04 concrete
DESCRIPTION
concreteTRANSCRIPT
-
I Struct E Part 3 Exam Preparation
-
Concrete
Charles Johnson
-
When to use concrete In building superstructures
1. Minimum depth
Flat slab- passive steel or post-tensioned
Ribbed or waffle slab
2. Complex floor shapes
3. Acoustics
4. Vibration
5. Steel supply problem
6. Personal preference
7. Cost
-
Concrete Design The Big Issues
1. Shrinkage and thermal cracking
2. Durability
3. Weight
4. Workmanship / Finishes
-
1. Shrinkage and thermal cracking
In UK buildings:
Mostly shrinkage
Long term.
Total Long Term Strain K ~ 300 x 10-6
Joint spacing:
Internal: 50 - 75 m
Un-insulated roof slabs: 25m
Beware of effect of shrinkage on distant cores
-
1. Shrinkage and thermal cracking
In UK structures exposed to ground/water
only consider early shrinkage - little long term drying
Drying shrinkage K ~ 100 x 10-6
Thermal effects relatively more important, especially in massive structures with high hydration heat.
K ~ 12 x 10-6 /degree C
-
2. Durability
Not normally important issue in internal environments
[cover controlled by fire]
External:
Cement Content
Cover
Concrete Density (i.e. compaction & curing)
Special protection against aggressive conditions
Sulphates BS8110 Tab 6.1
Chlorides
-
3. Weight
Say 300mm ave. conc thickness per floor. = 7.5 kN/m2
Equiv. steel build: 120 conc + 1.5 kN/m2 beams = 4.5 kN/m2
Say three floors, and footings ~ 20% of footprint:3 kN/m2 x 5 = 15 kN/m2 extra bearing pressure per floor.
x3 floors = 45 kN/m2
Or, Say 6m x 5m grid and 150 kN/m2 safe bearing pressure:Concrete solution needs 1.8m2 larger pads than steel
Pre-cast components: Beware of transport limits:
~ 40T total? 10T axle load?
25T mobile crane: ~ 10T capacity @ 7m radius (i.e. 4m3)
-
Initial sizing-1-: Basic L/D
Beams: L/10 - L/20 Slabs: L/25 - L35
On beams: Use short span Flat slabs: Use long span
Cantilevers: L/5 - L/8 Corbels: L/1 - L/3
-
Initial sizing-2-: Bending
As = M .0.95fy 0.8d
[in finding d remember links/distribution steel ]
As < ~ 2% . Less on very large sections. Also check no compression steel needed: M . < 0.156* or M < 0.156* fcubd2
bd2fcu
* Varies if redistributing moments (down to 0.104) b = width of compression zone. Check bars fit comfortably / how many rows?
-
Initial sizing-3-: Deflection
BS8110 basic L/D Tension steel factor Factor for steel in compression zone (even if not
needed for compression in bending) Best to add compression steel, but check quantity no
too great uneconomic.
-
Initial sizing-3-: Shear
First check to do in retaining walls, foundations, pile caps, etc.
Avoid shear reinforcement in these if poss. So size section assuming:
vc = ~0.5 N/mm2 for 0.5% As= ~0.7 N/mm2 for 1.0% As
Also important in flat slabs. Good initial sizing charts in Scheme design guide if you want
to avoid shear links (vc only). If not... First perimeter length = col. perimeter + 12d Min links = 0.4 N/mm2. So v~ 1.0 N/mm2
-
Columns
For short columns Le/b < 15): From N = 0.35Acfcu = 0.7 Acp fy
p=1% N = 15Acp=2% N = 18Acp=3% N = 21 Ac
Min column size 220 x 220 Check min size and cover for fire resistance
Specially over 2h.
-
Reinforcement quantities
Volume of steel x 7800 = Wt of steel in kg For reinforcement estimates:
Calc. Vol of steel/ known m3 of conc. in sample areas Per (1m2 of slab/wall x h) Per (1m length of beam x A)
+ 10 for laps, + 10% contingency x 7800
-
Shear Walls and cores
Minimum thickness 200mm but may have problems with areas of steel congestion (e.g. beam junctions).
So unless quite simple say 250min Avoid using risers as cores: large holes above ceilings. Lifts OK but assume no wall on door side Stairs OK but risk of Arch. wanting it open later. To estimate As
Use Z~ 0.5d. Deduct min dead load from wind tension. Ideally no resultant
tension at working loads, then no cracking.
-
Stairs
May need greater crowd load capacity Decide form of support
Avoid support on masonry.- Difficult construction sequence On conc. walls: use bend-out bars or post-drill
Contractors will usually prefer to pre-cast Min depth: support flights on side of landing, and landing onto
side wall. (take span of flight to centre line of landing) Simplest: span flights + landings onto end walls For weight: use av. vertical thickness For bending strength use min (slope) thickness.
-
Water-retaining/excluding
BS8007. Concrete Grade C35A Generally design for 0.2mm crack width instead of the 0.3mm
implied in BS8110 Check for flexural crack width
Use design chart e.g. Batty and Westbrook Moment capacity limited by crack width, which is also dependent on
bar size and bar spacing. Check for thermal and shrinkage cracking
Affects distribution/minimum steel Full external restraint; and steel must control all shrinkage cracks,
or Enough joints to permit free shrinkage
-
Bending design chart for limiting
service crack width.(From Batty and
Westbrook)
When to use concrete In building superstructuresConcrete Design The Big Issues1.Shrinkage and thermal crackingIn UK buildings: 1.Shrinkage and thermal cracking In UK structures exposed to ground/water2. Durability3. WeightInitial sizing-1-: Basic L/DInitial sizing-2-: BendingInitial sizing-3-: DeflectionInitial sizing-3-: ShearColumnsReinforcement quantitiesShear Walls and coresStairsWater-retaining/excludingBending design chart for limiting service crack width.(From Batty and Westbrook)