005.01 contract performance - nabholz construction · 005.01 contract performance page 1 of 34...

34
005.01 Contract Performance Page 1 of 34 Recommended Use of This Section 005.01 Rev 2 February 2017 The purpose of Section 005.01 is to provide Subcontractor with the necessary forms and information to assist Subcontractor in the administration of subcontract agreements. 1. Review the procedures outlined in this manual with applicable “Action” personnel in Subcontractor’s company. Ensure that all concerned understand and comply with the requirements. Any questions should be directed to the designated Construction Manager’s Contact, as identified in Section 1.04 of the Construction Manager’s Manual. 2. Revisions to this CM Manual and additional information will be issued periodically and should be inserted in the applicable sections. 3. Several sections contain references to manuals and other Project documents not contained within. These can be inspected at the Construction Manager’s office or copies obtained upon request. 4. The contents of this CM Manual do not supersede or change the requirements of the Contract Documents or Subcontract between Construction Manager and Subcontractor. NOTE: As stated above, this CM Manual is provided for Subcontractor’s use in facilitating the Work and is not intended to either alter or compromise the terms and provisions of the Subcontract between Construction Manager and Subcontractor.

Upload: others

Post on 09-Oct-2020

7 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 005.01 Contract Performance - Nabholz Construction · 005.01 Contract Performance Page 1 of 34 Recommended Use of This Section 005.01 Rev 2 – February 2017 The purpose of Section

005.01 Contract Performance

Page 1 of 34 Recommended Use of This Section 005.01

Rev 2 – February 2017

The purpose of Section 005.01 is to provide Subcontractor with the necessary forms and information to assist Subcontractor in the administration of subcontract agreements.

1. Review the procedures outlined in this manual with applicable “Action” personnel in Subcontractor’s company. Ensure that all concerned understand and comply with the requirements. Any questions should be directed to the designated Construction Manager’s Contact, as identified in Section 1.04 of the Construction Manager’s Manual.

2. Revisions to this CM Manual and additional information will be issued periodically and should be inserted in the applicable sections.

3. Several sections contain references to manuals and other Project documents not contained within. These can be inspected at the Construction Manager’s office or copies obtained upon request.

4. The contents of this CM Manual do not supersede or change the requirements of the Contract Documents or Subcontract between Construction Manager and Subcontractor.

NOTE: As stated above, this CM Manual is provided for Subcontractor’s use in facilitating the Work and is not intended to either alter or compromise the terms and provisions of the Subcontract between Construction Manager and Subcontractor.

Page 2: 005.01 Contract Performance - Nabholz Construction · 005.01 Contract Performance Page 1 of 34 Recommended Use of This Section 005.01 Rev 2 – February 2017 The purpose of Section

005.02 Definition of Terms

Page 2 of 34 Definition of Terms 005.02

Rev 2 – February 2017

1. The term “Subcontractor” means the trade-contractor holding a contract with Nabholz Construction Services.

2. The term “Construction Manager” means “Nabholz Construction Services”

3. The terms “you”, “his”, etc., as used in this manual refer to Subcontractor.

4. The term “day” means calendar day unless specifically noted otherwise.

5. The term “provide” means to furnish and install.

6. The term “contract” as used in this manual refers to the Subcontract agreement between Nabholz Construction and Subcontractor unless specifically noted otherwise.

7. The term “Owner” refers to OWNER NAME

8. The term “Architect” refers to ARCHITECT NAME.

Page 3: 005.01 Contract Performance - Nabholz Construction · 005.01 Contract Performance Page 1 of 34 Recommended Use of This Section 005.01 Rev 2 – February 2017 The purpose of Section

005.03 Insurance Requirements for Subcontractors

Page 3 of 34 Insurance Requirements for Subcontractors 005.03

Rev 1 – January 2013

CONSTRUCTION MANAGER WILL NOT AUTHORIZE PAYMENTS TO SUBCONTRACTOR UNLESS SUBCONTRACTOR’S CURRENT CERTIFICATE OF INSURANCE AND CERTIFICATE OF SAFETY AND HEALTH IS ON FILE AND APPROVED.

FOLLOWING ARE MINIMAL INSURANCE REQUIREMENTS FOR SUBCONTRACTORS. WHERE THESE GENERAL REQUIREMENTS ARE LESS THAN THE REQUIREMENTS SET BY THE CONTRACT DOCUMENTS, THE CONTRACT DOCUMENTS WILL PREVAIL. 1. Commercial General Liability, with limits, no less than: Each occurrence: $2,000,000 General aggregate (project specific): $2,000,000 Products/completed operations aggregate: $2,000,000

Policy shall contain no less than the following: a. Policy form ISO CG 00 01, or equivalent. b. Coverage shall be primary and non-contributory. c. ISO standard severability of interest’s clause and separation of insureds clause. d. ISO CG 24 04 10 93, or equivalent endorsement form waiving subrogation. e. ISO CG 20 10 and CG 20 37, or equivalent endorsement(s) for ongoing and

completed operations. Vicarious liability exclusion is not acceptable. 2. Automobile Liability Insurance, no less than:

Combined single limit: $2,000,000 Policy shall contain no less than the following:

a. Coverage for “any auto,” including owned, non-owned, and hired motor vehicles. b. Additional insured endorsement or omnibus clause. c. Waiver of subrogation endorsement.

3. Workers’ Compensation and Employer’s Liability Insurance, with limits no less than:

Workers’ Compensation: Per Statute EL Each Accident $1,000,000 EL Disease – EA Employee $1,000,000 EL Disease – Policy Limit $1,000,000

Workers’ compensation policy shall contain a waiver of subrogation endorsement, if permitted by law.

4. Umbrella Liability or Excess Liability Insurance OPTIONAL Limits may be used to obtain the required limits for commercial general liability, automobile liability, and employer’s liability insurance. Such insurance shall follow-form with any primary policies.

Page 4: 005.01 Contract Performance - Nabholz Construction · 005.01 Contract Performance Page 1 of 34 Recommended Use of This Section 005.01 Rev 2 – February 2017 The purpose of Section

005.03 Insurance Requirements for Subcontractors

Page 4 of 34 Insurance Requirements for Subcontractors 005.03

Rev 1 – January 2013

5. Additional Insured Entities. Each insurance policy (except for workers’ compensation and employer’s liability insurance) shall include the following entities as additional insured parties:

a. Nabholz Construction Corporation, its parent and affiliated companies, employees, agents, and principals; and

b. Owner and others as required by Prime Contract.

6. Subcontractor must maintain evidence of insurance through the warranty period.

7. The certificate of insurance must include a 30 day written cancellation notice. 8. All coverage must be on an “occurrence” basis rather than “claims made.”

9. See sample certificate of insurance at Nabholz.com/trade-contractors

Page 5: 005.01 Contract Performance - Nabholz Construction · 005.01 Contract Performance Page 1 of 34 Recommended Use of This Section 005.01 Rev 2 – February 2017 The purpose of Section

005.04 Quality Control

Page 5 of 34 Quality Control 005.04

Rev 2 – February 2017

Construction Manager’s policy is to provide the maximum quality of construction and materials within the guidelines of the specifications and plans under Contract.

1. All Work to be performed by experienced workmen per industry trade association standards, applicable codes and standard practice.

2. The Subcontractor and/or Supplier shall inspect all new materials, equipment, etc., as it arrives to Project for compliance with Contract requirements, shop drawings, and visual quality. Inspection during fabrication should be considered.

3. Subcontractor or Supplier shall ensure that correct engineering data is being followed for layout.

4. Subcontractor or Supplier shall discuss with Construction Manager early if items can be ordered with guaranteed dimensions or must wait for field measurements.

5. Subcontractor shall provide a competent person who shall be responsible for performing quality control responsibilities on the Project.

6. Each Subcontractor to provide a list of inspections required for the Scope of Work and maintain documentation of inspection logs.

7. A checklist shall be submitted by each Subcontractor containing a list of all inspections required to complete the Work for the trade package as specified.

8. Before Work begins, request and attend a pre-installation conference to be attended by Construction Manager, Architect, and Owner at their discretion.

9. Subcontractor is required to send a foreman, project manager or owner to all weekly Project site coordination meetings pertaining to the Scope of Work and/or as required by Project Superintendent. Employees attending meetings must have the authority to make commitments on subcontractor’s resources (manpower, equipment, tools, etc.) to maintain Project Schedule or meet milestone dates.

10. Subcontractor shall exercise all required precautions necessary to protect all buildings and other construction on property adjacent to that under Scope of Work.

11. Subcontractor is responsible for Subcontractor’s own quality control. Subcontractor shall conform to all manufacturers’ requirements. All Work shall be performed in a good workmanship-like manner, acceptable to Construction Manager at all times.

12. Subcontractor shall check all surfaces prior to the application of Work. Subcontractor shall notify Construction Manager of any discovered deficiency or faulty workmanship, in order for Construction Manager to remedy the surface. If Subcontractor does not follow this process prior to the installation of Work, Subcontractor agrees to be responsible for the repair or replacement of Work, as necessary, at no extra charge to Construction Manager.

13. Punch list items must be addressed within a reasonable amount of time to ensure continuation of Work by other trades. Failure to complete Punch List items may be sufficient cause to withhold a portion of monthly payments.

Page 6: 005.01 Contract Performance - Nabholz Construction · 005.01 Contract Performance Page 1 of 34 Recommended Use of This Section 005.01 Rev 2 – February 2017 The purpose of Section

005.04 Quality Control

Page 6 of 34 Quality Control 005.04

Rev 2 – February 2017

Construction Manager is committed to constructing a high quality project for Owner. To that end, Subcontractors shall actively participate in Construction Manager’s Quality Management System (QMS) Program. For all work associated with Subcontractor’s trade contract, the Work shall be performed in strict accordance with the Contract Documents and with Construction Manager’s Quality Management System Requirements. The Nabholz Quality Management System Program is hereby incorporated into Subcontractor’s contract and is available for inspection or replication upon request.

Page 7: 005.01 Contract Performance - Nabholz Construction · 005.01 Contract Performance Page 1 of 34 Recommended Use of This Section 005.01 Rev 2 – February 2017 The purpose of Section

005.05 Contract Scope and Price, and Change Orders

Page 7 of 34 Contract Scope and Price, and Change Orders 005.05

Rev 2 – February 2017

1. Contract Scope and Price.

Definition: This is the Subcontract price for the Scope of Work associated with Subcontractor or Supplier’s base Subcontract amount.

a. Subcontract is written with the intent to be a "turn-key" agreement, inclusive of all anticipated costs, fees, and taxes. All labor, installation, materials, insurance, equipment, and clean-up of any debris left by workers will be included in the Subcontract price for a complete operation.

b. Subcontract prices are good for duration of Subcontract.

c. Subcontract is based on a lump sum amount. Field measuring quantities for final payment is not an option. Units and quantities may be indicated for scope determination only.

d. Subcontractor agrees to provide all required mobilizations necessary to complete Scope of Work.

e. Subcontractor agrees that Subcontract is inclusive of all incidentals required for a complete Scope of Work and all functional intent that may or may not be expressly implied within the plans and specifications.

2. Change Order Work.

Definition: Any Work that changes the Scope of Work of the Subcontractor or Supplier’s base Subcontract. This classification includes both “changes in Scope of Work” and “extra Work” as further defined in paragraphs “3” and “5” below.

a. Instructions for change order Work of any type will be in writing. All change order Work must be approved in writing by Construction Manager’s Project Manager before Work commences. Any extra work performed by Subcontractor without prior written instructions will be at Subcontractor’s expense.

b. Subcontractor shall ensure that field supervisors are familiar with the extent and Scope of Work so that Work is not delayed due to arguments regarding contractual responsibilities.

3. Change in Scope of Work.

Definition: A change initiated by the Owner that adds to or deletes from Subcontractor’s Scope of Work or affects the time required for the performance of the Work.

a. Construction Manager will review all changes initiated by the Owner or Architect, assign a control number, and forward the information to applicable Subcontractors. Subcontractors must reply in writing within five (5) days.

b. If Subcontractor submits a quotation (Change Proposal) and does not specify that a time extension is required, Subcontractor will be required to complete the Work, including the Work required by the change, as indicated by the most current Project Schedule.

c. Reference each change only by Construction Manager’s control number. Change Proposals that do not have the proper control number listed or a complete cost and breakdown will be returned to Subcontractor with no action taken.

Page 8: 005.01 Contract Performance - Nabholz Construction · 005.01 Contract Performance Page 1 of 34 Recommended Use of This Section 005.01 Rev 2 – February 2017 The purpose of Section

005.05 Contract Scope and Price, and Change Orders

Page 8 of 34 Contract Scope and Price, and Change Orders 005.05

Rev 2 – February 2017

d. When Subcontractor submits a Change Proposal for a change under a particular control number, it will be assumed to cover all Work required by that change unless indicated otherwise. It is Subcontractor’s responsibility to investigate the total scope of the change and notify Construction Manager at the time Subcontractor submits the Change Proposal of any exclusions or qualifications that would affect Subcontractor’s quote.

4. Disputed Work.

Definition: Work that is considered to be “extra” by Subcontractor but considered to be “base contract work” by Construction Manager, or Work that is believed to be beyond the scope of the Prime Contract with the Owner.

a. The procedure used to document and track the work is to be the same as that used for “Time and Material” Work. The signature of Construction Manager’s Project Superintendent on time and material daily slips is only to verify the Work that was performed. Signature is not an acceptance of responsibility for the cost of the Work, nor an affirmation that Work may be considered “extra.”

5. Extra Work.

Definition: Work beyond the scope of the Contract that is performed for other Subcontractors or Construction Manager. Procedure used to document and track Extra Work shall be the same as that used for Time and Material Work as defined in Paragraph “6” below.

6. Time and Material Work (“T&M”).

On limited occasions, Construction Manger may direct Subcontractor to do work on a T&M basis. If Subcontractor is so directed, the Cost of the Work shall be documented as follows.

a. T&M slips must be signed on a daily basis by Construction Manager’s Project Superintendent. One copy of the signed slip must be given to Construction Manager’s Project Superintendent or turned in at the Project site office. Information on the daily slips must include:

1) Date;

2) Subcontractor name;

3) Complete description of the work, including type, location, extent, quantities, etc.;

4) Number of hours worked by each labor classification;

5) Material used;

6) Equipment used; and

7) Construction Manager’s control number (if applicable).

b. Daily T&M slips that do not have the proper Construction Manager required information will be considered “VOID.”

c. Quotations for T&M must be submitted within ten (10) working days of the completion of Work. Copies of the signed daily T&M slips must be submitted as backup. Payment will not be authorized without signed time and material slips.

Page 9: 005.01 Contract Performance - Nabholz Construction · 005.01 Contract Performance Page 1 of 34 Recommended Use of This Section 005.01 Rev 2 – February 2017 The purpose of Section

005.05 Contract Scope and Price, and Change Orders

Page 9 of 34 Contract Scope and Price, and Change Orders 005.05

Rev 2 – February 2017

7. Deleted Material.

If material that was to have been purchased by Subcontractor as part of the Work is deleted by an Architect- or Owner-initiated change prior to installation, one of the following options will be used per Owner’s direction.

a. Credit will be given to Owner for the cost of the material minus any reasonable restocking charge.

b. Material will be turned over to Owner (only if the material cannot be returned to the manufacturer or supplier for a reasonable credit). An installation credit may be required depending on the activity in dispute.

Unless otherwise noted, material turned over to Owner must be turned over at the time that the building itself is being turned over and accepted by Owner (not at the time of the change).

1) Subcontractor must store the material (off-site, if required) until it is turned over. Subcontractor will be responsible for the care and custody of the material until it is turned over to Owner. All costs associated with the handling, storage, and turnover of the material are to be included in Subcontractor’s Change Proposal at the time the material is deleted.

2) Subcontractor must keep an accounting of all deleted material and submit an up-dated list with each progress payment request. Information on the list must include the Construction Manager’s change in which the material was deleted and quantities and descriptions of all items. The Owner may elect (optional) to have the deleted material disposed of in lieu of having it turned over.

3) Without written instruction issued by Construction Manager, Subcontractor will be liable for displacement costs for any deleted material that is disposed of without proper written instructions.

8. Billing of Changes.

Subcontractor agrees to furnish all labor, materials, tools, equipment, supplies, insurance, bonds, etc., required for additional Work, for which no pre-agreed price has been fixed, for net costs of all labor, materials, etc., furnished plus ten percent (10%) total mark-up for overhead and profit of the Subcontractor, unless otherwise noted in the Contract Documents.

All of Subcontractor’s billings for base Subcontract Work and Change Order Work (including “Change in Scope of Work,” “Extra Work,” and “Time and Material Work”) will be paid as progress billings only. There will be no payment for Change Order Work of any type without a signed change order from Construction Manager.

a. Change in Scope of Work: Upon receipt of a change order from the Owner, Construction Manager will issue a Subcontract change order.

b. Extra Work: Upon Construction Manager’s review and approval of Subcontractor’s quotation, Nabholz will issue a Subcontract change order.

Page 10: 005.01 Contract Performance - Nabholz Construction · 005.01 Contract Performance Page 1 of 34 Recommended Use of This Section 005.01 Rev 2 – February 2017 The purpose of Section

005.05 Contract Scope and Price, and Change Orders

Page 10 of 34 Contract Scope and Price, and Change Orders 005.05

Rev 2 – February 2017

9. Hourly Cost Breakdown.

Subcontractor must submit to Construction Manager a breakdown by trade and classification (foreman, journeyman, apprentice, etc.) for direct labor cost per hour. These amounts are not to be exceeded for Change Order Work unless the increase is due to actual labor cost increases during the duration of the Project. Subcontractor must notify Construction Manager, in writing, of changes to the labor cost breakdown.

Page 11: 005.01 Contract Performance - Nabholz Construction · 005.01 Contract Performance Page 1 of 34 Recommended Use of This Section 005.01 Rev 2 – February 2017 The purpose of Section

005.06 Contract Documents

Page 11 of 34 Contract Documents 005.06

Rev 2 – February 2017

1. Distribution.

Each Subcontractor and Supplier Subcontract or PO includes all Contract Documents. Do not submit quotes or changes without a complete set of Contract Documents, drawings, and specifications. Please coordinate request for documents through the Construction Manager’s Project team.

2. Contract Documents.

The Architect has issued a construction set of Contract Documents.

These documents are available to Subcontractor through the reproduction company at Subcontractor’s expense. Subcontractor must verify the completeness of these documents and notify Construction Manager of any discrepancies. Neither Construction Manager, Architect, nor Owner assume any responsibility in this request and consider this supply a convenience to Subcontractor.

3. Drawings Discrepancies.

Should Subcontractor find discrepancies in, or omissions from, the drawings or documents, or should Subcontractor be in doubt as to the meaning, Subcontractor shall obtain clarification from Construction Manager’s authorized representative before proceeding with any affected Work. All clarification requests shall be written (see Section 1.02 of the Construction Manager’s Manual for Request for Information Protocol). All Construction Manager official responses will be in writing.

Where a conflict exists between the construction documents (drawings and specifications) and the Form of Proposal, the following precedence prevails.

a. Scope of Work to be performed by Subcontractor or Supplier: Bid Package description and existing site conditions prevail.

b. Project specifications.

c. Project drawings.

Page 12: 005.01 Contract Performance - Nabholz Construction · 005.01 Contract Performance Page 1 of 34 Recommended Use of This Section 005.01 Rev 2 – February 2017 The purpose of Section

005.07 Submittals

Page 12 of 34 Submittals 005.07

Rev 2 – February 2017

The following requirements are not intended to supersede any more strenuous requirements elsewhere in the Contract Documents. See specifications for submittal procedures.

1. Submittals.

a. Subcontractor is responsible for Subcontractor’s submittals to be in compliance with applicable Contact Documents and for any delays occasioned by lack of such compliance.

b. Subcontractor Submittal Log and Presentation.

Prior to first submittal, Subcontractor shall identify the list of all items required for submittal. Include all guarantees and warranties in this log. Indicate the required approval date and lead times for materials and equipment.

c. Index.

All sets of drawings must have an index on the front sheet listing each drawing by sheet number, title, original drawing date, revision number, and revision date.

d. Submittal Reference.

Each drawing must be marked with proper descriptive title, including but not limited to part, location, Project number, manufacturer’s number, reference to contract drawing number, detail section number, or specification section number.

e. Reviews.

Construction Manager’s review of submittals is not construed as a complete check or relief from responsibility for errors of any sort, or from necessity of furnishing Work required by the Contract Documents which may not have been shown in the submittal.

Subcontractor is responsible for quantities and dimensions shown on submittals and for all field verifications of dimensions.

Construction Manager’s Project team will receive, verify completeness, and log submittals prior to forwarding to the Architect. Construction Manager will review all submittals for general compliance with the Contract Documents.

f. Variations from Contract Documents.

Subcontractor must obtain specific approval for variations from the Contract Documents. Use RFI form to initiate approval process. Deviation or variations shall be identified in writing, separate from the drawings, and will be submitted as one package. “Obtaining specific approval” is defined as flagging details on the shop drawings, clearly noting them as deviations from the Contract Documents, and receiving written verification that the change has been accepted by the Owner.

Construction Manager will not accept variations from the Contract Documents solely for the convenience of Subcontractor. The specifications clearly define the reasons for the variations so as to be beneficial to the Owner, both monetarily and due to stringent schedule time restraints. Construction Manager will not process a variation, however, that has cost savings but at the same time may delay the project.

Page 13: 005.01 Contract Performance - Nabholz Construction · 005.01 Contract Performance Page 1 of 34 Recommended Use of This Section 005.01 Rev 2 – February 2017 The purpose of Section

005.07 Submittals

Page 13 of 34 Submittals 005.07

Rev 2 – February 2017

Any costs incurred by Construction Manager that are the result of changes to the Contract Documents which are made by Subcontractor for convenience, will be Subcontractor’s responsibility.

g. Nonconforming Details.

Nonconforming details that are required for reasons beyond Subcontractor’s control (Contract Document details that are incorrect, proven to be faulty or not feasible, etc.) and that will result in an increase in Subcontractor’s Subcontract, are to be immediately brought to Construction Manager’s attention in writing. Failure to follow this procedure will jeopardize Subcontractor’s ability to recover additional incurred costs.

h. Revisions.

All revisions must be flagged, properly indexed, and dated. Previously submitted drawings are not to be revised without flagging all changes on each sheet. Subcontractor shall specify the origin of any revision.

i. Coordination.

Subcontractor shall coordinate the requirements of Work with that of other trades prior to the preparation of shop drawings through review of all Contract Document drawings and any necessary coordination meetings with other trades which shall be scheduled through Construction Manager.

j. Distribution.

In accordance with Contract Documents, shop drawings are to be submitted in sets of seven (7) prints. Subcontractor will receive an approved copy back for the purpose of providing all necessary coordination and Project use sets. Coordinate quantity of Project use sets with Construction Manager’s Project Manager.

2. Brochures and Submittals.

In accordance with the Contract Documents, brochures and submittals are to be submitted in sets of seven (7). Subcontractor will receive two (2) sets back for file.

3. Samples.

Typically, three (3) samples will be required for submission. If a specific quantity of samples is referenced by specification other than that noted above, one additional sample must be furnished for Construction Manager’s records. All required certification shall accompany the sample submission with cover letter noting the following.

a. Subcontractor’s name.

b. Project name and number.

c. List of samples being submitted.

d. Specification section to which sample refers.

e. Number of standard (ASTM, USASI, Commercial Standard, Federal Spec.), if any, with which sample complies.

f. Manufacturer’s name or source of supply.

g. Trade name.

Page 14: 005.01 Contract Performance - Nabholz Construction · 005.01 Contract Performance Page 1 of 34 Recommended Use of This Section 005.01 Rev 2 – February 2017 The purpose of Section

005.07 Submittals

Page 14 of 34 Submittals 005.07

Rev 2 – February 2017

h. Catalogue number.

i. Other pertinent information.

j. Any deviation from Contract Document requirements.

k. Subcontractor’s certification that all samples have been checked for compliance with contract requirements and availability of material represented thereby.

l. Fill out submittal cover sheet, 1 copy for each separate submittal.

4. Drawings

a. Submit seven (7) copies.

b. Plans must include a 6” wide x 3” high block for the Quality Control approval stamp.

c. Submittal cover sheet to be filled out and must be attached to each set of drawings. This will facilitate review and distribution.

5. Electronic Submittals

a. When possible, electronic submittals will be accepted and are preferred to paper copies. Submit electronic submittals in .pdf or .dwg format. Other electronic formats will be considered with pre-approval of Construction Manager.

b. All other information listed above applies to electronic submittals just as it applies to paper copies of submittals.

6. Bidder shall be held responsible for submission of all submittals within three weeks of Notice of Intent to Award, including but not limited to shop drawings, product data, samples, mock-ups, operating, service and maintenance manuals, MSDS information, and other submittals required by the specifications and Construction Manager’s QMS. Submittals are to be checked and signed off on by Subcontractor’s representative indicating such. Shop drawings should be started upon Notice of Intent to Award Subcontract and completed expeditiously so as to not delay construction. Coordinate with existing conditions and Subcontractors or other trade contractors as needed for locations, sizes and penetrations required. Color samples to be treated as part of the submittal process.

Page 15: 005.01 Contract Performance - Nabholz Construction · 005.01 Contract Performance Page 1 of 34 Recommended Use of This Section 005.01 Rev 2 – February 2017 The purpose of Section

005.08 Schedule

Page 15 of 34 Schedule 005.08

Rev 2 – February 2017

Construction Manager will create a Project Schedule with milestone and phasing dates which must be met. Construction Manager will execute a collaborative meeting with the major Subcontractors to define the actual Project Schedule. All Subcontractors shall be aware of this process upon award of Work and are contractually bound to same.

Subcontractor is required to send a foreman, project manager or owner to all weekly jobsite coordination meetings pertaining to the Scope of Work and/or as required by Project Superintendent. Employees attending meetings must have the authority to make commitments on Subcontractor’s resources (manpower, equipment, tools, etc.) to maintain Project Schedule or meet milestone dates.

1. Project Schedule.

Construction Manager will keep a Project master construction schedule (the “Project Schedule”) on-site for Subcontractor’s review. This schedule will be updated on a continual basis. Construction Manager maintains that Project Schedule will be executed as detailed. Construction Manager intends to maintain Project Schedule and to improve upon it. Certain areas may be made available earlier than currently indicated. Subcontractor shall strictly adhere to Construction Manager’s Project Schedule, inclusive of acceleration, and must be prepared for any adjustments to Project Schedule as Work progresses.

2. Schedule of Subcontractor’s Work.

As required by Construction Manager, Subcontractor will submit (and update as required) a schedule for Subcontractor’s Work. Any Work that is required to be in place before Subcontractor’s Work can start is to be noted on Subcontractor’s schedule.

3. Commencement and Sequence of Work.

Subcontractor shall be ready to commence Work as required by the Project Schedule and immediately upon receiving a Notice to Proceed; and receipt from Subcontractor of executed Subcontract, insurance that complies with Subcontract requirements, and performance and payment bonds (if required).

If Project, in the opinion of Construction Manager, shall not be in condition to receive Subcontractor’s Work at the time hereinafter stipulated, then Subcontractor shall hold in readiness, and upon receipt of seventy-two (72) hour written notice from Construction Manager, shall commence Work at the Project.

4. Out of Sequence Work.

Subcontractor shall stay informed as to the general progress of the Project and shall bring to Construction Manger's attention any Work that must be performed before Subcontractor’s Work can start. When Project construction is required, Subcontractor shall omit any sections or portions of Work that may be required by Construction Manager and shall later fill in such sections or portions when directed, at no additional cost. Subcontractor shall also perform any Work out of sequence that may be required by Construction Manager at no additional cost.

Page 16: 005.01 Contract Performance - Nabholz Construction · 005.01 Contract Performance Page 1 of 34 Recommended Use of This Section 005.01 Rev 2 – February 2017 The purpose of Section

005.08 Schedule

Page 16 of 34 Schedule 005.08

Rev 2 – February 2017

5. Completion Dates.

Subcontractor will be required to complete all Work by scheduled completion dates, as set forth in the Project Schedule. Subcontractor must notify Construction Manager in writing if conditions at the Project site prohibit Subcontractor from completing Work on time. Failure to notify Construction Manager of these conditions will leave Subcontractor responsible for making up time required to meet the Project Schedule at no additional cost.

6. Submittals.

Construction Manager requires no less than ten (10) working days, not including transit time, for review of submittals, shop drawings, samples, manufacturer’s literature, etc. Subcontractor must make submittals in a timely manner. Costs incurred for delays caused by re-submittal of drawings will be Subcontractor’s responsibility.

7. Weekend and Overtime Work.

Construction Manager will provide a Supervisor on-site when any type of Work is performed at the Project site. Subcontractor must notify Construction Manager’s Project Superintendent to schedule any weekend or overtime Work. If overtime Work is required due to schedule deficiencies caused by Subcontractor, Subcontractor will be responsible for Construction Manager’s costs, as well as including but not limited to, all labor (wages, fringe benefits, etc.), and hoisting which may be required as a result of Subcontractor’s overtime Work. In the case where more than one subcontractor is working on overtime, the direct labor cost and hoisting cost, if required, will be prorated as deemed appropriate by Construction Manager.

8. Milestone Dates.

All Subcontractors are bound by the phase milestone dates as agreed upon in the collaborative schedule meeting.

Page 17: 005.01 Contract Performance - Nabholz Construction · 005.01 Contract Performance Page 1 of 34 Recommended Use of This Section 005.01 Rev 2 – February 2017 The purpose of Section

005.09 Material Procurement, Expediting, and Handling

Page 17 of 34 Material Procurement, Expediting, and Handling 005.09

Rev 2 – February 2017

1. Critical Item.

Materials critical to the timely completion of Project will be Subcontractor’s responsibility. Subcontractor must make every effort necessary to expedite shop drawing submittals and subsequent acquisitions of these items. No substitutions of materials and products will be made without prior written approval from Construction Manager.

2. Handling.

All material handling equipment, including but not limited to hoisting with certified operators, bracing, shoring, scaffolding, necessary to move materials and complete Scope of Work.

3. Loose Material.

Loose material is defined as material that is required by the Contract Documents to be turned over to the Owner, but is not installed or attached to the building. Examples of loose material include spare parts, attic stock, special tools, or chemical supplies.

a. Loose material of any type must be inventoried and provisions must be made for Owner’s authorized agent to sign the inventory sheet verifying the quantity. Signed inventory sheet must be submitted to Construction Manager at the Project site office. Construction Manager will not sign for, nor accept responsibility for, the care and custody of loose material.

b. Should disagreements arise regarding loose material, Subcontractor must produce copies of the signed acceptance sheet(s). If Subcontractor does not have signed copies of the acceptance sheets, Subcontractor will be required to furnish the material in question.

4. Off-Site Stored Materials.

Provided that the contract between Owner and Construction Manager (the “Prime Contract”), allows for payment of off-site stored materials, Subcontractor/Supplier must ensure that the following conditions are met before payment is released.

a. Receipt of documentation noting off-site stored material location, site contact, and inspection hours of the storage facility.

b. Receipt of off-site stored material insurance for the location where the off-site material is stored. Coverage must include replacement value for all loss from any cause, including loss during transportation from the off-site storage facility to the Project site. Such policies must name the Additional Insured Entities, as identified in Section 005.03, as additional insureds.

a. Receipt of date-stamped digital photos showing that off-site materials are stored in a secure facility where the items are protected from the elements, theft, and vandalism.

b. Receipt of date-stamped digital photos showing that off-site materials are segregated from the common stock and are clearly marked and identified as being specifically for the Project requiring the materials.

c. Receipt of unconditional/conditional lien releases (if requested by Construction Manager) for the materials being stored.

Page 18: 005.01 Contract Performance - Nabholz Construction · 005.01 Contract Performance Page 1 of 34 Recommended Use of This Section 005.01 Rev 2 – February 2017 The purpose of Section

005.09 Material Procurement, Expediting, and Handling

Page 18 of 34 Material Procurement, Expediting, and Handling 005.09

Rev 2 – February 2017

d. Receipt of copies of actual invoices for the off-site materials being stored and billed. No mark-up by Subcontractor is allowed on off-site stored materials.

If Subcontractor/Supplier fails to comply with the requirements outlined in this Section, or in the event of a Subcontractor/Supplier default, Construction Manager shall have free access to enter Subcontractor’s/Supplier’s premises and to take possession of and utilize, sell, lease or otherwise dispose of the property in such a manner as Construction Manager, in its sole discretion, may elect.

Subcontractor/Vendor shall warrant and defend the sale of the property hereby made against all and every person whomsoever lawfully claiming the same or any part thereof.

Subcontractor /Vendor shall protect and bear the risk of loss or damage to such property until Project completion and upon acceptance of the Work by Owner, in accordance with the terms of the Contract Documents. Subcontractor/Vendor, on behalf of its insurance companies insuring the property against loss, waives right of subrogation against Construction Manager.

Page 19: 005.01 Contract Performance - Nabholz Construction · 005.01 Contract Performance Page 1 of 34 Recommended Use of This Section 005.01 Rev 2 – February 2017 The purpose of Section

005.10 Protection of Materials and Installed Work

Page 19 of 34 Protection of Materials and Installed Work 005.10

Rev 2 – February 2017

1. Protection of Material and Installed Work.

Subcontractor shall be responsible for protection of material, tools, equipment, and installed Work.

a. Subcontractor shall be responsible for furnishing, installing, and maintaining protection measures for materials, tools, equipment, and installed work until final installation and upon acceptance of the Work by Owner. Any loss due to theft or breakage prior to final installation and acceptance of the Work by Owner shall be replaced by Subcontractor at no additional cost to Construction Manager or Owner.

b. Construction Manager will not accept responsibility for the care, custody, and control of material between the time of installation by the Subcontractor and acceptance of the Work by Owner.

2. Repair or Replacement of Installed Work.

At no additional cost, Subcontractor shall touch-up, repair, replace, repaint, or rehabilitate Work as required to bring Work to an acceptable condition per the Contract Documents at the time the Work is to be turned over and accepted by Owner.

a. Subcontractor responsibility as noted above will be in effect until both of the following conditions are met.

1) Certificate of Substantial Completion for the Project has been issued by the Architect and accepted by Owner and Construction Manager.

2) Acceptance of the Work by Owner and Owner can occupy or utilizes the Work for its intended use.

b. Construction Manager will not accept any claim for repair or replacement of Subcontractor’s material or installed work due to vandalism, malicious mischief, normal construction traffic, theft, etc. All such repairs or replacements are to be either handled by Subcontractor directly at Subcontractor’s cost or covered by Subcontractor’s insurance.

3. Damage by other contractors..

If Subcontractor’s Work is damaged by another subcontractor or trade contractor performing Work at the Project site, Subcontractor shall promptly notify Construction Manager of any discovered deficiency or faulty workmanship by the other subcontractor or trade contractor performing Work at the Project site that affects Subcontractor’s Scope of Work. The subcontractor who caused the damage will be responsible for any repair or replacement costs. If Subcontractor fails to notify prior to the installation of its Work, Subcontractor shall be solely responsible for the costs of repair or replacement of Subcontractor’s Work. The Work may not be delayed by disputes regarding cost responsibility for damaged Work. Should a dispute arise regarding cost responsibility, repair, or replacement must be tracked in accordance with Section 31 of Article X in the Master Contract. The burden of proof will be on the Subcontractor whose Work was damaged. Subcontractor must protect Work until acceptance of the Work by Owner.

4. Schedule.

Page 20: 005.01 Contract Performance - Nabholz Construction · 005.01 Contract Performance Page 1 of 34 Recommended Use of This Section 005.01 Rev 2 – February 2017 The purpose of Section

005.10 Protection of Materials and Installed Work

Page 20 of 34 Protection of Materials and Installed Work 005.10

Rev 2 – February 2017

No wording contained herein shall relieve Subcontractor from the responsibility to fabricate, install, and complete Work in a timely manner as required to meet the Project Schedule.

Page 21: 005.01 Contract Performance - Nabholz Construction · 005.01 Contract Performance Page 1 of 34 Recommended Use of This Section 005.01 Rev 2 – February 2017 The purpose of Section

005.11 Field Operations

Page 21 of 34 Field Operations 005.11

Rev 2 – February 2017

1. Work Hours.

Normal work hours will be Monday through Friday from 7:00 AM to 4:00 PM unless otherwise notified. Adjustments may be made in accordance with actual daylight hours. The Project Schedule will dictate an expanded Work schedule for most trades. All Subcontractors are expected to provide sufficient labor to maintain the Project Schedule, avoid delays to other trades, and perform out of sequence Work requested by Construction Manager. Major building stocking operations shall be conducted during off-hours on a pre-determined schedule.

2. Job Meetings.

Meetings will be held at the Project site office on a determined day and time and as required by the Project Superintendent with all Subcontractors’ foremen on the Project or scheduled to be on the Project.

3. Daily Manpower.

Subcontractor must submit a subcontractor daily report to the Construction Manager’s Project Superintendent no later than 9:00 AM of the following workday. Daily report information must include number of workers, major equipment, material received, and a brief description of the Work being performed on that day. The form must be dated and signed by Subcontractor’s field supervisor.

4. Subcontractor’s Field Supervision.

Subcontractor must provide an English-speaking Supervisor on the Project site who has the authority to control all aspects of Subcontractor’s Work, (“Subcontractor Project Manager”) shall have the authority to receive and act upon directions given to Subcontractor by Construction Manager. Subcontractor’s Project Manager will have authority to control all aspects of Subcontractor’s Work, including crew size, scheduling, trouble-shooting, quality assurance, coordination with Construction Manager and other trades, and punch list. The Subcontractor’s Project Manager must be available by mobile phone during working hours and provide a 24-hour emergency number.

Subcontractor must provide its field personnel with adequate drawings, specifications, and instruction as required to undertake and complete the Work in an efficient and timely manner. Subcontractor’s personnel who arrive at the Project site without adequate information and instructions may be sent back and Subcontractor will be responsible for the cost of any delays incurred per the terms and conditions of the Contract Documents. Subcontractor shall be fully responsible for the acts or failures to act, and omissions of the Subcontractor’s own employees, sub-subcontractors, and vendors.

5. Field Communications.

Unless other methods are implemented, field copies of drawings, field memorandums, and miscellaneous field instructions will be distributed to Subcontractors via a “pick up” mail routing box in Construction Manager’s Project site office. Subcontractor’s field personnel will be required to check the mail routing box at least once each day (before 9:00 AM) while working on the Project site. Responsibility for communications given to Subcontractor’s Project Supervisor will be the same as if given to Subcontractor’s office. Copies will be distributed via regular mail or fax to Subcontractor’s offices in cases when Subcontractor is not mobilized on site.

Page 22: 005.01 Contract Performance - Nabholz Construction · 005.01 Contract Performance Page 1 of 34 Recommended Use of This Section 005.01 Rev 2 – February 2017 The purpose of Section

005.11 Field Operations

Page 22 of 34 Field Operations 005.11

Rev 2 – February 2017

6. Material Storage and Field Offices.

All deliveries of materials to the Project site for storage are to be cleared with Project Superintendent with respect to date, time of unloading, and storage area location. All deliveries will be scheduled at least 24 hours in advance. Subcontractor is responsible for receipt and unloading of all materials delivered. Subcontractor will be responsible for all costs if Construction Manager must unload materials. Construction Manager may reject a delivery for which Construction Manager has not made unloading provisions. Any delays or costs due to Subcontractor’s lack of preparedness will be Subcontractor’s responsibility.

To the extent that space will permit, and only after Construction Manager’s review and approval, Construction Manager will cooperate with Subcontractors in assigning areas for material storage and field offices. During the course of construction, however, it may become necessary to relocate the storage areas or field offices if conditions warrant. In these cases, Subcontractor shall, at no additional cost, remove materials, clean all debris and vacate the area promptly.

7. Instructions.

Subcontractor shall not consult directly with the Owner, Architect, or Consultants without written permission from Construction Manager. No verbal instruction given to Subcontractor by the Owner, Architect, or Consultants will be honored by Construction Manager.

8. Traffic Control.

Subcontractor must provide any flagmen, barricades, etc., that may be required for pedestrian or vehicular traffic control related to delivery, unloading and stocking of Subcontractor’s material or equipment on Project.

All vehicles, company-owned or personal, which enter the Project must be coordinated with Construction Manager’s Superintendent. Access to the Project site will be described and on traffic control maps provided by Construction Manager.

If Subcontractor does not provide adequate traffic control as determined by Construction Manager, Construction Manager may provide traffic control without prior notice. Subcontractor shall be responsible for Construction Manager’s direct costs plus mark-up.

9. Permits, Licenses, Inspections, and Testing.

Subcontractor must obtain and pay for all permits and licenses required for Work except the main building permit.

The costs of all third-party testing and inspection will be paid for by others. Subcontractor must fully cooperate with third party testing and inspection agencies and provide in-place ladders and scaffolds as required for safe inspection. Subcontractor shall allow the third party testing and inspection agencies adequate time and notice to inspect all completed Work. Subcontractor shall be responsible for any additional testing and inspection costs due to failure to maintain adequate progress in Work or necessitated by its failure to pass initial test or inspection. This requirement does not apply to air test & balance tests.

Mechanical, electrical, and plumbing Subcontractors shall secure and pay for all required special permits and licenses, and shall give notices, coordinate and pay for all inspections

Page 23: 005.01 Contract Performance - Nabholz Construction · 005.01 Contract Performance Page 1 of 34 Recommended Use of This Section 005.01 Rev 2 – February 2017 The purpose of Section

005.11 Field Operations

Page 23 of 34 Field Operations 005.11

Rev 2 – February 2017

necessary to comply with all the applicable laws, ordinances, rules and regulations, and other requirements of public authorities and agencies having jurisdiction over the Work.

10. Radios.

No AM/FM radios, CD players, iPods, MP3 players, or other form of audio player are allowed on the Project site. Any radios, CD players, iPod, MP3 Players or other form of auto playerc. will be confiscated and discarded by Project Superintendent.

11. DRINKING WATER AND ICE.

Subcontractor is responsible for providing drinking water, ice, and waste cans for its personnel.

12. Worker Parking Facilities.

Subcontractor parking will be provided in the locations designated by Construction Manager. Subcontractor shall be responsible for the conduct of its employees at all times while on the Project site and will ensure that they park only in the designated area. Construction Manager will not be liable for any loss or damage of Subcontractor’s employees’ property.

13. Project Signs and Photographs.

Identification signboards and notices for safety or instruction are permitted on the Project site only after approval of the Project Superintendent for format, location, and quantity. No signage is permitted on street or frontage road.

No photography shall be used on the Project site without Construction Manager’s and Owner’s approval. This includes drone and aerial photos.

14. Graffiti.

Graffiti will not be tolerated. Any person found placing graffiti on any portion of the Work or materials, equipment, portable toilets, etc., shall be promptly removed from the Project. Further, Construction Manager will charge Subcontractor the costs of graffiti removal or repair Work.

15. Construction Manager Field Office

Construction Manager’s field office, storage container, and the equipment and supplies contained therein are for the sole use of Construction Manager’s employees.

16. Behavior.

Subcontractor’s field personnel will be expected to treat all other field workers, management, and visitors with respect and courtesy. Individuals exhibiting behavior less than the expectation of a working professional will be asked to leave the Project immediately.

17. Temporary Facilities.

Portable toilets will be provided for Subcontractors use. Permanent toilets constructed in the buildings may not be used by anyone.

18. Storm Water Prevention Plan.

Subcontractor shall comply with Construction Manager’s Storm Water Pollution Prevention Plan for the duration of the Project. See Section 005.16 SWP3 Protocol.

Page 24: 005.01 Contract Performance - Nabholz Construction · 005.01 Contract Performance Page 1 of 34 Recommended Use of This Section 005.01 Rev 2 – February 2017 The purpose of Section

005.12 Coordination with Other Trades

Page 24 of 34 Coordination with Other Trades 005.12

Rev 2 – February 2017

1. Coordination.

Subcontractor will visit the Project site prior to commencement of Work and be thoroughly familiar with the working conditions and the exact nature and extent of Work to be done, taking into account any special or unusual features specific to this Project.

2. It is the responsibility of Subcontractor to coordinate Work with that of other trade subcontractors to prevent interference between its Work and other trade Subcontractors’ Work and ensure compatibility of all Project site processes and installations. Construction Manager will, at its discretion, provide shop drawings or data submitted by other trade subcontractors to Subcontractor for information and coordination. As the expert in the trade, however, Subcontractor is responsible for advising Construction Manager as to the information Subcontractor will require from other trade subcontractors for the proper coordination and installation of Work. Sleeves, Cut-Outs, Embedments.

Within thirty (30) days of the date of the Subcontract, or earlier if required by the Project Schedule, Subcontractor must submit a detailed listing (or drawings if requested) of all locations for sleeves, cut-outs, or embedment items related to the structure for coordination with other trade subcontractors and structural and architectural requirements.

Sleeves for penetrations through beams, walls, foundations, and slabs shall be furnished and installed by Subcontractor so as not to delay or impede Work of other trades. Subcontractor must adequately secure such sleeves and verify the correct location immediately prior to, during, and after concrete placement. Locations must be coordinated with Construction Manager and approved by the structural engineer.

3. Cutting and Fitting.

Subcontractor shall perform all cutting and fitting for the installation for Work and cutting and fitting of Work to accommodate the Work of other trades within Subcontractor’s Work as noted by the Contract Documents.

4. Cutting and Patching.

Subcontractor shall perform all cutting and patching under jurisdiction of its trade. Additionally, if cutting and patching is required due to failure in Subcontractor’s Work performance, Subcontractor will be responsible for additional cutting and patching at Subcontractor’s expense.

5. Layout.

Subcontractor shall be responsible for its own layout, including layout of housekeeping pads required for its equipment, from control lines provided by Construction Manager. This layout is required immediately after a concrete slab is ready. If these are not laid out at that time, Subcontractor shall form and place own pads.

6. Ceiling Heights.

Ceiling heights and designated walkways in the Project are crucial and must be maintained. Subcontractor shall lay out and be responsible for installation of the Work in such manner that the distance from the floor to ceiling called for in the architectural drawings will be maintained. Subcontractor shall notify Construction Manager immediately of any conflict in construction requirements.

7. Access Panels.

Page 25: 005.01 Contract Performance - Nabholz Construction · 005.01 Contract Performance Page 1 of 34 Recommended Use of This Section 005.01 Rev 2 – February 2017 The purpose of Section

005.12 Coordination with Other Trades

Page 25 of 34 Coordination with Other Trades 005.12

Rev 2 – February 2017

Unless otherwise directed, Subcontractor must furnish access panels as required for Subcontractor’s Work for installation by others. Access panels in architectural sheetrock areas, such as ceilings and soffits, must be of the highest quality, made to receive sheetrock as flush, mounted, and tape-able. Access panels in tiled walls must be stainless or bronze as selected by the Project architect.

Subcontractor shall locate and dimension all access panels on Subcontractor’s shop drawings including those required by Contract Documents, applicable codes and for reasonable operation and maintenance of the system. Coordinate access panel locations including field identification and verification with other trade Subcontractors who must frame or block out its Work to receive access panels (i.e. drywall, CMU, concrete formwork, etc.).

8. Caulking and Sealant.

Unless otherwise directed, Subcontractor is responsible for all acoustical, architectural, fire and smoke, and weatherproof caulking and sealant within and adjacent to its Work. Subcontractor shall take care so as not to leave unacceptable surface for other trades such as painting, escutcheons, electrical trim, etc.

9. Fireproofing and Fire Insulation.

All hangers and other items that are attached to the structural steel or metal deck must be in place before the fireproofing or fire insulation is installed. If fireproofing or fire insulation is existing, Subcontractor shall remove only the amount of material required to properly attach its Work to the building structure. Subcontractor must provide all clean-up associated with removal and replacement of fireproofing or fire insulation. Replacement of fireproofing or fire insulation materials removed or damaged will be the responsibility of Subcontractor.

10. Supports.

Subcontractor must furnish and install all inserts, hangers, threaded rod, wires, and braces (including seismic) for its Work.

11. Backing and Blocking.

Subcontractor shall provide information to Construction Manager for all backing, blocking, or concealed framing required for its Work that is not called out for Subcontractor installation.

Page 26: 005.01 Contract Performance - Nabholz Construction · 005.01 Contract Performance Page 1 of 34 Recommended Use of This Section 005.01 Rev 2 – February 2017 The purpose of Section

005.13 Debris and Cleanup

Page 26 of 34 Debris and Cleanup 005.13

Rev 2 – February 2017

1. Subcontractor shall perform clean-up and removal of construction debris on a daily basis so as not to impede the progress of Work or the Work of other trades subcontractors. Deposit all debris into Project site dumpsters as designated by Construction Manager.

2. Subcontractor shall provide clean-up and removal of all debris generated by its employees, sub-subcontractors, suppliers, or representatives. Debris includes, but is not limited to, water cups, food, containers, wrappers, lunch trash, scrap, excess materials, boxes, crating, and packing materials. Construction Manager will not provide general clean-up services for the entire Project.

3. Food may not be consumed on floors where finishes have begun. Food trash should always be properly disposed regardless of location on the Project site. If Subcontractor’s workers are unable to comply with this condition, its workers shall be promptly removed from the Project.

4. Subcontractor shall employ adequate personnel whose sole responsibility is the performance of clean-up as described herein.

5. Construction Manager shall be responsible for removal of debris from the dumpsters.

6. If Subcontractor fails to comply with these requirements, Construction Manager shall perform the necessary clean-up and deduct the cost of such Work from the amount due or to become due to Subcontractor. Trash will be identified by the predominant material in the pile or area and the associated Subcontractor will be charged for the removal.

7. The costs for unidentifiable trash removed by Construction Manager will be deducted from Subcontractor’s Subcontract amount on a prorated basis determined by manpower on the Project on a percentage of the total manpower. Joint crew clean-up methods will be required in order to avoid back-charges.

8. Flammable materials shall not be disposed of in Project site dumpsters/containers. These materials must be removed daily from the Project site and disposed of properly.

Page 27: 005.01 Contract Performance - Nabholz Construction · 005.01 Contract Performance Page 1 of 34 Recommended Use of This Section 005.01 Rev 2 – February 2017 The purpose of Section

005.14 Record Drawings and O&M Manuals

Page 27 of 34 Record Drawings and O&M Manuals 005.14

Rev 2 – February 2017

1. Subcontractor must maintain a complete set of up-to-date record drawings on Project site at all times during the entire course of the Project. These drawings must be prepared at the same scale as the Contract Documents unless noted otherwise in Subcontractor’s specification section. Construction Manager reserves the right to review Subcontractor’s record drawings monthly and withhold an appropriate value for the Subcontract requisition if the record drawings are not up to date.

2. Subcontractor must submit maintenance manuals in accordance with the format outlined in the specification requirements. Additionally, Subcontractor must include an index of all keys that must be turned over to the Owner. Keys must be properly labeled and turned over with the final submission of the maintenance manuals.

3. Retainage will not be released until all closeout documents are transmitted to Construction Manager.

Page 28: 005.01 Contract Performance - Nabholz Construction · 005.01 Contract Performance Page 1 of 34 Recommended Use of This Section 005.01 Rev 2 – February 2017 The purpose of Section

005.15 Requests for Information

Page 28 of 34 Requests for Information 005.15

Rev 2 – February 2017

Construction Manager has established a system through which RFI can be handled in a simple, efficient manner.

1. A RFI form should be filled out and transmitted to Construction Manager. Most RFI will require the Project architect’s review and response. If the response time is particularly critical, Subcontractor shall note the required response time. Otherwise, Construction Manager will establish the required response time.

2. Any verbal direction received by Subcontractor’s field forces from inspectors should be confirmed in writing through the RFI process. Action on verbal direction is at Subcontractor’s own risk.

3. Subcontractor must reference drawing number, coordinates (column lines), specification section, room number, etc. to facilitate resolution. Construction Manager’s Project Manager will fill in the Construction Manager’s RFI number and submission date.

Page 29: 005.01 Contract Performance - Nabholz Construction · 005.01 Contract Performance Page 1 of 34 Recommended Use of This Section 005.01 Rev 2 – February 2017 The purpose of Section

005.16 SWPPP Protocol

Page 29 of 34 SWPPP Protocol 005.16

Rev 2 – February 2017

Congress has recognized that contaminated storm water adversely affects water quality. In 1987, the Clean Water Act was amended to require the EPA to address storm water runoff. The EPA has delegated responsibilities for storm water discharges associated with construction and industrial sites to state agencies such as the states’ Departments of Environmental Quality. Federal and state laws and regulations prohibit and/or regulate the discharge of pollutants from point sources and require contractors to obtain permits, conduct inspections and monitor the site for actual and potential points of discharge. This includes “ground disturbing” construction activities, as well as activities that involve paints, chemicals and other hazardous materials. Nabholz Construction will oversee the Project’s Storm Water Pollution Prevention Plan (SWP3), including obtaining required permits; however, if awarded Work for the Project, Subcontracto shall be responsible for complying with the permit(s), Notice of Intent (NOI), SWP3, and Best Management Practices (BMP). Subcontractor’s compliance is required to avoid or eliminate actual or potential adverse effects upon the environment that could arise or result from Subcontractor’s Work. Upon award, Subcontractor agrees to be thoroughly familiar with the NOI, permits, the SWP3, and BMP for the Project and assumes responsibility for complying with these documents with respect to any and all construction activities performed by Subcontractor and those for whom Subcontractor is responsible. By executing Subcontract or PO, Bidder agrees to the following certification and agrees to its incorporation into the Contract Documents: Subcontractor/Vendor/Supplier certifies that it understand the terms and conditions of all federal, state, and local requirements that authorize storm water discharges associated with construction activity from the construction Project site location identified in the Contract Documents. Subcontractor/Vendor/Supplier has read and understands the Owner/operators Notice of Intent and the eligibility requirements for coverage under the general permit for storm water discharges from construction activities, including those requirements published in the SWP3 and BMP described pertaining to the Project location identified in the Contract Documents. Subcontractor/Vendor/Supplier agrees that it is responsible for installing and/or maintaining the appropriate pollution prevention measures it is responsible for according to the agreement they have with the permittee. Subcontractor/Vendor/Supplier also agrees that continued coverage under this permit is contingent upon maintaining eligibility as provided for in the permit.

Subcontractor is responsible for the protection of the SWP3 devices in place. If Subcontractor is required to move a SWP3 device in order to complete Work, Subcontractor must replace the device as installed. Subcontractor shall coordinate removal and replacement of SWP3 device with Project Superintendent.

Page 30: 005.01 Contract Performance - Nabholz Construction · 005.01 Contract Performance Page 1 of 34 Recommended Use of This Section 005.01 Rev 2 – February 2017 The purpose of Section

005.17 Virtual Design Construction Protocol

Page 30 of 34 Virtual Design Construction Protocol 005.17

Rev 2 – February 2017

Subcontractor’s Virtual Design Construction (“VDC”) Scope of Work and Spatial Coordination Requirements, as follows:

1. Alternate Section 1 language if Nabholz is providing the BIM services firm for the Project. Subcontractor shall agree to participate in the Project BIM coordination process by attending the BIM coordination and review meetings and provide guidance to the project BIM service firm as necessary to achieve the requirements below.

2. Subcontractor shall agree to provide Construction Manager an electronic three dimensional (3D) model (such models are functionally referred to herein as “BIM” or “Building Information Models”). The models provided will be used to facilitate coordination, sequencing, and/or production of as-built depictions of the Project. The Subcontractor’s costs of such participation shall be included in the lump sum Proposal unless explicitly outlined herein.

3. The BIM provided by Subcontractor shall be of sufficient detail (refer to Appendix A for details) to enable complete clash detection and shall be submitted to Construction Manager at a point in time that is reasonably in advance of Subcontractor’s shop drawing submittals and the subsequent Project site construction of Subcontractor’s Work. Each trade is required to submit six (6) copies of its respective, coordinated systems in two dimension (2D) format as required by Subcontract, for approval through the regular approval process.

4. Construction Manager will make available its Project BIM website that will allow all parties to upload and download its respective “in progress shop models,” manage electronic drawing files or models, and other documents used in the BIM coordination process.

5. Subcontractor shall attend Project kick-off meeting and participate in review and finalization of the Project BIM execution plan which will be signed by all participating parties.

6. Subcontractor shall participate in BIM coordination and review meetings as Construction Manager may require (usually once a week or 48 hours after the submissions of the BIM). As a result of such meetings, both the 2D (traditional method) and 3D (BIM) may be required to be changed by Subcontractor to achieve coordination with other elements of the Project that are provided by other parties. The anticipated duration of BIM spatial coordination is XX weeks.

7. Subcontractor agrees to promptly update and post changes to the BIM originating from RFIs, submittals, and bulletins throughout the course of the Project so that the BIM at the conclusion of the Project accurately depicts the Work as actually performed and installed. Such changes shall be accomplished at no increase in the price or time of completion.

8. All Subcontractors participating in the BIM must use the following file naming convention for their BIM/CAD files to track the version and date by each trade.

NCS Job #_Trade/Subcontractor Phase/Location

9. Subcontractors are responsible for providing a true 3D solid or surface model (not line and wireframe model) that represents the actual dimensions of the trade system elements and the equipment that will be installed. Individual pieces of equipment shall be modeled as a single complete element rather than connected lines and surfaces.

Page 31: 005.01 Contract Performance - Nabholz Construction · 005.01 Contract Performance Page 1 of 34 Recommended Use of This Section 005.01 Rev 2 – February 2017 The purpose of Section

005.17 Virtual Design Construction Protocol

Page 31 of 34 Virtual Design Construction Protocol 005.17

Rev 2 – February 2017

10. Subcontractor’s drawing and model files shall be based on an origin point provided by Construction Manager. The cost of any changes required by Subcontractor to its drawings or models due to the use of an unauthorized origin shall be borne by Subcontractor.

11. All files supplied by Construction Manager will be as Autodesk .dwg, .nwc, .nwd or .rvt file format or other file format as necessary and agreed to by Construction Manager.

12. See the following spatial coordination requirements for BIM.

Spatial Coordination Requirements for BIM

1. Major Components.

HVAC Duct and Piping.

The HVAC and Piping Subcontractor will generate and provide in a timely manner BIMs of the HVAC systems including, but not limited to, duct work, piping, and all equipment installed in the HVAC scope of Work (fans, air handling units, built-up air handling units, pumps, tanks, valves, controls, heat exchangers, smoke and fire dampers, valves (including valve stems and handles), gauges and control valves, insulation on piping and ductwork, hangers and seismic bracing (if applicable), diffusers, registers, louvers, grilles, high and low point drains, starters, etc.). The HVAC and Piping Subcontractor shall also include in the BIMs all Owner or Construction Manager provided equipment that is installed under this Contract, concrete equipment pads, and inertia pads, and accessibility requirements for above listed items for code and maintenance purposes. The HVAC and Piping Subcontractor shall label the BIMs elements for all equipment under this contract as indicated in the Contract Documents.

Plumbing.

The Plumbing Subcontractor will generate and provide in a timely manner BIMs of the plumbing systems including, but not limited to, all piping systems and equipment installed in the Plumbing Subcontractor’s scope of Work (domestic water, chilled water, steam, storm and roof leaders, pumps, tanks, water heaters, in-wall carriers, in-wall plumbing equipment, valves, gauges and control valves, insulation on piping, hangers and seismic bracing (if applicable), clean-outs, etc.). The Plumbing Subcontractor shall also include in the BIMs all Owner or Construction Manager provided equipment that is installed under this contract, concrete equipment pads, inertia pads, and accessibility requirements for above listed items for code and maintenance purposes. The Plumbing Subcontractor shall label the BIMs elements for all equipment under this contract as indicated in the Contract Documents.

Fire Protection System.

The Fire Suppression System Subcontractor will generate in a timely manner BIMs of the Fire Suppression Systems including, but not limited to, all risers, main and branch piping, heads, pumps, controllers, ATS, and equipment installed in the Fire Suppression

Page 32: 005.01 Contract Performance - Nabholz Construction · 005.01 Contract Performance Page 1 of 34 Recommended Use of This Section 005.01 Rev 2 – February 2017 The purpose of Section

005.17 Virtual Design Construction Protocol

Page 32 of 34 Virtual Design Construction Protocol 005.17

Rev 2 – February 2017

System scope of Work (pre-action system, dry system, and main fire suppression systems, hangers and seismic bracing (if applicable), valve assemblies, drain valves, Fire Department valves, etc.) The Fire Suppression System Subcontractor shall also include in the BIMs concrete equipment pads, inertia pads, and access doors. The Fire Suppression System Subcontractor shall identify, under separate model element or drawing layer, access doors, and accessibility requirements for above listed items for code and maintenance purposes. The Fire Suppression Subcontractor shall label the BIMs elements for all equipment under this contract as indicated in the Contract Documents.

Electrical.

The Electrical Subcontractors, including, Low Voltage Subcontractor, Audio-Video Subcontractor, and Scoreboard-Ribbon Board Subcontractor, will generate in a timely manner BIMs of its respective electrical systems and/or devices including, but not limited to, all conduit systems, and equipment installation in its respective scopes of Work (individual conduits over 2”, racks carrying more than 4 conduits 1” and smaller, panels, transformers, switch/paralleling gear, ATS’, generators, cable tray, data racks, starters, VFD’s, cast-in-place floor boxes, hangers and seismic bracing (if applicable), etc. for normal, emergency and isolated power systems or applicable specialty systems). Subcontractor shall also include in the BIMs equipment pads, inertia pads, light fixtures, exit signs, fire alarm components and devices, speakers, A/V equipment and devices, scoreboards, ribbon boards (and related devices), recessed electrical devices and access doors. Subcontractor shall identify under model element, or separate drawing layer access doors and accessibility requirements for above listed items for code and maintenance purposes. Electrical Subcontractor shall label the BIMs elements for all equipment under this contract as indicated in the Contract Documents.

Structural.

The Structural Steel Supplier will generate and provide in a timely manner BIMs of its scope of Work in addition to the contractually required 2D documentation. The BIMs will represent an “as fabricated” fully detailed level of information. The fabrication-level detailed model shall include, but is not limited to, major structural members such as trusses, beams, columns, etc., as well as secondary and miscellaneous steel connections including gusset plates, bracing, angles, knife plates, etc. necessary for the successful coordination of other building trades. These models shall be updated and maintained to reflect changes in the Work as a result of coordination or design changes and shall be delivered at the end of the Project as an “as built” record model of the structural steel system in its entirety.

2. Minimum Hardware Requirements.

TBD

3. Minimum Software Requirements.

TBD

Page 33: 005.01 Contract Performance - Nabholz Construction · 005.01 Contract Performance Page 1 of 34 Recommended Use of This Section 005.01 Rev 2 – February 2017 The purpose of Section

005.17 Virtual Design Construction Protocol

Page 33 of 34 Virtual Design Construction Protocol 005.17

Rev 2 – February 2017

4. Structural / Architectural Features Required for Coordination.

Spatially accurate and dimensionally scalable building elements including but not limited to soffits, fixture locations, ceiling/floor tile locations, ADA clearances, interior wall framing, moment-frame side plates, cross bracing, gusset plates, beam stiffeners, miscellaneous steel framing, and other similar entities within the modeling space requiring coordination with the MEP trades.

5. Fully Annotated Installation Drawings.

Fully annotated installation drawings shall include all text, dimensions, and annotations required for physical location of all elements shown on the drawings in the physical space at the time of their installation.

Page 34: 005.01 Contract Performance - Nabholz Construction · 005.01 Contract Performance Page 1 of 34 Recommended Use of This Section 005.01 Rev 2 – February 2017 The purpose of Section

005.18 Nothing Hits The Floor

Page 34 of 34 Nothing Hits the Floor 005.18

Rev 2 – February 2017

Nothing Hits The Floor: An initiative to improve productivity, reduce waste and construction debris, improve housekeeping, and enhance worker safety on the project. Subcontractor agrees to actively participate in the program, which includes but is not limited to the following activities:

1. All materials brought into the building shall immediately be loaded onto wheeled carts or dollies to allow easy movement and facilitate organization within the work areas.

2. Flow of work activities shall be planned to minimize or eliminate off-cuts, debris, and excess materials from piling up on the floor. Waste and recycling containers in the building shall be wheeled to facilitate efficient placement and ease of debris transport.

3. All work areas shall be kept clean and well organized, and shall be broom swept, with no materials left on the floor at the end of the work day.

4. All materials small tools are to be neatly stored and organized and work areas kept free of waste, debris, surplus equipment and surplus materials.

5. Subcontractor shall participate, at Construction Manager’s discretion, in a project-wide cleanup effort to maintain housekeeping of common areas.

6. Right-time material deliveries are encouraged. Materials delivered to jobsite shall be incorporated into the Work within 10 days of delivery. Materials stored on site shall be roped off and labeled with Subcontractor’s name, Subcontractor’s Foreman’s name and phone number, and the date of material delivery.

7. Whenever feasible, assembly of components shall be accomplished at tabletop height to encourage more ergonomically correct posture for craftsmen.

8. Wherever feasible, Subcontractor shall unpackage materials and dispose of packaging waste at his own shop.

9. Wherever feasible, Subcontractor shall endeavor to utilize cordless tools to eliminate the trip hazards associated with electrical extension cords.

10. Wherever feasible, and with the prior approval of the Construction Manager, Subcontractor shall endeavor to prefabricate components off-site in a warehouse or other controlled environment to eliminate jobsite cut-off debris, improve quality, and reduce safety hazards.