Work Plan and Progress Report III OUTPUT EXPECTED PRODUCTS
1.The Establishment of the INSET System (SMASSE Malawi) [1] Progress Report I
2. The Promotion of the Decentralisation in the Education Sector3. Capacity Building in the Ministry of Education, Science and Technology [3] Progress Report II4. The Coordination with other development partnars in the Education Sector [4] Progress Report III
5. The Project Formulation for the Education Development
[6] Final Report
ACTIVITIES
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 ACTUAL PRODUCTS
(EXPECTED TIME FOR PRODUCTS OUT) [1] [2] [3] [4] [5] [6]
(Year)
(Month)
[1] Progress Report I (on Work Plan)[2] Report on the 1st Stakeholders' Meeing for SMASSE
INSET Malawi (Oct. 2002)
[3] Working Paper (Progress Report I) on the Pilot
Programme for Establishment of SMASSE INSET
Malawi (Dec. 2002)
[4] Progress Report II (on Work Plan)
[5] Progress Report II on the Pilot Programme for
Establishment of SMASSE INSET Malawi (Feb. 2003)
[6] Progress Report I on St. John's Primary School
Construction Project (Apr. 2003)
[7] Progress Report II on St. John's Primary School
Construction Project (May 2003)
[8] Status Analysis Report of South Division (May 2003)
[9] Progress Report III on St. John's Primary School
Construction Project (Jun. 2003)
[10] Progress Report III on the Pilot Programme for
Establishment of SMASSE INSET Malawi (Sep. 2003)
INPUT
JAPAN SIDE
2004
1-6. Technical advice for planning,
implementing, monitoring and evaluating the
INSET system
2-1. Supporting the development of micro-
planning
[2] Report on Status quo Analysis in Education Sector I
[5] Report on Status quo Analysis in Education Sector II
1-4. Promotion for smooth implementation of
the project
1-5. Monitoring and evaluating the project
TIME (-th month)
1-1. Coordination of the pre-condition for
launching the pirot project
1-2. Coordination and advisory role on needs
assessment
1-3. Planning and Coordinating the Workshop
for strengthening the collaborative activities
2002 2003
2-2. Supporting of the On the Job Training for
the local education officer
(1) Office Room
(2) Desks and Chairs2-3. Promoting the Information &
Communication Sharing
INPUT
RECIPIENT COUTRY SIDE
(1) Lap top PC (2) Printer(3) Copy Machine (4) Video Camera
Plan Actual
Ministry of Education, Science and Technology, Malawi
Education Planning Adviser
Yoshihito NAKAYAMA
-
8/14/2019 04 annex4_ Work Plan & Progress Report (18 months)
2/2
Work Plan and Progress Report III 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6(Month)
TIME (-th month)
(Year) 2002 2003 2004
5-3. Developing the new activities and project
formulation
5-4. Coordinating on-going JICA&ODA
projects
5-5. Monitoring & Technical Advice on
completed JICA&ODA projects
5-1. Status-quo Analysis
Information gathering on activities in education
sector
5-2. Needs Assessment
3-5. Strengthening the Information &
Communication Sharing
4-1. Contribution to Education Sector Meeting
4-2. Coordination and development of the
possibility on collaborative activities with otherdevelopment partnars
4-3. Follow-up the Sector Wide Approach
3-1. Status quo Analysis
3-3. Strengthening the management of planning
department
3-2. Training Needs Analysis
3-4. Technical Advice on planning and
Implementation of school mapping and EMAS
Ministry of Education, Science and Technology, Malawi
Education Planning Adviser
Yoshihito NAKAYAMA