© 2002 hulett & associates, llc will your project overrun? do a cost risk analysis presented by...

30
© 2002 Hulett & Associates, LLC Will YOUR Project Overrun? Do a Cost Risk Analysis Presented by David T. Hulett, Ph.D. Hulett & Associates, LLC Los Angeles, CA 90049 (310) 476-7699 / [email protected]

Upload: rosamund-owens

Post on 24-Dec-2015

219 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: © 2002 Hulett & Associates, LLC Will YOUR Project Overrun? Do a Cost Risk Analysis Presented by David T. Hulett, Ph.D. Hulett & Associates, LLC Los Angeles,

© 2002 Hulett & Associates,

LLC

Will YOUR Project Overrun?Do a Cost Risk Analysis

Presented by

David T. Hulett, Ph.D.

Hulett & Associates, LLCLos Angeles, CA 90049

(310) 476-7699 / [email protected]

Page 2: © 2002 Hulett & Associates, LLC Will YOUR Project Overrun? Do a Cost Risk Analysis Presented by David T. Hulett, Ph.D. Hulett & Associates, LLC Los Angeles,

© 2002 Hulett & Associates,

LLC

Cost Overrun Risk

• Estimate at Completion (EAC)

• Sources of Overrun Risk

• Steps in Cost Risk Analysis

• Collecting Risk Analysis Data

Page 3: © 2002 Hulett & Associates, LLC Will YOUR Project Overrun? Do a Cost Risk Analysis Presented by David T. Hulett, Ph.D. Hulett & Associates, LLC Los Angeles,

© 2002 Hulett & Associates,

LLC

Estimate at Completion (EAC)

• Basis of estimates -- at the cost element level– Historical data– Engineering estimates– Bids from contractors and suppliers– Labor productivity rates– Pricing Experience– Parametric– Industry database

• Each of these produces a single-point estimate for the cost elements

Page 4: © 2002 Hulett & Associates, LLC Will YOUR Project Overrun? Do a Cost Risk Analysis Presented by David T. Hulett, Ph.D. Hulett & Associates, LLC Los Angeles,

© 2002 Hulett & Associates,

LLC

Traditional Project Estimate At Completion (EAC) Methodology• We usually:

– Estimate the cost by cost breakdown element– Add up the elements’ costs– Present the total as the total project cost– Cross our fingers

• But, is this what the project “will cost?”– Only if everything goes according to plan

Page 5: © 2002 Hulett & Associates, LLC Will YOUR Project Overrun? Do a Cost Risk Analysis Presented by David T. Hulett, Ph.D. Hulett & Associates, LLC Los Angeles,

© 2002 Hulett & Associates,

LLC

Real Projects

Do projects usually go according to plan? NO!

Do projects sometimes overrun their budgets? YES!

Do we always have the right contingency? NO!

Page 6: © 2002 Hulett & Associates, LLC Will YOUR Project Overrun? Do a Cost Risk Analysis Presented by David T. Hulett, Ph.D. Hulett & Associates, LLC Los Angeles,

© 2002 Hulett & Associates,

LLC

Is the Traditional EAC Accurate?

• The traditional single-point EAC is precise– It can be audited for summation accuracy

• But it may be wrong– Cost estimates are often overrun

Traditional cost estimates are “precisely wrong”

Page 7: © 2002 Hulett & Associates, LLC Will YOUR Project Overrun? Do a Cost Risk Analysis Presented by David T. Hulett, Ph.D. Hulett & Associates, LLC Los Angeles,

© 2002 Hulett & Associates,

LLC

Why Conduct a Cost Risk Analysis?

• We do not know what the estimate means -- e.g. – How much risk is there of overrun?– What is the overrun exposure?– How does it relate to ultimate cost at completion?

Cost Risk Analysis answers these questions

Page 8: © 2002 Hulett & Associates, LLC Will YOUR Project Overrun? Do a Cost Risk Analysis Presented by David T. Hulett, Ph.D. Hulett & Associates, LLC Los Angeles,

© 2002 Hulett & Associates,

LLC

Cost Risk Analysis -- A New Opportunity

• Opportunity to improve the accuracy of the estimate

We can determine the contingency needed

to reduce the risk to an acceptable level

• Opportunity to improve our risk management

We can determine where the risk is in a complex project

Page 9: © 2002 Hulett & Associates, LLC Will YOUR Project Overrun? Do a Cost Risk Analysis Presented by David T. Hulett, Ph.D. Hulett & Associates, LLC Los Angeles,

© 2002 Hulett & Associates,

LLC

Steps in a Cost Risk Analysis

• Develop cost analysis model (e.g. WBS)• Identify risky cost elements• Determine the two dimensions of risk by element

• Likelihood of occurring and impact if it does

• Explore correlation between elements of cost• Insert model and data into simulation software• Simulate the model• Calculate risk of overrun, contingencies• Prioritize risky cost elements for risk management

Page 10: © 2002 Hulett & Associates, LLC Will YOUR Project Overrun? Do a Cost Risk Analysis Presented by David T. Hulett, Ph.D. Hulett & Associates, LLC Los Angeles,

© 2002 Hulett & Associates,

LLC

Example -- Risk Analysis Model of Project Cost

• What is the likelihood this project will cost $29,200,000?

Cost Category Value for EAC($000)

Project Design 1,500Equipment 5,000Foundation, Structure 7,000Piping, Elect. HVAC 1,000Labor 8,700Indirects 6,000

Total Project Cost 29,200

Project Cost Risk Analysis

Page 11: © 2002 Hulett & Associates, LLC Will YOUR Project Overrun? Do a Cost Risk Analysis Presented by David T. Hulett, Ph.D. Hulett & Associates, LLC Los Angeles,

© 2002 Hulett & Associates,

LLC

Interview to Quantify Cost Risk by Element• Identify “experts” in the project area

– Probably area or team leaders– May have estimated the cost and have considered risk

• Sometimes experts are biased– Project Manager who is committed– Subcontractor looking for relief

• Interview them for risk information– Optimistic extreme scenario– Pessimistic extreme possible costs– Most likely possible cost

Page 12: © 2002 Hulett & Associates, LLC Will YOUR Project Overrun? Do a Cost Risk Analysis Presented by David T. Hulett, Ph.D. Hulett & Associates, LLC Los Angeles,

© 2002 Hulett & Associates,

LLC

Pessimistic Scenario -- High Range

• Worst -case scenario -- the 99% case– What happens if everything goes wrong?– Include failure and need to do it over if possible– Can several things go wrong simultaneously?

• Criterion -- at least a 1% chance of occurring– Has it ever happened? At least once?– Are you uncomfortable with this specification?– Not yet unbelievable never-never land

Page 13: © 2002 Hulett & Associates, LLC Will YOUR Project Overrun? Do a Cost Risk Analysis Presented by David T. Hulett, Ph.D. Hulett & Associates, LLC Los Angeles,

© 2002 Hulett & Associates,

LLC

Optimistic Scenario -- Low Range

• Lower costs than included in the estimate– Estimates usually include contingency for some things going wrong “most

likely

• Optimistic scenario -- the 1% case– Even expected problems do not materialize– “Murphy” takes a holiday– Equipment works fine– Labor productivity is uncommonly high– Material, equipment comes in as advertised

Page 14: © 2002 Hulett & Associates, LLC Will YOUR Project Overrun? Do a Cost Risk Analysis Presented by David T. Hulett, Ph.D. Hulett & Associates, LLC Los Angeles,

© 2002 Hulett & Associates,

LLC

Most Likely Scenario

• Sometimes the EAC is not the “most likely” cost• Too Low to:

– Get the contract (contractor) or please the boss– Keep the bankers and other stakeholders happy

• Too High to:– Provide cushion– Include contingency in estimate -- not bare bones

• Explore this possibility before ending the interview

Page 15: © 2002 Hulett & Associates, LLC Will YOUR Project Overrun? Do a Cost Risk Analysis Presented by David T. Hulett, Ph.D. Hulett & Associates, LLC Los Angeles,

© 2002 Hulett & Associates,

LLC

Triangular Probability Distribution

– Relative likelihood determined by the height of the triangle– Impact determined by X-Axis– Easy to use, commonly used

Relative Likelihood of Occurring

Possible Element Costs

Low Most Likely High

ThreatsOpportunities

Page 16: © 2002 Hulett & Associates, LLC Will YOUR Project Overrun? Do a Cost Risk Analysis Presented by David T. Hulett, Ph.D. Hulett & Associates, LLC Los Angeles,

© 2002 Hulett & Associates,

LLC

Some Analysis Usingthe Triangular Distribution

Average (expected) cost = (low + most likely + high) / 3(70 + 100 + 180) / 3 = 350 / 3 = 116.7

RelativeLikelihoodofOccurring

Possible Element Costs

70 100 180

Expected Cost = 116.7

Page 17: © 2002 Hulett & Associates, LLC Will YOUR Project Overrun? Do a Cost Risk Analysis Presented by David T. Hulett, Ph.D. Hulett & Associates, LLC Los Angeles,

© 2002 Hulett & Associates,

LLC

Uniform Probability Distributions

• Uniform distribution, little information early in project, cannot determine “most likely” cost

Expected cost(high + low)/2

RelativeLikelihoodofOccurring

Possible Element Costs

Page 18: © 2002 Hulett & Associates, LLC Will YOUR Project Overrun? Do a Cost Risk Analysis Presented by David T. Hulett, Ph.D. Hulett & Associates, LLC Los Angeles,

© 2002 Hulett & Associates,

LLC

Beta Distribution

• Beta distribution– Flexible, hard to use (shape parameters)– Expected cost approximated as (H - L) / 6

0.00 24.17 48.33 72.50 96.67

Beta

0.00 8.67 17.33 26.00 34.67

Beta

Page 19: © 2002 Hulett & Associates, LLC Will YOUR Project Overrun? Do a Cost Risk Analysis Presented by David T. Hulett, Ph.D. Hulett & Associates, LLC Los Angeles,

© 2002 Hulett & Associates,

LLC

Normal Distribution

• Normal distribution– Symmetrical– Many automatically think of the Normal distribution

70.00 85.00 100.00 115.00 130.00

Normal

Page 20: © 2002 Hulett & Associates, LLC Will YOUR Project Overrun? Do a Cost Risk Analysis Presented by David T. Hulett, Ph.D. Hulett & Associates, LLC Los Angeles,

© 2002 Hulett & Associates,

LLC

Construction Project Interview and Display Low and High Ranges

Cost Category Value for EAC Low Most Likely High($000) ($000)

Project Design 1,500 1,200 1,500 2,000Equipment 5,000 4,500 5,000 6,000Foundation, Structure 7,000 6,200 7,200 8,600Piping, Elect. HVAC 1,000 800 1,000 1,600Labor 8,700 4,500 5,000 5,900Indirects 6,000 5,000 6,000 6,700

Total Project Cost 29,200

Project Cost Risk Analysis

Page 21: © 2002 Hulett & Associates, LLC Will YOUR Project Overrun? Do a Cost Risk Analysis Presented by David T. Hulett, Ph.D. Hulett & Associates, LLC Los Angeles,

© 2002 Hulett & Associates,

LLC

Assumptions and Results Highlighted

Cost Category Value for EAC Low High

Project Design 1,500 1,200 2,000Equipment 5,000 4,500 6,000Foundation, Structure 7,000 6,200 8,600Piping, Elect. HVAC 1,000 800 1,600Labor 8,700 7,500 12,500Indirects 6,000 5,400 6,700

Total Project Cost 29,200

Project Cost Risk Analysis

($000)

Assumptions -- Input Distributions

Result Distribution

Page 22: © 2002 Hulett & Associates, LLC Will YOUR Project Overrun? Do a Cost Risk Analysis Presented by David T. Hulett, Ph.D. Hulett & Associates, LLC Los Angeles,

© 2002 Hulett & Associates,

LLC

The EAC is Not the Average Cost. It is Not Even the Most Likely Cost!

Frequency Chart

Mean = 30,733.000

.008

.015

.023

.030

0

37.75

75.5

113.2

151

27,000 29,250 31,500 33,750 36,000

5,000 Trials 0 Outliers

Forecast: Total Project Cost

EAC = $29,200

Average Cost is Not the EAC

Page 23: © 2002 Hulett & Associates, LLC Will YOUR Project Overrun? Do a Cost Risk Analysis Presented by David T. Hulett, Ph.D. Hulett & Associates, LLC Los Angeles,

© 2002 Hulett & Associates,

LLC

Cumulative Distribution

Cumulative Chart

Certainty is 10.24% from -Infinity to 29,200

Mean = 30,733.000

.250

.500

.750

1.000

0

5000

27,000 29,250 31,500 33,750 36,000

5,000 Trials 0 Outliers

Forecast: Total Project Cost

$29,200 is only 10% likely

Page 24: © 2002 Hulett & Associates, LLC Will YOUR Project Overrun? Do a Cost Risk Analysis Presented by David T. Hulett, Ph.D. Hulett & Associates, LLC Los Angeles,

© 2002 Hulett & Associates,

LLC

Cumulative Distribution Table

EAC of $29,200is just over 10%

Need a contingency of $2,615 for 80%

likelihood

Forecast:Total Project CostPercentile Value

0% 27,29610% 29,17220% 29,62030% 29,98940% 30,30550% 30,63360% 31,01070% 31,37780% 31,81590% 32,461100% 35,143

Page 25: © 2002 Hulett & Associates, LLC Will YOUR Project Overrun? Do a Cost Risk Analysis Presented by David T. Hulett, Ph.D. Hulett & Associates, LLC Los Angeles,

© 2002 Hulett & Associates,

LLC

Contingency Percentages on Baseline Project Cost Estimate

Percentile Value Contingency0% 27,296 -7%10% 29,172 0%20% 29,620 1%30% 29,989 3%40% 30,305 4%50% 30,633 5%60% 31,010 6%70% 31,377 7%80% 31,815 9%90% 32,461 11%100% 35,143 20%

Forecast: Total Project Cost

Page 26: © 2002 Hulett & Associates, LLC Will YOUR Project Overrun? Do a Cost Risk Analysis Presented by David T. Hulett, Ph.D. Hulett & Associates, LLC Los Angeles,

© 2002 Hulett & Associates,

LLC

How do You Identify the Most Risky Cost Elements? • Which cost elements contribute most to overrun risk?• One measure of total project risk

– Difference between the EAC and the average cost from the simulation

• The Method of Moments (MOM) rule is that:The average total project cost is the sum of the

average cost from the elements’ distributions• For the triangular distribution (only) remember:

Average = (low + most likely + high) / 3

Page 27: © 2002 Hulett & Associates, LLC Will YOUR Project Overrun? Do a Cost Risk Analysis Presented by David T. Hulett, Ph.D. Hulett & Associates, LLC Los Angeles,

© 2002 Hulett & Associates,

LLC

Which Elements Contribute Most to the Difference?

Frequency Chart

Mean = 30,733.000

.007

.013

.020

.026

0

33

66

99

132

24,000 27,500 31,000 34,500 38,000

5,000 Trials 0 Outliers

Forecast: Total Project Cost

Explain the Contingency at the Mean

Page 28: © 2002 Hulett & Associates, LLC Will YOUR Project Overrun? Do a Cost Risk Analysis Presented by David T. Hulett, Ph.D. Hulett & Associates, LLC Los Angeles,

© 2002 Hulett & Associates,

LLC

Compute the Average Project EAC Assuming Triangular Distribution

Cost Category Value for EAC Low High AverageProject Design 1,500 1,200 2,000 1,567Equipment 5,000 4,500 6,000 5,167Foundation, Structure 7,000 6,200 8,600 7,267Piping, Elect. HVAC 1,000 800 1,600 1,133Labor 8,700 7,500 12,500 9,567Indirects 6,000 5,400 6,700 6,033

Total Project Cost 29,200 30,733

Project Cost Risk Analysis

Page 29: © 2002 Hulett & Associates, LLC Will YOUR Project Overrun? Do a Cost Risk Analysis Presented by David T. Hulett, Ph.D. Hulett & Associates, LLC Los Angeles,

© 2002 Hulett & Associates,

LLC

Calculate the (Average - EAC) and Sort on It to Help Focus Risk Management

Cost Category Value for EAC Average Average - EACLabor 8,700 9,567 867Foundation, Structure 7,000 7,267 267Equipment 5,000 5,167 167Piping, Elect. HVAC 1,000 1,133 133Project Design 1,500 1,567 67Indirects 6,000 6,033 33

Total Project Cost 29,200 30,733 1,533

Identifying High-Risk Elements Using Method of Moments

Page 30: © 2002 Hulett & Associates, LLC Will YOUR Project Overrun? Do a Cost Risk Analysis Presented by David T. Hulett, Ph.D. Hulett & Associates, LLC Los Angeles,

© 2002 Hulett & Associates,

LLC

Will YOUR Project Overrun?Do a Cost Risk Analysis -- Summary

• The EAC is not even the most likely cost• A cost risk analysis can improve the accuracy of the estimate,

provide a contingency amount, and identify the high-risk elements

• Correlation is important in developing cost risk estimates• Data collection is the main part of the risk analysis

– There are several steps that have proved effective– It is important to recognize several important biases