4 APM30 Installation Guide About This Chapter This describes the procedures and methods for installing the APM30. 4.1 Preparing for APM30 Installation Before installing the APM30, you must perform unpacking inspection and keep the tools and instruments ready. 4.2 Installing the APM30 The equipment to be installed include the extended battery cabinet, APM30 cabinet, Power Monitoring Unit (PMU), Power Supply Unit (PSU), user equipment, cables, and batteries. The extended battery cabinet and user equipment are optional and can be installed for specific needs. 4.3 Installing the Extended Battery Cabinet The extended battery cabinet of the APM30 can be installed on the concrete floor. 4.4 Installing the APM30 Cabinet The APM30 cabinet can be installed on the concrete floor, on an overhead platform, on a metal pole, or on a wall, depending on field conditions. 4.5 Installing the Power Monitoring Unit The Power Monitoring Unit (PMU) provides power system management, battery management, and environment monitoring for the APM30. 4.6 Installing the Power Supply Unit The power supply subrack of the APM30 is installed with three Power Supply Units (PSUs) for rectification. 4.7 Installing the User Equipment The APM30 provides space for the user equipment. APM30 installers can determine an appropriate position for the user equipment to meet actual needs. 4.8 Installing the Heater and Related Cables The heater can be installed in the APM30 cabinet or the extended battery cabinet. It applies to low-temperature environment. 4.9 Installing the Cables of the APM30 The cables to be installed on site include the AC input power cables, DC output power cables, PGND cables, and communication cables. APM30 User Guide 4 APM30 Installation Guide Issue 03 (2007-10-24) Huawei Technologies Proprietary 4-1

Upload: naveed-islam

Post on 22-Oct-2014

1.826 views

Category:

Documents


25 download

TRANSCRIPT

Page 1: 01-04 APM30 Installation Guide

4 APM30 Installation Guide

About This Chapter

This describes the procedures and methods for installing the APM30.

4.1 Preparing for APM30 InstallationBefore installing the APM30, you must perform unpacking inspection and keep the tools andinstruments ready.

4.2 Installing the APM30The equipment to be installed include the extended battery cabinet, APM30 cabinet, PowerMonitoring Unit (PMU), Power Supply Unit (PSU), user equipment, cables, and batteries. Theextended battery cabinet and user equipment are optional and can be installed for specific needs.

4.3 Installing the Extended Battery CabinetThe extended battery cabinet of the APM30 can be installed on the concrete floor.

4.4 Installing the APM30 CabinetThe APM30 cabinet can be installed on the concrete floor, on an overhead platform, on a metalpole, or on a wall, depending on field conditions.

4.5 Installing the Power Monitoring UnitThe Power Monitoring Unit (PMU) provides power system management, battery management,and environment monitoring for the APM30.

4.6 Installing the Power Supply UnitThe power supply subrack of the APM30 is installed with three Power Supply Units (PSUs) forrectification.

4.7 Installing the User EquipmentThe APM30 provides space for the user equipment. APM30 installers can determine anappropriate position for the user equipment to meet actual needs.

4.8 Installing the Heater and Related CablesThe heater can be installed in the APM30 cabinet or the extended battery cabinet. It applies tolow-temperature environment.

4.9 Installing the Cables of the APM30The cables to be installed on site include the AC input power cables, DC output power cables,PGND cables, and communication cables.

APM30User Guide 4 APM30 Installation Guide

Issue 03 (2007-10-24) Huawei Technologies Proprietary 4-1

Page 2: 01-04 APM30 Installation Guide

4.10 Installing the Batteries of the APM30Different batteries are used for the APM30 in different scenarios. The batteries can be installedin the APM30 cabinet without an extended battery cabinet. If the APM30 has an extended batterycabinet, the batteries are installed in the extended battery cabinet.

4.11 Sealing the Cable HolesThe cable holes need to be sealed with fireproof clay after the installation of the APM30 cables.

4.12 Checking the Installation of the APM30After the APM30 is installed, you must check the cabinet installation, electrical connections,power-on status, and field cleanliness.

4 APM30 Installation GuideAPM30

User Guide

4-2 Huawei Technologies Proprietary Issue 03 (2007-10-24)

Page 3: 01-04 APM30 Installation Guide

4.1 Preparing for APM30 InstallationBefore installing the APM30, you must perform unpacking inspection and keep the tools andinstruments ready.

Unpacking Inspection

The APM30 can be unpacked only after the equipment is delivered to the installation site. Theunpacking inspection must be performed by the representative of the customer and the personnelauthorized by Huawei.

To perform unpacking inspection, unpack the APM30, take out the Packing list, and then checkthe customer's name and address, machine number, total number of products, case number, andcontract number according to the Packing list.

l If the product type and quantity comply with the packing list, sign the Packing list with thecustomer.

l If there is any missing or wrong shipment, fill in the Cargo Problem Report and providefeedback for the order management engineer in the local Huawei office within three days.

Tools and Instruments

Table 4-1 lists the tools and instruments for the APM30 installation.

Table 4-1 Tools and instruments

Universal tool

Measurement Tool

5 m measuring tape

Markingtools

Marking pen, ink fountain, and pencil

Drillingtools

Percussion drill with drill bits Ф14 and Ф16, and cleaner

Fasteningtools

Straight screwdriver (M3 to M6)Cross screwdriver (M3 to M6)Adjustable wrenchSocket wrench (M6, M8, M12, M14, M17, M19)Double offset ring wrench M6, M8, M12, M14, M17, M19Combination wrench (M17 and M19)Long-arm wrench

Pliers Sharp-nose pliers, diagonal pliers, rubber hammer, and clawhammer

Auxiliarytools

Brush, paper knife, insulating tape, electric knife, and powerconnector board with 3 two-phase sockets and 3 three-phasesockets (current capacity > 15 A)

APM30User Guide 4 APM30 Installation Guide

Issue 03 (2007-10-24) Huawei Technologies Proprietary 4-3

Page 4: 01-04 APM30 Installation Guide

Special tools Earth resistance tester, ESD wrist strap, ESD gloves, cable peeler,crimping pliers, RJ-45 crimping pliers, wire punchdown tool, wirecutter, non-conductive screwdriver, multi-purpose crimpingpliers, and wire punchdown pliers

Instrument Digital multimeter

Space Requirements of the APM30

Figure 4-1 shows the space requirements of the APM30.

Figure 4-1 Space requirements of the APM30

4.2 Installing the APM30The equipment to be installed include the extended battery cabinet, APM30 cabinet, PowerMonitoring Unit (PMU), Power Supply Unit (PSU), user equipment, cables, and batteries. Theextended battery cabinet and user equipment are optional and can be installed for specific needs.

Procedure

Step 1 Install the APM30 cabinet. For details, refer to 4.4 Installing the APM30 Cabinet.

Step 2 Install the PMU and PSU. For details, refer to 4.5 Installing the Power Monitoring Unit and4.6 Installing the Power Supply Unit.

Step 3 Install the user equipment. For details, refer to 4.7 Installing the User Equipment.

Step 4 Install the cables. For details, refer to 4.9 Installing the Cables of the APM30.

4 APM30 Installation GuideAPM30

User Guide

4-4 Huawei Technologies Proprietary Issue 03 (2007-10-24)

Page 5: 01-04 APM30 Installation Guide

Step 5 Install the DC power cable of the BTS3006C/BTS3002E. For details, refer to 4.9.5 Installingthe DC Power Cable of the BTS3006C/BTS3002E.

Step 6 Check the installation of the APM30. For details, refer to 4.12 Checking the Installation of theAPM30.

----End

4.3 Installing the Extended Battery CabinetThe extended battery cabinet of the APM30 can be installed on the concrete floor.

ContextThe extended battery cabinet can be installed directly on the concrete floor or fixed on the baseof the APM30. In the following example, the extended battery cabinet is installed on the concretefloor. To install the extended battery cabinet on the base, which is the same as to install theAPM30 cabinet on the base, refer to 4.4.2 Installing the APM30 Cabinet on the ConcreteFloor.

NOTE

l When the extended battery cabinet is installed on the concrete floor, the cables must be led through theside cable holes at the lower part of the cabinet.

l When the extended battery cabinet is fixed on the base, the cables must be led through the cable holesat the bottom of the cabinet.

Figure 4-2 shows the space requirements of the extended battery cabinet.

Figure 4-2 Space requirements of the extended battery cabinet (unit: mm)

APM30User Guide 4 APM30 Installation Guide

Issue 03 (2007-10-24) Huawei Technologies Proprietary 4-5

Page 6: 01-04 APM30 Installation Guide

Procedure

Step 1 According to the space requirements, determine the position for installing the extended batterycabinet on the concrete floor.

Step 2 Mark the four anchor points according to the spacing between holes, as shown in Figure 4-3.

Figure 4-3 Determining the anchor points (unit: mm)

Step 3 Use a percussion drill with a Ф16 drill bit to make holes at the marked positions.

CAUTIONl When drilling holes, ensure that the drill bit is vertical to the floor.

l Ensure that the depth of the holes ranges from 52 mm to 60 mm.

Step 4 Use a cleaner to clear the dust inside and around the holes.

Step 5 Measure the spacing between the holes. If the spacing has an error, relocate and drill anotherhole before installing the expansion bolt assembly.

Step 6 Align the expansion bolt assemblies with the holes, and then use a claw hammer to hit eachassembly until the expansion tube is completely buried into the hole, as shown in Figure 4-4.

4 APM30 Installation GuideAPM30

User Guide

4-6 Huawei Technologies Proprietary Issue 03 (2007-10-24)

Page 7: 01-04 APM30 Installation Guide

Figure 4-4 Installing the expansion bolt assembly

(1) Bolt M12x 60

(2) Springwasher 12

(3) Flat washer12

(4) Expansion tube (5) Guiding slot (6) Guiding rib (7) Nut

CAUTIONWhen installing the expansion bolt assembly, ensure that the guiding rib of the nut are in fullcontact with the guiding slot of the tube.

Step 7 Remove the bolt M12 x 60, spring washer 12, and flat washer 12, as shown in Figure 4-5.

Figure 4-5 Disassembling the expansion bolt assembly

APM30User Guide 4 APM30 Installation Guide

Issue 03 (2007-10-24) Huawei Technologies Proprietary 4-7

Page 8: 01-04 APM30 Installation Guide

CAUTIONAfter disassembling the expansion bolt assembly, ensure that the top of the expansion tube ison the same level as the ground.

Step 8 Repeat Step 6 and Step 7 until all bolts are inserted into the expansion tubes.

Step 9 Place the extended battery cabinet on the concrete floor and align the holes at the bottom of thecabinet with the bolt holes in the floor.

Step 10 Install the spring washers and flat washers on the four bolts M12 x 60. Then lead the bolts intothe expansion tubes through the holes in the floor, as shown in Figure 4-6.

Figure 4-6 Fixing the cabinet

(1) Bolt M12 x 60 (2) Spring washer 12 (3) Flat washer 12 (4) Expansion tube (5) Concrete base

Step 11 Use a wrench to fasten the cabinet onto the ground by tightening the bolts clockwise.

----End

4 APM30 Installation GuideAPM30

User Guide

4-8 Huawei Technologies Proprietary Issue 03 (2007-10-24)

Page 9: 01-04 APM30 Installation Guide

4.4 Installing the APM30 CabinetThe APM30 cabinet can be installed on the concrete floor, on an overhead platform, on a metalpole, or on a wall, depending on field conditions.

4.4.2 Installing the APM30 Cabinet on the Concrete FloorThis describes how to install the APM30 cabinet on the concrete floor.

4.4.3 Install the APM30 Cabinet on an Overhead PlatformThis describes how to install the APM30 cabinet on an overhead platform.

4.4.4 Installing the APM30 Cabinet on a Metal PoleThis describes how to install the APM30 cabinet on a metal pole.

4.4.5 Installing the APM30 Cabinet on a WallThis describes how to install the APM30 cabinet on a wall.

4.4.6 Installing the APM30 Cabinet on the Extended Battery CabinetThe extended battery cabinet and the APM30 cabinet can be installed separately or installedtogether. Installing the APM30 cabinet on the extended battery cabinet can save space.

4.4.1 Installing the BaseWhen installing the APM30 cabinet on the concrete floor or on the overhead platform, you mustinstall the base and then fix the APM30 cabinet on the base.

ContextFigure 4-7 shows the base of the APM30.

Figure 4-7 Base of the APM30

Procedure

Step 1 Determine the position for the base according to Space Requirements of the APM30.

APM30User Guide 4 APM30 Installation Guide

Issue 03 (2007-10-24) Huawei Technologies Proprietary 4-9

Page 10: 01-04 APM30 Installation Guide

Step 2 Place the base in position and use a marking pen to mark four anchor points. You can also markthe four anchor points according to the spacing between holes, as shown in Figure 4-8.

Figure 4-8 Determining the anchor points (unit: mm)

Step 3 Use a percussion drill with a Ф16 drill bit to make holes at the marked points.

CAUTIONl Take measures when drilling holes lest the flying dust hurt your eyes or you inhale the dust.

l The expansion tube must be fully buried into the floor to ensure that the cabinet can standsteady on the floor.

l The depth of the hole must range from 52 mm to 60 mm. The depth of the hole must be thelength of the expansion tube plus the length of the drill bit. If the depth is out of the range,the expansion bolt cannot be fastened.

l If the floor is too hard or too smooth to hold the drill bit, use a chisel to dig a pit.

Step 4 Use a cleaner to clear the dust inside and around the holes.

Step 5 Measure the spacing between the holes. If the spacing is too long or too short, relocate and drillholes.

Step 6 Insert the guiding rib of the nut into the guiding slot of the expansion tube.

Step 7 Align the expansion bolt assemblies with the holes, and then use a claw hammer to hit eachassembly until the expansion tube is completely buried into the hole, as shown in Figure 4-9.

4 APM30 Installation GuideAPM30

User Guide

4-10 Huawei Technologies Proprietary Issue 03 (2007-10-24)

Page 11: 01-04 APM30 Installation Guide

Figure 4-9 Installing the expansion bolt assembly

(1) Bolt M12x 60

(2) Springwasher 12

(3) Flat washer12

(4) Expansion tube (5) Guiding slot (6) Guiding rib (7) Nut

Step 8 Remove the bolt M12 x 60, spring washer 12, and flat washer 12, as shown in Figure 4-10.

Figure 4-10 Disassembling the expansion bolt assembly

CAUTIONAfter disassembling the expansion bolt assembly, ensure that the top of the expansion tube ison the same level as the floor.

Step 9 Repeat Step 7 through Step 8 until all bolts are inserted into the expansion tubes.

Step 10 Place the base on the concrete floor and align the holes at the bottom of the base with the boltholes in the floor.

APM30User Guide 4 APM30 Installation Guide

Issue 03 (2007-10-24) Huawei Technologies Proprietary 4-11

Page 12: 01-04 APM30 Installation Guide

Step 11 Install the spring washers and flat washers on the four bolts M12 x 60. Then lead the bolts intothe expansion tubes through the holes in the floor, as shown in Figure 4-11.

Figure 4-11 Fixing the base

(1) Bolt M12 x 60 (2) Spring washer 12 (3) Flat washer 12 (4) Expansion tube

Step 12 Turn the bolts clockwise using a wrench to fix the base on the floor.

----End

4.4.2 Installing the APM30 Cabinet on the Concrete FloorThis describes how to install the APM30 cabinet on the concrete floor.

Context

CAUTIONThe APM30 in full configuration is 130 kg. The concrete floor must be able to bear the weightof a full APM30 cabinet.

4 APM30 Installation GuideAPM30

User Guide

4-12 Huawei Technologies Proprietary Issue 03 (2007-10-24)

Page 13: 01-04 APM30 Installation Guide

Procedure

Step 1 According to the Space Requirements of the APM30, determine the position for installing thecabinet on the concrete floor.

Step 2 Check the installation of the APM30. For details, refer to 4.4.1 Installing the Base.

Step 3 Lift the APM30 cabinet onto the base.

Step 4 Open the cabinet door.

Step 5 Adjust the position of the cabinet to align the holes at the bottom of the cabinet with the holesof the base.

Step 6 Lead each bolt M12 x 25 through the spring washer 12 and flat washer 12 in turn. Insert the boltassemblies into the holes at the bottom of the cabinet, and then tighten the four bolts diagonally,as shown in Figure 4-12.

Figure 4-12 Fixing the APM30 cabinet

(1) APM30 cabinet (2) Bolt M12 x 25 (3) Spring washer 12 (4) Flat washer 12 (5) Base

Step 7 Remove the lifting eyes and keep them for future use. Fill the sealing clay delivered with theAPM30 in the holes.

----End

4.4.3 Install the APM30 Cabinet on an Overhead PlatformThis describes how to install the APM30 cabinet on an overhead platform.

APM30User Guide 4 APM30 Installation Guide

Issue 03 (2007-10-24) Huawei Technologies Proprietary 4-13

Page 14: 01-04 APM30 Installation Guide

Context

CAUTIONThe APM30 in full configuration is 130 kg. The platform must be able to bear the weight of afull APM30 cabinet.

Procedure

Step 1 According to the Space Requirements of the APM30, determine the position for installing thecabinet on the overhead platform.

Step 2 Install the base on the overhead platform.

Step 3 Lift the APM30 cabinet onto the base.

Step 4 Open the cabinet door.

Step 5 Adjust the position of the cabinet to align the holes at the bottom of the cabinet with the holesof the base.

Step 6 Lead each bolt M12 x 25 through the spring washer 12 and flat washer 12 in turn. Insert the boltassemblies into the holes at the bottom of the cabinet, and then tighten the four bolts diagonally,as shown in Figure 4-13.

4 APM30 Installation GuideAPM30

User Guide

4-14 Huawei Technologies Proprietary Issue 03 (2007-10-24)

Page 15: 01-04 APM30 Installation Guide

Figure 4-13 Fixing the APM30 cabinet

(1) APM30 cabinet (2) Bolt M12 x 25 (3) Spring washer 12 (4) Flat washer 12 (5) Base

Step 7 Remove the lifting eyes and keep them for future use. Fill the sealing clay delivered with theAPM30 in the holes.

----End

4.4.4 Installing the APM30 Cabinet on a Metal PoleThis describes how to install the APM30 cabinet on a metal pole.

Context

CAUTIONThe APM30 in full configuration is 130 kg. The metal pole must be able to bear the weight ofa full APM30 cabinet.

Procedure

Step 1 Use bolts M10 x 180 and nuts to install the two fixture assemblies on the metal pole, as shownin Figure 4-14.

APM30User Guide 4 APM30 Installation Guide

Issue 03 (2007-10-24) Huawei Technologies Proprietary 4-15

Page 16: 01-04 APM30 Installation Guide

Figure 4-14 Installing the fixture assemblies

(1) Fixture assembly (2) Spring washer 10 (3) Flat washer 10 (4) Bolt M10 x 180 (5) Metal pole

Step 2 Fasten the bolts and nuts, as shown in Figure 4-15.

NOTE

Because it is very difficult to keep the two fixture assemblies on the same plane, Huawei recommends thatyou should not fasten the lower fixture assembly until the cabinet is properly positioned.

4 APM30 Installation GuideAPM30

User Guide

4-16 Huawei Technologies Proprietary Issue 03 (2007-10-24)

Page 17: 01-04 APM30 Installation Guide

Figure 4-15 Fastening the fixture assemblies

(1) Fixture assembly (2) Metal pole (3) Bolt M10 x 180 (4) Vertical plane (5) Horizontal plane

Step 3 Use screws M8 x 16 to install four mounting ears on the back of the APM30 cabinet, as shownin Figure 4-16.

Figure 4-16 Installing the mounting ears

APM30User Guide 4 APM30 Installation Guide

Issue 03 (2007-10-24) Huawei Technologies Proprietary 4-17

Page 18: 01-04 APM30 Installation Guide

Step 4 Install the screws assembled with spring washers and flat washers on the fixture assemblies andfasten the screws for six to seven pitches, as shown in Figure 4-17.

Figure 4-17 Installing the screws on the fixture assemblies

(1) Spring washer (2) Flat washer

Step 5 Lead the screws through the mounting ears, put on the spring washers and flat washers, and theninstall them on the fixture assemblies. Fasten the screws in turn, as shown in Figure 4-18.

4 APM30 Installation GuideAPM30

User Guide

4-18 Huawei Technologies Proprietary Issue 03 (2007-10-24)

Page 19: 01-04 APM30 Installation Guide

Figure 4-18 Installing the APM30 cabinet on the metal pole

Step 6 Use a wrench to tighten the bolts clockwise.

Step 7 Loosen the screws on the anchor bolt blocking plate, turn the anchor bolt hole blocking plate by180º, and then tighten the screws to block the anchor bolt holes, as shown in Figure 4-19 andFigure 4-20.

Figure 4-19 Anchor bolt hole

(1) Anchor bolt hole (2) Anchor bolt hole blocking plate

APM30User Guide 4 APM30 Installation Guide

Issue 03 (2007-10-24) Huawei Technologies Proprietary 4-19

Page 20: 01-04 APM30 Installation Guide

Figure 4-20 Blocking the anchor bolt hole

(1) Anchor bolt hole blocking plate (2) Bottom plate

----End

4.4.5 Installing the APM30 Cabinet on a WallThis describes how to install the APM30 cabinet on a wall.

ContextThe APM30 in full configuration is 130 kg. The wall must be able to bear the weight of a fullAPM30 cabinet.

Procedure

Step 1 According to the Space Requirements of the APM30, determine the position for installing thecabinet on the wall.

Step 2 Place the mounting bracket against the wall. Then mark four anchor points using a marking pen.You can also mark the four anchor points according to the spacing between holes, as shown inFigure 4-21.

4 APM30 Installation GuideAPM30

User Guide

4-20 Huawei Technologies Proprietary Issue 03 (2007-10-24)

Page 21: 01-04 APM30 Installation Guide

Figure 4-21 Determining the anchor points (unit: mm)

(1) Anchor point

Step 3 Use the percussion drill with a Ф12 bit to make holes at the marked points. Use a cleaner to clearthe dust both inside and around the holes. If the inter-hole spacing is too long or too short, locateand drill holes again.

CAUTIONl Take measures when drilling holes lest the flying dust hurt your eyes or you inhale the dust.

l The depth of the hole must range from 52 mm to 60 mm. The depth of the hole must be thelength of the expansion tube plus the length of the drill bit. If the depth is out of the range,the expansion bolt cannot be fastened.

l If the wall is too hard or too smooth to hold the drill bit, use a chisel to dig a hole.

Step 4 Mount the flat washer, spring washer, and nut on the expansion bolt M10 x 60, slightly fastenthem, and then put the expansion bolt into the hole. Hit the expansion bolt using a rubber hammeruntil the expansion tube is completely buried into the hole, as shown in Figure 4-22.

APM30User Guide 4 APM30 Installation Guide

Issue 03 (2007-10-24) Huawei Technologies Proprietary 4-21

Page 22: 01-04 APM30 Installation Guide

Figure 4-22 Installing the expansion bolt assembly

(1) Hole (2) Expansion bolt 10 x 60 (3) Wall

Step 5 Remove the nut, spring washer, and flat washer in turn.

CAUTIONAfter disassembling the expansion bolt assembly, ensure that the top of the expansion tube is atthe same level as the wall.

Step 6 Use screws M8 x 16 to install four mounting ears on the back of the APM30 cabinet, as shownin Figure 4-23.

4 APM30 Installation GuideAPM30

User Guide

4-22 Huawei Technologies Proprietary Issue 03 (2007-10-24)

Page 23: 01-04 APM30 Installation Guide

Figure 4-23 Installing the mounting ears

Step 7 Align the mounting ears with the four holes and insert them into the holes. Then, put the flatwasher, spring washer, and nut on the expansion bolt in turn and fasten the nut, as shown inFigure 4-24.

APM30User Guide 4 APM30 Installation Guide

Issue 03 (2007-10-24) Huawei Technologies Proprietary 4-23

Page 24: 01-04 APM30 Installation Guide

Figure 4-24 Fixing the APM30 cabinet

(1) Nut (2) Spring washer (3) Flat washer

Step 8 Turn the bolts clockwise using a wrench to secure the APM30 cabinet to the wall.

Step 9 Loosen the screws on the anchor bolt blocking plate, turn the anchor bolt hole blocking plate by180º, and then tighten the screws to block the anchor bolt holes, as shown in Figure 4-25 andFigure 4-26.

4 APM30 Installation GuideAPM30

User Guide

4-24 Huawei Technologies Proprietary Issue 03 (2007-10-24)

Page 25: 01-04 APM30 Installation Guide

Figure 4-25 Anchor bolt hole

(1) Anchor bolt hole (2) Anchor bolt hole blocking plate

Figure 4-26 Blocking the anchor bolt hole

(1) Anchor bolt hole blocking plate (2) Bottom plate

----End

4.4.6 Installing the APM30 Cabinet on the Extended Battery CabinetThe extended battery cabinet and the APM30 cabinet can be installed separately or installedtogether. Installing the APM30 cabinet on the extended battery cabinet can save space.

Space RequirementsFigure 4-27 shows the space requirements for installing the APM30 cabinet on the extendedbattery cabinet.

APM30User Guide 4 APM30 Installation Guide

Issue 03 (2007-10-24) Huawei Technologies Proprietary 4-25

Page 26: 01-04 APM30 Installation Guide

Figure 4-27 Space requirements for installing the APM30 cabinet on the extended batterycabinet (unit: mm)

Procedure

Step 1 Determine the position for installing the extended battery cabinet on the concrete floor byreferring to Figure 4-27.

Step 2 4.3 Installing the Extended Battery Cabinet on the concrete floor and apply fireproof clayaround the cable outlet at the top of the cabinet. This prevents water from entering the stackedcabinets, as shown in Figure 4-28.

Figure 4-28 Applying fireproof clay around the cable outlet

(1) Fireproof clay

Step 3 Lift the APM30 cabinet onto the extended battery cabinet. Align the cable inlet at the bottom ofthe APM30 cabinet with the cable outlet at the top of the extended battery cabinet. Place theAPM30 cabinet on the extended battery cabinet, as shown in Figure 4-29.

4 APM30 Installation GuideAPM30

User Guide

4-26 Huawei Technologies Proprietary Issue 03 (2007-10-24)

Page 27: 01-04 APM30 Installation Guide

Figure 4-29 Placing the APM30 cabinet on the extended battery cabinet

Step 4 Use bolts M12 x 10 to fasten the APM30 cabinet and the extended battery cabinet.

----End

4.5 Installing the Power Monitoring UnitThe Power Monitoring Unit (PMU) provides power system management, battery management,and environment monitoring for the APM30.

Context

CAUTIONTake proper ESD protection measures, for example, wear an ESD wrist strap or a pair of ESDgloves, to prevent electrostatic damage to the PMU.

The PMU of the APM30 is of two types. The front panels of the two types of PMU are shownin Figure 4-30 and Figure 4-32 respectively.

APM30User Guide 4 APM30 Installation Guide

Issue 03 (2007-10-24) Huawei Technologies Proprietary 4-27

Page 28: 01-04 APM30 Installation Guide

Figure 4-30 Front panel of the PMU (1)

(1) RS232/RS422 port (2) Indicator (3) Power test switch

(4) TEST port (5) Battery switch (6) COM port

NOTE

For the first type of PMU, the DIP switch is on the side of the PMU, as shown in Figure 4-31.

Figure 4-31 DIP switch on the PMU

4 APM30 Installation GuideAPM30

User Guide

4-28 Huawei Technologies Proprietary Issue 03 (2007-10-24)

Page 29: 01-04 APM30 Installation Guide

Figure 4-32 Front panel of the PMU (2)

(1) Indicator (2) Power test switch (3) Battery switch

(4) RS232/RS422 port (5) COM port

NOTE

For the second type of PMU, the DIP switch is at the rear of the PMU.

ProcedureStep 1 Determine the position for installing the PMU.

Figure 4-33 shows the position of the PMU.

Figure 4-33 Position of the PMU

Step 2 Set the DIP switch according to different applications of the APM30. Table 4-2 shows the settingof the DIP switch on the PMU of the APM30.

Figure 4-31 shows the DIP switch on the PMU.

APM30User Guide 4 APM30 Installation Guide

Issue 03 (2007-10-24) Huawei Technologies Proprietary 4-29

Page 30: 01-04 APM30 Installation Guide

Table 4-2 Setting the DIP switch on the PMU

Application ofthe APM30

DIP SwitchAddress

1 2 3 4

Working withGSM mini basestations

ON ON OFF OFF 3

Working withdistributed basestations

ON OFF OFF ON 9

Step 3 Place the PMU in the slot, loosen the screws on the handle of the PMU panel using a straightscrewdriver, as shown in Figure 4-34.

Figure 4-34 Loosening the screws on the handle

Step 4 Pull the handle on the PM panel, as shown in Figure 4-35.

Figure 4-35 Pulling the handle of the PMU panel

Step 5 Slide the PMU along the guide rails into the slot and then push the handle.

Step 6 Fasten the screws on the handle.

----End

4 APM30 Installation GuideAPM30

User Guide

4-30 Huawei Technologies Proprietary Issue 03 (2007-10-24)

Page 31: 01-04 APM30 Installation Guide

4.6 Installing the Power Supply UnitThe power supply subrack of the APM30 is installed with three Power Supply Units (PSUs) forrectification.

Context

CAUTIONTake proper ESD protection measures, for example, wear an ESD wrist strap or a pair of ESDgloves, to prevent electrostatic damage to the PMU.

Procedure

Step 1 Determine the position for installing the PSU.

Figure 4-36 shows the position of the PSU.

Figure 4-36 Position of the PSU

Step 2 Place the PSU in the slot, loosen the screws on the handle of the PSU panel using a straightscrewdriver, as shown in Figure 4-37.

APM30User Guide 4 APM30 Installation Guide

Issue 03 (2007-10-24) Huawei Technologies Proprietary 4-31

Page 32: 01-04 APM30 Installation Guide

Figure 4-37 Loosening the screws on the handle

Step 3 Pull the handle on the PSU panel, as shown in Figure 4-38.

Figure 4-38 Pulling the handle of the PSU panel

Step 4 Slide the PSU along the guide rails into the slot and then push the handle.

Step 5 Fasten the screws on the handle.

----End

4.7 Installing the User EquipmentThe APM30 provides space for the user equipment. APM30 installers can determine anappropriate position for the user equipment to meet actual needs.

Context

The user equipment that can be installed in the APM30 cabinet includes the BBU3806 andtransmission equipment. They are installed in the same way. The following task takes theBBU3806 as an example.

Procedure

Step 1 Determine the position for installing the BBU3806 in the APM30, as shown in Figure 4-39.

4 APM30 Installation GuideAPM30

User Guide

4-32 Huawei Technologies Proprietary Issue 03 (2007-10-24)

Page 33: 01-04 APM30 Installation Guide

Figure 4-39 Position for installing the BBU3806 in the APM30

(1) to (5) Filler panel (1 U)

NOTE

A space of 1 U under the power distribution box (position 1 shown in Figure 4-39) is unfurnished bydefault. The BBU3806 is usually installed in position 2 or 3, as shown in Figure 4-39.

Step 2 Loosen and remove the panel screws M6 x 12 from the mounting bar, and then remove the fillerpanel.

Step 3 Check whether there are floating nuts on the square holes of the mounting bar where screws ofthe BBU3806 panel may be installed. If there is no floating nut, install floating nuts on the screwholes, as shown in Figure 4-40.

APM30User Guide 4 APM30 Installation Guide

Issue 03 (2007-10-24) Huawei Technologies Proprietary 4-33

Page 34: 01-04 APM30 Installation Guide

Figure 4-40 Installing the floating nuts

NOTE

To install the floating nuts, do as follows:

1. Attach the lower part of the floating nut to the square hole.

2. Use a straight screwdriver to press the upper part into the square hole.

3. Release the screwdriver to make the upper part automatically hook to the square hole. Then, the floatingnut can be firmly fixed on the mounting bar.

Step 4 Slide the BBU3806 gently along the guide rails into the cabinet and fasten the screws M6 x 12on the panel, as shown in Figure 4-41.

4 APM30 Installation GuideAPM30

User Guide

4-34 Huawei Technologies Proprietary Issue 03 (2007-10-24)

Page 35: 01-04 APM30 Installation Guide

Figure 4-41 Sliding the BBU3806 along the guide rails into the cabinet

----End

4.8 Installing the Heater and Related CablesThe heater can be installed in the APM30 cabinet or the extended battery cabinet. It applies tolow-temperature environment.

Contextl A heater keeps the cabinet temperature higher than –10℃. When the internal temperature

of the cabinet is lower than 5℃, the heater starts to work; when the internal temperature ishigher than 15℃, the heater stops working.

l The maximum power consumption of a 220 V heater is 300 W.

Procedure

Step 1 Install a heater in the APM30 cabinet.1. Place the heater in position and gently push the heater along the heater tray until the holes

of the mounting ears are aligned with the holes in the support. Then, fasten the screwsdelivered with the cabinet, as shown in Figure 4-42.

APM30User Guide 4 APM30 Installation Guide

Issue 03 (2007-10-24) Huawei Technologies Proprietary 4-35

Page 36: 01-04 APM30 Installation Guide

Figure 4-42 Installing a heater in the APM30 cabinet

(1) Heater

2. Make the blue wire and brown wire of the power cable into OT terminals. Then, connectthe bare wires of the power cable to the L and N terminals on the heater respectively, asshown in Figure 4-43.

Figure 4-43 Connecting the power cable to the heater

3. Remove the nuts and flat washers from the screws of the voltage converter, align the grooveof the voltage converter with the screws, and then put on the flat washers and nuts, as shownin Figure 4-44.

4 APM30 Installation GuideAPM30

User Guide

4-36 Huawei Technologies Proprietary Issue 03 (2007-10-24)

Page 37: 01-04 APM30 Installation Guide

Figure 4-44 Installing the voltage converter of the heater

(1) Voltage converter (2) AC output power cable

4. Connect the OT terminals of the blue wire and brown wires to AC OUTPUT wiringterminals N2 and L2, as shown in Figure 4-44.

5. Connect the self-contained red and black power cables of the heater to the L and N wiringterminals on the voltage converter, and then bind the cables properly, as shown in Figure4-45.

Figure 4-45 Cable connections of the heater

Step 2 Install a heater in the extended battery cabinet.NOTEThe voltage converter must be installed before the heater in order not to affect equipment installation.

APM30User Guide 4 APM30 Installation Guide

Issue 03 (2007-10-24) Huawei Technologies Proprietary 4-37

Page 38: 01-04 APM30 Installation Guide

1. Install the voltage converter of the heater. For details about how to install the voltageconverter and connect related cables, go to 1.2 through 1.5. Figure 4-46 shows the positionfor installing the voltage converter.

Figure 4-46 Position for installing the voltage converter

(1) Position for installing the voltage converter (2) Position for installing the mounting ears

2. Remove the screws from the heater tray and then take out the tray.

Figure 4-47 Heater tray

(1) Heater tray

3. Align the holes of the mounting ears with the holes in the guiding slots, fasten the screws,and at the same time install the heater tray. Fix the heater on the tray, as shown in Figure4-47.

4. Bind related cables, as shown in Figure 4-48.

4 APM30 Installation GuideAPM30

User Guide

4-38 Huawei Technologies Proprietary Issue 03 (2007-10-24)

Page 39: 01-04 APM30 Installation Guide

Figure 4-48 Connecting related cables of the heater

(1) Input power cable of the heater

NOTEIf both APM30 cabinet and extended battery cabinet need to be installed with heaters, the AC inputpower cables of the two cabinets can be connected together to AC OUTPUT terminals N2 and L2.

----End

4.9 Installing the Cables of the APM30The cables to be installed on site include the AC input power cables, DC output power cables,PGND cables, and communication cables.

Description of the Power CablesCable Color

AC power cable (L wire) Brown

AC power cable (N wire) Blue

DC power cable (–48 V) Blue

DC power cable (RTN+) Black

PE cable Green and yellow

4.9.1 Installing the Grounding Cables of the APM30A grounding busbar is available inside the cabinet. The grounding bus of the cabinet, thegrounding cable of the surge protector, and the grounding cable of the user equipment areconnected to the grounding busbar.

APM30User Guide 4 APM30 Installation Guide

Issue 03 (2007-10-24) Huawei Technologies Proprietary 4-39

Page 40: 01-04 APM30 Installation Guide

4.9.2 Installing the AC Input Power Cable of the APM30The APM30 obtains AC input power through the AC input power cable.

4.9.3 Installing the Power Cable of the BBU3806When the APM30 is installed with only one BBU3806, the –48 V DC power cable (with signalwires) is used for the BBU3806. When the APM30 is installed with two BBU3806s, the –48 VDC power cable (with signal wires) is used for the active BBU3806 and the –48 V DC powercable (without signal wires) is used for the standby BBU3806.

4.9.4 Installing the DC Power Cable of the RRUThe DC power cable of the RRU is a shielded cable.

4.9.5 Installing the DC Power Cable of the BTS3006C/BTS3002EThe BTS3006C/BTS3002E obtains power from the APM30 and so you must use a DC powercable to connect the APM30 and the BTS3006C/BTS3002E.

4.9.6 Installing the Internal Communication Cables of the APM30For the APM30, the internal communication cables to be installed on site include the RS485communication cable and the PMU monitoring cable.

4.9.7 Installing the E1/T1 Cable of the BBU3806The E1/T1 cable transmits baseband signals between the BBU3806 and the RNC.

4.9.8 Installing the CPRI Optical Cable Between the BBU3806 and the RRU3801CThe CPRI optical cable connects the BBU3806 to the RRU3801C and transmits CPRI signalsbetween them.

4.9.9 Installing the Alarm Cable Between the APM30 and the BTS3006C/BTS3002EThis describes how to install the alarm cable between the APM30 and the BTS3006C/BTS3002E.

4.9.1 Installing the Grounding Cables of the APM30A grounding busbar is available inside the cabinet. The grounding bus of the cabinet, thegrounding cable of the surge protector, and the grounding cable of the user equipment areconnected to the grounding busbar.

Grounding Instructionsl Three lightning protection grounding terminals are available on each column in the front

of the cabinet. The user equipment can be grounded nearby. For the detailed groundingmethod, refer to the installation guide of the user equipment.

l The PGND cables of the door, DC power distribution subrack, AC surge protector, and DCsurge protector are connected before the delivery of the equipment. You need not connectthese PGND cables on site.

Procedure

Step 1 Determine the position of the grounding busbar in the APM30 cabinet, as shown in Figure4-49.

4 APM30 Installation GuideAPM30

User Guide

4-40 Huawei Technologies Proprietary Issue 03 (2007-10-24)

Page 41: 01-04 APM30 Installation Guide

Figure 4-49 Position of the grounding busbar in the APM30 cabinet

(1) Grounding busbar

Step 2 Remove the screws from the baffle plate in front of the base and take out the baffle plate, asshown in Figure 4-50.

Figure 4-50 Removing the baffle plate

Step 3 Remove the screws from the partition plates on both sides of the base and take out the baffleplates, as shown in Figure 4-51.

APM30User Guide 4 APM30 Installation Guide

Issue 03 (2007-10-24) Huawei Technologies Proprietary 4-41

Page 42: 01-04 APM30 Installation Guide

Figure 4-51 Removing the partition plates

Step 4 Route the grounding bus through the cable hole at the cabinet bottom, lead it into the cabinetthrough the cable hole for AC power cables, and then fix the OT terminal of the grounding busto the grounding busbar. Fasten the nuts on the grounding busbar.

Step 5 Connect the other end of the grounding bus to the outdoor grounding bar nearby.

----End

4.9.2 Installing the AC Input Power Cable of the APM30The APM30 obtains AC input power through the AC input power cable.

ContextWhen the 110 V AC dual-live-wire input is used, the L1 wire connects to AC terminal L andthe L2 wire connects AC terminal N. When the 220 V AC single-phase three-wire input is used,the L wire connects to AC terminal L, the N wire connects AC terminal N, and the PE wireconnects to the grounding terminal. This task takes the 220 V AC to 240 V AC single-phasethree-wire input as an example.

Figure 4-52 shows the AC wiring terminals on the power distribution unit.

Figure 4-52 AC wiring terminals

(1) AC output terminal (L1) (2) AC output terminal (L2) (3) AC input terminal (L)

(4) AC output terminal (N1) (5) AC output terminal (N2) (6) AC input terminal (N)

4 APM30 Installation GuideAPM30

User Guide

4-42 Huawei Technologies Proprietary Issue 03 (2007-10-24)

Page 43: 01-04 APM30 Installation Guide

NOTE

l Wiring terminals L and N are AC input terminals.

l Wiring terminals L1 and N1 are AC output terminals, which are connected to the power subrack.

l Wiring terminals L2 and N2 are AC output terminals, which are reserved for the heater.

Procedure

Step 1 Loosen the nut and remove the transparent protecting hood from the AC input terminal.

Step 2 Strip off the power cable jacket in proper length at one end to expose the L, N, and PE wires.

Step 3 Make the L, N, and PE wires into OT terminals.

Step 4 Lead the AC power cable into the APM30 cabinet through the cable hole, as shown in Figure4-53.

Figure 4-53 Leading the AC power cable through the cable hole

Step 5 Connect the OT terminals of the L and N wires to AC input terminals L and N on the powerdistribution unit. Connect the OT terminal of the PE wire to the grounding terminal and thentighten the nut.

Step 6 Secure the nut and the protecting hood.

Step 7 Bind the AC power cables neatly with cable ties.

APM30User Guide 4 APM30 Installation Guide

Issue 03 (2007-10-24) Huawei Technologies Proprietary 4-43

Page 44: 01-04 APM30 Installation Guide

CAUTIONl The AC power cables are shielded cables. An AC power cable inside the cabinet is shorter

than 100 mm. If the AC power cable is longer than 100 mm, it should be routed separatefrom other cables in an independent cavity.

l The AC power cables and the DC power cables should be routed separately.

l The power cables and the signal cables should be routed separately except when they arerequired for lightning protection and decoupling.

Step 8 Install the partition plates and seal the cable holes with fireproof clay, as shown in Figure4-54.

Figure 4-54 Sealing the cable holes

----End

4.9.3 Installing the Power Cable of the BBU3806When the APM30 is installed with only one BBU3806, the –48 V DC power cable (with signalwires) is used for the BBU3806. When the APM30 is installed with two BBU3806s, the –48 VDC power cable (with signal wires) is used for the active BBU3806 and the –48 V DC powercable (without signal wires) is used for the standby BBU3806.

DC Output TerminalsFigure 4-55 shows the DC output terminals on the front panel of the DC power distribution unit(PDU).

4 APM30 Installation GuideAPM30

User Guide

4-44 Huawei Technologies Proprietary Issue 03 (2007-10-24)

Page 45: 01-04 APM30 Installation Guide

Figure 4-55 DC output terminals

(1) DC output wiring terminalLOAD2

(2) DC output wiring terminalLOAD1

(3) Protecting hood of the DC wiringterminal

NOTE

l There are four pairs of DC output wiring terminals LOAD1 for power supply to RRU3801Cs and minibase stations.

l There are four pairs of DC output wiring terminals LOAD2 for power supply, one pair for the fans andthe other three pairs for the BBU3806 and user equipment.

Procedure

Step 1 Loosen the screws and remove the protecting hood of the DC wiring terminal.

Step 2 Remove the two green connectors from the left of the DFFU/APMI panel and connect the foursignal wires to the connectors.

The sequence of connecting the signal wires is shown in Figure 4-56.

Figure 4-56 Sequence of connecting the signal wires

CAUTION The signal wires must be connected to the ports labeled TX and RXon the panel of the DFFU/APMI accordingly.

Step 3 Make the blue wire and black wire of the power cable into OT terminals.

The power cable with OT terminals is shown in Figure 4-57.

APM30User Guide 4 APM30 Installation Guide

Issue 03 (2007-10-24) Huawei Technologies Proprietary 4-45

Page 46: 01-04 APM30 Installation Guide

Figure 4-57 BBU3806 power cable with OT terminals

Step 4 Link the 7W2 female connector of the power cable to the PWR/RS485 port on the panel of theBBU3806 and fasten the screws.

Step 5 Connect the blue wire and black wire of the power cable to one pair of DC output wiring terminalsLOAD2 on the PDU. The blue wire connects to wiring terminal NEG(-) and the black wireconnects to wiring terminal RTN(+),

Step 6 Plug the connector with signal wires into the panel of the DFFU/APMI.

NOTE

The signal wires are connected in the order of orange, white, blue, and white from left to right.

The connection of the BBU3806 power cable is shown in Figure 4-58.

Figure 4-58 Connecting the BBU3806 power cable

(1) Signal cable (2) Power cables

Step 7 Bind the cable with cable ties.

----End

4 APM30 Installation GuideAPM30

User Guide

4-46 Huawei Technologies Proprietary Issue 03 (2007-10-24)

Page 47: 01-04 APM30 Installation Guide

4.9.4 Installing the DC Power Cable of the RRUThe DC power cable of the RRU is a shielded cable.

Context

CAUTIONIf a DC power cable leads external power input to the RRU, the cable must be shielded. If theDC power cable is not shielded, the equipment is prone to lightning stroke.

Procedure

Step 1 Loosen the screws and remove the protecting hood of the DC wiring terminal.

Step 2 Strip off the power cable jacket and shielding layer about 100 mm.

Step 3 Make the blue wire and black wire of the power cable into OT terminals.

Step 4 Lead the power cable into the cabinet through the bottom hole for the DC power cable, andconnect the cable to one pair of wiring terminals LOAD1 for DC output on the power distributionbox. The blue wire connects to wiring terminal NEG(-) and the black wire connects to wiringterminal RTN(+), as shown in Figure 4-59.

Figure 4-59 Connecting the power cable of the RRU

Step 5 Strip off the power cable jacket about 20 mm to 30 mm from the part near the hole to exposethe shielding layer, as shown in Figure 4-60.

APM30User Guide 4 APM30 Installation Guide

Issue 03 (2007-10-24) Huawei Technologies Proprietary 4-47

Page 48: 01-04 APM30 Installation Guide

Figure 4-60 Shielding layer of the power cable

Step 6 Seal the DC cable hole with fireproof clay, bind the conductive cloth and shielding layer withcable ties, and ground the shielding layer, as shown in Figure 4-61.

Figure 4-61 Grounding the shielding layer of the power cable

NOTEBe cautious when you use the conductive cloth. The conductive cloth tears easily. If the conductive clothis torn, loosen the captive screws around the cable hole and use a piece of new cloth.

Step 7 Connect the other end of the DC power cable to the corresponding wiring terminal on the RRU.

Step 8 Bind the cable with cable ties.

----End

4.9.5 Installing the DC Power Cable of the BTS3006C/BTS3002EThe BTS3006C/BTS3002E obtains power from the APM30 and so you must use a DC powercable to connect the APM30 and the BTS3006C/BTS3002E.

4 APM30 Installation GuideAPM30

User Guide

4-48 Huawei Technologies Proprietary Issue 03 (2007-10-24)

Page 49: 01-04 APM30 Installation Guide

Procedure

Step 1 Loosen the screws and remove the protecting hood of the DC wiring terminal.

Step 2 Strip off the power cable jacket about 100 mm.

Step 3 Make the blue wire and black wire of the power cable into OT terminals.

Step 4 Prepare a corrugated pipe in proper length and lead the power cable through the corrugated pipeto wrap the part outside the APM30 cabinet with the pipe.

Step 5 Lead the power cable into the cabinet through the bottom hole for the DC power cable, andconnect the cable to one pair of wiring terminals LOAD1 for DC output on the power distributionunit. The blue wire connects to wiring terminal NEG(-) and the black wire connects to wiringterminal RTN(+), as shown in Figure 4-62.

Figure 4-62 Connecting the power cable of the BTS3006C/BTS3002E

Step 6 Connect the other end of the DC power cable to the corresponding wiring terminal on theBTS3006C/BTS3002E.

Step 7 Bind the cable with cable ties.

----End

4.9.6 Installing the Internal Communication Cables of the APM30For the APM30, the internal communication cables to be installed on site include the RS485communication cable and the PMU monitoring cable.

Procedure

Step 1 Unpack the connectors on the RS485 communication cable and the PMU monitoring cable.

APM30User Guide 4 APM30 Installation Guide

Issue 03 (2007-10-24) Huawei Technologies Proprietary 4-49

Page 50: 01-04 APM30 Installation Guide

Before delivery, the connectors are packed for protection, as shown in Figure 4-63.

Figure 4-63 PMU communication cable

Step 2 Link the RJ45 connector of the RS485 communication cable to the RS232/RS422 port on thepanel of the PMU, as shown in Figure 4-64.

Figure 4-64 Connection of the PMU communication cable

(1) RS485 communication cable (2) PMU monitoring cable

Step 3 Link the DB50 male connector of the PMU monitoring cable to the COM port on the panel ofthe PMU, as shown in Figure 4-64.

4 APM30 Installation GuideAPM30

User Guide

4-50 Huawei Technologies Proprietary Issue 03 (2007-10-24)

Page 51: 01-04 APM30 Installation Guide

CAUTIONYou must install the DB50 connector with both hands and plug or pull the connector verticallyto prevent false alarms caused by bent pins.

Step 4 Bind the cable with cable ties.

----End

4.9.7 Installing the E1/T1 Cable of the BBU3806The E1/T1 cable transmits baseband signals between the BBU3806 and the RNC.

Procedure

Step 1 Lead the E1/T1 cable into the APM30 cabinet through the cable hole for the signal cable at thecabinet bottom.

Step 2 Link the DB44 male connector of the E1/T1 cable to the E1/T1 port on the panel of the BBU3806and fasten the screws on the connector, as shown in Figure 4-65.

Figure 4-65 Connecting the E1/T1 cable to the BBU3806

Step 3 Strip off the cable jacket about 20 mm to 30 mm from the part near the cable hole. Expose theshielding layer and apply fireproof clay to the cable hole. Then, bind the conductive cloth andshielding layer with cable ties to ground the shielding layer, as shown in Figure 4-66.

APM30User Guide 4 APM30 Installation Guide

Issue 03 (2007-10-24) Huawei Technologies Proprietary 4-51

Page 52: 01-04 APM30 Installation Guide

Figure 4-66 Grounding the shielding layer of the E1/T1 cable

NOTEBe cautious when you use the conductive cloth. The conductive cloth tears easily. If the conductive clothis torn, loosen the captive screws around the cable hole and use a piece of new cloth.

Step 4 Connect the other end of the E1/T1 cable to the corresponding equipment.

Step 5 Bind the cables with cable ties.

----End

4.9.8 Installing the CPRI Optical Cable Between the BBU3806 andthe RRU3801C

The CPRI optical cable connects the BBU3806 to the RRU3801C and transmits CPRI signalsbetween them.

Precautionsl The bending radius of the CPRI optical cable should be no less than 20 times the diameter

of the cable. Do not bend the optical cable and the fiber tails too much.

l Take proper ESD protection measures, for example, wear an ESD wrist strap or a pair ofESD gloves, to prevent electrostatic damage to the board, module, or electronic parts.

Procedure

Step 1 Insert the optical module into the CPRI0, CPRI1 or CPRI2 port on the BBU3806, as shown inFigure 4-67.

4 APM30 Installation GuideAPM30

User Guide

4-52 Huawei Technologies Proprietary Issue 03 (2007-10-24)

Page 53: 01-04 APM30 Installation Guide

Figure 4-67 Installing the optical module on the BBU3806

Step 2 Lead the CPRI optical cable into the APM30 cabinet through the cable hole for the signal cableat the cabinet bottom.

Step 3 Attach the optical connector of the cable to the optical module, as shown in Figure 4-68.

Figure 4-68 Attaching the optical connector to the optical module

Step 4 Sheath the optical cable with a winding pipe and then bind the cable properly with cable ties, asshown in Figure 4-69.

Figure 4-69 Binding the optical cable

(1) Winding pipe (2) Cable tie

----End

APM30User Guide 4 APM30 Installation Guide

Issue 03 (2007-10-24) Huawei Technologies Proprietary 4-53

Page 54: 01-04 APM30 Installation Guide

4.9.9 Installing the Alarm Cable Between the APM30 and theBTS3006C/BTS3002E

This describes how to install the alarm cable between the APM30 and the BTS3006C/BTS3002E.

ProcedureStep 1 According to different wire colors, connect wires X1.2, X1.1, X1.4, and X1.3 to the connector

in turn.

Table 4-3 shows the pin assignment for the wires of the alarm cable.

Table 4-3 Pin assignment for the wires of the alarm cable

X1 End Wire Color Wire Type Port on the APM30

X1.1 Blue Twisted pair RX+

Red, blue

X1.2 Orange Twisted pair RX-

Red, orange

X1.3 Green Twisted pair TX+

Red, green

X1.4 Brown Twisted pair TX-

Red, brown

Step 2 Lead the alarm cable into the APM30 cabinet through the cable hole for the signal cable at thecabinet bottom.

Step 3 Link the connector to the port on the panel of the DFFU/APMI, as described in Table 4-3.

Step 4 Bind the cable with cable ties.

----End

4.10 Installing the Batteries of the APM30Different batteries are used for the APM30 in different scenarios. The batteries can be installedin the APM30 cabinet without an extended battery cabinet. If the APM30 has an extended batterycabinet, the batteries are installed in the extended battery cabinet.

4.10.1 Installing the Batteries of the APM30The APM30 obtains backup power from batteries.

4.10.2 Installing the Batteries of the Extended Battery CabinetThe extended battery cabinet can be configured with a group of –48 V 50 AH or –48 V 200 AHbatteries to supply backup power to distributed base stations and mini base stations for arelatively long period of time.

4 APM30 Installation GuideAPM30

User Guide

4-54 Huawei Technologies Proprietary Issue 03 (2007-10-24)

Page 55: 01-04 APM30 Installation Guide

4.10.1 Installing the Batteries of the APM30The APM30 obtains backup power from batteries.

DANGERl Before installation, set the MCB labeled Bat under the rectifier to OFF in case of high current.

l During the installation, the positive and negative poles of batteries should not be short-circuited. Tools like wrenches and screwdrivers must be insulated. Otherwise, a burnt batterymay cause human injuries.

Precautionsl The power cables of batteries are black and red cables, among which the –48 V power cable

is black and the RTN(+) power cable is red.l The batteries are very heavy and so you must hold them with both hands. You must carry

and place the batteries gently to avoid damage to the batteries.l The installation tools must be insulated.

l The plastic housing of the batteries and the electrode wiring terminals must be kept intactduring the installation.

l The inter-spacing of batteries must be kept longer than 10 mm.

Cable Connections of the BatteriesThe cable connections of the batteries are shown in Figure 4-70.

APM30User Guide 4 APM30 Installation Guide

Issue 03 (2007-10-24) Huawei Technologies Proprietary 4-55

Page 56: 01-04 APM30 Installation Guide

Figure 4-70 Cable connections of the batteries

(1) Battery busbar (2) RTN(+) power cable (3) –48 V power cable

(4) A single 12 V 50 AH battery (5) Cable for series connection

Procedure

Step 1 Determine the position for installing the batteries, as shown in Figure 4-71.

4 APM30 Installation GuideAPM30

User Guide

4-56 Huawei Technologies Proprietary Issue 03 (2007-10-24)

Page 57: 01-04 APM30 Installation Guide

Figure 4-71 Position for installing the batteries

(1) A single 12 V 12 AH battery

NOTE

l When the –48 V 12 AH or –48 V 24 AH batteries are available, they are installed in a space of 3 U inthe APM30 cabinet.

l When the –48 V 36 AH built-in batteries are available, they need to use the space of 3 U reserved forthe user equipment.

Step 2 Place the four 12 V 12 AH batteries in the front of the battery cabin.

Step 3 Use cables to connect the batteries in series, as shown in Figure 4-72.

Figure 4-72 Connecting the batteries in series

NOTE

The two ends of the cables are female connectors. The positive and negative poles of the batteries are maleconnectors. When connecting the batteries in series, link the female connectors of the cables to the maleconnectors on the batteries.

CAUTIONThe positive and negative poles of the batteries cannot be short-circuited.

APM30User Guide 4 APM30 Installation Guide

Issue 03 (2007-10-24) Huawei Technologies Proprietary 4-57

Page 58: 01-04 APM30 Installation Guide

Step 4 Connect the power cables to the positive and negative poles of the batteries and wrap the OTterminals of power cables with insulation tapes.

One end of the power cable is a female connector that connects to one of the poles on the battery,whereas the other end is an OT terminal that connects to the battery busbar.

Step 5 Push the battery gently into the rear of the battery cabin and install another battery.

Step 6 Loosen the screws and remove the protecting hood from the battery busbar, as shown in Figure4-73.

Figure 4-73 Removing the protecting hood from the battery busbar

Step 7 Use a –48 V power cable to connect the negative battery busbar to wiring terminal BAT(-) onthe power subrack, and use an RTN(+) power cable to connect the positive battery busbar towiring terminal RTN(+) on the power subrack.

Step 8 Remove the insulation tapes from the OT terminals of the power cables at both positive andnegative poles of the batteries, as described in Step 4, and connect the OT terminals to the batterybusbar.

Figure 4-74 Connecting the power cables to the battery busbar

(1) RTN(+) power cable (2) Power cable at the positivepole

(3) –48 V power cable (4) Power cable at the negativepole

4 APM30 Installation GuideAPM30

User Guide

4-58 Huawei Technologies Proprietary Issue 03 (2007-10-24)

Page 59: 01-04 APM30 Installation Guide

NOTE

Lead the –48 V power cable of the battery busbar from the left side of the protecting hood, lead the RTN(+) power cable from the right side, and then route the two power cables along the right side of the cabinetto the power subrack.

Step 9 Reinstall the protecting hood of the battery busbar.

Step 10 Bind the DC power cables neatly with cable ties.

----End

4.10.2 Installing the Batteries of the Extended Battery CabinetThe extended battery cabinet can be configured with a group of –48 V 50 AH or –48 V 200 AHbatteries to supply backup power to distributed base stations and mini base stations for arelatively long period of time.

DANGERl Before installation, set the MCB labeled Bat under the rectifier to OFF in case of high current.

l During the installation, the positive and negative poles of batteries should not be short-circuited. Tools like wrenches and screwdrivers must be insulated. Otherwise, a burnt batterymay cause human injuries.

Precautionsl The power cables of batteries are black cables and red cables, among which the –48 V

power cable is black and the RTN(+) power cable is red.l The batteries are very heavy and so you must hold them with both hands and carry and

place them gently to avoid damage to the batteries.l The installation tools must be insulated.

l The plastic housing of the batteries and the electrode wiring terminals must be kept intactduring the installation.

Cable Connections of the BatteriesFigure 4-75 and Figure 4-76 show the cable connections of the –48 V 50 AH and –48 V 200AH batteries respectively.

APM30User Guide 4 APM30 Installation Guide

Issue 03 (2007-10-24) Huawei Technologies Proprietary 4-59

Page 60: 01-04 APM30 Installation Guide

Figure 4-75 Cable connections of the –48 V 50 AH batteries

(1) –48 V power cable (2) RTN(+) power cable (3) A single 12 V 50 AHbattery

(4) Copper bar (5) Battery plate

Figure 4-76 Cable connections of the –48 V 200 AH batteries

(1) –48 V power cable (2) RTN(+) power cable (3) A single 12 V 100 AHbattery

(4) Copper bar (5) Battery plate

Procedure

Step 1 Place the batteries on the guide rails one by one, from bottom to top and left to right. Then, slidethem into the cabinet, as shown in Figure 4-77 and Figure 4-78.

4 APM30 Installation GuideAPM30

User Guide

4-60 Huawei Technologies Proprietary Issue 03 (2007-10-24)

Page 61: 01-04 APM30 Installation Guide

Figure 4-77 Installing the –48 V 50 AH batteries

(1) A single 12 V 50 AH battery

Figure 4-78 Installing the –48 V 200 AH batteries

(1) A single 12 V 100 AH battery

Step 2 Remove the protecting hood from the wiring terminals and connect the batteries in series withthree pieces of battery plates, as shown in Figure 4-79.

APM30User Guide 4 APM30 Installation Guide

Issue 03 (2007-10-24) Huawei Technologies Proprietary 4-61

Page 62: 01-04 APM30 Installation Guide

Figure 4-79 Connecting the batteries in series

(1) Battery plate

Step 3 Use the RTN(+) power cable and –48 V power cable to connect the positive and negative polesof the batteries to the copper bar, and install the protecting hood of the wiring terminals. Figure4-80 shows the connection of the RTN(+) power cable. The –48 V power cable is connected inthe same way.

4 APM30 Installation GuideAPM30

User Guide

4-62 Huawei Technologies Proprietary Issue 03 (2007-10-24)

Page 63: 01-04 APM30 Installation Guide

Figure 4-80 Connecting the RTN(+) power cable

(1) –48 V power cable (2) RTN(+) power cablebefore connection

(3) RTN(+) power cableafter connection

(4) Protecting hood ofwiring terminals

Step 4 Route the power cables along the copper bar through the DC cable hole on the right of the cabinettop into the APM30 cabinet and then connect the cables to wiring terminals BAT(-) and RTN(+) on the power supply subrack respectively, as shown in Figure 4-81.

APM30User Guide 4 APM30 Installation Guide

Issue 03 (2007-10-24) Huawei Technologies Proprietary 4-63

Page 64: 01-04 APM30 Installation Guide

Figure 4-81 Connecting the battery power cable

(1) –48 V power cable (2) RTN(+) power cable

Step 5 Bind the DC power cables neatly with cable ties.

----End

4.11 Sealing the Cable HolesThe cable holes need to be sealed with fireproof clay after the installation of the APM30 cables.

Procedure

Step 1 Route the cables orderly and bind them with cable ties.

Step 2 Seal the cable holes with fireproof clay.

To seal the cable holes, do as follows:

l Fill the fireproof clay in the cable holes. If the APM30 cabinet is installed on a pole or a wall,you can fill the clay from both inside and outside of the cabinet.

l If the APM30 cabinet is installed on the floor, you can fill the fireproof clay only from insideof the cabinet.

l To fully seal the cable holes with fireproof clay, you should keep the cables in the center ofthe hole.

Figure 4-82 shows the fireproof clay filled from outside of the cabinet.

4 APM30 Installation GuideAPM30

User Guide

4-64 Huawei Technologies Proprietary Issue 03 (2007-10-24)

Page 65: 01-04 APM30 Installation Guide

Figure 4-82 Filling the fireproof clay

----End

4.12 Checking the Installation of the APM30After the APM30 is installed, you must check the cabinet installation, electrical connections,power-on status, and field cleanliness.

Procedure

Step 1 To check the cabinet installation, refer to 4.12.1 Checklist for the APM30 Cabinet.

Step 2 To check the electrical connections, refer to 4.12.2 Checklist for the Electrical Connection ofthe APM30.

Step 3 Check the power-on status.

DANGERThe power-on status check involves high-voltage operation. Be cautious when conducting thepower-on check. Any direct contact with the input voltage or indirect contact through dampobjects might endanger your life.

1. Ensure that the input voltage of the APM30 is from 176 V AC to 290 V AC and that theequipment is powered on.

2. Set the AC input MCB SW1 of the APM30 to ON to power on the APM30.

3. Turn the multimeter to the DC range. Measure the voltage of the DC output terminalsLOAD1 and LOAD2 in the power supply subrack. The proper range is from –58 V DC to–44 V DC.

4. Set the DC power distribution MCB to OFF. Turn the multimeter to the DC range. Measurethe voltage of the DC output terminals in the DC power distribution unit. The proper rangeis from –58 V DC to –44 V DC.

5. Set the AC input MCB SW1 of the APM30 to OFF to power off the APM30.

6. Check whether the DC backup power is in normal condition by referring to 3.3 and 3.4.

APM30User Guide 4 APM30 Installation Guide

Issue 03 (2007-10-24) Huawei Technologies Proprietary 4-65

Page 66: 01-04 APM30 Installation Guide

Step 4 When all the previously mentioned check items are covered, check the field cleanliness byreferring to 4.12.3 Checklist for the Installation Environment of the APM30.

----End

4.12.1 Checklist for the APM30 CabinetThis describes the checklist for the APM30 cabinet.

Table 4-4 Checklist for the APM30 cabinet

SN Item

1 The cabinet is located in strict compliance with the engineering design.

2 When the APM30 is mounted on a wall, the holes of the mounting ears arealigned with the bolt holes. The mounting ears are placed against the wallsecurely.

3 When the APM30 is mounted on a metal pole, the pole fixtures are secure andreliable.

4 When the APM30 is installed on the floor, the base is securely installed.

5 The horizontal error of the cabinet is less than 3 mm and the vertical error isnot greater than 3 mm.

6 All the bolts are tightened, especially for electrical connections. The flatwashers and spring washers are completely and properly installed.

7 The cabinet is neat and clean.

8 The paint on the surface of the cabinet is satisfactory.

9 The space reserved for the transmission equipment is covered by a filler panel.

10 The cabinet door and the lock are functional. The locking lever is tightened.

11 All the labels are complete, correct, and legible.

4.12.2 Checklist for the Electrical Connection of the APM30This describes the checklist for the electrical connection of the APM30.

Table 4-5 Checklist for the electrical connection

SN Item

1 All self-made PGND cables are copper-based with proper wire diameters. Nobreaking device such as the switch and fuse is allowed for the electricalconnection of the grounding system. Any open or broken circuit is prohibited.

4 APM30 Installation GuideAPM30

User Guide

4-66 Huawei Technologies Proprietary Issue 03 (2007-10-24)

Page 67: 01-04 APM30 Installation Guide

SN Item

2 According to the wiring diagram of the power system, check whether thePGND cables are securely connected, whether the AC lead-in and cables insidethe cabinet are properly connected, and whether the screws are tightened.Ensure that no short circuit occurs in output and input cables.

3 The redundant part of the power cable or PGND cable is stripped off ratherthan coiled.

4 The lugs at both ends of the power cable or the PGND cable are securelysoldered or crimped.

5 The exposed wires at the wiring terminals and the lug handles are insulatedby the insulating tape or heat-shrinkable tube.

6 The flat washers and spring washers are well mounted to all wiring terminals.

7 The connectors of each cable are securely connected, especially those at thebottom of the APM30 cabinet.

8 All cables are neatly bound with cable ties arranged at even intervals, to propertightness, and in the same direction.

9 The power cable and PGND cable are routed separately from other cables.

10 The cables are distributed in a way to facilitate maintenance and capacityexpansion.

11 Both ends of each cable are legible. That is, both ends of the cable are labeled.

12 Extra cable ties are stripped off. All cuts are smooth without sharp projections.

13 The negative pole and the positive pole of batteries are correctly connected.

4.12.3 Checklist for the Installation Environment of the APM30This describes the checklist for the installation environment of the APM30.

Table 4-6 Checklist for the installation environment

SN Item

1 There are no fingerprints or other smears on the surface of the APM30.

2 There are no unnecessary adhesive tapes or cable ties on the cables.

3 There are no adhesive tapes, cable ties, wastepaper, or packing bags aroundthe APM30.

4 All the stuff around the APM30 is neat, clean, and intact.

APM30User Guide 4 APM30 Installation Guide

Issue 03 (2007-10-24) Huawei Technologies Proprietary 4-67