 2/13/87 .001284 readings after 1 min. 125 McGill 2/13/87 .001281 readings after 1 min. 125 McGill 2/13/87 .001280 readings after 1 min.

(j~i 125 McGill 2/13/87 .001273 readings after 3 min.

-~ 125 McGill 2/13/87 .001296 readings after 3 min. ";o!>l .. ? 125 McGill .f 2/13/87 .. ,0,01310 readings after 6 min.

125 mine 8/1/87 .001197 under ground l.('~. 125 mine ' 8/1/87 .001273 under ground

1. 125 mine 8/1/87 .00l-'332 under ground ~<.".~-'"., t

"

-107 McGill 2/15/87 .001192 first calibration 107 McGill 2/15/87 • 001133 readings after 1 min • 107 McGill 2/15/87 .001137 readings after 1 min.

0 .107 McGill 2/15/87 .001146 readings after 1 min.

107 McGill 2/15/87 .001153 readings after 5 min. 107 McGill 2/15/87 .001162 readings after 5 min. 107 McGill 2/15/87 .001161 readings after 5 min.

'\. 92

'1\

Page 102: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

c

r

c

,

~

-, ~of 'a' u~ed in determination of modulus should correspond to ~he # 'i f... .1

diameter at the test location. --(

~"

A correction, to account for pressure head,' is required when 1 • 'II

testing in vertical holes. A pressure equivalent to- the static head ~f the hydraulic fluid lipe ~s added to the gauge ~

pressure. The value is insignificant from 0 to 8 m below the elevation of the/gauge.

~.2.2 DBTIRNŒNATION or BOLI DIAMBTBR .;;'

It is possible to determine the approximate size of the borehole, at the pofht of testing, by observing the volume at which contact

... '. ia made with the borehole wall. Wall contact i5 indicated by'a pressure increase. Some initial pressure increase is expected due to membrane inertia." Diameter i5 determined by the following formula.

;., -­. where

o = 2 V (V 0 + Ya)

11" l

o = diameter of hole -:, ...

.Vo = initial volume of probe Va = volume added to contact borehole wall

l = probe length

The equation àssumes equal inflation along the length of the ~ membrane. It ignores end tapering and thi~ning of membrane material. A second method to determine volume is to mea~ure the diameter and volume of the unconfined membrane as it i5 inflated. The borehole diameter is determined by mat ching the volume at which wall contact is made with the unconfined volume and diameter. Detecting the exact volume at which the probe seats itself is difficult. With both t~chniqu~s, the calculated diameter w~s found tq exceed the actual diameter.

Page 103: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

J

o

/

5.2.3 PROBBX-l TBSTING CONSIDERATIONS

The membrane is r~ted to a maximum ing pressure of 20.7 MPa in a 82.5 mm'borehole and 30.0 MPa n a 76.2 mm borehole. These a're values at' which membrane rupture as occurred, intermediate

"values are not known. Maximum pressu es well below these values were used to avoid rupture. Hole diameter was determined using the techniques discussed in the previous section. Rupture has resulted from material flaws not linked to excessive pressure.

Readings taken during testing, as with calibration, are slow to

stabilize. This may be due to leakage, time dependent 'system dilation or time depen'dé,nt rock dilation (creep). The technique

used during testing was to allow a con~tant stabilizati~ime for each measurement; ~aiting for complete.stability proved too

• time consuming. The method suggested by the manufacturer is to

take readings at one minute intervals until the volume change is

within 5 percent of the initial reading. This method,Js only suitable if the percent age difference is always the iame. The

following two cases would yield different results. Case 1:

volume reading at pressure 1 is taken after a 5 percent

difference has been reached, reading at pre~sure 2 is taken after

a 2 percent difference has been reached. Case 2: votume reading

at pressure one and 2 are taken after a 2 perèent difference has been reached. Koopman~ and Hughes (1984) have improved the data

collection on\.their dilatometer by using an electric pump and l"

automated datq acquisition system.

The testing proce8ur~ used was to inflate the membran~the desired position to seat the probe. The pressure was then

, released and allowed to drpp to just above the seating pressQre.

A m~nimum of three loading cycles were then rune Unloading .. cycles ~ere attempted, however, they proved to be extremely

\ difficult with the pump arrangement used.

Data was'collected along the entire length of all ,bore_holes.

D:e to system r~liabil~d experimental error, dilatomete~

94

Page 104: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

c

( • 0

J • , .

\.

c

deforPlation modulus value should not be a'ssiqned to q.iscrete test location. Values should b~'averaged and assigned to àn area of the rock mass.

Fig~re 5-4 shows a typfcal hard rock load versus deformation curve. This curve includes both thé rock and testing system stiffness components. As with the calibration curve" thé rock plus testing system slope is not linear. Stiffness depends on

" the segment of the curve over which the slope is analyzed. The slope increases at higher pressure values.

When testing in high modulus rock a number of,additional problems arise due to the small increase in rock volume as compared to the change in testing instrument volume. The sensitivity of results to experimental error is greatly increased. In sorne cases the stiffness of the rock plus testing system exceeded the stiffness of the testing system alone ie. rock stiffness exceeded testing system stiffness. In this case meanirigless negative values for deformation modulus resulted •

Figure 5-5 schemati~ally illustrates the problem of testing in high modulus rock. Where rock plus system stiffness, curve l, exceeds system stiffness alone, curve 2,'negative modulus values result~ Anomalously high modulus values occur when the rock Q

plus system stiffness apprOach that of the system alone, curve 3. Curve 4 represents acceptable results. If the rock plus system stiffness falls between curve"l and 3 erroneous results will oeeur. Analysis of the data indicates that if the rock plus testing system stiffness approaches within 4.5 percent of the testing system stiffness then erroneous results will occur. This is due to the sensitivity of testing at high pre~sure and low deformation. When testing in high mo~ulus rock a large portion of the volume change is due to system dilation / compression, and only a srnall portion to rock dilation. As the percent age of dilation attributed to the testi~ system increases, the ~uracy

.~

of·rneasurement deereases.

95

Page 105: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

o \

1

o

l 2

\

Where results arg negative, or erroneously high, reasonable • •

values can be obtained by analyzing the slope of êhe rock plus <

system curve over a lower pressure interval. This results in a . ~ -

lowey stiffness value, h~wevër, the volume of rock con~idered in the kest is reduced. Analysis over a 13 to 20 MPa pressute interval was the standard practice used during this research.

r.- •• •

A second approach t6 allevtati~g the problems of testing in high modulus rock is. to increase the testing systemstiffness. This ,

can be done by replacing sorne e~the water ~ith a more stiff material such as steel balls. At 30 MPa water is compressed approximately 1 percent, the total water capacity of the Probex-l is 1 liter. Reducing the total water volume by r~placing it with , steel balls will significantly increase the system stiffness.

~

Reducing the wat~r volume, however,. would reduce the' capability te test in oversized bo~eholes.

The validity of dilatometer testing in high modulus rocks ~ppears questionable. Kaneshiro et al. (1987) suggest an upper limit of 41 GPa with the Probex-l. The author, however, has meaaured in situ dilatometer deformation moduli closely comparable to laboratory values of Young' s modulus in rock, up to, .80 GPa. .1

.. 5.2.4 SBNSITIVXTY AND RBP&ATABILI~Y OF

MODULUS or DErORMATIQN RESULTS ..

" The ability of instrument~ion to yield repea~ble and accurate results is of utmost impo tanè~. In order to asses the Probex-1 performance a number of st di~ were conducted. Repeatability

./

tests were Cfnducted in the calibration cylinder as weIl as in ha rd rock boreholes. A study to evaluate instrument gauge

,/

sensitivity was also undertake~ In situ results were compared to labo rat ory derived modulus values. /\

. . Tests conducted in the calibration cylinder should reflect the repeatability of the Probex-l. The cylinder ia of known ~terial

~

.96

Page 106: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

J'

- .--

c -/

c

. . ,

___ 1

properties and is not affected by repeated testing. As is , discuBse~ in the section on calibration, results of repeated , tes~s under standard laboratory conditions, have been variabl~.

~ '" " Repeated tests within a rock borehole wére found to be variable. In borehdles with few fractu~es, subsequent test generally yield higher modulus vâlues. Increases are due to closiqg of pores and cracks within the test area. In highly fractured boreholes, subsequent tests generally yield reduced modulus values. -The reduction is assu~edJto result from hole degr~dation c~used by

,c the first measurement. Reductions from 0 to 20 GPa occurred • . Increases have been from 0 to beyond the point of measur,ement, ie. \he ~tiffness of the rock plus testing system curve exceeded that of the testing system alone.

A sensitivity analysis was conducted on the accuracy of instrument readings. Specifie results ar~ dependent upon the data used in the analysis, however, trends are similar: ,

<l..

altering the recorded volume inj~ted, at a single reading by as little as 0.05 ec significantly alters results.

, altering the recorded pressure, at a single reading, by as little as 50 kpa significantly alters results. altering _aIl recorded volume readings or all recorded pressure readings by 3% significantly alters results. sensitivity to reading accuracy is g~eater at higher .. ..... pressures.

al~ering aIl recorded pressures or volumes by an equal qu~ntity does not affect the results.

A comparison of dilatometer derived modulus and laboratory , derived modulus frdm uniaxial loading was under,aken. It should

'\-be noteq that the dilatometer y1elds modulus r~sult$ for the plane normal to the bore hole axis, while core samples measure modulus parallel to the borehole axis. Core samples are from competent sections of rock while dilatometer tests are conducted over fractured ground. As discussed earlier, modulus values are

97

Page 107: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

,(j' •

..;.

o

dependent on the orien~ation of the test with respect to an~sotropy. Th~ ,results, Table 5-2, show htgh ,variability. oilatometer deformation values both lower and higher than laboratory derived'deformation modulus~~eurred. In the case of high modulus rock~, the dilatometer gave the lower value, where as with low ~odulus rocks the di1atometer returns a higher value.

Hustrulid and Schrauf (1979) report a 35 to 40 percent reduction from laboratory values using a Colorado School Of Mines dilatometer. Kaneshiro et al. (1987) report Probex-l results as being only 40 percent of laboratory values. Correction factors have been utilized by sorne researchers, while others have consi-_ dered dilatometer d~rived modulus a lower bound value for the rock mass.

5 .3 IMPRESSION PACKING

Impression packing is a means ,whereby an impres~ion is made of th(! surface of a borehole wall. The impressi~n records' fractures and other indentation or protruding features in ,the borehole. The tec~nique with the Probex-l is to wrap the membrane in a material that will record the borehole features after it has inflated at the desired location. A number of different materials have been tested to deter~ine the most suit able for impression recording.

;

-.a been

The impression technique has fts·limitations although at\present not weIL defined. Simple experiments indicated that a c~ck that could be detected by a fingernail (approximately 0.1 mm) would , -create an-impression. Hairline fractures not detectable by

fingernail would not create an impression. Fracture orientation,

packing pressure and the effects of in situ stresses ,have yet to - -- J</

be fully explored. Reductions in modulus have been~detected

where no impressions wereQrecorded. It is assumed that fractures

too small to be resolved by the impression technique yet significant enough to alter modulus existed.

98

Page 108: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

c

c

c

. -'

Table 5-2: Probex-l versus Laboratory Deformati~n Modulus

Modulus (GPa) Sample Probex-l laboratory

1 69 83.0

2 50 81. 3

3 18 7.4

4 22 21.1

5 33 20.7

6 36 17 .5

7 29 22.0

8 19 12.5

9 47 26.7

Koopmans and Hughes (1985) have reported similar findings. A

~ 1-imitation may weIl be the result of the material used to record ~ \

the impression. Vinyl cOding tape or electrical tape proved to be the most suitab1e. Red was found to be the best color for working in an underground environment. Other impression materials tried made poor impressions, were too thick, or were

~

not durable enough.

The procedure to mak~ an impression is as follows:

tif; wrap the membrane _~ith tape, overlap to ensure complete coverage. insert the probe ta the desired position within the borehole

and inflate. \

mark a reference 1ine on the drill casing string to identify top of hole. - remove probe from boreho1e.

o

trace impressionsonto plastic film, marking the reference line.

·99

(

--

Page 109: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

o

. ,

Figure 5-6: Tracing Fracture Impressions From Dilatometer ......

,t

• J

100

Page 110: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

c

• •

c

y \

( F!gure 5-7: Fracture Impression Maps

b

101

Page 111: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

o

o

N ,0

N

h

102

Flgu r. 5-8: Incllned Ol.'è ontlnulty

Plane eutt'n g Drill. Hoi.

,Figure 5,-9: Impression Map From

Drill Hole

Page 112: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

c

c

,1 !

c

..

Figure 5-6 shows the impressions being traced from the probe onto . ~lastic film. The resulting fracture maps are illustrated in Figure 5-7. A reference line is only possible when using drill casing insertion. It is still possible to orient the core, withçut reference line, if an impression Qt a known feature is

~~" -

recorded.

If the drill cote is of sufficient integrity it is .possible to physically align the drill core in the hole direction with co~rect rotatiQn. Discontinuity directions can be measured

1 .

directly from the core with suitable instruments, ie. compass-inclinometer.

It is also possible to obtain discontinuity orientations from borehole impressions. Figure 5-8 is an inclined discontinuity plane passing through a section of drill hole. Figure 5-9 shows the impression map created from this borehole. The reference line (Lr) represents the apex of the borehole. The line of maximum dip .(Ld) is also shown. In the case of a horizontal or vertical hole, determination of discontinuity orientation is found by the following equations:

dlp = arctan h/D d

dip direction = e + direction of Lr

where h ='distance between sinusoidal peaks D = borehole diameter e = angular distance between Lr and Ld

_ ,- Ii

.. If the drill hole is inclined the,above method yields the

, apparent dip. Sterographic projections are the most convenient way of correction. Figure 5-10 is an equal angle net with an example solution. The borehole (and reference line) trend 315 degrees and dip 30 degrees from horizontal. From the 76 mm diameter hole impressio~, the distance between sinusoidal peaks, h, is measured to be 64 mm resulting in a 40 degree

103

Page 113: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

..

,

o

\

" , ,6'0

" l , , , , ~

Nd

FI~re 6-10: E,qual Angle Stereograph Wlth Example Solution

r r 104

Page 114: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

~" \

/ - ---- ... --..'

apparent dip. The angular distance between Lr and Ld (e) is 60

degrees.

-_\~ The-borehole (B.H.) is brought to the vertical by a 60 dégree ~ /

c

/'

(

-' auxiliary rotation along the east-west diameter to B.H. ' • On the stereo net perimeter 60 degrees (9) is counted of from the 315

( degree mark. The apparent dip is counted-off along the east-west diameter to establish point D'. The normal to D' is found, ND'. The pole ND is determined by recovering the original 60 degree auxiliary rotation along a smaii circie. From this the

..

, . .::. -discontinuity is determined to he: dip 49 degrees, dip direction :qJ

86 degrees.

An area of concern was the potentiai damage to the impression

recording material dur~' , probe insertion and retraction. A tape wrapped membrane was ru p and down a horizontal three meter

~ long borehole three times. Very few marks were observed. AlI

the marks produced were either parallel to the probe axis or along the tape edges. Most marks occurred along the botto~ of the membrane where it made contact with the borehole. Marks created by probe movement are straight edged while those due to ' fractures are irregular. Movement marks and those caused py inflation over'rock debris are indentations while fracture

, l

impressions are extrusions. Impressions due to rock cuttings may

~bscure the fr~cture pattern, it 15 therefore "recommended that -

holes be flushed weJl prior to testing. Non fracture markings ~

are readily identitiable and ornitted f;om analysis.

1

A number of impression packing repetit~ons were conducted. Figure 5-7a and 5-7b are su ch repetitiorts. The pa~king pressures

\ were 20 MPa for Figure 5-7a and 26 MPa f6r Figure 5-7b, the

, higher pressure used yields a more detailed impression. Reproducablity is considered good.

\ J

'" 105

.. "

Page 115: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

,

o "

o

)

5.4 SOMMARX AND CONCLUSIONS ON TBB PROB&X-l DlLATONITSR

The Probex-l borehole dilatometer is capable of yielding a relative value of rock mass deformability. Magnitudes and locations of deformation changes are detectable by the instrument. Care and attention on the part of the user ls ~~ired for effective use. The instrument is wel~ suited for in situ investigations of blast related fracturation and modulu8

, ' reductions. particular noteworthy points are as follows:

> the accuracy and repeatability limitations of the instrument indicate that modulus values assigned to the rock mass should be based on the average of as man y tests as possible. This

-also applies to the derivation of the probe ~alibration factors. to reduce instrument reacling errors a pressure transducer with digital read-out is recommended. modulus values should be calculated using as high a pressure as possible to incorporate the greatest volume of rock in the

test. instrument readings should be taken after stabilit~~as

-J been reached. Where this is not practical due to time constraints, then readings should be taken after a fixed time

, interval. , "

the Probex-l can be used effectively as an impression packer, this is useful to aid in evaluating results in fractured ~

and anisotropie ground. - -a more complete study is required to assess the applicability

of dilatometers for testing in high modulus rock.

106

Page 116: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

c

c

c

6 MICROSJlISMIC MONITORING

Microseismic monitoring has become an accepted tool for ground control purposes. Structural instability can be detected and located, as can areas of high stress. Discontinuities can be located and delineated. The method is based on the detection and analysis of mi~roseismic energy waves that originated in, and travel through the rock mass.

The origin of naturally occurring microseismic energy is unknown . . Hardy (1987), attributes it to the sudden release of strain energy which generates an elastic stress w~ve. These r~actions are due to the ground trying to achieve stability under changing stress conditions. Possible causes are divided,into micro, macro and mega levels of emissions. At the micro level it is related to dislocations. At the macro level micro sei smic activity is related to twining, grain boundary movement and the propagation of microfractures through and between mineraI grains. At the

mega level it is r~ated to fracturing and failure of large volumes of rock or m6tion between two structural units. McGarr (1984) reports that there are no systematic physical differences , /"

between the microseismic waves generated by rockbursts and those generated by small earthquakes. Microseismic energy can also be imparted into the rock by a physical means such as blasting or sudden impact.

This chapter discusses the microseismic wave form and the equipment used at Campbell Red Lake Mine to monitor microseismic emissi~ns. The application of this equipment to evaluate ' destress blasts is also discussed.

6. 1 '1'SB NICROSIISNIC 'tIAVB l'ORM

Microseismic wave motion is recorded as either a displacement variation, a velocity variation or acceleration variation with respect to time or distance. The most common monitoring systems

\

107

"

Page 117: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

~

o

L

record either velocity or acceleration with respect to time.

An idealized microseismic event, recorded as a displacement time • history is shown in Figure 6-1. The wave can ~e characterized by a number of values including amplitude, rise time, duration,

~article velocity and acceleration. The threshold limit is the amplitude above which the wave must pass in order to be considered for further processing. It is an arbitrarily selected value. The threshold is usually set at 2 to 3 times the background or cultural noise'level. D~sp~acement, velocityand

acceleration are aIl numerically interrelated as shown bY,the

" following expressions.

dU dU

u = Ü = dt dt

u.= displacement

u = velocity

Ü = acceleration

.. ,

As with blast vibration monitoring, the wave form can be considered as a sinusoidal approximation. The advantages and limitations are presented by Dowding (1985). The simplification

allows the following for;!lulae to be develope'd.

il = 2 uf

ü = 2 uf

f = freqJ,lency

Microseismic events generate both shear (5) and compression (P)

waves, known as body waves, which travel through the rock masse Raleigh and Love waves, known as surface wa~es, are created when

body waves reach a surface. The P wave has the greatest

velocity, while most of the enérgy iB associated with the S wave

or Rayleigh wave if at a surfate.

108

Page 118: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

("

c 0 .. CIl t ... ~ '0 .. C

• > •

\

.L ... . . . ... .... . . ... ... ~ ...... . ... .. ~~-+------+--~-- -....

c • • ! e • .. - a. .. 0 • • • • • • " - - ~ ... .. .. .II: a. • • e . a. •

'0 C ::. 0 .. Q • .II: • U CIl 0 s:. c

~ --4

~ ) .II: • • • '" " Q. :2

" = • 0 Q. 0 • .. oC • .II:

e • s:. • • \ • ... • oC

\ Q. .. ,

Figure 8-1: Mlcroaelamlc Event

~. modlfl.d aU.r Blake 1882

C

Page 119: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

)- '

o

It is possible to represent a microseismic signal in the time d~ain, as in Figure 6-1, or in the frequency ajmain. Conversion to a frequency domain is achieved by numerical methods such as Fourier transforms or pseudovelocity response spectra, Dowding (1985) .

- .. Frequency spectra of seismic events at their source are unknown. Laboratory studies suggest they are fairly broad band, from 300 to 300,000 Hz, Hardy (1982). Small events, such as the formation of microcracks, generate high frequency waves, larg events produce lower frequencies. Lower frequencies contain a greater #

portion of the seismic energy.

Small, high frequency events have1pulse durations of . milliseconds, larger events may last for more than ten seconds. The duration is a function of distance. Frequency separation and wave type separation occur with distance. Amplitude ls a function of size of event. More extensive information on the nature of seismic waves can be found in Richter (1958).

Rock acts as a low p~ss filter; low frequency waves pass with ,

little alteration, while high frequencies are attenuated. There is an approximate linear relationship between frequency and

attenuation. Energy attenuation is proportional to_the square of the distance traveled, pulse duration, and a number of environmental and rock properties. Environmental factors include pressure, temperature and saturation. Rock properties include density, seismic velocity and nature of discontinuities. Details of these factors can be found in Young (1986).

r Il

6.2 TD CAMPBELL DD LAD MID MONITOIUNG SYSDM

Campbell Red Lake has a 64 channel Electrolab MP-250 microseismic monitoring system installed at the mine. An original system used 32 veloci~y and 16 accelerometer transducers. The present system uses 64 accelerometers. Data manipulation and storage ia

11'0

Page 120: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

,

o

c

performed with a POP 11/23+ computer. HareL copy is ~btained from a Teletype model 40 printer. Figure 6-2 i8 a schematic diagram of the system.

Transducer location depends upon monitoring priorities. Mine wide event detection as weIl ~ 'tight' monitoring of areas of

~~Jeater concern are possible. Source location accuracy improves r)1 ...

with the 'tightness' of the transducer array.

The MP-250 system sweeps the transducer input signaIs for signal voltages exceeding the preset threshold. The tbreshold is set to .. a level above mine cultural noise. Once the threshold ls exceeded, a time window opens and event processing commences. T4e time window can be set from 100 microseconds to 999 milliseconds. A-minimum of five transducer channels must be triggered within thë time window in order for event processing to continue. The time of the event is set when the time window first opens. At the end of the time wi~dow, information for that event is no longer collected and the window is reset for the next event. If fewer than five geophones are triggered, no event is registered. , The MP-250 is also equipped with an energy integrator. The signal from a preset"transducer passes through the integrator which calculates a relative energy for the event.

The processor receives the channel numbers and arrivaI times for each event. The transducer co-ordinates and the p wave velocity must already he entered into the computer. From this information, the source location is calculated by the solution of linear equations. The mathematics of these calculations are given by Blake (1982) and Electrolab (1981).

The PDP 11/23+ receives the data from the MP-250, it in turn calculates source location based on a least squares solution. The POP 11/23+ also calculates a standard deviation error for the solution. Interactive programs allow removal of spurious triggered geophones and other data manipulation to enhance foource location accuracy. Accurate source location by these methods

111

Page 121: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

o o • "" ID c: ~

0

G) 1

1'1)

junctron ~I amplifier 1. Itra nsd ucerl .. box

i: li!. UNDERGROUND EQIPMENT

. () .. O-

• 0 MP250 MICROSEISMIC PROCE$SOR

• .. 3 .. N ()

i: g -.. 0 ..

1 I~ energy -filter volt

L circuit sensor

event dota . r -.

prodessing -r-- tlmer

. ,

:a ca Ct) 'IC • -• data 3 processing, "

POP 11/23 data printer COMPUTER storage piotter

\

T

t

.. •

Page 122: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

(

(

assumes straight ray propagation which is only the case in

homogeneous media. In a mine, the radiated rays are distorted by ope~ings, changes in rock type, fracture zones and stress

changes. High energy events, occurring close to transducers, can be located with reasonable accuracy.' Low energy events and event~ occurring at a great distance result in po or arrivaI time data tiue to energy attenuation and ray bending.

Cultural noise derived from drilling and electrical currents is a

major problem. Although costly, sorne cultural noise can be

removed by notch filters. "Electrically induced 60 Hz and its

harmonies are easily remo~d. Drilling noi5~ i5 too broad band . -for simple notch filtering and i5 generally eliminated by

increasing the trigger level" however, increàsing trigger levels

results in the 105S of sensitivity to low energy events.

6.3 MONITORING DESTRESS BLASTING

T~e remainder of this chapter deals with microseismic monitoring

for determining the effectiveness of destress blasting. ~

Microseismic monitoring to determine the location of highly

stressed ground that may require destressing is beyond the scope

of this report. Information on this topic and other usês of

microseismic monitoring are available from Leighton (1982, 1984),

Ob~rt and Duvall (1957).

There are three possible mïcroseismic methods for tne analysis of

the effectiveness of a destress blast. The first is the

monitoring of the noise and energy emissions following the blast ~

and comparing them to the emissions before the blast. The second

-- is to conduct ~ seismic velocity survey be~ore and after the

blast. The third is to evaluate the energy released during and

. immediately fOllowing the blast, and equating this to a reduction

of the stored strain and potential energy of the rock.

113

Page 123: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

J Source location is of importance to any monitoring program.

Before any data c~ be analyzed, its location must be determined. A tight array of geophones should be placed around any stope to be destressed to ensure accurate location of aIl events.

Lahoratory tests have shown that as the stress level on a rock increases, the microseismic noise rate increases. AS rock known

to have failed adjusts to a stable condition, the noise rate decreases. Laboratory results of Obert and Duvall (1945) are shown in Figure 6-3. These results have also been observed in the field, Obert and Duvall (1957). Experience at Campbell Red

Lake Mine has shown that areas can be stressed to the point of bursting with little precursory or postburst aqÙivity. In only

one case has a correlation between microseism~~ activity and instability been made, Neuamann and Makuch (1984). It is this authors opinion that with highly sensitive monitoring equipment placed in strategie locations, evaluation of stability can be

provided by microseismic monitoring.

The pre-blast activity level is usually higher than the mine

background due to the ground being overstressed. High microseismic noise and energy release rates are "expected to

follow a destress blast~ These are due to readjustment of. tb~

fractured ground to the stresses imposed upon it. The activity should diminish within a short time if the destressing has been

successful. If the microseismic activity remains high following

a destress blast, then the blast has had no effect or has reduced

the stability of the area. Destressing causes stresses to be

transferred to adjacent ground. The potential exists to destress

one area and create an overstressed area sorne where else. Stress transfer is best predicted by numerical modeling methods.

Rock noise rate is the most widely used form of analysis. The method is simple and requires a minimum amount of equipment for

collecting the data and for data analysis. Both single and

mult1~channel monitoring equipment can be used. The rate can be

analyzed in terms of number of microseismic emissions per u~it

114

Page 124: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

C 60 ....

50 GRANITE ·A"

40'

• CI.I JO +' ~ c::

'r- 20 e s... CI.I 0..

'" 10

+' c:: cu > CI.I ,. 0 10 20 30 40 50 60 70 80, 90 100 CI.I

+'

"' 50 s... u

'r-- -e 40 GRANITE -B H

'" 'r-e cu VI 0 s-ur 30 .~

::E:

20

10

o 10 26 30 40 50 60 70 80 90 100

Applied load/ultimate strength. percent

Figure 8-3: Selamle Actlvlty Veraua load

~fter Obert and Duval 1946

c .~-

115

Page 125: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

o

time, accumulated emissions and time betweenflmissions. It should be noted that an emi~sion registered by the monitoring system is dependent upon certain parameters of the particular system; these include: the threshold trigger level, the-frequency response, and in the case of multi-channel systems, the time window and number of transducers requirea to register an event.

Energy can be analyzed for release rate per unit time, accumulated energy and time between events with a specified energy value. Any analysis of energy must proceed with ca~tion, as_J:he computer calculated energies are relative values for the foilowing reasons; . "

i) Calculations based on a single axis geophone are unrealistic as seismic waves, hence energy, are three dimensional ..

fJ(

ii) Attenuation is neglected or assumed equal in aIl directions: this is seldom true.

iii) The time window may cut off part of the wave to the energy transducer, giving a reduced value.

Energy can still be used for analyzing destresB b~astsl ,although its limitations/must be considered. It is still possible to compare the relative energy of mlcroseismic events occurring in ~ose proximity to each other. The to~al energy of a destress blast can be estimated and compared to the theoretical energy re1ease of the explosives a10ne. Any energy above that of the explosives is energy--released by the rock mass.

Seismic velocity or wave propagation velocity.can be used to determine the stress conditions in a rock masSe The velocity at which seismic energy traveis through ~ medium iB proportional to the modulus of deforrnation. A reduction in the seismic velocity indicates a reduction in the modulus, hence, a reduction in stress concentration. Figure 6-4 shows a sei smic survey layout

- and results of moni~oring a destress bIaBt.

116

Page 126: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

c

c

• i 0: ... ~

SECTION" A'

, ,

M .,A

NO, @t.

• G.o ......... 5700 levil

~ • el: • •

~ë~:··oœ~ 0'\.00

0

V.loclfy lU' "., fftol hole o o o o o o

• ; l' U

~ SHORE OESTRESSING

" IV ... , . • • •

o 10 ZO )0 . , , . AnER OESTRESSING

aelamle contour plota ln "feet per aecond

Figure 6-4: Selsmlc Survey layout And Résults

afte' Leighton 1082

..

117

Page 127: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

)

6.4 SOJeGUa AND CONCLUSIONS 01' HIcaoSKISMIC MONITOlUNQ

The microseismic monitoring technique is an extremely useful tool fo~ ground control purposes, although like ~osy monit?ring equipment, its limitations must pe recognized. The problems associated with attenuation, ray bending, cultural noise and energy calculation need to be further addressed.

Microseismic monitoring can be used to asses the effectiveness of destress blasting in a number'of ways: monitor the stability of

1

the g~~und before and after destressing, monitor the energy . .

released during the destress blast and immediately, following it, asses seismic- velocity before and after the blast.

t:.

\

. -

. - ---~

118

Page 128: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

( ~

c

(

7 rIBLD STOnIES or OESTRESSING HARROW VElM STOPE rACES

Many mines have utilized blast fracturing methods to control

high stresses at stope faces. The technique is to drill and blast short length holes in the breast face or out into the wall

• rock. The holes generally exceed the length of the production round by 1 to 1.8 m. Blasting is conducted either pre or

synchronous with the production blast.

In general, the practice has not been weIl documented, with the

exception of the early South African efforts, Hill et al. (1957).

In Canada, Kerr Addison used breast face destressing extensively

during square set mining, see Chapter 4. It is also known that

Dickenson, Macassa ~d Lac Shore mines used the method, although

documentation is min~mal. , Campbell Red Lake Mine (CRLM) has destressed horizontal breast faces in cut and fill stopes for a

number of years, ~etails are given in Chapter 4. The mine

recognized the need to gain a better understanding of the destressing process in order to evaluate its effectiveness and to

aid in optimizing blast design.

This chapter reports on two investigations carried out by the

author at the CRLM, mine site. The first investigation was

designed to evaluate the fracture zone created around a single

destress hole in a breast face. The second investigation

evaluated the influence of destress blast hole position and

overall stope reaction to destressing. The effectiveness of the

destress technique is also appraised.

7.1 rRACTURATION AROUNO A SINGLE DESTRKSS BOLI

The object of this study was to investigate the extent of

fracturing around a single confined hole blasted in a breast

face. A single blasted hole has no possibility of constructive

stress interaction with adjacent blasted holes. Other

researchers have undertaken"similar studies, as discussed in

119

Page 129: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

l

)

o

~

Chapter 3, however, they have been conduct~in reasonably

isotropic rock with low in situ stress levels. The work /

conducted in this study comprised of observation and measurement

of fractures about blasted holes.

The stope selected for the study was 1702 lE 'B', located in the

'A'- ore zone on the 17 level. This stope had a history of significant sei smic activ~ty and was being destressed on a

re~ular basis' at the time of the study. Destressing was

conducted by blasting a 32 mm diameter, 4.5 m long destress hole

in the center of a 3 m long breast round. The destress hole was

fired with t~e round. After blasting the bottom 1.5 m of th~ destress hole could be examined. Only six destress holes were examined as mine scheduling caused tne project to be

discontinued.

After blasting, the destress hole diameter was observed to

fluctuate greatly. In one case the hole was completely closed

off; the driller reported'very easy drilling in this face. The

maximum diameter at a depth of 0.45 m from the new face was 43.2

mm, the average was 38 mm. These measurements were taken in. the

direction of maximum elongation. At the collar the hole wouid

usually be belled. Figures 7-1 and 7-2 show the variation in • direction of elongation. In Figure 7-1 elongation i5 in a

direction at high angle to the vein structure, but still paraI leI

to a pre-existing discontinuity direction. In Figure 7-2

elongation is parallel to the direction of the vein st~ucture . •

Figures 7-1 and 7-2 also indicate the discontinuous nature of the

rock in the study area. Major discontinuities are perpindicular

and paraI leI to the strike and dip of the ore body.

A crushed zone was observed to extend from 3 to 10 mm around the

destress hole periphery. In cases where the hole was belled and

could not be scaled it was not possib~.to get accurate measurernents. Brady and Brown (1985)' suggests that the crushed

zones should extend out to one bore hole diameter, in the case of

,~CRLM, the strength of the rock appears to limit damage.

120

Page 130: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

• Figure 7-1: Blast Hole Elongation in Horizontal Direction

c Figure 7-2: Blast Hole Elongation ParaI leI to Ore Vein

c 121

Page 131: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

...

)

.Visible fractures were non-existent in sorne instances but generally extended from 50 to 100 mm (1.8 tOI 3 borehole diameters), as shown in Figures 7-1 and 7-2. The fractures were of varying orientation but always followed along pre-existinq discontinuies.

....1

In order to gain a more accurate measure of the cru shed zone and extent of fracturing, attempts were made to force diluted masonry paint into the fractures. The first method use~ was to fill the destress hole with paint then blast with PowerrneK cartridge explosive. This proved to be unsatisfactory as the paint appeared to becorne involved in the explosive reaction. The second method was to fill the destress hole with paint after being blasted but prior to blasting the breast round. A pluq and header, similar to those used to plug diamond drill holes, was installed at the collar of the hole, and the hole w~s pressurized to approximately 600 kpa with compressed air. Good results were

obtained with this method although after blasting the round, the ' paint tended to spill out making ~racture identification in the

lower portion of the hole difficult, Figure 7-3. A crushed zone clearly extended out to 10 mm and a fractured zone to 50 mm in a number of radiating directions. At this point the project was terminated. The next blast was to use red paint, instead of white; as weIl, after pressurizing ex cess paint was to be flushed from the hole.

General comments solicited from the driller were that he liked the ide~ that destressing may prevent rockbursts. He reported that destressing had no influence on subsequent drilling.

7.2 zrrZCTS or DZSTRBSSING ON STOPZ REACTIONS

The second single hole destress blast monitoring program was conducted in 1704~W sto~e, located in the 'Al' ore zone on the 17 level. The program was designed to ass~ss stope reactions, and the effectiveness of breast face destress blasting. In

122 ..

Page 132: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

Figure 7-3: Blast Hole After paint Injection Trial

c i r

. '"

o

c 123-

Page 133: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

'. ;.

o

o

addition, the differences between destressing a back hole or

center hole were ~luated.

The 1704 EW stope was selected for the study for a number of reasons; it was experiencing a large number of seismic events suggesting high stress, percent age extraction in the vicinity was high, the stope was being mined through a section with a

~

relativel~ consistent width and geology. The stope and the location of instrumentation and monitored breast faces is shown in Figure 7-4. Figure 7-48 is an enlargement of the test area. The notation on these Figures is N for no destress hole, B for back destress hole and C for center destress hole.

A total of 10 cQnsecutive breast blasts were taken during the study; 4 with no destress hales, 3 with the back hole as the destress hole, and 3 with a hole 0.6 to 0.8 m from the back as the destress hole. Face dimensions were: width between 1.5 and 2.4 m, height between 2.4 and 2.8 m. Breast length was 3 m, the dèstress hole was 4.5 m long. Production and destress holes were 32 mm diameter. The destress hole was incorporated into the breast round and blasted as such with AN/FO, detonated with safety fuse. A typical blast pattern is shown in Figure 7-5; this blast did not contain a ~estress hole. A destress blast pattern would have either the center of back hole extended.

Blast and stope monitoring inciuded a microseismic monitoring system, tape extensometer and visual inspections after each blàsts. Vibrating wire stress gauges, fill pressure cells and stope convergence met ers previously installed in the stope ~ere also monitored. Minera comments were solicited.

7.2.1 NICROSBISNIC MONITORING

The stope was instrumented with a tight array of transducers, the closest ones weQe located in 1604 W. drift and 1602 W. drift as indicated in Figure 7-5. Monitoring consisted of recording •

124 /

Page 134: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

<,

z

C fi ::

GI 0 CI CD :J ..

! al ~ -- CI • ca 1! 10 • CD Q. 10 ..

G Q.

! ;

_ ........... _--11-1 ..

c

c 1

~ ~

FIgLn 1-4: 1104 EW Stope, Test Location And instrumentation ..

125

Page 135: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

o ,

DO

r

o

Flgwe 7-48: Test Blut 8equance

o 1,26

t,

- -" T,

Page 136: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

Figure 7-5: ~ypica~B1ast Pattern in Narrow Vein Stope

(

c 127

_. __ ._-----

Page 137: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

..

\

everits occurring in the stope as well as keep±ng a record of the number of hits to each of the four closest transducers for three and one half hours after each blast. As discussed earlier, the object of destress blasting is to fracture the ground. This being the case, it is expected that the m:J,.croseism'ic system should record -0/ greater number of low energy events as slippage occurs along ffactures. High energy events, caused by the formation of fractures, are expected ta be less prevalent with ~he use of destress holes. Figure 7-6, presents a summary of the activity from the stope after each blast. Low energy events were those whose energy determined by the MP2St was less than 100,

high energy events greater than 100; the recorded energy values are relative magnitudes only. The nurnber of hits is the sum of the hits to aIl four transducers. \ .

The three types of seismié activity analysis (low energy, high

energy, total hits) aIl followed the sarne trends in terms of number of events. Monitoring errors causea by the following factors would introduce sorne error: triggering events by blasts

in adjacent stopes and rnasking events by blasting or seismic

events in other stopes. There was no distinction between the different blast designs based on anàlysis of seismic acti~ity.

In blasts Cl and N4 reblast, seismic events with MP2~0 energy greater than 500 were recarded. This i5 approximately equivalent to bla5ting 1 kg of AN/FO. Although the mlcro5eismic system dete_J:"rnined the è'vents to be at the breast face, in nei ther case was any visual evidence of the event detected .

7 .2 • 2 STOPB CONVBRGB!NCB •

Stope convergence monitoring was originally conducted witn RST Ltd. electrical convergence monitors. This equipment broke down and was replaced by a tape extensometer w1th eye-bolte installed 0.3 m into the wall. The RST equipment 18 more accurate,

however, it i5 not very rugged; it i8 designed for permanent

128 ,,'

Page 138: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

·c

c

,-

110

100

go

80

~

~ 70

0

.2 60

e -i 50 • e u 40 Ë ~~

30

20

10

0

e:2I hlt8 (x10)

N1 S1 C1 N2 92 C2 . bla8t type

ISSI evont. (low)

N3

Figure 7-6: Mlcroselsmlc Actlvlty After Blasting

83 C3 N4 N4

l?2ZI eveti~ (hlgh) •

7~-------------------------------------------------------'

8'

1 ~ " E S -

1 1 •

O~------~~~----~~------~~~~--~------~~------~

~1 + pt. 2

Figure 7-7: Stope Closure

12"9

B3 C3 N4

l pt. 4- x pt. 5

Page 139: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

)

o

installation such as in backfill. The accuracy of the tape ext~nsometer is 0.5 rom.

The location of the monito;ing points is shown in Figure 7-4b. /

--In aIL cases stope clos~re occurred after blasting. Closure wAs recorded until the breast face was 3 to 6 m ahead of the

• monitoring p0~nt. It was expected t~t the initial closure would be greatest for destressed faces if they were successful in creating an increased fracture zone. Because of the failure of the electrical convergence rr.eter, data is only available for 6 of the 10 blasts. Figure 7-7 is a graph of the measured results.

~ Instrument installation and measurement was conducted as soon 'after the blast as possible, however, it is likely that the greatèst closure occurred prior to installation. The high convergence at point 4 is attributed to the eye bolts not being anchored in solid rock. No distinction can be made between destressed and non-destressed blasts on stope convergence.

7.2.3 VISOAL INSPECTIONS

After each blast 'the stope was visited; records were made of the condition of the blasted area including such items as stress fracturing, the amount of sca1ing, seismic activity, bootiegs, condition of destress hole, miners comments and any other

·anoma1ous conditions. It was expected that destressing wou1d decrease the amount of stress fracturing and a1so reduce spitting from the face. Based on the information c01lected there i8 no perceivable difference in the different b1ast designs.

Stress fracturing extended up the face, from the brow, 0.9 to 1.7 m before scaling and 0.6 to 1.2 m aftèr sca1ing, typica1 stress fracturing is shown in Figures 7-S"and 7-9. The fa ct that much of the stress fracturing is superficial and easily 8caled' away suggests that it May be blast induced fracturing.

130

Page 140: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

«

-Figure 7-8: Stress Fractures Before Scaling

p~.r , ,f." "l

,j .. J.

"

Fractures extend to within 1.5 m of the back . .,;1

Figure 7-9: Stress Fractures After Scaling Fractures restricted to vicinity of brow.

131

Page 141: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

)

-

o

The hanging wall was defined by joint contacts running sub­parallel to the vein. For blasts NI to B2 foot wall contact was a~ong a shear plane, there was no pronounced foot wall

for blast C2. Foijblasts N3 to N4 the foot wall broke jo,int contacts similar to those on the hanging wall.

contact 1 along

After blasting the destress holes wertenlarged and generally

belled at the mouth. A crushed zone extended from 8 to 29 mm (rneasured after scaling). In sorne cases the h~le was ovoid with the long axis vertical or horizontal. Both vertical and

horizontal open radial cracks were observed, these were always

related to pre-existing discontinuities; The B3 destress hole ls

shown4ln Figure 7-10, a vertical crack runs parallel to a quartz-, calcite infilled joint. A horizontal fracture is shown in Figure

7-11, blast B2. Closed radial fractures not associated

with known discontinuities, extended from 50 to 150 mm, fractures

associated with pre-existing diséontinuities extended much

further. Fractures were best observed after being sprayed with paint.

Much of the information proved to be ambiguous and very difficult

to interpret. For exarnple, it was found that in blast Cl there

were ;ery few stress fractures and a large amount of seismic

activity during the shifti after blast N3 there was little stress

fracturing and only a small amount of sei smic activity during

shift. The greatest amount of stress fra~turing and on shift

seismic activity occurred after blast C2, this was located

adjacent to the highly jointed and fractured pillar separating

the off shoot ore vein. Microseisrnic activity recorded

irnrnediately after this blast was not high.

Ovoid holes, along with the greatest crushed zone around blast

holes, occurred after blast B3 and C3. These indicate the

presence of high stresses. In the case of B3, extensive

microseisrnic activity was recorded after blasting, much less was

recorded after the C3 blast. The on shift seismic activity was

similar in both cases. ,

132

Page 142: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

c Figure 7-10: Blast B3 Destress Holé

Open fracture runs parallel to ore ~~in.

Figure 7-11: Blast B2 Back perimeter Hole Fracture runs sub perpendicular to vein direction.

c

, - 133

Page 143: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

,

The drillers reported having difficulty drilling holes in

fractured ground below the previously blasted destr,s.ss hole.

Holes drilled immédiately below the destressed hole were the

most difficult. This observation contradicts that of the 1702 E stope study. Two possible explanations are: differences in rock

ty \or differences in miners sensitivit8 to such factors. Other

wo has indicated that fracturing in Campbell Red Lake Mine

extends to 15 blast hole diameters, Chapter 8. 1 -

l f~actures can also be expected around the brow where

the compressive waves are reflected as tensile waves .

. Damage to the stope back due to back destress holes was noted in

only one case. Addi~ion~l scaling was r~quired which ~ft the back with an unfavorable slot shape. After a few days and more

scaling, the slot was no longer prese~t. After project

completion back degradation was inv,estigated. The amount of

100se in the screen, and general condition of the rock was noted.

Breasts blasted with center destress holes had the least amount

of back degradation. Breasts with no destress hole or back

destress hole generally had 5 lo 15 cm of loose in the screen.

It must be recognized that this study is subject to the quality

of the original scaling and whether or not lObse was removed from

behind the sereen at a later time.

7.2.4 OTHER INSTRUMENTATION

Vibrating wire stress rneters, backfill pressure cells and

convergence meters installed in backfill were monitored during

the test. The position of the instrumentation is shown in

Figure 7-4. The instrumentation was ~ocated at distances too

great to diseern the different blast types.

As mining progressed under the stress g~uges no change was

recorded in gauge l, a stress reduction ~as recorded in gauge 2.

Gauge 2 was approximately 6 m above the mined lift. It was

expected that an increase in stress would be registered as the

134

Page 144: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

(

(

c

distance is beyond that normally associated with excavation damage and stress relaxation. It is concluded that the wedge holding the gauge in place was loosened by blast, vibrations.

The fill pressure cell and convergence meter registered no change

after being mined over. They were located approximately 25 feet

below the lift back. It is thought that initial closure occurs when ground is first opened, however, no further closure occurs

until after a much greater area of ground is opened.

-7.2.5 DISCONTINUITY SORVEY

t In order to assess the influence of geological discontinuities on

the microseismic activity, the study area was mapped for joi~s, fractures and other pertinent information. AlI together 7

discontinuity orientations were identified, listed in table 7-1. l

A substantially greater number of low energy events occurred

a~ter passing through a zone of high joint frequency. The high

discontinuity zone acts like a destressed area, non violent

yielding may be occurring, resulting'in an increase in low energy

seismic emissions. Discontinuity orientation did not appear to

influence microseismic activity.

Figure 7-12 presents the results of the mapping. The respective

discontinuity traces are marked on the hanging wall, foot wall

and back. Stress fractures in the back generally broke along the

major joint breaks, these have not been marked on the figure. It

was common to find large differences in the hanging wall and foot

wall discontinuity patterns. In the area of blast Cl very few

joints penetrated the foot wall shear conta the area

of blast C3 the foot wall rock was extensively fr tured. This

is a result of it being in the pillar of the off shoot ore vein.

135

Page 145: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

o

\

o

o

Tabla 7-1: Dlacontlnuity Orientation

Type 1: strike 260 deg. dip 30 deg. N., joint set quartz-calcite infilled a - 1 mm

Type 2: strike 280 - 315 deg.,dip 80 - 85 deq. NE. joint set, quartz-calcite infilled 0 - 20 mm

'shear contact ore vein cleavage.

Type 3: strike 60 deg., dip 85 deg. SE. joint set

Type 4: strike 350 - 005 deg., dip 20 E. joint set, trace quartz-calcite infilling

Type 5: strike 350 - 000 deg., dip 85 deg. E. joint set, trace quartz-calcite infilling

Type 6: strike 180 deg., dip 30 W. joint set

Type 7: strike' 70 - 80 deg., dip 30 deg. S. joint set

(

136

Page 146: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

( hanging wal foot wal back

(

1 1

1

1 1

Il ~ 1

1

1 1

c FlgLra7-12: Dtacontlnulty Map

~ 37

Page 147: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

,

l

o

7.3 SUMMARY AND CONCLUSIONS OW BRBAS~ ~ACB DISTRKSSIHQ STODI.S

Single holes blasted as destress holes in narrow vein stopes resulted in a number of observations of blast induced damage and response of the stope to destress blasting. From these observations general conc~sions on the effectiveness of the destress blasting technique can be made.

The studies indicated that a blast induced crushed zone extends 2 to 30 mm about the blast hole. The crushed zone was circular and apparent1y not affected by pre-existing discon~inuities or stress regime. The variation in extent of the crushed; zone is attributed to the strength of the rock about the blasted hole.

A blast induced fracture zone extends from 0 to over 100 mm about ~the blast hole. The fractures a1ign themselves along pre­existing discontinuity planes. The influence of in situ stresses could not be determined. Blasted holes tended to be ovoid with the long ~xis parallel to the orientation of maximum fracture extension. Blast induced damage may extend beyond the visible fracture zone as has been obser~ed in other studies, Chapter 8. Damage is dependent upon

4

the proxirnity of a free face, the pre­existing fracture density, in situ stresses and the strength of pre-existing discontinuities. A destress hole placed towards the

r'\ back will not induce fractures as a\result of tensile reflection of the stress waves at a free face. This view is based on theoretical considerations of stress wave attenuatio~tlined in Chapter 3. The creation of an adequate sized cushion zone la likewise not possible.

The study revealed no significant differences, relating to a reduction in rockburst potential, between breast blasta with a destress hole and those without. It is possible that differences did exist but were beyond the range of detection of the

instrumentation used. Attempts were made to reduce the number of variables duting the tests, however, variables su ch as geology and in situ stresses could not be controlled. The number of pre-

138

Page 148: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

c

(

(

..

existing discontinuities was observed to significantly effect the microseismic- emission rate after blasting.

The normal'extent of damage;about a stope May well extend beyond the distance of any additional, destress blast, induced damage. This bein? the case, it is unlikely that a 4.5 m destres8 hole in a 3 m breast would have any significant effect on stope reactions.) This May expl~in why damage i8 seldom seen in a

/ breast J8ce after high energy sei smic events; the events occurred at a distance beyond the existing fracture zone.

Future work should investigate the extent of the blast induced fracture zone about the breast face, if this distance exceeds 1.5 m destress holes should be drilled to fracture the solid rock beyond. The location of high stress areas should be determined for hole positioning, this could be done with the microseismiç system by monitoring the exact location of seismlc energy being released.

Based on the information collected during thls study, blasting a . . 4.5,m destress hole in a 3 m production round is not an effective

" means of destressing. This conclusion i5 specifie to the test. environment; changes in geology or stress regime May yield different result5. It ia believed that a single 32 mm diameter hole in a 3 by 2 m face does not impart enough energy to the

groupd to cause adequate fracturing. In order, to be effective, the ground must be hit with sufficient energy to cause extensive fracturing, not just local. Fraèturing and reduction in modulus must be created throughout the entire breast face'area.

• J 139

Page 149: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

1

o

8 BUST l'RAC'l'URING STODl:ZS r

During'the course of research at Campbell Red Lake Mine (CRLM) , experimental studies on blasting and its influence on the rock ' mass were carried out at the mine site. The experimental studies were designed~to investigate a number of factors of importance

- " to destress blast design; the attenuation of blast induced seismic waves was investigated in an attempt to estimate blast induced fracturation; the extent and nature of fracturation

between two blasted holes was investigated to determine actual fracture extension and reduction in modulus of deformation caused

-by fracturation. One of the planned studies involved an 'intensive investigation of a stope pillar before and after destressing. Because of a change in mine scheduling this study

, could not be completed. '\

, 8.1 l'RACTURATION STUDIES IN 'l'BE 1670 W 'A' S'l'OPB CROWN PILLAR

The 1670 W 'A' stQpe crown pillar is located in a miscellaneous mining zone on the 15 level, Figure 8-1. Original plans for this pillar called for destress blasting followed by underhand cut and fill mining. The pillar had not shown any signs of being over stressed, however, production supervisors wished to destress the

pillar as a safety precaution. As a result of a change in mi~e scheduling the planned study for this pillar could not be completed.' One hole was drilled thro~gh the pillar resulting in . . information on the relationship between ex~avation induced fracturation and modulus of deformation.

The anticipated destress blast design, for the pillar, was similar to that used in the 1604 EW and 1802 E destress blasts, Chapter 4. Site investigation plans included drilling 76 mm boreholes through the pillar before and after the destress blast. Probex-l dilatometer surveys would be run in these holes'to obtain modulus of deformation and fracturation data. The change in mine scheduling resulted in only the pre-destres8 blast hale

,:-J 140

\

Page 150: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

f . \ .~

, .

(

, . \

. ,

il.

, ..

1" 1 & Lev.1 Plan FIGur. 8-" .

f

_3.é::.17.LN3/1 J.N!Or ~.

4"

141

)

Q

Page 151: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

l

-0

being drilled and logged. The location of the hole, and pillar geometry a~e shown i9 Figure 8-2.

The results of the dilatometer survey and core analysis are presented in Table 8-1. As was expected, the c~nter of the pillar contained few fractures. A greater nurnber of fractures were detected at the two collars .. These fractures were the rësult of excavation damage and high stress. Reasonable correlation exists between decreasing modulus and increasing fracture density as indicated in Table 8-1. Dilatometer results around the collar cannot be substantiated as the instrument was cauaing rock movement along discontinuities. This was detected

~ b~ audible 'snaps' and, in one case, observation of moveme~t.

~The core is shown in Figure 8-3. Selected core samples were tested for uniaxial compressive strength and Young's modulus, Table 8-1. It is dirficult to' compare dilatometer modulus of

deformation and laboratory derived modulus for the following

reasonSi the two methods measure deforma~ion in different directions, laboratory samples are intact while the dilatometer measures over, and includea in, any reductions due to fractures; laboratory moduli determined in the laboratory w~th strain gauges are unlikely to include effects of fracturation due to the small length over which they measure. ~

Two horizontal and two vertical strain gauges were mounted on

each core sample tested. Poisson/s ratio was determined to vary

from 0.19 to 0.25, the mean being 0.21. It was observed that Poiason's ratio increased alightly with confining pressure. This is expected when loading is para11el to major discontinuities, as

was the case. A s1ight increase in Poisson's ratio a1so occurred ,

with increasing fracture density. A typical stress strain curve and horizontal versus-~ertical strain curve is shown in Fi9ure~

8-4 and 8-5.

Page 152: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

Flgur • • -~: 1670 W"A' Stop •

•• ctlon vl.w

c

• .. - 0 = .. .... ... (1)

~ -- , ~ 0 .... .. eo 0 .... • c

0 .. N • = -. \ IL

c: • 0 .. 0

C ,-

l 0 ., (1) , 4(

~ 0 r-. G ..

= -...

. .

,

1

\ )

}

Page 153: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

Table 8-1: 1670 W'A' Stope Crown Pillar Test Results

~ • " dist., fracture (~-1)

modulus (GPa) strength Poisson's from density u.c.s. ratio collar dilate core dilate core (MPa) 50% U.C.s. {~m}

• 139 16 2 ./

190 10 Il 260 4 75 134 0'.22 266 5 ,25 295 2 84 199 0.19 380 7 85 123 0.12

• 505 3 86 ' 176 0.21 520 3 97 647 0 94 901 3 -68 915 3 87 148 0.18 978 7 37 1043 7 49 1060 10 88

'( 166 0.24

:> 3 41 10 10 14 10 10 10

5 8 87 188 0.25

o

144

Page 154: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

.'

c

Figure 8-3: Core Recovered From 1670 WA Stope Crown Pillar Extensive fracturing occurred at both collars •

• l

.. 145

Page 155: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

~

-1It . .iJ

··0 ..

.~

FIGur. 8-4: Str ••• Straln Curv. CRLM And •• It •

170

160

150

HO 130

120

• lUI A. :1 100

• 90 • • 80 .. .. 70 • 60

50

~,

, JO

20

10

0

0 00002 0.0004 0.0006 00008 0.001 0.0012 00014 0.001 li 0.001'11

Figure 8-5: Horizontal ver,uI Vertical Str.ln

II: -• .. .. • • .. II: o ~ .. o ~

0.0005 ..,-------------------------"':1..

00004

o.ooo~

00002

0.0001

0 0 0.0002 0.0004 0.000& 0.00011 0.001 0.0012 0.0014 0.001' 0.00111

.ertlca' .traln ..

/'"

1'6

\.

Page 156: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

c

c

c

Compressive failure of most samples was along pre-existirig

discontinuities, 0 to 10 degrees to the core axis. A few samples failed along planes at 10 to 25 d7grees to the core axis; this

failure was of ar_~w tooth nature across the pre-existing 1

discontinuities. Two samples failed violently, although there

was no apparent feature that distinguished these samples from the others.

The central portion of the pillar was relatively intact. Few

fractures exist beyond the pillar boundaries. Analysis shows a

fractured zone to exist to a depth of 2 m from the top of the

pillar and 2.5 m from the bottom, Figure 8-2. The fractures are attributed to excavation damage or tension fractures resulting

from high horizontal stresses. Stress relaxation may be the

cause of sorne fracturing in the immediate vicinity of the opening. The greatest fracture frequency and least RQD occurred

within the first meter away from the openings. Fracture densities

greater than 15 and rock quality designation (RQD) of 0 percent

occurred in these regions. A transition zone of increasing RQD ~

and decreasing fracture density lies between the ~ighly fractured

zone and pillar core. Fracture density in the central region was

from 0 to 7 based on core analysis, RQD was 100 percent. Only

one bore hole impression was made in the pillar center, no

fractures were detected. Although a double barrel core recovery

system was used it ls possible that m?ny of the fractures

recorded from the core were drill !nduced. Nin~ty percent of the

fract~res recorded by core analysis and impression packing ~

occurred along known discontinuity directions. Many of the core

fractures were quartz carbonate or phyll~ilicate infilled.'

8.2 rRACTURATION STUDIIS IN THE 1470 STOPE ACCESS DRIrT

The 1470 Stope access drift is located 645 m below surface on the , 14 level, Figure 2-3. The study evaluated blast fragmentation

between adjacent blast holes.

147

Page 157: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

,.. The 1470 drift was selected because of its ease of access, proximity to an in 9itu stress measurement location, and remoteness from mining activity. Severe rockbursting has

occurred 150 rn west of the test location, Hedley et al. (1985), suggesting the area is heavily stressed. Virgin ground stress

rneasurements conducted by CANMET, Arjang (1986), were taken 400 m south of the test site, on the sarne level. A 23 MPa horizontal stress was rneasured in a northeast -'southwest direction, the

other two principal stresses were 16 MPa, refer to Chapter 2.

8.2.1 ROCK CHARACTERlZATION

An extensive investigation of the rock properties at the test

site was undertaken. The rock was c1assified by the mine as an altered andesite. Typical modal composition is as fol1ows: biotite 5 to 15 percent, calcite 20 to 45 percent, chlorite 25 to

30 percent, feldspars 8 to 12 percent, muscovite 0 to 4 percent,

opaques 2 to 6 percent, quartz 12 to 18 percent, and fine matrix

,

15 to 50 percent. The rock was subdivided into units A to F ~, based on modal composition, degree of foliation, and number of cross cutting joints. The units were sub-parallel to the major

cleavage direction and andesite - altered rock contact. Detailed

thin section descriptions are given in Appendix 1. For

simplicity, the mechanical properties of the different units were

assurned the same. Subsequent laboratory testing proved this to

be a valid assumption.

The rnechanical properties of rocks are dependent upon a number

of variables. These varIables include mineralogical composition,

structural and textural features, crystal size and orientation,

stress level, temperature, degree of saturation and testing

method. Significant variation of these factors' can occur

over a very small distance. Assigning absolute values of rock

properties is therefore not recommended. Values should be given

a range based on statistical analysis of collected data.

1..J8

Page 158: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

( ,

c

Table 8-2 list the rock properties at the 1470' drift test site.

The methods used to obtain the results are also listed. AlI the testing methods assume a homogeneous linear elastic and isotropie

rock maSSe

In the case of blasting, dynamic stresses are produced by the initial detonation pressure while a quasi-static pressure is

generated by the ensuing gas pressure. The way in which a rock

reacts to dynamic stresses or static stresses ls different. When

considering the dynamic str~ss, dynamic elastic constants govern

J Ck behavior. Static elastic constants govern rock behavior

der the quasi-static gas pressure.

Dynamic elastic constants can be determined by either resonance

or pulse methods. The resonance method involves exciting a

specimen to its natural frequency then measuring wave length and frequency. The pulse or ultra-sonie method requires measuring

wave velocity and material density. Static elastic constants are

determined by loading the rock and monitoring deformation.

The method of determinfng the two types of elastic constants

differ considerably. Static constants are determined with slow

loading rates and high stress and strain levels. Dynamic

constants are obtained at high loading rates but low stress and strain levels. \ A comparlson of values determined by the the two

methods is only viable if done at equal stress levels. In

homogeneous, isotropic rock, the methods should yield similar

results.

An extensive literature review conducted by Lama and Vutukuri

(1978), found static constants to be from 0 to 30 percent less

than dynamic constants. The difference is attributed to the

greater influence of discontinuities on static constants. Highly

compacted rocks had similar dynamic and elastic values.

Different elastic constants are effected to differènt degrees by

parameters such as discontinuity density, saturation, stress

levei and testing direction. Kaneshiro et al. (1987) detèrmined

149

Page 159: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

1

"-i

• Table 8-2: 1470 Drift Rock propfrues #

parame ter m~thod value no. samples standard (me~n) tested deviation

Young's static 84 GPa 10 . 3.9 GPa tangent (47 mm core) modulus

Dilatometer Probex-l 62 GPa 11 22 GPa , deformation (borehole ~ modulus dilatometer)

Young's dynamic 96 GPa * modulus (ultrasonic)

o~ poisson's static 4 0.03 . " (47 mm core) ratlo

Poisson's dynamic' 0.22 * ratio (ultrasonic)

density, 2.83 g/cc -~ unconfined static 151 MPa 15 28 MPa

compressive (47 mm'and strength 26 mm core)

tensile static 15.6 MPa 5 strength

,

* Moh~nty 1988

• /

150

Page 160: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

c

c

~ . that the in situ seismic modulus was less than the laboratory derived static modulus, but greater than the in situ dilatométer modulus.

8.2.2 BLAST rRACTURATION

As was discussed &t length in Chapter 3, rock response to blasting is not well understood. Explosive interaction with the

rock mass has yet to be fully characterized, as such, accurate prediction of rock mass response to blasting by numerical

modeling is not yet possible. Examination and measurement of in

situ blasts can lead to characterization of rock response to

blasting, which in turn, can result in empirica~ predictive capabilities. A predictive model developed in this way is very site specifie due to the variable nature of different rock

masses.

Experimental test blasts were conducted in the 1470 dr~t wall.

Horizontal, 45 mm diameter holes were drilled perpendicula~ to

the drift wall to a depth of 2.5 m, Figure 8-6. The holes were spaced at 0.3, 0.6, 0.9 and 1.2 m. The bottom 1.2 m of each hole

was loaded pneumatically with Amex blasting agent (AN/FO) and

initiated with Nonel ms delays (numbers 0, 2, 4, 6, 8). prev!ous destress blasts at éRLM have utilized Amex in 45 mm

holes. After blasting, NQ (76 mm) diamond drill holes were cored

midway between blast holes, Figure 8-6. Diamond drill holes 1 and 2 were stopped after 1.2 and 1.4 m because of drilling difficulties.

AIl diamond drill hole cores were logged for fractures, joints

and petrology, and tested for point load strength, sei smic

velocity, and uniaxial compressive strength. A RocTest Probex-l borehole dilatometer was used to measure in situ deformation

modulus and make bore hole impressions. A complete description

of the instrument and testing procedure is given in Chapter 5.

fractured sections repeated dilatome~r tests were not performed

151

Page 161: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

Figur. 8-8: Bla.t Hole and Dlamond Drill Ho" Looatlon. 1470 Drift

o

o

4860N

0.& m

O. OESTRESS H~

1 • ODH

o \

152

Page 162: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

(

C

(

Where 'fracturing and spalling was excessive, dilatometer testing wa not possible. A graphical summary of the test results for bore hol 3 and 4 is given in Figures 8-7 and 8-8.

The core RQD and percent recovery as well as fracture measurements correlate weIl with the location of the blasted zone. The point load strength does not exhibit any clear trend. Because of a limited number of suitable test specimens little can be said about the seismic veloC'i,ty. Fra,cture and joint counts were taken over 10 cm intervals then normalized to count per meter. Figure 8-9 shows the core recovered from hole 4. A large amount of fractures occurred at the collar; a result of both the initial excavation damage and this blast study. The core from the toe is intact, it appears that blast induced fracturation does not extend far beyond a line drawn perpendicular to the end of the explosive charge. A 15 cm section of core, indicated in .. Figure 8-9 appeared to be disced. This phenomena is usually

attributed to stress relief of the cored rock; discing is

considered to be indicative of high stresses. Considering the fractured condition of the surrounding rock it is unlikely that

high stresses are the cause.

Samples from the core were observed under the optical and electron scanning micr~scope. No microfractures or other stress related featur~s were observed. It is suggested that aIl the blast induced fractures in the 1470 drift test site were formed along pre-existing discontinuities. This is in agreement with results obtained in the narrow vein destress blast, Chapter 7,

b and the results of other researchers who report that existing fractures grow in preference to new ones and ~ause a fracture free zone in their vicinity.

Bore hole fracture impressions were measured for orientation persistence, and intensity. It was not possible to measure orientation of the short persistence fractures. Very short

_ fractures (less than 3 cm) grouped a10ng the top and bottom of the borehole; a satisfactory explanation for this has yet to be

153

Page 163: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

... Ut

l: ... Go w ~

,.

o

F

E 1

[ 1-C'

A

ROCK TYPE

r

o 50 100

ROO

050100

RECOVERY - Ci 50 100

MOOULUS GPa

"'-

150

, 0/

l

l o S 10 15

la 47.5 M~

o b

o o

& 7

VELOCITY km/S

6

IMPRESSION DRILL CORE FRACTURES JOINTS

m-1 m- 1

,.

b '-~ , :j

~~ b :J

h JO' • o 5 10

DRILL CORE FRACTURES

m-1

..... ~

w Z o N

o UJ )-

'9 .- . - --. ID

...

~ G' 1: ~ • C» t ... .. ... .,. ... o o .. :: ".

Q • • :: • • • :r Il :ID • • 1: ~ • Z o i c.t

Page 164: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

~I i

\

.. Ut Ut

:s: 1-0.. W 0

~

......

IF

1 E

. 0

'e

B

lA1

lA

" ROC'K TYPE

\ --.J

f.

,

-;

. / 'J ,

~ 1-

f\

)

L cl .

l

-

} 1 - -

~-\ - ~

o 50 100 0 50 100 0" 50 100 150

Rao

,

~RECOVERY 010

MODULUS GPa

~

'\

i J

1

~

Is 47.5 MPa

l:

o o Cl

o

o

o o 87

1 a-L-o 5 10

VELOCITY IMPRESSION DRILL CORE km/s FRA~~r~S JOIN~~,

DRILL CORE FRACTURES

m- 1

~ -

-n G c: .. . '

• • • .. .. ,. .... 0

0 .. = 0 • • .. .. • • • -::1 CI

w :II z • 0 • N c: -Q .. • W •

1- :z: Cf)

-< 0 ...J -al •

~

Page 165: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

Figure 8-9: .1

Core Recovered From 1470 Drift, Diamond Drill Hole 4 The core is disced over a 10 cm interval at the start of the third run. Dises were between .4 an 1.2 em thîck.

--

156

Page 166: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

(

c

/ _/

determined. Of the measurable fractures, 80 percent were aligned . with known discontinuities, the remaining 20 percent appeared random. however, it was noted that most aIIigned with other pre-

e -

existing disco,ntinuities observed on the core. Stereographic

plots of the fractures measu~ed from the bore hole impressions and from tee core are shown in Figures 8-10A and a-lOB. The bore hole impression maps are located in Appendix 2.,

~t was observed that fracture frequency determined from the core

waS 30 to 60 pe~c~nt less than that recorded by the impresston

technrque. A plausible explanation for this is that the high

pressure u~d to create the impressions opens weaker fractures; drilling induced fractures may also be occurring. Many of the

drill, core fractures could not be identified' on the impression

map~, presum~bly these were due to drilling induced breakage (a single core barrel was used for recQvery). Attempts were made to

-

complete fracture traces to aid orientation procedures and

eliminate the possibility of counti~ a crack more than once.

Fractures less than 25 mm were very difficult to deal with.

Fractures parallel to the drill hole axis may have introduced

sorne bias to the results, however, very few of these were

observed in either the core or on the impression maps.

Figure 8-11 shows the relationship between fracture frequency,

from the impressions maps, and distance between blast holes.

Figure 8-12 shows the relationship between dilatometer modulus of

.deformat~on and distance between blast holes. Distance between

b1ast holes is measOreçi a.long a 1ine perpendicular to the diamond

drtll l~ole. No adjustments have been made for the diarnond drill

holes not being exactly c~ntered between the blast holes. The

9~neral trends are decreasing fracturation and increasing modulus with increasing distance.

Figure 8-13 demonstrates the general reduction of in situ

deformation modulus with increasing fracturation. Current CRLM

practice has utilized 1.3 to 1.5 m destress blast hole spacing.

Based on the experim~tal results, at 1.5 m spacing no

157

Page 167: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

• Figur. 8-10: 1470 Drift Fractur ••• Imp ..... lon Pack.r

\

o 158

Page 168: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

-Ut ~

---

II'

+

• ~I

5-9 À-Z

~

\

1\.

N ~- r

/

Î/·/'

++ l, + +

s

} r

"

'+

~

" :

"II II c ; • • ,-0 Il •• -... -III 0 G .. -... 1 • .. .,. ; ft

~ ... . , • 1

"0 :: II: n 0 .. •

~

.r

Page 169: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

0

..

Figure 8-11: Fractur •• ver.ue BI •• t Hole Spaclnl

80r---------------~--------------------~---f r a

--c 60 f­, t u r e 40 ~ a

m O~--~----~I----~----~--~~--~----~--~ o 0.2 0,4 0.6 0,8 , 1.2 1.4 1.6

distance betw6en blast holes m

Figure 8-12: Modulu.' verlu. 81 •• t Hole Spa~lng

100

m 801-o - ---d ~

u 1 60 ~ u . ,.. 8 • 40

G p 20 a

0 0 0.2 0.4 0.6 o.e , 1.2 ',4 1.6

distance between blast holes m

) 160

)

Page 170: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

..•

Figur. '-13: Modulu. Y.rtu. Fr.ctur • ....,.n.lty

( ----------~-

190

m 80 0 d

~ .u , 1 60 ---u 8 -~. ....

40

G p 20 ~ 8 ..

0 \

0 20 40 60 ao fracture denslty per m

k (

c 161

Page 171: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

o

(

f fracturing would be expected to occur midway between the blast

holes, however, a slight reduction in modulus may occur. The

trends of the relationships are obvious, however, fitting a curve

to the data is not easy due the hig~scatter and relatively small

data base. The information does provide a starting point for practical destress blast design.

8.3 BLAST VIBRATION STODIES

A nurnber of test blasts were conducted throughout the mine in an

attempt to establish attenuation characteristics of the rock

masse A blast vibration monitoring instrument and the mine's

microseismic monitoring equipment were used in the study.

Neither of these instruments was capable of providing information

on vibration within the fractured zone about the blast holes.

Peak particle velocity attenuatlon curves were developed for the

elastic response region beyond the area of fracturing. The

attenuation characteristics of particle velocity change

significantly once the stress wave is below the amplitude which

can fracture rock. In order to determine attenuation and

establish peak particle velocity as a predictive tool for rock

fracture, measurements must be taken in the region were

fracturation and other nonelastic processes are occurring.

Test blasts were conducted by drilling holes 0.8 m into the drift

wall. Holes were spaced from 3 to 28 m away from a cement pad

monitoring station were a three axis geophone was mounted. The

geophone was linked ta an Instantel Limited DS377 blast

vibration monitor. Limitations associated with the rsponse

frequency and sampling rate of the OS3?7 may have adve~sely

effected the results of the tests.

The 05377 has a maximum frequency response of 250 Hz, blasting

produces frequencies greater than this. These frequencies are

filtered out as the wave travels through the rock. Using the

DS377 close to a blast, where high frequencies still exist, will

162

Page 172: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

(

... lead to erroneoUB re'sults aB the entïre wave form will not be

captured and analyzed. Data sampling rate is inversely

proportioanl to sampling time. A long monitoring period results

in a low samp~ng r~; this may introduce error. Typical output

from the ins~rJmen~s shown in Appendix 3. \ ''--

The OS377 proved to be very unreliable. In sorne instances the

tri~ger mechanism would fail, other times keyboard operation

would lock for no apparent reason. It is concluded that the

instrument is not suitable for near field monitoring and is not

rugged enough for underground operation.

Attempts were made to use the mine's microseism!c system linked

to a wave form analyzer to monitor blasting. Details of the

microseismic monitoring system are given in Chapter 6. Knowing

the response characteristics of the transducers and any signal

amplification, it is possible to determine a peak particle

velocity or acceleration (depending on type of transducer; ~

geophone or accelerometer). The study used aIl geophones with a

peak resRonse of 6.8 volts peak to zero; transducers within 100 m

of a blast were over-driven. Results from far field blasting

were highly variable indicating the non homogeneity of the mine

with respect to sei smic wave transmission.

Energy values generated by the energy integrator on the

microseismic system were investigated for possible attenuation

characterization. Results of both the Instantel and MP250

monitoring are presented in Table 8-3. Regression analysis on

the 05377 data resulted in a best fit curve of the form;

1

/ )'

/ . where R = radial distance from blast

w = weight of explosive ,1

1 i

The limitations of the data collection must be considered wh~n using this equation for blast design purposes.

163

/ l

)

Page 173: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

l

3

\ "

0

~ Il ,"

Tabl. 8-3: R •• ultl of Blaltln. ~.It.

i

RECORDINGS FROM ELECTROLAB MP:50 AND INSTANTEl 05370

LOCATION EX PL WEIGHT ("g)

INSTANTEL DIST PPV

("''''/5 )

MP250 COMMENTS OIST ENERGY

( PI )

----------------------------------------------------------------------------

-- 1470 ANFO 2.35 12.00 7948 OESTRESS 8LA'il 1470 ANFb 2.35 13.00 5954 SUSPECT DATA 1470 ANFO 2.35 15.00 -. 9165 POS5IBLY TWO

1470 PMEX 0.30 11.00 6865 HOLE 15 TES18 1470 ANFÔ 1.88 -12.50 9020 HOLE #\ TEST9 1470 PMEX 1.50 12.40 8948 HOlE #2 TEST'" 1470 ANFO 1. 88 \1.90 9198 HOLE #3 TEST' , 1470 PME'X 0.30 11.90 8332 HOLE 13 TEST? 1470 PMEX 0.30 10.40 7292 HOlE #5 TES1:' \470 PMEX 0.30 10.40 8011 HOLE #5 TES T 5

1470 PMEX 0.30 44.20 5.40 14.40 9073 HOLE 84 rES TI

1470 PMEX 0.30 48.80 5.20 9.90 4706 HOlE #7 TEST4

1470 PME X 0.40 45.80 2.22 1470 PMEX 0.30 44.80 20.70

1604- ANFO 1. 92 61.00 5.41 1604 ANFO 1. 92 61.00 4.84 1604 ANFO \.92 9.20 35.58 1604 ANFO 1. 92 70.20 3.44 1604 ANFO 1. 92 6\ .00 4.00

2700 PMEX 0.40 4.60 21.24 2700 PMEX 0.20 3.10 14.56 2700 PME X 0.20 9.80 6.00 2700 PMEX 0.20 7.60 10.-42 2700 PMEX 0.20 7.60 11.00 2700 PMEX 0.20 9.80 8.08 2700 PME X 0.40 15.30 4.66 597.00 21 -

2700 PMEX 0.40 18.20 Il.22 597.40 59 2700 PMEX 0.40 21.40 6.S6 597.40 53 2700 PMEX 0.40 21.40 Il • J0 2700 PME X 0.40 3.10 29.58 596.60 99 2700 PMEX" 0.40 4.60 Il.38 . 596.60 91 2700 PMEX 0.40 6.10 Il.02 596.60 90 2700 PME X 0.40 9.20 4.12 597.00 89 2700 PMEX 0.40 12.20 7.46 597.40 113 2700 Pf1EX 0.40 24.40 2.80 597.40 69 27.00 PMEX O.40 27.50 3.84 597.0O 108

'2700 Pf1EX 0.40 27.50 3.64 597.O0 107

164

Page 174: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

c.

8.4 SUMMÂRY AND CONCLUSIONS OP BLAST PRACTURING STUDIES

~ The studies, reported on in this chapter, allow a number of \ conclusions to be made as to the extent of fractures existing

around a stope, and the extent of fractures induced by confined

blasts. Modification of rock mass properties by blast fracturing

is also quantified.

stope pillars generally have an intact core, while, a fractured

zone borders any excavation openings. The fracture zone in the , . l670'W A pillar waS measured to extend a distance equal to 18

-percent of the width of the excavation opening. Fàctors such as

stress level, excavation shape and pre-existing discontinuities

will also affect the depth of the fractured zone. Fractures

caused by excavation damage or destress blasting forro

predominately alqng pre-existing discontinuities. Destress

blasting should not be conducted in the fractured zone,

surrounding a pillar, as it may result in cratering, as has been

experienced at other mines, Chapter 4.

The CRLM andesite was observed to be highly variable in

mineralogical composition and fabric, however, its mechanical

properties were found to be relatively uniforme

Blasting AN/FO in confined 45 mm holes resulted in detectable

changes in the modulus of deformation, midway between blast holes

wh en blast holes were spa?ed up to 1.6 m apart. Modulus of

deformation was measured in situ with a Probex-1 bore hole

dilatometer. Fractures, detected by impression packing, were

observed when blast holes were spaced up to 1.4 m apart. The

trial blasts indicated that fracture frequency 'decreases with

increasing blast hole spacing, modulus of deformation decreases

with decreasing blast hole spacing, and modulus of deformation

decreases with increasing fracture frequency. The relationship

.between these parameters is approximately linear.

165

Page 175: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

'.

o

Damage beyond a line drawn perpendicular to the end of the

explosive, charge is minimal in confined blasts. This ia

attributed to a reduction in stress supurposition beyond the end "'­of the charged hole.

In order for destressing to be successful, fracturing must oceur

across the plane connecting adjacent blast holes. A wide blast

hole spacing may result in an unfractured zone between holes.

The unfractured zone wi~l attract stress and may result in a rock

burst at a latter time. In CRLM andesite the maximum hole

spacing should be 1.6 m for 45 mm blast holes using AN/FO.

Greater fracturing and rock mass modification would be achieved

with a tighter spacing.

Neither the microseismic system nor an Instantel-DS377 blast

vibration monitor were capable of determiqing peak particle

velocity characteristics of the blast wave for analysis of

fracturation. Analysis of fracturation requires knowledge of r

blast wave behavior in the non elastic response zone surrounding

the blast hol:" A peak\particle velocity attenuation curve for

sefsmic wave~ traveling beyond the blast fractured zone was

determined, however the supporting data is hi~hly scattered.

166 1

Page 176: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

, DIBTRIBS BLAST DISIGN

Destress blasting has been shown to be an effective tool for the

control of rockbursts. However, without proper design, a

destress blast may be ineffective or result in other~ (

potentially more severe, problems. This chapter presents

guidelines for de stress blast design based upon the research and

literature review conducted for this project. The case being considered is de stress blasting .in andesitic rock at Campbell Red . '

~ake Mine (CRLM). with appropriate modification the design

criteria are applicable for confined blast fracturi~ in any

situation. o ,

The design of blast patterns for destressing has generally

proceeded in a haphazard fashion with very little scientific

investigation. Further more, this author has observed that many

modifications are made to existing destress blast design for no

apparent technical reason. Blasting patterns ~eveloped at other mines, are often used as a starting design. A trial and error

approach, as is often used for optimizing production blasts

designs, is not suitable because of the small number of destress

blasts norrnally conducted. The large nurnber of influential

variab~es, and the difficulty of assessing thern adds to the

problem of destress blast design optimization.

Destress blast optimization i5 considered achieved when the

modulus of deforrnation is redu'ced to the desired level by

interconnecting fractures between blast holes. . Fradturing

should not be so extensive as to impede subsequept mining,

although this criteria may not be possible if the desired modulus or strength reduction is great .

167

Page 177: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

o

o

9.1 BLAS~ BOLE SPACINr AND GBOMBTRY ./

Blast hole spacing, and to a certain extent, hole diameter are

the most important variables in d~stress blast design. Hole spacing can be adjusted to achieve the desired degree of fracturing regardless of other parameters and in situ conditions, The appropriate blast hole spacing can be determined by powder factor calculation, peak particle velocity analysis or experimental investigation. AlI these methods are derived from

observations of fracturation under a given set of conditions:

Should the in situ environment change, the spacing selection may

no longer be valide

Destress blasting of stope pillars at CRLM has used powder factors between 0.2 and 0.7 kg/m3 . A review of these blasts

reveals that there were no significant differences in damage

caused by using different powder factors. The amount of energy

imparted to the rock is dependent upon \the chemical energy of the

explosive, the hole diameter and the rock - explosive

interaction. Powder factor considers the energy imparted to the rock as being dependent upon the weight of explosive only.

Destressing usually involves blasting only a single row of holes along the length 9f a pillar. The width of the pl1lar, which la

used in the powder factor calculation, la of no relevance.

powder factor ia a simplistic blast descriptor and is not

suitable for destress blast design.

Peak particle velocity (PPV) is related to strain which in turn

ls" related to fracture extension. The PPV requited to lnduce

fractures can be calculated theoreti~ally after determining the

strain at- whic~ the rock fractures. A PPV of 1000 mm/a ia <

generally accepted as sufficient to create fr~cturea in competent

rock. An estimate of PPV is given by the equation

;168

Page 178: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

' , ,

()

.,

(

, '

.'

.... ' ,

" wO'~ ) -n PPV = k R / ,.

where k = <J:round transmission constant n = empirical constant based on geology and explosive .. R = radial distance w = weight of explosive detonated

\t 'Knowing values for the k and n, the above equation can be rewor~ed to determine the desired weight of explosive to achieve the peak particle'velocity requlred for fracture extension to a -

specified distance. Values of k and n determined béyond the imediate vicinity of the blast hole cannot be used as they do not ~eflect the high stress conditions under which fracturing 'occurs.

~ , Determination of fracturing by peak particle velocity is not recommended beca~se of the inaccurate explosive energy considerations (based on weight of explosiv~J and the difficulty of.determining the transmission constant in the vicinity of the blast hole where fracturing is taking place.

),

In situhmeqsurement of fractures and the corresponding reduction in modulus between blast holes provides the most accurate inforrnat~on,for destress blast design. Figures 9-1 and 9-2 present results from in situ tests conducted i~ CRLM andesite.

·'Best fit curve~ were determined to be linear, these are also plotted on the' Figures. 'The equation Of the curve relating

" distance between -blast holes to fracture intensity at the mid point is:

frqcture density = 117 - 83.3'* (distance betweep blast holes)

The equation rel~ing dilatometer modulus of deforrnation to fracturation is:

modulus of defo.rrnation = 64.2 - 0.5 \ (fracture density~

~he corresponding corre~ation coefficients are 0.62 and 0.59.' Although low/~hey are not unreasonable when dealing with

169

Page 179: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

0 l

,--

0

" .

,

Figure 9-1: Relatlon.hlp aetween Fracture Den.lt, and ala.t Ho" Spa01n1

f r El 80 c t u r

60. e

d e -n 8

40 1 t Y

20

" p e 0 r

0 0.2 ; 0.4 0.6 0.8 1 1.2 1.4 '.6 m distance between blast holes m

Figure 8-2: Relatlon.hlp aetw.en Deformation ~odulu. and Fracture Oenelty

• 1'00

m 80 0 d u 1 _80 u e

40

-G p

20 a

0 0 20 40 60 80

, fracture denslty "par m

,1' i

170

Page 180: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

(

c

/

/

blasting studies where scatter is typically very high •

These studies were conducted in the unfavorable situation

requiring fracture extension perpendicular to the major ',-

discontinuity direction, as su ch they are considered

conservative. The reduction in modulus of deformation and reduction in~strength required for a successful destress blast is

beèt determined by numerical modeling. •

It may ai first seem logic~l to use a small number of large

diameter holes to achieve the desired fr-acturation. Larger holes

result in quicker detonation velocities, and for the most part, \

greater detonation and 'explosive pressures. Although not we,l,!

defined, there is a limit beyond which increasing the detonation

energy released from a single hole results in no increase in the

the extension ef fractures; the only result is an in crea se in

the crushed zone about the blast hole periphery. Further work is

required to determine the optimum hale diameter. The area about

thedblast hale has the greatest concentration of fractures 1

running in aIl directions. This zone causes the greatest

alteration ta rock mass properties. The use of small holes is

desirable in t:hat they result in a greater number of these areas

of high fracture concentration.

Provided that a sufficient number of fractures are created, then

the width of the fracture zone is not important, however, the

orientàtion of the fractures is consequential. Fractures created

perpendicular to the principal stress direction do little ta

reduce the modulus or strength. Fractures created at angles

other than 0 or 90 degrees to the principal stress direction have

much greater effect. Madel studies have indicated that fractures

at angles of 60 or 30 ~egrees ta the direction of principal

stress cause the greatest reduction in modulus of deformation and

uniaxial strength. An arrangement of two rows of holes offset 50

that connecting lines form a 60 degree angle with the direction

of principal stress should result in the gre~test decrease in '\

modulus of deformation.

('

171

Page 181: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

9.2 EXPLOSIVE SELECTION

The effectiveness of any explosi~ depends on both the explosive

properties and properties of the ~aterial belng blasted. Ground

response to various explosives can be estimated by numerical

means or investigated by in situ studies. In situ studies

provide the rnost reliable assessment of which explosives are

suitable for destress blasting.

w The total energy content of ~n explosive is readily calculated by .

thermodynarnic analysis, however, these calculations assume the

explosive to'behave in an ideal manor, and do not consider th~

influence of confinement and hole diameter. More important is

the rate of energy release and the energy division between.

detonation pressure, explosive pressure and wasted energy. It

should be noted that the energy division i5 a function of many

parameters including density and hole diarneter. The rate of

energy release can be significantly changed by small changes in

borehole diameter and density, although the degree of change ls

different for different explosives.

It is desired that the explosive induce a minimum number of

fractures extending at least to the midpoint between blast holes.

Fracturation must be extensive enough to reduce the modulus of

deformation, and rock strength, to the desired values. Sorne

researchers, e.g. Favreaù (1986), consider the detonation

pressure to be insignificant in creating fractures in a confined

environment with no free face. This means the explosive gas

pressure must exceed the rock or discontinuity strength as weIl

as the in situ stress across the desired fracture plane. This

author believes the explosive gas pressure is responsible for

sorne fracture creation through wedge action, however, with in

situ .stresses exceeding 50 MPa it seems unlikely that it is the

main mechanism .

The detonation pressure is of a much greater intensity, although

of shorter duration, than the explosive gas pressure. The

172

Page 182: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

~'

~

c

«

J

explosive pressure generates radial and tanqential seismic waves

,with compressive and tensile components. In a high in situ stress regime, where significant stress superposition may

occur,blasting may lead to compressive failure out to a

considerable distance from the-blast hole. Tensile failure is

unlikely to occur except in the immediate vicinity of the

borehole and in the direction perpendicular to the desired'

fracture direction. This discussion has assumed the area to be

fractured is already highly stressed. In preconditioning a high

stress environment may not exist; in this case the tensile

component and action of the gas pressure would be much more

significant.

The greatest detonation pressure occurs with the most violent

detonation reaction. A measure of detonation reaction is the

velocity of detonation. High velocity explosives are therefore

preferred over lower velocity types. There may be a limit beyJnd

which increasing the detonation pressure results in an increased

cru~Q~d-4Qne, but no increase in fracture extension at greater

distances. "~ore work is required to investigate the shock wave

phenomena in rock, and this particular problem.

Factors that must also be considered in explosive selection are

availability, cost and safety. It may be cheaper and more

, practical to use a regular production explosive than to use a

specialty product. Additional drilling costs required, in order

~o achieve the desired fracturing with production explosives, may

be less than the cost of buying and stocking specialty products.

It mu}t be considered that no savings will be realized if the

blast is not successful because of poor explosive selection, or ~

~ for any other reason.

9.3 OTHER BLAST DESIGN CONSIDERATIONS

There are a number of additional factors influencing blast

results. ~hes~ include the location of the holes in relation

173

Page 183: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

l

to the ore zone, the detonatibn sequence, mode of detonation, and

the use of stemming. r

1 Little information is available on the effect of destrè~

blasting on and off vein. Karwoski et al. (1979) conducted pre­

conditioning blasts on and off vein, they concluded that there

was no difference in terms of subsequent ground control problems.

Their computer modeling suggested that on-vein blasting is

preferential. The advantage of off-vein blasting is that

subsequent mining need not be conducted in fractured ground, nor

is there a risk of mining into residual explosives. Further

numerical and in situ investigations are required before any

conclusions can be drawn.

The greatest benefits of blast hale interaction are achieved when

\ detonation Gccurs simultaneously with the passage of the

C) detonation pressure wave from the adjacent hole. This can be

achieved by delay timing or using pressure sensitive caps. The

safety hazard of pressure sensltive caps makes them undesirable.

High quality mili-second delay caps must be used as conventional ~

caps have a high time scatter. Blasting simultaneously, using \

conventional cap, with equal delay may provide good results, the

delay scatter will result in some constructive stress interaction.

When blasting on-vein it is important to ensure complete

detonation to eliminate the possibility of mining into residual . explosives. Multiple initiation points are recommended. Holes

should not be traced with detonating cord as this may initiate

undesired deflagration. Adequate priming should be used to

ensure the explosive reaches the maximum detonation velocity as

early as possible.

The contribution of the explosive gas pressure ta destress

blasting i5 not weIl defined. Any contribution should be

enhanced by maintaining the gas pressure for as long a time

period as possible. stemming should be used for this purpose.

The length of stemming should be the entire uncharged collar.

174

Page 184: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

The length of hole not charged depends upon the condition oÏ the

rock. A highly fractured zone surrounding the collar will lead

to large craters if an insufficient uncharged l~ngth is not l~ft.

9.4 NUMERICAL MODELING FOR DESTRESS BLAST DESIGN

~

Nurnerical rnodeling, run on comp~ters, are use fui for analysis of

a number of aspects related ta destress blast design. The

accuracy of the results of numerical simulations must always be

consideredi this is dependent upon the sophistication of the cgde

and the accuracy of the input parameters. Any model must be

calibrated by back analysis, and shouid be verified against in

situ conditions whcnever po',~Jble. Nuwericai modellng for

fracture prediction is not yet ta astate where it can reliably

model the effects of in situ stress and pre-existing

discontinuities. It is hoped that more sophisticated models will

become availâble in the near future .

Numerical modeling of stresses is a weIl accepted and proven

technique. The method is extremely usefai for determining what

rnodulus and strength reductions are required for a particular

destress blast ta be successful. The models can also be used to

10cate areas requiring destressing, what aerial extent should be

fractured, and the potential for creating new areas of

instability as a result of stress transfer .

175

Page 185: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

J

10 CONCLUSIONS

The technique of destress blasting for rockburst control has been utilized with apparent success at Campbell Red Lake Mine.

However, the mine recognizes that the need exists to imp~ove the understanding of rock mass response to blasting~ upon which

dastress blast design and optimization are based. Without proper consideration and design, a destress blast may be ineffective, or

result in other, potentially more severe problems. In situ

studies and a literature review, aimed to provide a better

understanding of rock fracturing and develop destress blast

design criteria were carried out during the course of this

project. Conclusions of the study are presented in this chapter.

'J . The nature of the fracturing ptoduced by explosives i8 dependent

upon bath explosive and ~ock properties. The literature review

and experimental studies suggest that the most influential

parameters are discontinuity strength, discontinuity orientation,

existing in si tu stress, and degree of confinement. "

" Given a blast hole size and explosive type, the blast hole

spacing can be adjusted to achieve any degree of fracturing , between blast holes. The extent of fractures will be

gradational; the most extensive fracturing being nearest to the

blast holes. The extent of fracturing ~t the midpoint between

blast hales was found ta be linearly, inverse-proportional ta the

blast hale spacing.

Fracturing alters rock mass properties. For the purpose of

destressing it is des~abie to reduce po~h the rock mass modulus of deformation and st'rengthi this is achieved by introducing

fractures in to the rock. The modulus of deformation was found

to be linearly inverse-proportional to fracture frequency. It

was observed that peak, unconfined compressive strength decreased

with increasing fracture frequèncy, however, insufficient data

was collected to allow for any statistical relations~ip to be

determined. .. \ l

176 (

Page 186: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

(~

(~

(

Blast fracturing studies were conducted in Campbell Red Lake Mine andesite, using ammonium nitrate and fuel oil explosive detanated

in 33 and 45 mm diameter holes. Rock mass canditioning,

resulting from fracturing, was measured at the midpaint between

adjacent 45 mm holes. Using an impression packer, fractures were

abserved where blast hole spacing was a maximum of 1.4 m. Using

a borehole dilatometer, a reduction in modulus of deformatian was

abserved where blast hale spacing was a maximum af 1.6 ID.

Blast fractur.1pg, araund single 33 mm diameter blast hales, was • ..1

obverved to extend upwards of 0.5 m along pre-existing

discontinuities. A radial, heavily fractured zone extended

between 10 and 100 mm about the blast holes. A crushed zoner

which was independent of pre-existing discontinuities extended

between 2 and 30 mm about the blast hales. AlI fracturing, with

the exception of the immediate blast hole periphery, occurred

alang pre-existinq discontinuities.

Blast in~uced fractures were observed to not extend significantly

past a line drawn perpendicular to the end of the explosive

charge. This ls a result af a decrease in constructive stress

interaction. In an area close ta the cent pr of an explasi ve

charge, the cumulative effects of energy being released along the

entire length af the charge must be cansidered.

Studies in narrow veln stopes at CRLM provided no evidence that

single hale destressing is an effective means af rockburst

control, however, it is possible that benificial changes, beyond

the detection af the monitoring equipment, occur. Destressing

was conducted using a single, 4.5 m long, destress hole in a 3 m

breast round. Stope ,monitoring was conducted with a microseismic

system, e~tensometer, vibrating wire stress gauges, visual

inspections and fracture mapping. The study revealed no

significant differences, relating to a reduction in rockburst

potential, between breast rounds with a destress hole and those

without. It should be noted that, as a safety precaution, CRLM

continues te use this destressing methed.

177

Page 187: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

.. <,

J

Destress blast design requires the knowledge of what level of

modulus and strength reduction is required, what amount of

fracturing will cause the desired alteration to the rock mass

properti~s, and what blast design will achieve the required

fracturing. The level of modulus and strength reduction,

required for the destress blast to be successful is best

deterrnined by numerical modeling. Nurnerical rnodeling ls also

useful for determining what area of ground requires destressing,

and if the destressing is likely to cause unstable conditions in

adjacent areas. The relationship between modulus of deformation

and fracturing is dependent upon rock type, in situ stress and

fracture orientation. The rnost accurate method of determining

the forrn of this relationship is by in situ studies. The blast

design required to aehieve a specifie amount of fraeturing can be

deterrnined by predictive methods or in situ studies. Predictive

methods, either numerieal or ernpirical, are at present not v~ry

accurate for frac tu ring caused by destress blast~ng; this is a

result of insufficient consideration of in situ stress, pre­

existing discontinuities and blast confinement. The relationship

between blast design and fracturing is best determined by in situ

studies.

A number of additional factors pertaining to destress blast

design were reviewed, including; explosive selection, blast hale

geometry and initiation sequence. An explosive with high

velocity of de~onation is most desirable.

the greatest detonation and gas pressures.

These explosives have

There is a limit

beyond Vhich increasing the explosive energy imparted to the rock

is no longer beneficial. Beyond this limit the energy serves

only to increase the crushed zone. The most desirable blast hole

configuration, for reducing modulus and strength, is two

staggered lines where a line drawn between holes makes a 60

degree angle with the normal of the hale lines. Explosive

initiation sequence should be designed te enhance stress, wave ~

interaction. This carrbe achieved using pressure sensitive caps

or with low delay scatter caps.

178

~

Page 188: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

, t ; ~" , _

APPENDIX 1 Thin Section Descriptions

f /' , /

c , .

"

,

179 :.-,

Page 189: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

)

o

This appendix contains selected thin section descriptions for both. the ~ 6~4 'EW stope crown pillar and 1470 drift. The sampl,es are ~dent~f~ed by a sample number followed by the location. Samples from the 1604 EW stope are listed first, they have a sample number suffixed with either a 400 or 401. Samples from the 1470 drift are prefixed with a 4. Thin section photographs

-are located at the end of the appendix.

- -- 1

2-400: located 4.1 m from hole collar, 4.1 m from 1604 destress holes. ~he core was logged as an&esite, blue-medium

Mode: biotite 1-2 % calcite 15-20 % chlorite 30-35 % fine matrix 30 % muscovite opaques 8-10 % quartz 5 % plagioclase

The absence of calcite is expected since the sample is not in an area of hydrothermal solution pa$sage. One small quartz-calcite vein does cut the section. Coarse, anhedral q~artz crystals are present, these may be relie or possibly vein rnaterial. The absence of biotite and high percentage of chlorite indicate extensive low grade metamorphism of the ferro-magnesium mineraIs. No fracturing or other evidence of stress is observed in this sample.

3-400: located 8.2 rn from collar, between 1604 destress holes. The core was logged as andesit~, blue-medium.

Mode: biotite 5-6 % Calcite )25-30 % chlorite 25-30 % fine matrix 40-45 % muscovite 8-9 % opaques 5-6 %

l quartz plagioclase

A number of small veins eut this sample: the veins contain quartz, calcite, mica and plagioclase. The presence of biotite -indicates less low-grade metamorphism than sample 2-400. The high calcite percent age indicates close proxirnity to hydrothermal conduits. No fracturing or other evidence of stress is observed in this sample.

1 4-400: located 12.2 m from collar, 4 rn from 1604 destress noles. Sample i5 above pillar separating 1604 A and B veins. The core was, logged as andesite, green-medium, with tourmaline faults.

180

Page 190: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

'C

(

Theo sample is divided into three distinct zones; a zone of coarse grained qua~tz, calcite and plagioclase, an zone of fine matrix,

. and a zone of coarse quartz with associated unknown porphyroblasts. The unknown porphyroblasts arè prismatic with

· polysynthetic twining, extinction is parallel; 1-2 degrees.

5-401: located 12.5 m from collar, between 1604 destress holes. The core was logged as blue-medium andesite with smooth fIat joints and parallel foliation 75 degrees to core axis.

Mode: biotite 10-15 % ~ calcite 30-35 %

chlorite 10-12 % fine matrix 35-40 % muscovite 5-6 % opaques 5-6 % quartz plagioclase q!V

A number of quartz-calcite-plagioclase veins cross eut the sample. The chlorite was often found as anhedral blades enclosed in calcite. Calcite and plagioclase trystals contained intracrystal microfractures. The fractures were anastimosing and in sorne instances the fractures fol'owed a curved path. The fractures were limited to isolated areas of the sample. Quartz associated with fractured crystals showed no fracturing, but did exhibit undulose extinction. Undulose extinction indicates high stress although it is usually thought to be produced by the in situ stress field, not blasting. The sample contained_ deformed mica cry~t~s and cUFved twin lameli in the calcite, both result from high in situ stresses.

4-30: located 0.3 m from collar, midway between 3 m spaced destress holes. The core was logged as andesitè with quartz­calcite infilled joints parallel to cleavage, 6 cm spacing. The core was fractured along infilled joints. The core is quite competent, RQD is 95 percent and core recovery is 1~ percent.

Mode: biotite 10-15 % ( calcite 30-35 % chlorite 25-30 % fine matrix 30-35 % muscovite 1-2 %

181

Page 191: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

opaques 4-5 % quartz plagioclase

, The sample contains many calcite flasers and augens in a chlorite matrix,. as weIl as sorne chlorite augens in a calcite' matrix. Fo+iation is strongly developed, and ls post contact metamorphism (hydrothermal intrusion), as indicated by the flasers and augens. ' See Figure A)-l.

4-120: located 1.2 m from collar, between 1.3 ~'spaced destress holes. The core was logged as andesite, blue-medium, with quartz-calcite filled joints, mostly paraI leI to cleavage, 4 cm spacing. Fracturing was along cleavage in rnost cases,-a few new fractures ran 015/85. RQD of core was a, core recovery was 90 percent.

Mode: biotite 6-7 % calcite 35-40 % chlorite 20-25 % fine matrix 20-25 % muscovite 1-2 % opaques 3-4 % quartz plagioclase

D

Good foliation development, weak augen development.< .

4-160: located 1:6 m from collar, between ).3 rn spaced destress holes. Logged as andesite, blue-medium. The sectiun bf core contained 0~005-0.1~m dises, indicating high stresses. Core RQD was a, core recover~ 94 percent.

Mode: biotite 6-7 % calcite 35-40 %

'chlorite 20-25 % fine matrix 20-25 % muscovite 1-2 % opaques 3-4 % quartz

1 plagioclase

i

The sample was very fine grained comparéd to others,. If stress induced features were created it is un1ikely,that they would be visible. The foliation is strongly developed and üefined b~ chlorite ribbons. WeIl developed flasers and augens ~re a1so present. Biotite also i5 in ribbon forme See Figure Al-2.'

4-190: located 1.9 m from co1lar, between 1.3 rn spaced destress hales. Core logged as andesite, blue-medium, the core wàs" broken up, maximum size 0.05 m. Sorne infilled joints were evident . Core ROD was 0,' percent recovery was not determ,ined.

, ,

182 \

'" ...

Page 192: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

j

~ . )

o li '

Mode: biotite 10-12 % calcite 40-45 %

.' chlorite 20-25 % fine matrix 20-25 % muscovite 2-3 % opaques 3-4 % quartz pla~oclase

Weakly developed foliation.

~~210: located 2.1 m from collar, between 1.3 m spaced destress holes. Logged as andesite, core was fractured along clea~age,

':"

strike 130, dip 80 west. The fractures were not infilled. \ Quartz calcite infilled.jo~nts parallel cleavage, 3 cm spacing, \ minor infilled joints 100/80, 5 cm spacing. Core ROD was 0, recovery was 100 percent.

Mode: biotite 10-12 % calcite 40-45 % . ~ chlorite 15-20 % fine matrix 20-25 %

'f

muscovite 2-3 % "- opaques 3-4 %

quartz plagioclase

Strongly developed foliation, chlorite ribbons. Very fine grained, similar to 4-160. Sorne coarse grained calcite aggregates, weakly developed auge~ and flasers.

~ , r-4-284: located 2.84 m from collar, between 1.3 m spaced dlstress holes. Core logged as andesite, dark blue. Quartz calcite infilled joints parallel. cleavage, 8 cm spacing, mi~or infilled joints at 040/30, lb cm spacing. The core fracturèd perpendicular to the core axis. The 'core also was subject to high drill wear indicating a softer rock. ROD and CQre recovery were both 100 percent.

Mode:

.

biot~e 12-15 % calcite 40-45 % chlorite 16-20 % fine matrix 20-25 % muscovite 1-2 % opaques 4-5- % quartz plagioclase

The sample contained cross c~tting_calcite veins. Broken veins form augens. Sorne chlorite ribbons are present, foliation not strong. Fine grained, similar to 4-160 and 4-210. The hiqh biotite content accounts for the darker color and possibly tor the observed drill wear. ~

183

Page 193: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

(

,J

(

" •

1 r ,. ,

4-325: locat'ed 3.25 m from collar, between 1.3 m spaced <1estress holes. Con! logqed as àndesite, blue-medium. Vis.ible cleavage strike 130, dip 80 west: No fractures. Quartz calcite filled joints paraI leI cleavage, 6 cm spa~ing. The sample·is from- a location remote from theodestress blasts. Core RQD and ~ecovery were both 100 percent.

Mode: biotite 5-6 % . calcite 40-45 % • chlorite 29-25 % fine matrix 20-25 % muscovite 4-5 % opaques 3-4 %

~ quartz , plagioclase ----....:.

One large quartz-calcite .vein cuts the sample. Muscovite i5 developed as porphroblasts crystaîs within the fine matrix. Good foliation. The muscovite cross cuts the foliation, indicating a second'metamorphic'event. See Figure Al-3. ~

\

..

1 184

Page 194: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

'. 1

, .

'r

Figure-Al-l: Sample 4-30, Chloritic Augen in Calcite Matrix.

1 .-

• Figure Al-2: Sample 4-160, Strong FOliation, Chlorite Ribbons,

Well Developed Augens

185

Page 195: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

••

c

(

)

Figure Al-3: Sample 4~5, Muscovite Porphryoblast \

186

Page 196: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

. \ • Î

0-

APPENDIX 2 Bor. Hoi. Impr ••• lon Mapa

. ,0

.. , -

"

p "'l;..,.'

o t

187

Page 197: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

ho •• 1

c colla" , \ --1-

f -\

) r ..,.,-

'-../

'-

/'-..... - ) /

10 cm ) '---'

"

, ,

- ! , !

1

/ t 1 ,

.- 1 /,

/ ,

1

~

t 1 ,

J c i ,. to.

"1

Page 198: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

1

hol.2

• coll~u -'

• t •

6 1~~" ~'

"

S:·

L '\

l,

l,

'1. l"'.

, - .>.

10 cm 1..-.-1

"

..

l

o to.

189

.J.J,

Page 199: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

\' ,.., '- J'

" " ~ hol. 3 .

"'. I~

• L ~

. "

. .... .

,

"

\ •

\

Page 200: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

-. Aï ----:------::------:---~-----:--~----_._._-_ .. __ .... -'f _,'

\ ' "

, ~ .

,/

\ ~ , /

1 (

1

\-

o

: __ --+-__ ........ t~.

[ .

o ,(

191

Page 201: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

,\

hol ...

coUa'

c --

-,

<

'/

,

10 cm -

( \

L -'\

Page 202: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

'-". 1

• r ~.

.....J-...

/ -- ~

'-

--... ~

- -

1

,~

" \ ...

-D

\.., \-~

-Ar '\ r

J ....

0 -

t

, .

to

. 193

- . .... ..-J

Page 203: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

..

c' •

APPENDIX 3 INSTANTEL DS3700 Output

...

194

Page 204: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

D

\ '

o

_:. .... ~1_,.~._ .;, .... ':sMI-

~.; j: :=. cCI ........ dL,:"g SC"RCf

- ~ 4'",:8 l FUEl i=:';;'"(1 T lnf

-1--

Î

INSTANTEl OS-3n

.l)':;)

ll'll" Cl.!Ll-EN "CGIU llNluE-RSITT l,pa DR. 1 • n/5

Ge ophOllQ

13 e7 • n/, J Socond.'

:zs ,"'v,

m .. .. .. Xl .. n ., ...

.\----~------~--------~~--~~~ . ,

115

..

........... " ...... _ .... '.' .~.,

• ........ _ ....... ~ ....... .

l

'1

.--l-.~~ _~ __ , •• l .. _._ ~

CHECK TR~NSVERS~L TE$' R:~_ ;_1 F T.~C or -20. Fu·~a OV'2, ;", '

Ir ,g9.,.d go

euk Se!

LOn9. Ch. "'

9)' 1 ~ ~8

Fob :6, ~~

13.1007 Se:

9."1301' PI ' 42.15 P.-/_--

GIPRbQ~o , • U!II!S /nc'" • .:;. 4, 7j] "J~/ ..

112 08 8 P •• • 0'1110 p,

etH Ueleeit ••• ;

Tf .n ..... ' ••

U.rlIC.'

\.on, 1 t "d.

.'98t> 11~90 .11152 4.211 .411'4 HI. 49

.118 28.'4

."!h •• , ..

~.~.i. c:

: .. :. .... , ,.. 'i.e:.

.l''!''.',,,, ., .. '" i.:

}r:",,""'", , • .l'.c

..

\ ..

J

Page 205: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

(.

(

(

UJ'ZUNCZS

Amadei, B., 1985. "The Influen.ce of Rock Mass Fractuf.ing on the Measurement of D~ormability by Borehole Expansion Tests", Proc. 26th U.S. Symp. on Rock Mech., Rapid City. pp. ~59-867.

Arjang B., 1986. "Field and Stress Determination at Campbell Red Lake Mine, Ontario", CANMET M&ET/MRL 86-57 TR.

Atchison T.C., Duval W.L, Pug'liese J.M., 1963. "Effect of Decoupling on Explosive Generated Strain Pulses in Rock Il •

USBM RI 6333 Blake W., 1984. "Rock precondition±n2L as a Seismic Control

Measure". Pr9c. 1st Int. Congo 9n ~ckbursts and Seismicity in Mines, SAIMM, Johannesburg. pp. 225-230.

Blake W., 1982. "Microseismic Applications for Mining: A Practical Guide". USBM Contract Report. No. J02J.5002, 1982.

Blake W., 1982b. "Destressing To Control Rockbursts Il. undergroupd~ Mining Methods Handbook, chap. 7, W.A. Hustrulid (ed), Society of Mining Engineers AIMM, New York, pp. 1535-1539.

Blake W., 1981. "Preconditioning an Entire Stope Block For Rock Burst Controi ll

• USBM OFR-51-81. f Blake W., 1972 IIRockbur~t Mechanics", Quarterly, Colorado School

of Mines. Vol. 67, No. 1. Blake W., 1972b. '''Oestressing Test at the Galena 1:1.iz:1e, Wallace,

Idaho". Trans. SME-AIME, Vol. 252. pp. 294-299~ Brady B., Brown E., 1985. "Rock Mechanics For Underground Mining"

George Allen and Unwin, London. ; Board M., Fairhurst d., 1983."Rockburst Control Through

Destressing: A Case Example". Proc. Rockburst Prediction And Control, IMM, London. pp. 91-102.

Butkovich T.,R., Hearst J.,R., 1976. "Prediction and Determination of Explosive Induced Fracture", Proc 2nd Conf. ~ on Expl. and Blast. Tech. pp 301-340

Church R., 1985. "Campbell Red Lake Mine Mining Brief: Geology". Report presented to Ground Control and Emergency Preparedness Committee.

Cook M.A., Cook V.O., Clay R.B., Keyes R.T., Udy L.L., 1963. "Behavior of Rock, During Blasting". Trans. 5MB. pp 383-392.

Cook J.F., Bruce O., 1983. "Rockburst at Macassa Mine and the Kirkland Lake Mining Area". Proc.' Rockburst Prediction and Control, IMM, London. pp. 81-90.

Crouch S., 1974. IIAnalysis of Rockbursts In Cut an~Fill Stopes". Trans. AIME, Vol. 256. pp. 298-303

Dickhout M.,1963. "Ground Control at the Creighton Mine of INCa Il , Proc. Cano Rock Mech. Symp., McGi11 Univ. pp. 121-139.

Du Pont, 1977 "Blasters' Handbook". E.I. du Pont de Nemours and Co., Wilmington, U.S.A.

Duva'l W.I., Stephenson D.E., 1965. "Seismic Energy Available From Rockbursts and Underground Explosions". Trans. SME. pp. 235-240.

Electrolab "250MP Microseismic System Specifications and Operation". Electro-Lab, Spokane, Washington.

Favreau R.F.", 1969. "Generation of Strain Waves in Rock by an ExplosioI1" in a Spherical Cavity". Jour. Geoph. Research. Vol. 74, No. 17. pp. 4267-4280.

196

Page 206: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

o

\

( •

~ntzos O., 1980. "Destressing Practices in Ontario Mines". Memorandum, Ontario Ministry of Labour.

Hanson D. 1 Quesnel W. 1 ~ong R., 1981. "Destressing A Rockburst -Prone Crown Pillar - Macassa Mine" CANMET MRL 87- (TR) t

Harling J., 1965. Lakeshore Mine InternaI Report. <)

Hardy, R., 1982. "Applications of Aeoustic Emission Technique to Rock and Rock Structures: A State-of-the-Art Review". Acoustic gmissions in Geotechnical Engineering Practice. American

. Society for Testing and Materiala. pp. 4-92. Hedley D., 1987. "Rockburst Mechanies". CANMET MRL 87- (TR) Hedley D., Neumann M., Makueh A., Blake W., 1985. "Rockbursts at

Campbell Red Lake Mine"', CANMET, MRP/MRL 85 (OP). Hedley D., Bharti S., Blake W., 1984. "Fault-Slip Roekburst -at

the Falconbridge Mine". C~MET, MRP/MRL 85-115 (OP, J). Hill F., Plewman R.,1957. "Destressing: A Means of Ameliorating

Rockburst Conditions. Part II: Irnplementing Destressing with a Discussion on the Results so far Obtained". Jour. South African Inst. Min. Met. Vol. 56, 1957. pp. 270-289. ~

Hoek, E., Brown E.T., 1980, "Underground Excavations Jn Rock", IMM, London. .

Hustrulid A., Hustrulid W., 1972, "Development of a Borehole Deviee to determine the Modulu~ of Rigidity of Coal Measures Rocks", USBM Final Contract Report No. H010705.

Hustrulid W.A., Schrauf T.W., 1979, "Borehole Modulus Measurements with the CSM Celi in Swedish Granite", Proc. 20th U.S. Symp. on Rock Meeh., Austin. pp. 509-515.

ISRM, 1987 (International Society of Rock Mechanics) "Suggested Methods for Deformability Determination using a Flexible Dilatometer", Int. J. Rock Mech. Min. Sei. & Geomeeh Abst., Pergarnon Press. pp. 125-134.

Issaacson E., 1962. "Rock Pressure in Mines". Mining Publications Ltd., London.

Jaeger J.C., Cook N.G. W., 1976, "Fundamentals of Rock Mechanies", Chapman and Hall, London.

Jianyun M., Jiayou L., 1987. "The Phenomena, Prediction And Control Of Rockbursts In China". Proe. 6th Int. Cong. On Rock Mech., Montreal. AA Balkema, Boston. pp. 1135-1140.

~a shiro J.K., Harding R.C., Johannesson P., Korbin G.E.,

987, "Comparison of Modulus ValueS obtained frorn Dilatometer esting with Downhole Seisrnic Surveys and Unconfined

Compressive Tests at McKays Point Dam Site, California", Proc. 28th·U.S. Symp. on Rock Mech.,", Tuscon. AA Balkema, BostoI). pp.. 211-222.

Karwoski W., McLaughlin W., Blake W., 1979. "Rock preconditioning to Prevent Rockbursts - Report on a Field Demonstration", USBM RI8318.

Koopmans, R., Hughes, R.W., 1984, "An Automat~d and Comp~terized Dilatometer System to Measure Deformation ModuluB of Rock", Western States Mining Expo, Nevada.

Koopmans R., Hughes R., 1985. "Determination of Near Field Excavation Disturbance in Crystalline Rock", 9th Int. Symp. on Scientific Disturbance in Crystalline Rock, Sweden.

Kutter H., Fairhurst C., 1971. "On the Fracture Proces8 in Blasting", Int. J. Rock Mech. Min. Sci., Vol. 8. pp. 181-201.

, 197 ,

Page 207: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

c

J

c:

,.

Kutter H., Fairhurst C., 1968. "The Role of Stress Wave and Gas Pressure in Presplitting". cProc . 9 Rock Mech. Sym., Colarado. AIME, New York.~ pp. 265-284.

Ladanyi, B., 1975. "Quasi Static Expansion of a Cylindrical Cavity in Rock", Proc. 3rd Sym., Eng. Application of Sol id Mech., Toronto. pp. 219-240.

Ladanyi, B., Gill, D.E., 1981. "Determination of Creep Parameters of Rock Salt by Means of a Borehole Dilatometer", Proc. 1st Conf. on Mech. Behavior of Salt, Penn. State Univ., Trans Tech. Pub., Germany. pp. 267-273. )

Lama R.D., 1972. "The Use of ifestressing Techniques in the Maintenance of Roadways Under High Pressure". Proc. Int. Sym on Underground Openings, Lucerne. pp. 177-181.

Lama R.D., 1974. "The Uniaxial Compressive Strength of Jointed Rocks". Prof. L. MuLLer Festschrift Inst. Soil Mech. and Rock Mech, Univ. Karlsruhe, Karlsruhe.

Lama R.D., Vutukyri V.S., 1978. "Hanbook on Mechanical Properties of Rocks: vol. ii, iii, iv". Trans Tech Pub., Germany.

Le Bel G.R., Quesnel W.J.F., Glover W.,1987."An Analysis of Rockburst Evénts During Sinking of Macassa 13 Shaft". Proc. CIM AGM, Toronto.

Leighton F.,~984. "Microseismic ~onitoring and Warning of RQckbursts". Proc. lst Int Congo on Rockbursts and Seismicity in Mines, SAIMM, Johannesburg. pp.287-296.

Leighton F., 19B2a. "Dynamic Methods of rock Structure Analysis". Underground Mining Methods HanQ~, chap. 7, W.A. Hustrulid (ed.), Society of Mi~ing Engineers, AIME, N.Y. pp . 1523 -15 3 4 .

Leighton F.,1982b. "Case History of a Major Rockburst" USBM RI Love A.E.H., 1927. "A Treatise on the Mathematical Theory of

Elasticity". Cambridge, Cambridge University Press. Makuch A., Neumann M., Hedley D., Blake W.i 1987. "Practical

Applications of Pillar Destressing at Campbell Red Lake Mine", Presented at Bth Underground Oper. Conf., CIM.

Makuch A., 1986. "Field Stress M~asurements". InternaI Report Campbell Red Lake Mine

McGarr A., 1984. "Sorne Applications of Seismic Source Mechanism Studies to Assessing Underground Hazard". Proc. Rockburst and Seismicity, SAIMM, Johannesburg. pp. 199-208.

Mohanty B' f 1988. Personal Communication. Mohanty B' f 1982. "Characteristic Crack Patterns Close to an

Exploding Charge". 14th Cdn. Rock Mech. Sym., CIM Special Vol. 30. pp. 32-36.

Moruzi G., pasieka A., 1964. "Evaluation of a Blasting Technique for Destressing", Proc. 6th U.S. Symp. Rock Mech., Univ. Missouri. pp. 185-204.

Morrison R., 1961. "A Report on Rockburst Potentiality at Dickenson Mines Ltd. and Campbell Red Lake Mines Ltd.", Consultants Report.

Neumann M., Hedley O., Blake W., Makuch A., 1987. "An Instrumen­ted Destressing Blast in the 1604 EW Stope at Campbell Red Lake Mines", CANMET, Ontario/lndustry/Canada Rockburst Research Project.

198

Page 208: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

o

,

Neumann M., Makuch T.,l985. "Case Study of Microseiamic Monitoring of the 'F-2' Zone at Campbell Red Lake Mines Limited". Proc. Microseismic Monitoring in Canadian Mines, CANMET., MRP/MRL 85-23.

Neumann M.,1986. Personal communication. Obert L., Duvall W. 1 1957. "Microseismic Methods of Determinihg

the Stability of Underground Openings". USBM Bul. 573. 0bert L., f)uvall W., 1945. "Microseismic Méthod of Predict ing' Rock

Failure in Underground Mining: Part I~~ Laboratory Experiments". USBM. RI3803. ~

Oliver P., Wiles T., MacDonald ~., 0'Donne1l D., 1987. "Rockburst Control Measures At INCO's Creighton Mine. Presented at CIH AGM, Toronto.

Olsen J.J., Willard R.J., Fogelson D.E., Hjelmstad K.E., 1973. "Rock Damage from Small Charge Blasting in Granite", USBl1 R1 7751.

Ontario Government, ,1986. "Improving Ground Stability and Mine Rescue: The Report of the Provincial Enquirey into Ground ,~ Control and Emergency Prepardness In Ontario Mines". Ontario Government Puplication.

Quesnel W.J.F., Hong R., 1986. "The Use Of Rock Mass Conditioning: Destressing For The Safe Recovery Of Rockburst Prone'Pillars - Macassa Mine". Ground Control Seminar,

'Hailibury School Of Mines. Quesnel W.J.F., 1987. Personel communication. Rigg D. M., 1980. "Relationships Between Structure and Gold

~ Mineralization in Campbell Red Lake and Dickenson Mines, Red take District, Ontario". M.Sc. Thesis, Queen's University.

Robson W., 1946. "Rockburst Incidence, Research and Control Measures at Lake Shore Mines Ltd.". Trans. CIM., Vol. XLIX. pp. 347-375.

Rocha M., Silveira A., Peres-Rodrigues F., Silvero A., Ferreira A., 1970, "Characterization of the Deformability of Rock Masses by Dilatometer Tests", Proc. 2nd ISRM Cong., Belgrade. pp. 2-32.

Roctest, 1986. "Probex-1 Dilatometer Instruction Manual", Roctest Ltd., Montreal.

Roux A., Leeman E., Denkhause H., 1957. "Destressing: a Means Of Ameliorating Rockburst Conditions. Part 1: The Concept of Destressing and the Results Obtained From Its Application". Journal South African Inst. Min. Met, Vol. 56. pp. 241-267.

Salomon M., 1984. "Energy Considerations in Rock Mechanics: Fundamental Results". J. SAIMM, vol 84, No. 8. pp. 233-246.

Salomom M.,1983. "Rockburst Hazard and the Fight for its Alleviation in South African Gold Mines". Proc. Rockburst Predit ion and Control, IMM, London. pp. 11-36.

Scoble M.J., Cùllen M., Makuch A., 1987, "Experimental Studies of Factors Relating to Destress Blasting", Proc. 28th U.S. Symp. Rock Mech., Tuscon. AA Balkema, Bos.ton. pp. 901-908.

Scoble M.J., Cullen M., Carter M., Barclay R.,1988. "In Situ Deformability and Fracturation Studies Using The Probex-l Borehole Dilatometer". Proc. Conf. on Applied Rock Eng., New Castle. IMM, London. pp. 203-212.

199

Page 209: cdigitool.library.mcgill.ca/thesisfile61685.pdf · 1102 ,EB Stope Pillar Destress 1902 E Stope Pillar Destress Long Section Al Zone 1604'EW Stope Pillar Instrumentation 1604 EW Stope

c -1

8 Siskind D.E., Fumanti R.R., 1974. "Blast-Produced Fractures in

Lithonia Granite", USBM R1 7901. Siskind D.E., Steckley R.C., OIson J.J., 1973. "Fracturing in the

Zone Around a Blasthole, White Pine, Mich." USBM. RI 7753. Slade A., 1968. "Sorne Practical Aspects of Rock Mechanics in

Falconbridge's Sudbury Operations". CIM Bul., Vol. 61, No. 678. pp. 1161-1165.

Timoshenko S.P., Goodier J.N., 1970. "Theory of Elasticity". Wiley, New York.

Vutukuri V.S., Lama R.D., Saluja S.S.,' 1974."Mechanical Properties of Rocks: vol. i". Trans Tech Pub., Germany.

Walsh J.B.,1965a. "The Effects on the Unixial Elastic . Compresssion of Rqcks". Journal Geophys. Res., Vol 70, No. 2. pp. 399-411.

W~lsh J.B.,1965b. "The Effect of Cracks in Rocks on Poisson's Ratio". Journal Geophys. Res., Vol 70, No. 2. pp. 381-389.

Walsh J. B., 1965c. "The Effect of Cracks on the Compressibility of Rock" . Journal Geophys. Res., Vol 70, No. 20. pp. 5249-5257.

j Willan J., Scoble M., Pakalnis V,'

1985. "Destressing Practice in Rockburst Prone Ground", Proc. 4th Conf. Ground Control in Mining, W. Virginia Univ.

Young P.,1986. "Seismic Propagation in Rock Masses: Applications for Acoustic Ernissions/Microseismic Monitoring". 4th Conf. Acoustic Emissions/Microseismic Activity in Geologic Structures and Materials. Trans Tech Pub., Germany.

/

...

i

200 ,