Nabholz Construction
17300 W 116th St
Lenexa, KS 66219
Project: CP180131- University of Missouri Healthcare- Women’s and Children’s Hospital
Exterior Envelope Replacement
Bid Date & Time: 7/31/2019 @ 1:30PM
Bid Captain: Daniel Dercher – [email protected]
Mitchell Fuemmeler – [email protected]
ADDENDUM NOTICE
Addendum #2 has been issued
The following is included in Addendum #2:
o Construction Manager’s Manual Clarifications:
3.00 Bid Packages and Bid Forms
.02 Bid Form – DELETE AND REPLACE WITH- Revised Section .02 Bid Form
07.2 Wall Panels Bid Package
• Applicable Specifications- ADD Section – 055000 Metal Fabrications
• Section B, ADD: “Include aluminum ladders and safety cages per section 055000”
• Section B, Item 8- REVISE “Including required testing” TO: “Testing will be by
others”
07.3 Roofing, Flashing & Sheet Metal Bid Package
• Section A, Item 16- REVISE TO: “Include walk-pads/walkway protection as
indication on in the drawings”
• Section A, Item 18- REVISE TO: “Roof drains to be supplied and installed by
future Plumbing package. Roofing package is responsible for flashing in and
coordinating locations.
• Section B, Item 5- REVISE TO: “Roof protection will be the responsibility of all
trades as their work requires.”
• Section B, Item 9- REVISE TO: “Supply and install of roof curbs will be by
others. Roof package to include tying in roof system to the curb and maintaining
roof warranty.
• Section B, ADD: Include painting striped line referenced in note 10 on A117
• Section D, ADD: Item 3. Provide a unit price for the removal and replacement of
existing gypsum deck per B32 on S502
ATTACHMENTS:
o Revised Section .02 Bid Form (5 pages)
o International Architects Atelier – Addendum #2 (9 pages)
o Pre-Bid RFI Responses (7 pages)
Page 2 of 2
Acknowledgement of all addenda is a requirement of the bid process. Please acknowledge this and all addenda on
the Bid Form found in section 3.00.02 of the Construction Manager’s Manual.
Should you have any questions concerning this project, please contact the Bid Captain noted above.
Daniel Dercher
Senior Estimator
4
Construction Manager’s Manual – MU Women’s & Children’s Hospital – Exterior Envelope Replacement Pkg #1
02 Bid Form
Date of Bid ______________________
Submitting Company (“Bidder”)
Company Name__________________________________________________________________
Project State License Number_______________________________________________________
Company Representative
Name__________________________________________________________________________
Email Address____________________________________________________________________
Cell Phone_______________________________________________________________________
Scope of Work
Bid Package Number______________________________________________________________
Bid Package Description____________________________________________________________
Addenda
Bidder acknowledges receipt of the following addenda:
Addendum #________ Dated ________________
Addendum #________ Dated ________________
Addendum #________ Dated ________________
Addendum #________ Dated ________________
Addendum #________ Dated ________________
Addendum #________ Dated ________________
Base Bid
By submitting this proposal form, bidder acknowledges receipt of and compliance with Nabholz minimum
insurance requirements, Master Contract Agreement, Project Contract Agreement, Performance and Payment
Bond requirements, Purchase Order, CCIP Program Addendum, and Safety Standards.
Bidder agrees to complete the Scope of Work listed below for a lump sum of:
$________________________________________________________________________________
5
Construction Manager’s Manual – MU Women’s & Children’s Hospital – Exterior Envelope Replacement Pkg #1
Alternates
1. _____________________________________________________ Add/Deduct $ ____________
2. _____________________________________________________ Add/Deduct $ ____________
3. _____________________________________________________ Add/Deduct $ ____________
4. _____________________________________________________ Add/Deduct $ ____________
Voluntary Alternates
1. _____________________________________________________ Add/Deduct $ ____________
2. _____________________________________________________ Add/Deduct $ ____________
Unit Pricing
1. _____________________________________________________ $ _______________________
2. _____________________________________________________ $ _______________________
3. _____________________________________________________ $ _______________________
4. _____________________________________________________ $ _______________________
Work in Progress & Project Specific Qualifications
Bidder shall submit with their proposal a Work in Progress (WIP) Report that lists the ten (10) largest projects
currently being constructed. Moreover, final evaluation of Bidder’s proposal shall be conditional on review of
WIP Report, and Bidder’s experience with similar scope and projects.
Completion Time
All Work shall be completed within the schedules prepared by and agreed to by Nabholz. Bidder shall provide
adequate manpower and submit documentation for approval necessary to work within the timeframe
scheduled.
Bonding
Bidder can provide a Performance and Payment Bond and can meet the requirements set forth in the “Project
Contact”. (circle one)
Yes/No
Performance and Payment Bond Rate Cost in Percent_________
Name of Surety Agent_____________________________________________________________________
Surety Agent Phone Number________________________________________________________________
6
Construction Manager’s Manual – MU Women’s & Children’s Hospital – Exterior Envelope Replacement Pkg #1
Acceptance of Contract Forms
Bidder acknowledges that they have reviewed and accept the Contract Performance and Administration,
Sample Master Contract, Sample Project Contract, Payment and Performance Bonds, Sample Purchase
Order, Contractor-Controlled Insurance Program Addendum to Master Contract and the Nabholz Safety
Standards forms linked in Section 5.02. Proposed modifications must be submitted with bid.
Signature
Bidder agrees that this proposal remains valid for a period of 60 days. Bidder understands that Nabholz and
the Owner reserve the right to reject any or all bids. Bidder acknowledges Nabholz minimum insurance
requirements and understands that the Master Contract shall be the basis of any contract offered by
Nabholz Construction to Bidder. Proposed modifications of Master Contract language must be submitted
with bid. Attach additional sheets if necessary. Upon receipt of notice of acceptance of bid, Bidder agrees
to execute and return the contract and required insurance certificates within two weeks of notification.
By ______________________________________________________________
Title_________________________________
Printed name of individual signing this proposal________________________________________________
Contact phone number___________________________________________________________________
Date __________________
Supplier Diversity participation goals for this project are as follows:
Minority Business Enterprise (MBE) of Ten Percent 10%; Women/Disadvantaged Business
Enterprises/Veteran (WDV) of Ten Percent 10%; and Serviced Disabled Veteran (SDVE) of Three Percent 3%
of the GMP. The ability to meet diversity goals will be included in the considerations for how Nabholz and the
Owner will determine the lowest, responsible, qualified bidder. Bidders are encouraged to contract with
Diverse venders and suppliers, regardless of any tier, in order to meet these goals.
7
Construction Manager’s Manual – MU Women’s & Children’s Hospital – Exterior Envelope Replacement Pkg #1
CP180131 WCH – Exterior Building Envelope Replacement
SUPPLIER DIVERSITY COMPLIANCE EVALUATION FORM
This form shall be completed by all Subcontractors, Suppliers and Venders, regardless of any tier, and submitted with the
Bidder's Statement of Qualifications.
The undersigned submits the following data with respect to this firm's assurance to meet the goal for Supplier Diversity
participation.
I. Project:
II. Name of Contractor:
III. Name of Diverse Firm:
Address:
Phone No.: E-mail.:
Status (check one) MBE WBE Veteran Service Disabled Veteran DBE
IV. Describe the subcontract work to be performed. (List Base Bid work and any Alternate work separately):
Base Bid:
V. Dollar amount of contract to be subcontracted to the Diverse firm:
Base Bid:
Alternate(s), (Identify separately):
VI. Is the proposed subcontractor listed in the Directory of M/W/DBE Vendors and/or the Directory of Veterans
maintained by the State of Missouri?
Yes No
8
Construction Manager’s Manual – MU Women’s & Children’s Hospital – Exterior Envelope Replacement Pkg #1
CP180131 WCH – Exterior Building Envelope Replacement
VII. Is the proposed subcontractor certified as a diverse supplier by any of the following: federal government
agencies, state agencies, State of Missouri city or county government agencies, Minority and/or WBE
certifying agencies?
Yes No If yes, please provide details and attach
a copy of the certification.
VIII. Does the proposed subcontractor have a signed document from their attorney certifying the Supplier as a
Diverse and meeting the 51% owned and committed requirement?
Yes No If yes, please attach letter.
Signature:
Name:
Title:
Date:
END OF PROPOSAL FORM
ADD #2 – Page 1 of 3 Women’s and Children’s Hospital –
Exterior Envelope Replacement University of Missouri
Project No. CP180131 July 24, 2019
ADDENDUM # 2 DATE: July 24, 2019 TO CONTRACT DOCUMENTS ENTITLED:
WOMEN’S AND CHILDREN’S HOSPITAL - EXTERIOR ENVELOPE REPLACEMENT, EXTERIOR ENVELOPE PACKAGE ONE UNIVERSITY OF MISSOURI PROJECT NUMBER: CP180131
PREPARED FOR: The Curators of the University of Missouri CONSULTANT: International Architects Atelier, Inc.
912 Broadway Suite 300 Kansas City, Missouri 64105 Telephone: (816) 471-6522
Drawings and Specifications for the above noted project and the work covered thereby are herein modified as follows, and except as set forth herein, otherwise remain unchanged and in full force and effect: SPECIFICATION CHANGES: 1. Section 072726, Paragraph 2.3.A
ADD: f. Soprema; Sopraseal LM 204. 2. Section 074213.19, Paragraph 2.2.B.1.b
DELETE AND REPLACE WITH: Benchmark by Kingspan – Designwall Panel Series. 720 Marion Road, Columbus, OH 43207.
3. Section 075216, Paragraph 3.7.B
DELETE: Paragraph 3.7.B.
4. Section 075216, Paragraph 3.9.B DELETE: Paragraph 3.9.B.
5. Section 075216, Paragraph 2.4, 2.5 Vapor Retarder DELETE AND REPLACE WITH: Polyethlene-reinforced, self-adhering SBS vapor barrier: ASTM D5147, cross-machine direction 103 lbf 31.8 mil (polyethlene-reinforced) nonslip, UV-protected top surface.
ADD #2 – Page 2 of 3 Women’s and Children’s Hospital –
Exterior Envelope Replacement University of Missouri
Project No. CP180131 July 24, 2019
DRAWING CHANGES: 1. Sheets D200, D201, D202, D203, D204, D205, D206, D207, D208, D209, D210, D211, D212,
D213, D214, D300, D301 DELETE: Demo Keyed Note 14. REPLACE WITH: Where MEP penetrations are abandoned, remove existing louver or
cover and prepare to receive new studs, Re: Mech. Where MEP penetrations are still active, remove existing louver and prepare to receive new louver in coordination with new exterior envelope assembly, Re: Mech. Coordinate abandoned and active MEP penetrations with new construction drawings.
2. Sheet A207 DELETE: Entire Drawing. REPLACE WITH: Revised Drawing A207.
3. Sheet A215 DELETE: Entire Drawing. REPLACE WITH: Revised Drawing A215.
4. Sheet A216 DELETE: Entire Drawing. REPLACE WITH: Revised Drawing A216.
5. Sheet A230 – Added Keynote Legend ADD: Keynote legend with ‘099113.A EXTERIOR PAINT’ for reference to all
associated keynotes in elevation views.
6. Sheet A231 – Added Keynote Legend ADD: Keynote legend with ‘099113.A EXTERIOR PAINT’ for reference to all
associated keynotes in elevation views.
7. Sheet A232 – Added Keynote Legend ADD: Keynote legend with ‘099113.A EXTERIOR PAINT’ for reference to all
associated keynotes in elevation views.
8. Sheet A232, AA1 – Added Keynote ADD: Keynote ‘099113.A’ to door.
9. Sheet A520, B5 – Typical Base Detail CLARIFICATION: Refer to attached Drawing AD-01 for revised base flashing in Typical
Base Detail B5. 10. Sheet M101.1, U5 – 3rd Floor – Mechanical Plan – Phase Three
ADD: Demolition of abandoned dryer vent at 2nd Floor per Revised Drawing M101.1
11. Sheet M101.1, B14 – 4th Floor – Mechanical Plan – Phase Four
ADD: Demolition of existing sprinkler drain piping penetration through existing exterior wall and rerouting of same per Revised Drawing M101.1
ADD #2 – Page 3 of 3 Women’s and Children’s Hospital –
Exterior Envelope Replacement University of Missouri
Project No. CP180131 July 24, 2019
12. Sheet PM102.1, B27 – 4th Floor – Mechanical Plan – Phase Six
ADD: Rerouting of existing sprinkler drain piping same per Revised Drawing PM102.1
ATTACHMENTS: A207, A215, A216, AD-01, M101.1, PM102.1. END OF ADDENDUM # 2
E.L. 825' - 11 3/8"T.O. STEEL
E.L. 840' - 5 1/8"T.O. STEEL -
PENTHOUSES
EDC
4"3'
- 4"
3' -
4"3'
- 4"
2' -
0"2'
- 0"
1' -
9"12
' - 7
"1'
- 10
3/4
"
2' - 0" 10' - 1 1/4" 10' - 1 1/4" 10' - 1 1/4" 10' - 1 1/4" 2' - 0"
3' - 10 1/2" 17' - 6 1/2" 26' - 10 1/2" 3' - 8 1/2"
B33A502
CC14A320
CC14A320
* REFER TO B22 / A501 FOR WALL TYPE AT PENTHOUSE. * REFER TO B33 / A502 FOR TYPICAL WALL TYPE AT PENTHOUSE SIGNAGE.
SIM* SIM*
REINSTALL EXISTING ANTENNA AND ALL ASSOCIATED BRACKETS, CLAMPS, AND FASTENERS, TYP.
REINSTALL EXISTING CONDUIT, ELECTRICAL BOXES, AND ALL ASSOCIATED FASTENERS, TYP.
074213.BCOLOR "B"
076200.B
B5A521
SIM*
076200.C
FUTURE LOCATION OF MU HEALTH CARE LOGO. SIGNAGE PRODUCT, INSTALLATION & FINAL SIZE AND LOCATION TO BE COORDINATED WITH OWNER
055000.E BEYOND
1
PHASE FOUR
NORTH PENTHOUSE SOUTH
PENTHOUSE
E.L. 825' - 11 3/8"T.O. STEEL
E.L. 840' - 5 1/8"T.O. STEEL -
PENTHOUSES
5 6 7B14A501
2' - 0" 4' - 9 3/8" 7' - 0" 10' - 2 1/4" 10' - 2 1/4" 10' - 2 1/4" 2' - 0"
1' - 2" 17' - 5" 26' - 7" 1' - 2"
1' -
8 1/
8"7'
- 0"
1' -
11 7
/8"
B33A502
CC14A320
CC14A320
K33A320
SIM
SIM*
SIM*
* REFER TO B22 / A501 FOR TYPICAL WALL TYPE AT PENTHOUSE.* REFER TO B33 / A502 FOR TYPICAL WALL TYPE AT PENTHOUSE SIGNAGE.
074213.E
074213.A
REINSTALL EXISTING ANTENNA AND ALL ASSOCIATED BRACKETS, CLAMPS, AND FASTENERS, TYP.
COLOR "B"REINSTALL EXISTING CONDUIT, ELECTRICAL BOXES, AND ALL ASSOCIATED FASTENERS, TYP.
076200.B
4"3'
- 4"
3' -
4"3'
- 4"
2' -
0"2'
- 0"
1' -
10 3
/4"
B5A521
SIM*
076200.C
FUTURE LOCATION OF MU HEALTH CARE LOGO. SIGNAGE PRODUCT, INSTALLATION & FINAL SIZE AND LOCATION TO BE COORDINATED WITH OWNER.
SIM*
1
E.L. 825' - 11 3/8"T.O. STEEL
E.L. 840' - 5 1/8"T.O. STEEL -
PENTHOUSES
E D C
4"3'
- 4"
3' -
4"3'
- 4"
2' -
0"2'
- 0"
1' -
9"12
' - 7
"1'
- 10
3/4
"
2' - 0" 10' - 1 1/4" 10' - 1 1/4" 10' - 1 1/4" 10' - 1 1/4" 2' - 0"
3' - 8 1/2" 26' - 10 1/2" 17' - 6 1/2" 3' - 10 1/2"
CC14A320
SIM*CC14A320
B33A502
* REFER TO B22/ A501 FOR WALL TYPE AT PENTHOUSE.
SIM*
074213.ACOLOR "B"
076200.B
076200.C
055000.EBEYOND
E.L. 825' - 11 3/8"T.O. STEEL
E.L. 840' - 5 1/8"T.O. STEEL -
PENTHOUSES
567
2' -
0"2'
- 0"
3' -
4"3'
- 4"
3' -
4"4"
1' -
10 3
/4"
12' -
7"
1' -
9"
2' - 0" 10' - 0 3/8" 10' - 0 3/8" 10' - 0 3/8" 6' - 0" 6' - 2 7/8" 2' - 0"
1' - 2" 26' - 7" 17' - 5" 1' - 2"
CC14A320
CC14A320
B22A501
B14A522
K14A522
B33A521
B5A521
B5A521
K33A320
B5A521
SIM.
B5A521
SIM.
+/- 1
' - 9
1/8
" F.V
.2'
- 0"
+/- 1
0 7/
8" F
.V.
+/- 6
' - 0
" F.V
.
074213.E
* REFER TO B22 / A501 FOR WALL TYPE AT PENTHOUSE.
SIM*SIM*
SIM*
SIM*
081113.B
081113.A
4
074213.ACOLOR "B"
REINSTALL EXISTING ANTENNA AND ALL
ASSOCIATED BRACKETS , CLAMPS,
AND FASTENERS, TYP.
076200.B
K14A521
SIM
SIM*
SIM*
076200.C
055000.E
1
INDICATES LOCATION OF SPANDREL GLASS IN NEW WINDOW SYSTEM.
INDICATES LOCATION OF OBSCURED GLASS IN NEW WINDOW SYSTEM.
INDICATES LOCATION OF PREVIOUS WINDOW OPENING, OR PENETRATION THAT NEEDS TO BE FILLED IN WITH 3-5/8" METAL STUDS AT 16" O.C. PRIOR TO INSTALLATION OF NEW EXTERIOR SHEATHING AND INSULATED METAL PANELS.
RAISE EXISTING PARAPET WALL BY 1'-2" WITH 3-5/8" STRUCTURAL STUDS AT 16" O.C.
ADJUST EXISTING WINDOW OPENING ASNEEDED TO FIT NEW WINDOW SYSTEM INTHE EXISTING OPENING WITH SPECIFIEDDIMENSIONS.
ALIGN NEW SUN SHADE DEVICE BETWEENDIFFERENT CONSTRUCTION PHASES.
PROVIDE WATERTIGHT TRANSITIONBETWEEN COMPLETED PHASE AND THEFUTURE PHASE.
INDICATES LOCATION OF PERFORATED METAL PANEL SYSTEM.
ADJUST EXISTING WINDOW OPENING AS NEEDED TO FIT NEW WINDOW SYSTEM IN THE EXISTING OPENING WITH SPECIFIED DIMENSIONS.
1
2
3
EXISTING MEP PENETRATIONS. TO BECOORDINATED WITH NEW WALL SYSTEM.
4
INDICATES EXISTING METAL WALL PANEL TO BE PRIMED AND PAINTED PER ALTERNATE "2" - INTENT IS ALL EXPOSED METAL SURFACE INCLUDING BUT NOT LIMITIED TO METAL PANELS, TRIM, FLASHING, COPINGS, LOUVERS, DOWNSPOUTS, GUTTERS AND MISC. ITEMS TO BE PAINTED TO MATCH COLOR OF NEW INSULATED METAL PANELS.
SUN SHADES AT INTERIOR CORNERS TO BEINSTALLED AFTER COMPLETION OF BOTHPHASES. REFER TO T14/A320.
5
INDICATES LOCATION OF CURTAIN WALL SPANDREL GLASS.
GL-2
GL-3
GL-5
ABANDONED MEP PENETRATION TO BEINFILLED WITH NEW STUDS AND COVEREDWITH NEW EXTERIOR WALL ASSEMBLY.
6
EXISTING SECURITY CAMERAS TO BECOORDINATED WITH NEW WALL ANDROOFING SYSTEM. RE: ELECT.
7
PERFORATED PANEL TO BE PAINTED COLOR"D". SIGNAGE TO BE PAINTED ONTOPERFORATED PANEL SURFACE WITH COLOR"E". WHERE SIGNAGE IS INDICATED,PERFORATED PANEL SURFACE SHALL BEOPAQUE AND BE PREPARED TO RECEIVESIGNAGE PAINT.
8
DATE:
DESIGNED BY:
CHECKED BY:
PROJ. NO.:
1234567891011121314151617181920212223242526272829303132333436
1234567891011121314151617181920212223242526272829303132333436
A
B
C
D
E
F
G
H
J
K
L
M
N
P
Q
R
S
T
U
V
W
X
Y
Z
AA
BB
CC
A
B
C
D
E
F
G
H
J
K
L
M
N
P
Q
R
S
T
U
V
W
X
Y
Z
AA
BB
CC
DD DD
© 2019 INTERNATIONAL ARCHITECTS ATELIER
MAJID AMIRAHMADI - ARCHITECTMO#: A-5077
The Professional Architects seal affixed to this sheet appllies only to the material and items shown on this sheet. All drawings, instruments, or other documents not exhibiting this seal shall not be considered prepared by this architects, and this architect expressly disclaims any and all responsibility for such plan, drawings, or documents not exhibiting this seal.
APPROVED BY:
DRAWN BY:
SEAL:
35
35
EE
FF
GG
HH
JJ
KK
373839404142
373839404142
EE
FF
GG
HH
JJ
KK
816 471 6522 | 816.471.3755 | I-A-A.COMP: F: W:
MISSOURI STATE CERTIFICATE OF AUTHORITY #000582
912 BROADWAY BLVD, SUITE 300 | KANSAS CITY, MO 64105
STRUCTURAL CONSULTANT
BOB D. CAMPBELL & CO.
4338 BELLEVIEW AVE.KANSAS CITY, MO 64111PH: 816.531.4144
FOR THE CURATORS OF THE UNIVERSITY OF MISSOURI
MECHANICAL, ELECTRICAL, AND PLUMBING CONSULTANT
W.L. CASSELL & ASSOCIATES
1600 BALTIMOREKANSAS CITY, MO 64108PH: 816.842.837
LIGHTING CONSULTANT
FISHER MARANTZ STONE
22 WEST 19TH STREETNEW YORK, NEW YORK 10011PH: 212.691.3020
7/24
/201
9 1:
54:3
3 PM A207
NEW ELEVATIONS -PHASE FOUR
CP180131July 24, 2019
LB, MR
LB, MR
MA
MA
WOMEN'S ANDCHILDREN'SHOSPITAL -EXTERIORENVELOPEREPLACEMENT
ISSUE FOR BID: EXTERIORENVELOPE PACKAGE ONEADDENDUM #2
SCALE: 1/4" = 1'-0" AA5SOUTH PENTHOUSE - SOUTH ELEVATION - PHASE FOUR
B10KEY PLAN B5ELEVATION NOTESB22NOT USED B1KEYNOTES
DIVISION32 EXTERIOR IMPROVEMENTS
DIVISION31 EARTHWORK
DIVISION26 ELECTRICAL
DIVISION23 HVAC
DIVISION22 PLUMBING
DIVISION14 CONVEYING EQUIPMENT
DIVISION12 FURNISHINGS
DIVISION09 FINISHES
DIVISION08 OPENINGS081113.A HOLLOW METAL DOOR FRAME081113.B HOLLOW METAL DOOR
DIVISION07 THERMAL + MOISTURE PROTECTION074213.A 3" INSULATED METAL FLAT PANEL -
HORIZONTAL PROFILE074213.B 3" INSULATED METAL FLAT PANEL -
VERTICAL PROFILE074213.E INTEGRATED FIXED LOUVER UNIT076200.B PREFINISHED METAL COPING076200.C PREFINISHED METAL BASE FLASHING
DIVISION06 WOOD, PLASTICS + COMPOSITES
DIVISION05 METALS055000.E ROOF ACCESS LADDER
DIVISION04 MASONRY
DIVISION03 CONCRETE
000000.X
000000.X
EXISTING CONSTRUCTION
EXISTING CONSTRUCTION
TAG ALL MATERIALS WITH THEIR LOCATIONS AND SEQUENCING FOR RE-USE. REPAIR AND CLEAN ANY DAMAGED MATERIALS PRIOR TO BEING RE-SET.
NEW CONSTRUCTION
000000.X
DIVISION10 SPECIALTIES
DIVISION11 EQUIPMENT
0' 2' 4' 8'0' 2' 4' 8'
SCALE: 1/4" = 1'-0" AA24SOUTH PENTHOUSE - WEST ELEVATION - PHASE FOUR
SCALE: 1/4" = 1'-0" Q5SOUTH PENTHOUSE - NORTH ELEVATION - PHASE FOURSCALE: 1/4" = 1'-0" Q24SOUTH PENTHOUSE - EAST ELEVATION - PHASE FOUR
0' 2' 4' 8'0' 2' 4' 8'
AA24 / A207
Q5
/ A20
7
AA5
/ A20
7
Q24 / A207
NO. REVISION SUBMISSION DATE0 ISSUE FOR BID, DESIGN
PACKAGE ONE07/03/2019
1 ADDENDUM #2 07/24/2019
NORTH PENTHOUSE
SOUTH PENTHOUSE
PHASE TEN
E.L. 773' - 11 3/8"LEVEL 2 & T.O. MASONRY
E.L. 788' - 4 3/4"3RD FLOOR
E.L. 800' - 10 1/8"4TH FLOOR
E.L. 813' - 3 1/2"5TH FLOOR
E.L. 825' - 11 3/8"T.O. STEEL
E.L. 829' - 9"T.O. MASONRY
E.1 F.1 G.1 H.1
9
PHASE
10
PHASE
10
PHASE
5
PHASE
6"2'
- 0"
1' -
2"3'
- 4"
1' -
3 3/
8"
2' -
0"3'
- 4"
3' -
4"1'
- 2"
3' -
4"1'
- 3
3/8"
3' -
4"3'
- 4"
1' -
2"3'
- 4"
1' -
3 3/
8"3'
- 4"
3' -
4"1'
- 2"
3' -
4"1'
- 3
3/8"
3' -
4"3'
- 4"
1' -
7 1/
4"
2' -
0"3'
- 4"
3' -
4"3'
- 4"
4"
7' - 5 3/4" 24' - 0" 24' - 0" 24' - 0"
7' - 5 3/4" 12' - 0" 12' - 0" 12' - 0" 12' - 0" 12' - 0" 12' - 0"
4' - 6" 2' - 0" 5' - 6" 5' - 6" 5' - 6" 5' - 6" 2' - 0" 5' - 6" 5' - 6" 5' - 6" 5' - 6" 2' - 0" 5' - 6" 5' - 6" 5' - 6" 5' - 6" 2' - 0"
1' - 0" 1' - 0"
22' - 0"
1' - 0" 1' - 0"
22' - 0"
1' - 0" 1' - 0"
22' - 0" 1' - 0"
+/- 5' - 7 7/8" F.V. 4' - 6" 2' - 0" 5' - 6" 5' - 6" 5' - 6" 5' - 6" 2' - 0" 5' - 6" 5' - 6" 5' - 6" 5' - 6" +/- 3' - 1 1/8" F.V.
18' - 6" 4' - 6"
1' - 0" 1' - 0"
22' - 0"
1' - 0" 1' - 0"
22' - 0" 1' - 0"
+/- 11 3/4" F.V.6' - 6" 6' - 6" 5' - 6" 5' - 6" 6' - 6" 6' - 6" 5' - 6" 5' - 6" 6' - 6" 6' - 6" 5' - 6" 5' - 6" 6' - 6"
+/- 4' - 8 3/8" F.V. 6' - 6" 6' - 6" 5' - 6" 5' - 6" 6' - 6" 6' - 6" 5' - 6" 5' - 6" 6' - 6" +/- 2' - 1 1/8" F.V.
074213.D
074213.D
074213.D
074213.D
074213.A
076200.B
076200.F 076200.G
074213.B
COLOR "A"
COLOR "A"
074213.E
B5A321
SIM.
B5A500
B14A500
K14A522 SIM.
B14A522
T24A522
K14A321
SIM.
T5A320
CC5A320
SIM.
21001
32801
42801
52801
52901
42901
32901
21101
33001
43001
53001
53108
43108
33108
21208
CC24A320
TYP
B22 -A215
TYP.
076200.G
SIM. SIM.
SIM.
SIM. / TYP.
1
2
2
2
3TYP.
T24A320
TYP.T33A320
TYP.
COLOR "A"
COLOR "A"
COLOR "A"
COLOR "A"
EXTERIOR ENVELOPE IS CONTINUOUS FROM NORTH PENTHOUSE SOUTH WALL TO PHASE 10 SOUTH WALL AT HOSPITAL TOWER. METAL PANEL COLOR "B" APPLIED AT PENTHOUSE WALL ABOVE ROOF "A" PARAPET. METAL PANEL COLOR "A" APPLIED AT TOWER WALL BELOW ROOF "A" PARAPET.
4"
COLOR "B"074213.A
074213.A 074213.F COLOR "B"
INDICATES LOCATION OF SPANDREL GLASS IN NEW WINDOW SYSTEM.
INDICATES LOCATION OF OBSCURED GLASS IN NEW WINDOW SYSTEM.
INDICATES LOCATION OF PREVIOUS WINDOW OPENING, OR PENETRATION THAT NEEDS TO BE FILLED IN WITH 3-5/8" METAL STUDS AT 16" O.C. PRIOR TO INSTALLATION OF NEW EXTERIOR SHEATHING AND INSULATED METAL PANELS.
RAISE EXISTING PARAPET WALL BY 1'-2" WITH 3-5/8" STRUCTURAL STUDS AT 16" O.C.
ADJUST EXISTING WINDOW OPENING ASNEEDED TO FIT NEW WINDOW SYSTEM INTHE EXISTING OPENING WITH SPECIFIEDDIMENSIONS.
ALIGN NEW SUN SHADE DEVICE BETWEENDIFFERENT CONSTRUCTION PHASES.
PROVIDE WATERTIGHT TRANSITIONBETWEEN COMPLETED PHASE AND THEFUTURE PHASE.
INDICATES LOCATION OF PERFORATED METAL PANEL SYSTEM.
ADJUST EXISTING WINDOW OPENING AS NEEDED TO FIT NEW WINDOW SYSTEM IN THE EXISTING OPENING WITH SPECIFIED DIMENSIONS.
1
2
3
EXISTING MEP PENETRATIONS. TO BECOORDINATED WITH NEW WALL SYSTEM.
4
INDICATES EXISTING METAL WALL PANEL TO BE PRIMED AND PAINTED PER ALTERNATE "2" - INTENT IS ALL EXPOSED METAL SURFACE INCLUDING BUT NOT LIMITIED TO METAL PANELS, TRIM, FLASHING, COPINGS, LOUVERS, DOWNSPOUTS, GUTTERS AND MISC. ITEMS TO BE PAINTED TO MATCH COLOR OF NEW INSULATED METAL PANELS.
SUN SHADES AT INTERIOR CORNERS TO BEINSTALLED AFTER COMPLETION OF BOTHPHASES. REFER TO T14/A320.
5
INDICATES LOCATION OF CURTAIN WALL SPANDREL GLASS.
GL-2
GL-3
GL-5
ABANDONED MEP PENETRATION TO BEINFILLED WITH NEW STUDS AND COVEREDWITH NEW EXTERIOR WALL ASSEMBLY.
6
EXISTING SECURITY CAMERAS TO BECOORDINATED WITH NEW WALL ANDROOFING SYSTEM. RE: ELECT.
7
PERFORATED PANEL TO BE PAINTED COLOR"D". SIGNAGE TO BE PAINTED ONTOPERFORATED PANEL SURFACE WITH COLOR"E". WHERE SIGNAGE IS INDICATED,PERFORATED PANEL SURFACE SHALL BEOPAQUE AND BE PREPARED TO RECEIVESIGNAGE PAINT.
8
E.L. 773' - 11 3/8"LEVEL 2 & T.O. MASONRY
F.1
21208
3' -
4"2'
- 0"
1' -
3 3/
8"3'
- 4"
1' -
2"2'
- 0"
6"
5' - 8" ± F.V. 4' - 6" 1' - 0"
6' - 6"T33A320
T24A320
SIM
T5A320
SIM
K24A522
T5A520
INDICATES EXTENTS OF MOCK-UP UNIT.
A MOCK-UP UNIT OF WALL, WINDOW, AND SUN SHADE SYSTEM ASSEMBLIES SHALL BE CONDUCTED PRIOR TO FIRST PHASE OF CONSTRUCTION. MOCK-UP UNIT SHALL BE INSTALLED FOR NO LESS THAN 6 WEEKS PRIOR TO THE FIRST PHASE OF CONSTRUCTION.
DIMENSIONS AND ASSEMBLIES SHALL BE CONSTRUCTED AS SHOWN IN DRAWINGS. METAL PANEL, WINDOW MULLION, AND SUN SHADE COLORS TO MATCH FINAL FINISHES AS CLOSELY AS POSSIBLE. GLASS TYPE TO MATCH FINAL SPECIFICATIONS. AFTER 2 WEEKS OF COMPLETE INSTALLATION, MOCK-UP UNIT SHALL BE TESTED FOR WATER-TIGHTNESS AND THERMAL PERFORMANCE.
074213.ACOLOR "A"
074213.D
F.V.
± 1' - 1 7/8" 10' - 0"
B5A320
SIM.
T33A522
OPP.SIM.
CC33A320
SIM.
4' - 6"
1' - 0"
11 5/8"
2' - 6 3/8"
T33A521 SIM.
074213.A
074213.D
074213.B
SIM.
076200.B
074213.A074213.A
DATE:
DESIGNED BY:
CHECKED BY:
PROJ. NO.:
1234567891011121314151617181920212223242526272829303132333436
1234567891011121314151617181920212223242526272829303132333436
A
B
C
D
E
F
G
H
J
K
L
M
N
P
Q
R
S
T
U
V
W
X
Y
Z
AA
BB
CC
A
B
C
D
E
F
G
H
J
K
L
M
N
P
Q
R
S
T
U
V
W
X
Y
Z
AA
BB
CC
DD DD
© 2019 INTERNATIONAL ARCHITECTS ATELIER
MAJID AMIRAHMADI - ARCHITECTMO#: A-5077
The Professional Architects seal affixed to this sheet appllies only to the material and items shown on this sheet. All drawings, instruments, or other documents not exhibiting this seal shall not be considered prepared by this architects, and this architect expressly disclaims any and all responsibility for such plan, drawings, or documents not exhibiting this seal.
APPROVED BY:
DRAWN BY:
SEAL:
35
35
EE
FF
GG
HH
JJ
KK
373839404142
373839404142
EE
FF
GG
HH
JJ
KK
816 471 6522 | 816.471.3755 | I-A-A.COMP: F: W:
MISSOURI STATE CERTIFICATE OF AUTHORITY #000582
912 BROADWAY BLVD, SUITE 300 | KANSAS CITY, MO 64105
STRUCTURAL CONSULTANT
BOB D. CAMPBELL & CO.
4338 BELLEVIEW AVE.KANSAS CITY, MO 64111PH: 816.531.4144
FOR THE CURATORS OF THE UNIVERSITY OF MISSOURI
MECHANICAL, ELECTRICAL, AND PLUMBING CONSULTANT
W.L. CASSELL & ASSOCIATES
1600 BALTIMOREKANSAS CITY, MO 64108PH: 816.842.837
LIGHTING CONSULTANT
FISHER MARANTZ STONE
22 WEST 19TH STREETNEW YORK, NEW YORK 10011PH: 212.691.3020
7/24
/201
9 1:
54:5
7 PM A215
NEW ELEVATIONS -PHASE TEN &
MOCK-UP UNIT
CP180131July 24, 2019
LB, MR
LB, MR
MA
MA
WOMEN'S ANDCHILDREN'SHOSPITAL -EXTERIORENVELOPEREPLACEMENT
ISSUE FOR BID: EXTERIORENVELOPE PACKAGE ONEADDENDUM #2
SCALE: 1/4" = 1'-0" Q5SOUTH ELEVATION - PHASE TEN
B10KEY PLAN B5ELEVATION NOTESB37NOT USED B1KEYNOTES
DIVISION32 EXTERIOR IMPROVEMENTS
DIVISION31 EARTHWORK
DIVISION26 ELECTRICAL
DIVISION23 HVAC
DIVISION22 PLUMBING
DIVISION14 CONVEYING EQUIPMENT
DIVISION12 FURNISHINGS
DIVISION09 FINISHES
DIVISION08 OPENINGS
DIVISION07 THERMAL + MOISTURE PROTECTION074213.A 3" INSULATED METAL FLAT PANEL -
HORIZONTAL PROFILE074213.B 3" INSULATED METAL FLAT PANEL -
VERTICAL PROFILE074213.D INTEGRATED ALUMINUM SUN SCREEN
UNIT074213.E INTEGRATED FIXED LOUVER UNIT074213.F SHOP-FORMED INSULATED METAL PANEL
CORNER076200.B PREFINISHED METAL COPING076200.F PREFINISHED METAL CONTINUOUS CLEAT076200.G PREFINISHED METAL EXPANSION JOINT
FLASHING
DIVISION06 WOOD, PLASTICS + COMPOSITES
DIVISION05 METALS
DIVISION04 MASONRY
DIVISION03 CONCRETE
000000.X
000000.X
EXISTING CONSTRUCTION
EXISTING CONSTRUCTION
TAG ALL MATERIALS WITH THEIR LOCATIONS AND SEQUENCING FOR RE-USE. REPAIR AND CLEAN ANY DAMAGED MATERIALS PRIOR TO BEING RE-SET.
NEW CONSTRUCTION
000000.X
DIVISION10 SPECIALTIES
DIVISION11 EQUIPMENT
0' 2' 4' 8'
Q5
/ A21
5
SCALE: 1/2" = 1'-0" B22MOCK-UP UNIT
NO. REVISION SUBMISSION DATE0 ISSUE FOR BID, DESIGN
PACKAGE ONE07/03/2019
1 ADDENDUM #2 07/24/2019
E.L. 825' - 11 3/8"T.O. STEEL
E.L. 840' - 5 1/8"T.O. STEEL -
PENTHOUSES
C.1D.1E.1
2' - 0" 9' - 7" 9' - 7" 9' - 7" 9' - 7" 2' - 0"
1' - 2" 20' - 0" 20' - 0" 1' - 2"
B33A502
CC14A320
CC14A320
SIM.
4"3'
- 4"
3' -
4"3'
- 4"
2' -
0"2'
- 0"
1' -
10 3
/4"
SIM.
055000.E
074213.F
074213.ACOLOR "B"
076200.B
074213.A
076200.C076200.F
FUTURE LOCATION OF MU HEALTH CARE LOGO. SIGNAGE PRODUCT, INSTALLATION & FINAL SIZE AND LOCATION TO BE COORDINATED WITH OWNER
* REFER TO B22 / A501 FOR WALL TYPE AT PENTHOUSE. * REFER TO B33 / A502 FOR TYPICAL WALL TYPE AT PENTHOUSE SIGNAGE.
1
074213.FCOLOR "B"
TYP.
1
E.L. 825' - 11 3/8"T.O. STEEL
E.L. 829' - 9"T.O. MASONRY
E.L. 840' - 5 1/8"T.O. STEEL -
PENTHOUSES
C.1 D.1 E.1
4"3'
- 4"
3' -
4"3'
- 4"
2' -
0"2'
- 0"
1' -
10 3
/4"
+/- 3
' - 6
" F.V
.
2' - 0"+/- 2' - 1 7/8" F.V.
+/- 5' - 0" F.V. 10' - 4 3/4" 10' - 4 3/4" 11' - 2 3/4" 1' - 2"
20' - 0" 20' - 0"
3' -
6"1' -
10 1
/8"
2' -
0"2'
- 7
7/8"
K14A522
B14A522
B24A521
K33A320
SIM
CC14A320
SIMCC14A320
SIM
B17A531
SIM
SIM.
074213.F
074213.ACOLOR "B"
076200.B
TYP.
074213.ATYP.
055000.E
076200.C076200.F
074213.E
3' -
4"
1' -
7 1/
4"
2' -
0"3'
- 4"
3' -
4"3'
- 4"
4"
1
1
B22A501
074213.ACOLOR "B"
EXTERIOR ENVELOPE IS CONTINUOUS FROM NORTH PENTHOUSE SOUTH WALL TO PHASE 10 SOUTH WALL AT HOSPITAL TOWER. METAL PANEL COLOR "B" APPLIED AT PENTHOUSE WALL ABOVE ROOF "A" PARAPET. METAL PANEL COLOR "A" APPLIED AT TOWER WALL BELOW ROOF "A" PARAPET.
074213.A
074213.A
COLOR "A"
076200.B
E.L. 825' - 11 3/8"T.O. STEEL
E.L. 840' - 5 1/8"T.O. STEEL -
PENTHOUSES
0102 1
4"3'
- 4"
3' -
4"3'
- 4"
2' -
0"2'
- 0"
1' -
10 3
/4"
2' - 0" 3' - 9 7/8" 6' - 6" 11' - 8 1/8" 11' - 8 1/8" 2' - 0"
14' - 9" 21' - 5" 1' - 2 5/8" 3 3/8"
B22A501
K14A522
B14A522
K33A320
CC14A320
SIMCC14A320
SIM
+/- 2
' - 1
0" F
.V.
+/- 5
' - 0
" F.V
.
074213.E
SIM.
REINSTALL EXISTING CONDUIT, ELECTRICAL BOXES, AND ALL ASSOCIATED FASTENERS, TYP.
B5A521
076200.B
074213.A
074213.ACOLOR "B"
4
076200.C076200.F
074213.F COLOR "B"
1
E.L. 825' - 11 3/8"T.O. STEEL
E.L. 829' - 9"T.O. MASONRY
E.L. 840' - 5 1/8"T.O. STEEL -
PENTHOUSES
01 021
1' -
10 3
/4"
2' -
0"2'
- 0"
3' -
4"3'
- 4"
3' -
4"4"
2' - 0" 11' - 2 5/8" 11' - 2 5/8" 11' - 2 5/8" 2' - 0"
3 3/8" 1' - 2 5/8" 21' - 5" 14' - 9"
B22A501
B33A521
B5A521
SIM
SIM
CC14A320
CC14A320
SIM
055000.E
076200.B
074213.A COLOR "B"
074213.ACOLOR "B"
074213.A COLOR "B"081113.B081113.A 076200.F
076200.C
4
REINSTALL EXISTING ANTENNA AND ALL
ASSOCIATED BRACKETS, CLAMPS, AND FASTENERS,
TYP.
1
074213.F
074213.F
1
1
1
INDICATES LOCATION OF SPANDREL GLASS IN NEW WINDOW SYSTEM.
INDICATES LOCATION OF OBSCURED GLASS IN NEW WINDOW SYSTEM.
INDICATES LOCATION OF PREVIOUS WINDOW OPENING, OR PENETRATION THAT NEEDS TO BE FILLED IN WITH 3-5/8" METAL STUDS AT 16" O.C. PRIOR TO INSTALLATION OF NEW EXTERIOR SHEATHING AND INSULATED METAL PANELS.
RAISE EXISTING PARAPET WALL BY 1'-2" WITH 3-5/8" STRUCTURAL STUDS AT 16" O.C.
ADJUST EXISTING WINDOW OPENING ASNEEDED TO FIT NEW WINDOW SYSTEM INTHE EXISTING OPENING WITH SPECIFIEDDIMENSIONS.
ALIGN NEW SUN SHADE DEVICE BETWEENDIFFERENT CONSTRUCTION PHASES.
PROVIDE WATERTIGHT TRANSITIONBETWEEN COMPLETED PHASE AND THEFUTURE PHASE.
INDICATES LOCATION OF PERFORATED METAL PANEL SYSTEM.
ADJUST EXISTING WINDOW OPENING AS NEEDED TO FIT NEW WINDOW SYSTEM IN THE EXISTING OPENING WITH SPECIFIED DIMENSIONS.
1
2
3
EXISTING MEP PENETRATIONS. TO BECOORDINATED WITH NEW WALL SYSTEM.
4
INDICATES EXISTING METAL WALL PANEL TO BE PRIMED AND PAINTED PER ALTERNATE "2" - INTENT IS ALL EXPOSED METAL SURFACE INCLUDING BUT NOT LIMITIED TO METAL PANELS, TRIM, FLASHING, COPINGS, LOUVERS, DOWNSPOUTS, GUTTERS AND MISC. ITEMS TO BE PAINTED TO MATCH COLOR OF NEW INSULATED METAL PANELS.
SUN SHADES AT INTERIOR CORNERS TO BEINSTALLED AFTER COMPLETION OF BOTHPHASES. REFER TO T14/A320.
5
INDICATES LOCATION OF CURTAIN WALL SPANDREL GLASS.
GL-2
GL-3
GL-5
ABANDONED MEP PENETRATION TO BEINFILLED WITH NEW STUDS AND COVEREDWITH NEW EXTERIOR WALL ASSEMBLY.
6
EXISTING SECURITY CAMERAS TO BECOORDINATED WITH NEW WALL ANDROOFING SYSTEM. RE: ELECT.
7
PERFORATED PANEL TO BE PAINTED COLOR"D". SIGNAGE TO BE PAINTED ONTOPERFORATED PANEL SURFACE WITH COLOR"E". WHERE SIGNAGE IS INDICATED,PERFORATED PANEL SURFACE SHALL BEOPAQUE AND BE PREPARED TO RECEIVESIGNAGE PAINT.
8
NORTH PENTHOUSE
SOUTH PENTHOUSE
PHASE TEN
DATE:
DESIGNED BY:
CHECKED BY:
PROJ. NO.:
1234567891011121314151617181920212223242526272829303132333436
1234567891011121314151617181920212223242526272829303132333436
A
B
C
D
E
F
G
H
J
K
L
M
N
P
Q
R
S
T
U
V
W
X
Y
Z
AA
BB
CC
A
B
C
D
E
F
G
H
J
K
L
M
N
P
Q
R
S
T
U
V
W
X
Y
Z
AA
BB
CC
DD DD
© 2019 INTERNATIONAL ARCHITECTS ATELIER
MAJID AMIRAHMADI - ARCHITECTMO#: A-5077
The Professional Architects seal affixed to this sheet appllies only to the material and items shown on this sheet. All drawings, instruments, or other documents not exhibiting this seal shall not be considered prepared by this architects, and this architect expressly disclaims any and all responsibility for such plan, drawings, or documents not exhibiting this seal.
APPROVED BY:
DRAWN BY:
SEAL:
35
35
EE
FF
GG
HH
JJ
KK
373839404142
373839404142
EE
FF
GG
HH
JJ
KK
816 471 6522 | 816.471.3755 | I-A-A.COMP: F: W:
MISSOURI STATE CERTIFICATE OF AUTHORITY #000582
912 BROADWAY BLVD, SUITE 300 | KANSAS CITY, MO 64105
STRUCTURAL CONSULTANT
BOB D. CAMPBELL & CO.
4338 BELLEVIEW AVE.KANSAS CITY, MO 64111PH: 816.531.4144
FOR THE CURATORS OF THE UNIVERSITY OF MISSOURI
MECHANICAL, ELECTRICAL, AND PLUMBING CONSULTANT
W.L. CASSELL & ASSOCIATES
1600 BALTIMOREKANSAS CITY, MO 64108PH: 816.842.837
LIGHTING CONSULTANT
FISHER MARANTZ STONE
22 WEST 19TH STREETNEW YORK, NEW YORK 10011PH: 212.691.3020
7/24
/201
9 1:
55:1
7 PM A216
NEW ELEVATIONS -PHASE TEN
CP180131July 24, 2019
LB, MR
LB, MR
MA
MA
WOMEN'S ANDCHILDREN'SHOSPITAL -EXTERIORENVELOPEREPLACEMENT
ISSUE FOR BID: EXTERIORENVELOPE PACKAGE ONEADDENDUM #2
B10KEY PLAN B5ELEVATION NOTESB22NOT USED B1KEYNOTES
DIVISION32 EXTERIOR IMPROVEMENTS
DIVISION31 EARTHWORK
DIVISION26 ELECTRICAL
DIVISION23 HVAC
DIVISION22 PLUMBING
DIVISION14 CONVEYING EQUIPMENT
DIVISION12 FURNISHINGS
DIVISION09 FINISHES
DIVISION08 OPENINGS081113.A HOLLOW METAL DOOR FRAME081113.B HOLLOW METAL DOOR
DIVISION07 THERMAL + MOISTURE PROTECTION074213.A 3" INSULATED METAL FLAT PANEL -
HORIZONTAL PROFILE074213.E INTEGRATED FIXED LOUVER UNIT074213.F SHOP-FORMED INSULATED METAL PANEL
CORNER076200.B PREFINISHED METAL COPING076200.C PREFINISHED METAL BASE FLASHING076200.F PREFINISHED METAL CONTINUOUS CLEAT
DIVISION06 WOOD, PLASTICS + COMPOSITES
DIVISION05 METALS055000.E ROOF ACCESS LADDER
DIVISION04 MASONRY
DIVISION03 CONCRETE
000000.X
000000.X
EXISTING CONSTRUCTION
EXISTING CONSTRUCTION
TAG ALL MATERIALS WITH THEIR LOCATIONS AND SEQUENCING FOR RE-USE. REPAIR AND CLEAN ANY DAMAGED MATERIALS PRIOR TO BEING RE-SET.
NEW CONSTRUCTION
000000.X
DIVISION10 SPECIALTIES
DIVISION11 EQUIPMENT
0' 2' 4' 8'0' 2' 4' 8'
0' 2' 4' 8'0' 2' 4' 8'
SCALE: 1/4" = 1'-0" Q5NORTH PENTHOUSE - NORTH ELEVATION - PHASE TEN
SCALE: 1/4" = 1'-0" AA5NORTH PENTHOUSE - SOUTH ELEVATION - PHASE TENSCALE: 1/4" = 1'-0" AA24NORTH PENTHOUSE - WEST ELEVATION - PHASE TEN
SCALE: 1/4" = 1'-0" Q24NORTH PENTHOUSE - EAST ELEVATION - PHASE TEN
AA24 / A216
AA5
/ A21
6
Q5
/ A21
6
Q24 / A216NO. REVISION SUBMISSION DATE
0 ISSUE FOR BID, DESIGNPACKAGE ONE
07/03/2019
1 ADDENDUM #2 07/24/2019
E.L. 773' - 11 3/8"LEVEL 2 & T.O. MASONRY
C
4"
075216.F
075216.E
075216.D
075216.C
075216.A075216.B
075216.H
076200.G076200.F
074213.J
074213.H
074213.N
072726.A
074213.A
078443.C
078443.A
078443.B
092216.C
092900.A
072100.A
054000.A
061600.A
072100.CTWO-PIECE
1"
079200.A
076200.H
076200.P 076200.H
123456789101112
123456789101112
A
B
C
D
E
F
G
H
J
A
B
C
D
E
F
G
H
J
© 2019 INTERNATIONAL ARCHITECTS ATELIER
MAJID AMIRAHMADI - ARCHITECTMO#: A-5077
The Professional Architect's seal affixed to this sheet applies only to the material and items shown on this sheet. All drawings,
instruments, or other documents not exhibiting this seal shall not be considered prepared by this architect, and this architect expressly disclaims any and all responsibility for such plans,
drawings, or documents not exhibiting this seal.
SEAL:
816 471 6522 | 816.471.3755 | I-A-A.COMF: W:
MISSOURI STATE CERTIFICATE OF AUTHORITY #000582
912 BROADWAY BLVD, SUITE 300 | KANSAS CITY, MO 64105
TM
ADDENDUM #2
7/24/2019 1:55:58 PM
AD-01
WOMEN'S AND CHILDREN'SHOSPITAL - EXTERIOR ENVELOPEREPLACEMENT
July 24, 2019
SCALE: 3" = 1'-0" B5TYPICAL BASE FLASHING DETAIL
5 6 7 8 9 10
D
C.1
C
B.1
B
1
PATIENT ROOM
3336
PATIENT ROOM
3335
PATIENT ROOM
3334
PATIENT ROOM
3333
CALL ROOM
3332
CALL ROOM
3331
STAFF RR/SHW'R
3331A
STAFF RR/SHW'R
3332A
RR/SHW'R
3333A
RR/SHW'R
3334A
RR/SHW'R
3335A
RR/SHW'R
3336A
STAFF RR
3337ADISCONNECT AND REMOVE EXISTING DRYER
VENT THROUGH SECOND FLOOR WALL AND
ASSOCIATED DUCTWORK. CAP ABANDONED DUCTWORK BEYOND DEMO ZONE.
3
01 1 2 3 4 5 6
D
C.1
C
B.1
B
12"x10"DISC & REMOVE EXISTING DISCHARGE
OUTLET & PORTION OF DUCTWORK AS
REQUIRED FOR METAL PANEL REPLACEMENT. CLEAN & REINSTALL DISCHARGE DUCTWORK.
STAIR
S4001
PUBLIC RR
4112A
DICTATION ROOM
4111A
PATIENT ROOM
4402
PATIENT ROOM
4403
NURSERY
4404
STORAGE
4405
FAMILY WAITING
ROOM
4201
SEE SHEET PM102
FOR CONTINUATION
3
DISCONNECT AND REMOVE EXISTING
SPRINKLER DRAIN PIPING THOUGH
EXTERIOR WALL AND RE-ROUTE AS SHOWN.
PHASE
THREE
NORTH
PENTHOUSE
SOUTH
PENTHOUSE
PHASE
FOUR
HATCH KEY
INDICATES ADJOINING EXISTING
CONSTRUCTION NOT IN CONTRACT.
DATE:
DESIGNED BY:
CHECKED BY:
PROJ. NO.:
1234567891011121314151617181920212223242526272829303132333436
1234567891011121314151617181920212223242526272829303132333436
A
B
C
D
E
F
G
H
J
K
L
M
N
P
Q
R
S
T
U
V
W
X
Y
Z
AA
BB
CC
A
B
C
D
E
F
G
H
J
K
L
M
N
P
Q
R
S
T
U
V
W
X
Y
Z
AA
BB
CC
DD DD
© 2019 INTERNATIONAL ARCHITECTS ATELIER
BRUCE E. HARTMO#: E-22817
The Professional Engineers seal affixed to this sheet appllies only to the material and items shown on this sheet. All drawings, instruments, or other documents not exhibiting this seal shall not be considered prepared by this engineer, and this engineer expressly disclaims any and all responsibility for such plan, drawings, or documents not exhibiting this seal.
APPROVED BY:
DRAWN BY:
SEAL:
35
35
EE
FF
GG
HH
JJ
KK
373839404142
373839404142
EE
FF
GG
HH
JJ
KK
816 471 6522 | 816.471.3755 | I-A-A.COMP: F: W:
MISSOURI STATE CERTIFICATE OF AUTHORITY #000582
912 BROADWAY BLVD, SUITE 300 | KANSAS CITY, MO 64105
STRUCTURAL CONSULTANT
BOB D. CAMPBELL & CO.
4338 BELLEVIEW AVE.KANSAS CITY, MO 64111PH: 816.531.4144
FOR THE CURATORS OF THE UNIVERSITY OF MISSOURI
MECHANICAL, ELECTRICAL, AND PLUMBING CONSULTANT
W.L. CASSELL & ASSOCIATES
1600 BALTIMOREKANSAS CITY, MO 64108PH: 816.842.837
LIGHTING CONSULTANT
FISHER MARANTZ STONE
22 WEST 19TH STREETNEW YORK, NEW YORK 10011PH: 212.691.3020
07/03/19
7/2
4/2
019 1
:32:1
7 P
M M101.1
PHASES 3 & 4 -
MECHANICAL
EXTERIOR WALL
PENETRATIONS
CP180131
07/03/2019
MCS
MCS
SGB
SGB
WOMEN'S AND
CHILDREN'S
HOSPITAL -
EXTERIOR
ENVELOPE
REPLACEMENT
ISSUE FOR BID: EXTERIOR
ENVELOPE PACKAGE ONE
SCALE: 1/4" = 1'-0" U53RD FLOOR - MECHANICAL PLAN - PHASE THREE
SCALE: 1/4" = 1'-0" B144TH FLOOR - MECHANICAL PLAN - PHASE FOUR
B15NOT USED
B5KEY PLAN
B1NOTES
KEYED NOTES:
1 REMOVE LOUVER AND PORTION OF EXISTING DUCTPENETRATING WALL FOR REMOVAL & REPLACEMENT OFEXISTING BUILDING FAÇADE. PROTECT REMAININGDUCTWORK. NEW LOUVER FURNISHED & INSTALLED UNDERARCHITECTURAL SECTION. RECONNECT DUCTWORK TOLOUVER.
MECHANICAL DEMOLITION
GENERAL NOTES. .
1 SEE SHEET PM000 FOR GENERAL NOTES AND SYMBOLS LISTS.
2 WORK SHOWN LIGHTLY IS EXISTING TO REMAIN.CONTRACTOR SHALL FIELD VERIFY EXISTING CONDITIONS.
3 CONTRACTOR SHALL REFER TO ARCHITECTURAL PLANS FORDETAILS AND COORDINATE ALL PHASES OF THE WORK WITHARCHITECTURAL AND OTHER TRADES TO MINIMIZEDISTRUPTION TO AREAS OUTSIDE OF CURRENT AREA OFCONSTRUCTION.
4 THIS IS A CONTINUOUSLY OPERATING BUILDING AND SHUTDOWNS SHALL BE MINIMIZED AS ABSOLUTELY POSSIBLE ANDSHALL BE COORDINATED WITH OWNER A MIN. OF 2 WEEKSBEFORE PROPOSED SHUTDOWNS.
5 FIELD VERIFY ALL EXISTING EQUIPMENT, DUCTWORK, & PIPESIZES.
MECHANICAL PIPING
DEMOLITION GENERAL NOTES. .
1 SEE SHEET M000 FOR GENERAL NOTES AND SYMBOLS LISTS.
0
NO. REVISION SUBMISSION DATE
0 ISSUE FOR BID, DESIGNPACKAGE ONE
07/03/2019
3 ADDENDUM #2 PACKAGEONE
07/24/2019
01 1 2 3 4 5
E
E.1
D.1
2
12"ø
02 01 1
i.2
i.1
H.1
1
16"x10"
PATIENT ROOM
5554
PATIENT ROOM
5555
02 01 1
H.1
G.1
F.1
E.1
1
36"x16"
24"x8"
PICU ROOM
4449
PICU Room
4450
PICU ROOM
4451
PICU ROOM
4452
PHASE
FIVENORTH
PENTHOUSE
SOUTH
PENTHOUSE
PHASE
SIX
PHASE
NINE
PHASE
TEN
03 02 01 1
C.1
B.1
A.1
1
36"x16"
PICU ROOM
4441
PICU ROOM
4440
PICU ROOM
4442
PICU ROOM
4443
CRIB STORAGE
4444
FAMILY WAITING
ROOM
4201
4
SEE SHEET
M101 FOR
CONTINUATION
3
01 1
F.1
3
LOCATION OF EXTERIOR
ENVELOPE MOCK-UP
UNIT. TO BE
CONDUCTED PRIOR TO FIRST PHASE OF
CONSTRUCTION. RE:
ARCH.
HATCH KEY
INDICATES ADJOINING EXISTING
CONSTRUCTION NOT IN CONTRACT.
DATE:
DESIGNED BY:
CHECKED BY:
PROJ. NO.:
1234567891011121314151617181920212223242526272829303132333436
1234567891011121314151617181920212223242526272829303132333436
A
B
C
D
E
F
G
H
J
K
L
M
N
P
Q
R
S
T
U
V
W
X
Y
Z
AA
BB
CC
A
B
C
D
E
F
G
H
J
K
L
M
N
P
Q
R
S
T
U
V
W
X
Y
Z
AA
BB
CC
DD DD
© 2019 INTERNATIONAL ARCHITECTS ATELIER
BRUCE E. HARTMO#: E-22817
The Professional Engineers seal affixed to this sheet appllies only to the material and items shown on this sheet. All drawings, instruments, or other documents not exhibiting this seal shall not be considered prepared by this engineer, and this engineer expressly disclaims any and all responsibility for such plan, drawings, or documents not exhibiting this seal.
APPROVED BY:
DRAWN BY:
SEAL:
35
35
EE
FF
GG
HH
JJ
KK
373839404142
373839404142
EE
FF
GG
HH
JJ
KK
816 471 6522 | 816.471.3755 | I-A-A.COMP: F: W:
MISSOURI STATE CERTIFICATE OF AUTHORITY #000582
912 BROADWAY BLVD, SUITE 300 | KANSAS CITY, MO 64105
STRUCTURAL CONSULTANT
BOB D. CAMPBELL & CO.
4338 BELLEVIEW AVE.KANSAS CITY, MO 64111PH: 816.531.4144
FOR THE CURATORS OF THE UNIVERSITY OF MISSOURI
MECHANICAL, ELECTRICAL, AND PLUMBING CONSULTANT
W.L. CASSELL & ASSOCIATES
1600 BALTIMOREKANSAS CITY, MO 64108PH: 816.842.837
LIGHTING CONSULTANT
FISHER MARANTZ STONE
22 WEST 19TH STREETNEW YORK, NEW YORK 10011PH: 212.691.3020
07/03/19
7/2
4/2
019 1
:32:1
9 P
M PM102.1
PHASES 5, 6, 9, & 10 -
PLUMB & MECH
EXTERIOR WALL
PENETRATIONS
CP180131
07/03/2019
MCS
MCS
SGB
SGB
WOMEN'S AND
CHILDREN'S
HOSPITAL -
EXTERIOR
ENVELOPE
REPLACEMENT
ISSUE FOR BID: EXTERIOR
ENVELOPE PACKAGE ONE
SCALE: 1/4" = 1'-0" V142ND FLOOR - MECHANICAL PLAN - PHASE FIVE
SCALE: 1/4" = 1'-0" L145TH FLOOR - MECHANICAL PLAN - PHASE NINESCALE: 1/4" = 1'-0" L54TH FLOOR - MECH PLAN - PHASE TEN
B5KEY PLAN
B1NOTES
KEYED NOTES:
1 REMOVE LOUVER AND PORTION OF EXISTING DUCTPENETRATING WALL FOR REMOVAL & REPLACEMENT OFEXISTING BUILDING FAÇADE. PROTECT REMAININGDUCTWORK. NEW LOUVER FURNISHED & INSTALLED UNDERARCHITECTURAL SECTION. RECONNECT DUCTWORK TOLOUVER.
2 REMOVE PORTION OF EXISTING DUCT PENETRATING WALLFOR REMOVAL & REPLACEMENT OF EXISITNG BUILDINGFAÇADE. RECONNECT DUCTWORK AFTER FAÇADE HAS BEENREPLACED.
3 DISC. & REMOVE EXISTING ABANDONED PIPING SHOWN DARK& DASHED. CAP BACK AT VALVE.
4 RE-ROUTE EXISTING SPRINKLER DRAIN PIPING THROUGH NEWEXTERIOR METAL PANEL. COORDINATE EXACT LOCATION ASDIRECTED BY ARCHITECT.
SCALE: 1/4" = 1'-0" B274TH FLOOR - MECHANICAL PLAN - PHASE SIX
MECHANICAL DEMOLITION
GENERAL NOTES. .
1 SEE SHEET PM000 FOR GENERAL NOTES AND SYMBOLS LISTS.
2 WORK SHOWN LIGHTLY IS EXISTING TO REMAIN.CONTRACTOR SHALL FIELD VERIFY EXISTING CONDITIONS.
3 CONTRACTOR SHALL REFER TO ARCHITECTURAL PLANS FORDETAILS AND COORDINATE ALL PHASES OF THE WORK WITHARCHITECTURAL AND OTHER TRADES TO MINIMIZEDISTRUPTION TO AREAS OUTSIDE OF CURRENT AREA OFCONSTRUCTION.
4 THIS IS A CONTINUOUSLY OPERATING BUILDING AND SHUTDOWNS SHALL BE MINIMIZED AS ABSOLUTELY POSSIBLE ANDSHALL BE COORDINATED WITH OWNER A MIN. OF 2 WEEKSBEFORE PROPOSED SHUTDOWNS.
5 FIELD VERIFY ALL EXISTING EQUIPMENT, DUCTWORK, & PIPESIZES.
MECHANICAL PIPING
DEMOLITION GENERAL NOTES. .
1 SEE SHEET M000 FOR GENERAL NOTES AND SYMBOLS LISTS.
0
0' 2' 4' 8'
0' 2' 4' 8'
0' 2' 4' 8'
SCALE: 1/4" = 1'-0" B142ND FLOOR - PLUMBING PLAN - PHASE TEN0' 2' 4' 8'
NO. REVISION SUBMISSION DATE
0 ISSUE FOR BID, DESIGNPACKAGE ONE
07/03/2019
3 ADDENDUM #2 PACKAGEONE
07/24/2019
3
Pre-Bid RFI Responses– Page 1 of 7
Women’s and Children’s Hospital – Exterior Envelope Replacement
University of Missouri Project No. CP180131
July 24, 2019
Pre-Bid RFI Reponses:
Specification Section 075216 - SBS Modified Bituminous Membrane Roofing:
1. I have been in contact with several of the roof system manufacturer’s listed as approved per 075216, 2.1, B. Per their searches of Factory Mutual (FM) assemblies no manufacturer has testing of this roof assembly meaning that not only is an official RoofNav unavailable, but there is not a listed assembly for a FM 1A-90 as required per 075216, 1.5, D, 1, b. Approvals over gypsum decks are somewhat limited. The system as specified would perform fine and we can base fastening and adhesive rates as if the materials are being installed over a different deck type for FM 1A-90.
• Women’s and Children’s Hospital is insured by FM Global. The materials and installation of roof assembly shall meet FM 1A-90, but testing of the roof assembly is not required.
2. Will the thickness of the new insulation work with the height of the existing roof access door thresholds?
• No, door sills have been modified to meet new insulation thicknesses.
3. 2.2, A, 1 - VOC Limits – can you provide the roof adhesives VOC limits as required by MU Health?
• The allowable maximum VOC limit is 250 g/L.
4. 2.3, B - Fasteners – Perlok fasters are marketed by Performance Roof Systems and they are not a listed approved manufacturer. Can the listed manufacturer’s similar fastener be used?
• Yes, as long as the product has been submitted for review and accepted by the Architect.
5. 2.5 - Vapor Retarder – This is an APP Modified sheet and not self-adhered. Per section 3.5 Installation of Vapor Barrier this is to be a self-adhered sheet. Most manufacturer’s market a self- adhered vapor barrier such as GAF’s SF Vaper Retarder and JM’s SA Vapor Retarder. Would these be acceptable in lieu of the APP sheet specified in section 2.5?
• Yes.
6. 2.6/2.7, E – Modified cant strips – these are only marketed by Performance Roof System and Soprema as part of their assemblies. Can we use the manufacturer’s recommended standard perlite or woodfiber cant strips?
• Yes.
7. 3.3, A - This section references a FM RoofNav listed roof assembly. A FM RoofNav listed assembly is not required per section 1.5, D Code Approvals. Is a FM RoofNav listed assembly required? This may not be available for the system as specified.
• Women’s and Children’s Hospital is insured by FM Global. The materials and installation of roof assembly shall meet FM 1A-90, but testing of the roof assembly is not required.
Pre-Bid RFI Responses– Page 2 of 7
Women’s and Children’s Hospital – Exterior Envelope Replacement
University of Missouri Project No. CP180131
July 24, 2019
8. 3.4, A, 3 - This section references a FM RoofNav listed roof assembly. A FM RoofNav listed assembly is not required per section 1.5, D Code Approvals. Is a FM RoofNav listed assembly required? This may not be available for the system as specified.
• Women’s and Children’s Hospital is insured by FM Global. The materials and installation of roof assembly shall meet FM 1A-90, but testing of the roof assembly is not required.
9. 3.4, A 3 - This section requires us to fasten the substrate board to the existing gypsum deck. Per section 2.3, B we are to use a Perlok type fastener. These are only available in 1.4” and 1.8” lengths. The required MINIMUM penetration into the gypsum deck is 1.25”. We cannot achieve the 1.25” minimum attaching 5/8” Glass Mat Sheathing. Can we adhere the substrate board with Bead-Applied Insulation Adhesive per 2.6/2.7, B? Or, can the substrate board be omitted at we install a mechanically attached base sheet to the gypsum deck prior to the installation of the vapor barrier per 3.6, E – Installation over Filled Gypsum Decking?
• Provide fasteners to meet required minimum penetration into gypsum deck.
10. 3.5, A - The vapor barrier per section 2.5 is not self-adhered.
• Addressed by Addendum #2.
11. 3.6, D, 1, I - Is a FM RoofNav listed assembly required? This may not be available for the system as specified.
• Women’s and Children’s Hospital is insured by FM Global. The materials and installation of roof assembly shall meet FM 1A-90, but testing of the roof assembly is not required.
12. 3.7, A, 4 - Is a FM RoofNav listed assembly required? This may not be available for the system as specified.
• Women’s and Children’s Hospital is insured by FM Global. The materials and installation of roof assembly shall meet FM 1A-90, but testing of the roof assembly is not required.
13. 3.7, A, 4, a – What is this sheathing paper? It is not part of the listed roof manufacturers assemblies.
• Addressed by Addendum #2.
14. 3.9, B - What is this sheathing paper? It is not part of the listed roof manufacturer’s base sheets listed.
• Addressed by Addendum #2.
15. 3.9, C, D and 3.10, A - discusses installation of base sheets. Per the listed roof manufacturers base sheets, we are only installing two (2) base plies. Please confirm.
• To meet 30-year warranty, refer to each manufacturer’s recommended assembly.
16. 3.13, 1 – Are we to follow the walkway installation instructions per this section, or follow the walkway layout provided on plan sheets A117 and A118?
• Refer to drawings.
Pre-Bid RFI Responses– Page 3 of 7
Women’s and Children’s Hospital – Exterior Envelope Replacement
University of Missouri Project No. CP180131
July 24, 2019
17. 3.14, B Flood Testing - Will an engineer’s certification be provided confirming that the roof structure can withstand the weight of the water on the roof?
• Per the Structural Engineer, the roof structure can withstand the weight of the water on the roof.
Specification Section 055000 – Metal Fabrications:
18. 2.7, A – Basis of design is Standard Sheet Metal. I would assume we would be able to custom fabricate our own perforated metal panels and structure to conform to the requirements outlined in this spec. Please confirm.
• Yes, pending approval by Architect.
General:
19. Verify that all roof deck surfaces are structurally sloped and that tapered insulation isn’t
necessary.
• Yes, all roof deck surfaces are structurally sloped, and tapered insulation is not necessary.
20. Vapor Retarder specified in section 2.4 of 075216 is said to be APP modified in Cold Adhesive. Vapor Retarder in section 2.5 (Installation) is said to be self-adhering vapor retarder. Please clarify vapor retarder requirements
• Addressed by Addendum #2.
21. Please clarify that a type x substrate board will be required on a gyp fill roof deck. Also, I doubt that a Type X substrate board has been tested as part of this roof system per FM standards.
• Not required.
22. Per 075216 section 3.6.D.i.1 the iso to be adhered in full spread adhesive? Is 4” O.C. beads an acceptable method of attachment?
• No.
23. Confirm specified 5.2” thick/R-30 value (075216 Section 2.5.B.1) is required. Plans show 4” ISO thickness or R-23 value.
• The existing gypsum deck at its minimum depth near the roof drains has an R-Value of
2.3. The roof assembly, including the existing gypsum deck, must be designed to achieve a R-value minimum of 30.
24. Please confirm that all roof decks are gyp fill on 1” form board per the plan details and drawings.
• Per as-built drawings, all roofs are gypsum fill on 1” form board, except for Roof “S”, which is a sloped metal deck.
Pre-Bid RFI Responses– Page 4 of 7
Women’s and Children’s Hospital – Exterior Envelope Replacement
University of Missouri Project No. CP180131
July 24, 2019
25. Should the Roof Specification hold the products to a minimum ASTM D6162 instead of the ASTM D6164 that is listed?
• ASTM D6164 is for Standard Specification for Styrene Butadiene Styrene (SBS) Modified Bituminous Sheet Materials using polyester reinforcements and ASTM D6162 is for Standard Specification for Styrene Butadiene Styrene (SBS) Modified Bituminous Sheet Materials using a combination of polyester and glass fiber reinforcements. Specification requires meeting ASTM D6164.
26. Was a pullout test ever performed on the gypsum deck? If so, can we get the results?
• No, a pullout test has not been performed.
27. Detail T5/A320 is showing horizontal panel jamb details, based upon this it is acceptable to provide horizontal panels with a 3’4” and 1’2” module between the windows that equal the 4’ 6” dimension since no horizontal joints are shown. This will maintain a consistent horizontal joinery on the entire elevation, and prevent cutting and modifying the panels located between the windows and possibly voiding the 20-year weathertight warranty?
• Obtaining a 20-year water-tightness warranty is essential for this project. The Architect will work with the selected manufacturer to modify some detailing to meet their requirements.
28. Section 074213.19 per paragraph 2.3 C, 2.4, 2.5, and 2.6 specifies Centria Versacor Elite PF. Since the Louvers, Sun Shades, Windows and Extrusions are all spray applied, they will be a typical 2-coat Kynar that will have a 20-year finish warranty. Please advise if this is acceptable.
• Louvers, sun shades, windows, and extrusions shall get Centria Versacor Elite PF finish.
29. Section 074213.19 per paragraph 2.5 specifies integrated louvers, however the louver head and sill do not line up with the panel module heights. Will standard louver head and sill details be acceptable as long as the insulated metal wall panels manufacturer maintains the 20 year weathertight warranty?
• Obtaining a 20-year warranty is essential for this project. The Architect will work with the selected manufacturer to modify some detailing to meet their requirements.
30. Section 074213.19 per paragraph 2.6 specifies the Sun Screens to be integrated, but the details in the drawings do not reflect this. See attached for details from the basis of design for an integrated system. The DS Sunshade drawing shows the sunshades going into tubes, but this project will have a similar installation on studs. Please advise if this is the intent and will be required?
• The Architect will work with the selected manufacturer to modify some detailing to meet their requirements.
31. The membrane roofing will be replaced after the insulated metal wall panels have been installed. In many of the details there is a two-piece expansion joint labeled as 076200.F & G. Based upon the configuration this may allow some drainage between the air/membrane barrier and back of
Pre-Bid RFI Responses– Page 5 of 7
Women’s and Children’s Hospital – Exterior Envelope Replacement
University of Missouri Project No. CP180131
July 24, 2019
the flashing, becoming unhooked off the cleat, and difficult to install after the installation of insulated meta wall panels. Would the attached detail B5 sheet A520 which has been slightly modified to allow and or prevent the items above be acceptable?
• Please refer to attached Drawing AD-01 that clarifies the base flashing in Typical Base Detail B5.
32. The roof specs are for EPDM and the details are for modified. What are we to bid?
• Not applicable to this project.
33. The demolitions drawings say tear off the existing roofs and the roof plan mention overlay. What are we to bid?
• This project requires a total tear off of the existing roofing membrane. No overlay permitted.
07.2 Wall Panels Scope of Work:
34. Section B, Item 1: Calls out perforated panels. Is the spec section 055000 included in this scope of work?
• Yes, Add section 055000 Metal fabrications in its entirety
35. Please clarify who is responsible for the aluminum ladders and safety cages found in 055000.
• Wall Panel package will be responsible for these
36. Does the metal panel Mock-up need to be the final color?
• No. Color does not matter, but it needs to be the same system. Testing will be by others.
37. Section B, Item 8: Reads to include the required testing for the panel system, but spec section 074213.19-14, 3.6 D states “Owner shall engage a qualified testing agency to perform tests and inspections. Please define whom is responsible for contracting the qualified testing agency.
• Testing will be by others 07.3 Roofing, Flashing & Sheet Metal Scope of Work:
38. Can Nabholz provide a narrative of how material is to be moved up and down from roof if scaffolding is by others. Tell roofing bidder where they can hoist and stage material, dumpster location. We discussed and alternative staging location on the northwest corner, but could only set up a crane on weekends. Can we leave demolition on the roof?
• All contractors are responsible for their own hoisting to the roofs and moving materials from one area to the other. Overnight staging and dumpsters will only be allowed within the staging area South of Lansing Avenue and as coordinated with both Nabholz and MU. No access is allowed on the West side of the facility except from 5:30 Friday evening until 7:30 Monday morning or as coordinated and approved. Provide a deductive alternate to use crane provided by others for
Pre-Bid RFI Responses– Page 6 of 7
Women’s and Children’s Hospital – Exterior Envelope Replacement
University of Missouri Project No. CP180131
July 24, 2019
hoisting materials to each roof.
39. Will the roof replacement take place over occupied space? –
• Yes. All work required to be underneath will have to be done afterhours and as coordinated. Infectious control measures and interior demolition required to access above ceiling will be by others.
40. Does the building have an existing lighting protection system?
• No
41. Section A, Item 16: Are we to include more walkway protection than is shown on the plans? If so, can a lineal foot inclusion be provided so we are all including the same quantities?
• Include walk-pads/walkway protection as indicated on the drawings
42. Who demo’s the coping?
• Demolition of the parapet coping cap and the framing and blocking at the wall assembly will be by a future demolition package.
43. Section A, Item 18: Why would the roofing contractor be installing roof drains.
• Roof drains to be supplied and installed by future Plumbing package. Roofing package is responsible for flashing in and coordinating locations.
44. Section A, Item 21: Please clarify what this entails.
• Include testing as required per specification and Section 075216 RFI responses above.
45. Section B, Item 4: “Protect existing roofs, including roofs noted as NIC” Please clarify what
this entails. I understood in the pre-bid meeting that this would be covered in other scopes.
• Remove this note- roof protection will be the responsibility of other trades as their work requires.
46. Section B, Item 5. Include all temporary flashing/sealing necessary to meet phasing requirements. Please clarify what this entails.
• This is for sequencing of phasing within the Roofing package. Each trade will be responsible for their own temporary weathertightness between phases.
47. If temporary seal of existing roof to wall demo areas is to fall on roofing contractor, please provide an acceptable detail for what will be adequate and acceptable.
• The wall panel contractor will install their system first and will be responsible for sealing/weather protection at the base of wall to roof detail at the lower roofs. Roofing package to coordinate flashing details and tie-in to maintain roofing warranty.
48. Section B, Item 9: Installation of roof curbs should be by the mechanical contractor
providing the curbs
• Supply and install of roof curbs will be by others. Roof package to include tying in roof system to the curb and maintaining roof warranty.
49. Section D, Item 1: “Provide deductive alternate for a 20-year roof warranty” Will this entail reducing the roof system to a 2-ply assembly to conform to a typical 20-year modified roof system?
Pre-Bid RFI Responses– Page 7 of 7
Women’s and Children’s Hospital – Exterior Envelope Replacement
University of Missouri Project No. CP180131
July 24, 2019
• This only intended for systems that can meet the specification and provide savings for a 20-year warranty in lieu of 30-year.
50. Section E, Item 1: “Provide unit price to repair damaged gyp fill deck” Is this repair of the existing gypsum deck or removal and replacement similar to infill of the existing deck, note 7, on A117 & 118, B32 pm S502? If this is repair, please provide products and procedures required to repair this material.
• Provide a unit price and assumed products for the repair of existing gypsum deck and a separate unit price for the removal and replacement of existing gypsum deck per B32 on S502
51. Please confirm that MEP contractors will be responsible for all MEP equipment disconnects
and modifications.
• Yes
52. Who is responsible for painting striped line referenced in note 10 on sheet A117?
• Roofing package will be responsible
53. 1.5, B - Warranty- 36-month installer’s warranty: Will the liability of our surety need to be maintained for 36 months? This will be an additional cost. The typical agreement between the roof installer, manufacturer and our surety is 24 months.
• 36 months is required. Offer a voluntary alternate if relevant.