01/21/2009 telemetry process & progress ercot state estimator & lfc team operations advanced...

12
01/21/2009 Telemetry Process & Progress Telemetry Process & Progress ERCOT State Estimator & LFC Team Operations Advanced Network Applications Support

Upload: tamsyn-wilson

Post on 20-Jan-2018

212 views

Category:

Documents


0 download

DESCRIPTION

3 Telemetry Process & Progress01/21/2009 Telemetry Support ERCOT Full Time Staff ICCP Support –Advanced Network Applications Support 2 Engineers –Control Room 1 Operations Analyst & 1 Shift Engineer –IT 2 System Analysts –Additional Staff on a part time basis Market Participants –Contact for Nodal Issues –Timely Response on detected issues

TRANSCRIPT

Page 1: 01/21/2009 Telemetry Process & Progress ERCOT State Estimator & LFC Team Operations Advanced Network…

01/21/2009Telemetry Process & Progress

Telemetry Process & Progress

ERCOT State Estimator & LFC TeamOperations Advanced Network Applications Support

Page 2: 01/21/2009 Telemetry Process & Progress ERCOT State Estimator & LFC Team Operations Advanced Network…

Telemetry Process & Progress01/21/2009 2

ICCP

• Telemetry Support• Telemetry Reporting• State Estimator Tuning• Telemetry Issue Process• Telemetry Going Forward

Page 3: 01/21/2009 Telemetry Process & Progress ERCOT State Estimator & LFC Team Operations Advanced Network…

Telemetry Process & Progress01/21/2009 3

Telemetry Support

• ERCOT Full Time Staff ICCP Support– Advanced Network Applications Support 2 Engineers– Control Room 1 Operations Analyst & 1 Shift Engineer– IT 2 System Analysts– Additional Staff on a part time basis

• Market Participants– Contact for Nodal Issues– Timely Response on detected issues

Page 4: 01/21/2009 Telemetry Process & Progress ERCOT State Estimator & LFC Team Operations Advanced Network…

Telemetry Process & Progress01/21/2009 4

Telemetry Reporting

QSE & TDSP Dashboard

XXX Dash Board 99.99.9999 XXX

Missing

Unit T

elemetr

y * (Q

SE)

Market

Partici

pant W

ill Send

SR *

(TDSP

)

Telem

etry M

apped

in Zo

nal - N

ot in

Nodal

**

Status

Point

s and

Analo

gs w / D

ispute

d Owner

ship

***

* Market Participant is missing nodal unit telemetry. Appropriate points and analogs

are to be submitted to ERCOT. (A)

Organization x A B C

*** Currently, there are no known issues with disputed ownership. ERCOT will

contact relevant parties if any questions arise. (C)

Please note that tabulations are consistent with 99.99.9999 database load.

* Market Participant is missing nodal unit telemetry. Appropriate points and analogs

are to be submitted to ERCOT. (A)

** ERCOT is investigating this telemetry. No action is required from Market Participant at

this time. (B)

Page 5: 01/21/2009 Telemetry Process & Progress ERCOT State Estimator & LFC Team Operations Advanced Network…

Telemetry Process & Progress01/21/2009 5

Telemetry Reporting

Wind Dashboard

Resource Entity Coding•Green = No Telemetry Issues•Not Green = Issues to be corrected

Does Data Appear to be ‘Good’? Coding•Yes (Green) = Data Quality appears to be good, no action needed•No (Red) = Data Missing or of questionable quality corrective action needed

DEG MPH PRES TEMPPlant Name Conforming Entity N Yes Yes Yes YesPlant Name Entity with Improvement Opportunity N No No No No

Plant Resource EntityReceived

10/31 Letter Does Data Appear to be 'Good'?

Page 6: 01/21/2009 Telemetry Process & Progress ERCOT State Estimator & LFC Team Operations Advanced Network…

Telemetry Process & Progress01/21/2009 6

Telemetry Reporting

Observability Status Dashboard

Initial Number of Unobservable points(buses)*

Number of Unobservable points(buses) to date*

Number of unobservable buses due to a PUN*

A B CONCOR 131 3 1AEP/CPL 103 4 2TNMP 20 0 0STEC 15 0 0RCEC-Rayburn Country Electric 11 0 0LCRA 14 0 0PUB 11 0 0CNP 11 2 1BEPC 10 0AEN 0 0COD-City of Denton 0 0COG-City of Garland 0 0CPS 0 0MVEC 0 0BTU 0 0CSTX City of College Station 0 0GEUS-Greenville 0 0MEC 0 0TMPA 0 0

Total Points 326 9Tab Colours 3%Data availableNo data availableOut of scope

Buses that are unobservable due to an Pun load at the station ( C )

This number of unobservable buses in the system with all pseudo measurement removed(A)

Number of current unobservables in the system that have a load at the station where telemetry is required to make the bus observable.

(B)

If a number other then 0 is in column B, then there is missing telemetry which requires Market Participant Corrective Action.

Page 7: 01/21/2009 Telemetry Process & Progress ERCOT State Estimator & LFC Team Operations Advanced Network…

Telemetry Process & Progress01/21/2009 7

Telemetry Reporting

State Estimator (SE) Convergence October - December '08 SE

0102030405060708090

100

10/1/

0810

/8/08

10/15

/0810

/22/08

10/29

/0811

/5/08

11/12

/0811

/19/08

11/26

/0812

/3/08

12/10

/0812

/17/08

12/24

/0812

/31/08

Date

Con

verg

ence

%• SE & Supporting Telemetry Information is posted on EDW MIS

• Advanced Network Applications provides analysis assistance and be reached at the EDS3 email: [email protected]

Page 8: 01/21/2009 Telemetry Process & Progress ERCOT State Estimator & LFC Team Operations Advanced Network…

Telemetry Process & Progress01/21/2009 8

Telemetry Reporting

1.1 Log of Events & Observations FIT II Week 6 Day 1

Hour Ending Hourly

Convergence% Major Noted Issue(s) 01/13/2009 1:00:00 AM 100.00 Not FIT testing 01/13/2009 2:00:00 AM 33.33 Not FIT testing 01/13/2009 3:00:00 AM 100.00 Not FIT testing 01/13/2009 4:00:00 AM 100.00 Not FIT testing 01/13/2009 5:00:00 AM 100.00 Not FIT testing 01/13/2009 6:00:00 AM 100.00 Not FIT testing 01/13/2009 7:00:00 AM 75.00 Not FIT testing 01/13/2009 8:00:00 AM 53.85 Not FIT testing 01/13/2009 9:00:00 AM 91.67 Your Company Here 01/13/2009 10:00:00 AM 100.00

01/13/2009 11:00:00 AM 100.00 01/13/2009 12:00:00 PM 80.00 01/13/2009 1:00:00 PM 100.00 01/13/2009 2:00:00 PM 92.31 01/13/2009 3:00:00 PM 100.00 01/13/2009 4:00:00 PM 100.00

01/13/2009 5:00:00 PM 100.00 01/13/2009 6:00:00 PM 91.67 Not FIT testing 01/13/2009 7:00:00 PM 75.00 Not FIT testing 01/13/2009 8:00:00 PM 72.73 Not FIT testing 01/13/2009 9:00:00 PM 100.00 Not FIT testing 01/13/2009 10:00:00 PM 100.00 Not FIT testing 01/13/2009 11:00:00 PM 100.00 Not FIT testing 01/14/2009 12:00:00 AM 100.00 Not FIT testing

FIT Report• Log of Events & Observations

– If your company is listed it means that your involvement/assistance was required to resolve an issue.

Page 9: 01/21/2009 Telemetry Process & Progress ERCOT State Estimator & LFC Team Operations Advanced Network…

Telemetry Process & Progress01/21/2009 9

State Estimator Tuning

• FIT– Monitors Telemetry– Compares Generation between Zonal & Nodal

• ICCP Support Team– Analysis Support of FIT Issues– ICCP Issue Resolution Support– Produce FIT Report

Page 10: 01/21/2009 Telemetry Process & Progress ERCOT State Estimator & LFC Team Operations Advanced Network…

Telemetry Process & Progress01/21/2009 10

Current Telemetry Issue Process

ERCOT or Market Participant detects Telemetry, ICCP or other System Issue

Market Participant investigates to

determine correct ability

Requires ERCOT assistance to

resolve?

Contact ERCOT ANA by email

[email protected] for assistance

Yes

No

ERCOT Analyzes Issue and determines

corrective action

ERCOT Contacts MP to Affect Correction

Issue Resolved?

Done

Yes

NoMP Corrects Issue

During FIT? No

Yes

Contact ERCOT Shift Engineer @

512-248-6345

Page 11: 01/21/2009 Telemetry Process & Progress ERCOT State Estimator & LFC Team Operations Advanced Network…

Telemetry Process & Progress01/21/2009 11

Telemetry Going Forward

• SE FIT to continue through 3rd quarter ’09• Nodal Migration Preparation Testing September ’09

– 7/24 monitoring of SE by ERCOT personnel– 7/24 reporting of SE performance

• SE & SCED Testing November ’09– Continued 7/24 monitoring & reporting on SE– COP, TPO submissions– Monitoring & Reporting of SCED & LMP’s

Page 12: 01/21/2009 Telemetry Process & Progress ERCOT State Estimator & LFC Team Operations Advanced Network…

Telemetry Process & Progress01/21/2009 12

Telemetry Going Forward

• December ’09 & January ’10 System Wide Open Loop– EMBP & Responsive Reserve Test December ’09– Non-spin Test January ’10– Continued 7/24 monitoring of SE & SCED Performance

• February – December ’10 Production Migration Testing– LFC 2, 8 & 48 Hour Tests– 168 Hour Test– 2 additional 48 Hour LFC Tests (If required for Migration)