05.rtu560 step by step

48
ABB Oy PSS/SAS RTU560 Revision: 4 Cities RTU560 Step By Step ABB Oy 1-48

Upload: duy-anh-truong

Post on 01-Dec-2015

1.162 views

Category:

Documents


102 download

TRANSCRIPT

Page 1: 05.RTU560 Step by Step

ABB OyPSS/SASRTU560

Revision: 4 Cities RTU560 Step By Step

ABB Oy 1-38

Page 2: 05.RTU560 Step by Step

ABB OyPSS/SASRTU560

Revision: 4 Cities RTU560 Step By Step

Contents:

1. INTRODUCTION.............................................................................................................3

2. INSTALLATION..............................................................................................................4

3. EXCEL IMPORT..............................................................................................................6

3.1 PRECONDITION..............................................................................................................63.2 EDIT THE EXCEL FILE.....................................................................................................63.3 EDIT THE PATTERN FILE.................................................................................................83.4 START EXCEL IMPORT..................................................................................................143.5 BUILD RTU FILES........................................................................................................22

4. RTU560 WEB SERVER.................................................................................................27

4.1 PRECONDITION............................................................................................................274.2 ESTABLISH PPP- CONNECTION.....................................................................................274.3 START INTERNET EXPLORER WITH ADDRESS HTTP//10.0.10.50.......................................284.4 LOAD CONFIG.IOD (I/O DATA)......................................................................................294.5 LOAD CONFIG.GCD (GENERAL CONFIGURATION DATA)..................................................314.6 LOAD CONFIG.IOD (TEXTS FROM ARCHIV OR PRINTER)...................................................334.7 RESTART RTU560......................................................................................................35

ABB Oy 2-38

Page 3: 05.RTU560 Step by Step

ABB OyPSS/SASRTU560

Revision: 4 Cities RTU560 Step By Step

1. Introduction

This brief description does not replace the standard 560RTUtil NT User’s Guide and RTU560 Web Servers User’s Guide”. For details please refer to the manuals mentioned.

This description is made to show, how to change or add an item to an existing configuration in the RTU, in case the user has not been working with the tool for a while, or to help a newcomer to get easily started with the 560RTUtil NT.

This brief description handles:

Installation The description for this installation procedure is complete different from the installation procedure described in the Users’Guide. This way of installation is mainly based on field experience.

Excel import This Excel import procedure shows each step that has to be done if a change the RTU configuration is required. The precondition is, that this steps have been carried out before. This is the standard case when the RTU is delivered from the factory with the appropriate configuration files and the customer make changes for example during commissioning.

This guide advises you to keep the actual files which are in use in the RTU as backup. If everything goes wrong during Excel-import, you will still have the healthy GCD, IOD and PTX file which can be loaded to the RTU.

This steps seem more complicate as they really are. It is a matter of practice. The main goal for Excel import is, if you have a large amaount of I/O’s or IDE’s. The Excel-import helps to keep track of the parameters used in the RTU.

The output of this Excel-import chapter are the RTU-Files. The GCD-, IOD- and the PTX File will be loaded to the CPU with the WEB Server Tool.

ABB Oy 3-38

Page 4: 05.RTU560 Step by Step

ABB OyPSS/SASRTU560

Revision: 4 Cities RTU560 Step By Step

2. Installation

RTUtil NT is distributed as CD-ROM and is developed for the Windows NT 4.0 operating system.Copy the packed file ”RTUtilNT_xx_xx_xxx_00.exe” into a directory with the release name Wbtr xxx and unpack the file into the same directory. This will create the sub-directory Disk1 with additional subdirectories as shown below.Keep this directory for future use, for example when you have to re-install the RTUtil NT

Double-click Setup.exe in the directory Disk1. The installation Process guides you through the installation process.

ABB Oy 4-38

Page 5: 05.RTU560 Step by Step

ABB OyPSS/SASRTU560

Revision: 4 Cities RTU560 Step By Step

Follow the steps from the installation program and click through the following dialog sheets:

1. Acknowledge welcome page2. Accept license agreements3. Select the program path, where the files should be installed

4. Select the program group of RTUtil NT5. Restart your computer.

If you are working with different RTUtil NT releases as in the picture above, create your ”Release specific directory” and name it accordingly. Keep your projects in the appropriate release directories. If upgrade is required to the next higher release, please ask your supplier for support.

If you currently are working with release 6 and you need to edit a project made with release 5, just re-install RTUtil NT release 5 over the already existing directory from release 5. This will not affect the project files, but will set registry to keep track of internal paths.

ABB Oy 5-38

Page 6: 05.RTU560 Step by Step

ABB OyPSS/SASRTU560

Revision: 4 Cities RTU560 Step By Step

3. Excel import

3.1 Precondition

RTUtil NT is installed and at least the Pattern and the Excel file(s) exist in the appropriate directory.

The Pattern file contains: Complete Network Tree

(Including all links to the Hardware Tree) The Hardware Tree down to RTU560 board level

(Without I/O signal definitions and assignmentsThe Excel file(s) contains:

Project Signal Tree(Signal names structured according to the project settings of the project pattern)

The data object’s hardware assignment to RTU I/O points Data object parameters and addresses

The Pattern file and the Excel sheet will be merged into the RTU File!

3.2 Edit the Excel file

Open directory ”xls_import” under your current release ant open your project directory.

ABB Oy 6-38

Page 7: 05.RTU560 Step by Step

ABB OyPSS/SASRTU560

Revision: 4 Cities RTU560 Step By Step

Make a copy of the ”ACTIVE xls” file, change the date and remove the ACTIVE from the old version to keep track of history.

Open the Excel file and select the sheet in question.

For example change input range from 20 mA to 5 mA.

Save the changes and close the file.

ABB Oy 7-38

Page 8: 05.RTU560 Step by Step

ABB OyPSS/SASRTU560

Revision: 4 Cities RTU560 Step By Step

3.3 Edit the Pattern file

Open directory ”pattern” under your current release and open your project directory.

Make a copy of the ”ACTIVE TU” file, change the date and remove the ACTIVE from the old version to keep track of history.

ABB Oy 8-38

Page 9: 05.RTU560 Step by Step

ABB OyPSS/SASRTU560

Revision: 4 Cities RTU560 Step By Step

Start RTUtil from your work-directory or create a shortcut on your desktop or.

Start RTUtil via Windows ”Start / Programs / RTUtil NT/ RTUtil NT

ABB Oy 9-38

Page 10: 05.RTU560 Step by Step

ABB OyPSS/SASRTU560

Revision: 4 Cities RTU560 Step By Step

RTUtil NT workspace offers to setup a new project. As we are editing an already existing Project press Cancel!

Select ”Open” (existing pattern)

ABB Oy 10-38

Page 11: 05.RTU560 Step by Step

ABB OyPSS/SASRTU560

Revision: 4 Cities RTU560 Step By Step

Your project specific pattern file with ”View Network Tree” is now open.

ABB Oy 11-38

In the pattern directory select your project directory

Now select your ACTIVE pattern file and select Open

RTUtil NT offers you as default the project directory. Go one level higher by pressing this button

Now select the pattern directory.

Page 12: 05.RTU560 Step by Step

ABB OyPSS/SASRTU560

Revision: 4 Cities RTU560 Step By Step

Check that your pattern file does not contain any signals in the ”View Signal Tree”.

Check that your pattern file does not contain any signals in the ”View Signal Tree”.

ABB Oy 12-38

Page 13: 05.RTU560 Step by Step

ABB OyPSS/SASRTU560

Revision: 4 Cities RTU560 Step By Step

Check so that your pattern file does not contain any signals in the ”View Hardware Tree”.

Note:If there are already any signals in the ”View Signal Tree” or in the ”View Hardware Tree”They must be deleted, otherwise due to ”additive” import will signals will be doubled, and will cause an error message for each duplicated signals during RTU file generation.

ABB Oy 13-38

Page 14: 05.RTU560 Step by Step

ABB OyPSS/SASRTU560

Revision: 4 Cities RTU560 Step By Step

3.4 Start Excel Import

From the menu Extra select Excel Import.

As the pattern file is already open, RTUtil NT suggests the open file as pattern file. Accept with Next.

ABB Oy 14-38

Page 15: 05.RTU560 Step by Step

ABB OyPSS/SASRTU560

Revision: 4 Cities RTU560 Step By Step

Accept your RTU ”RHK”. (In standard projects is normally only one RTU available. Accept with Next.

Now select the Excel file that belongs to this project. Select Browse…..

ABB Oy 15-38

Page 16: 05.RTU560 Step by Step

ABB OyPSS/SASRTU560

Revision: 4 Cities RTU560 Step By Step

Check that path and filename of the excel file is correct! Then select next!

ABB Oy 16-38

Select your project directory! Select the ACTIVE Excel file of the project to be imported and continue with Select

Page 17: 05.RTU560 Step by Step

ABB OyPSS/SASRTU560

Revision: 4 Cities RTU560 Step By Step

Now as the Excel file is selected, you have to define the sheet(s) within the excel file to be imported. (The sheet for an IEC 870-5-103 Sub-Dev.Line is currently not used in this example. Otherwise this sheet would have to be selected too.)With the ” > ” or ” < ” button one single file is selected or deselected.With the ” >> ” or ” << ” button all existing files are selected or deselected.Select the Local IO sheet.

Continue with Next!

ABB Oy 17-38

Page 18: 05.RTU560 Step by Step

ABB OyPSS/SASRTU560

Revision: 4 Cities RTU560 Step By Step

Before the actual import RTUtil NT shows the selected files involved in the import procedure. Scroll the window if necessary. Continue with Start!

The Excel file is automatically opened for the import procedure. A log file with the extension log and an error file with the extension err are generated during this phase. If warnings or errors appear during this phase, the cells in the Excel file will be marked yellow for warnings and red for errors.

ABB Oy 18-38

Page 19: 05.RTU560 Step by Step

ABB OyPSS/SASRTU560

Revision: 4 Cities RTU560 Step By Step

Import has finished with 0 error(s) and 0 warning(s). The RTU file contains now the imported signals and must be saved. Continue with Browse to check the file name and directory to place the file.

ABB Oy 19-38

Select your project directory! For the first time, the directory is empty. Continue with Select. The RTU file will have the same name as the pattern file, but stored under the ”proj” directory.

Page 20: 05.RTU560 Step by Step

ABB OyPSS/SASRTU560

Revision: 4 Cities RTU560 Step By Step

Check that the path and filename of the project file is correct! Then select Finish!

Check that your project file does contain the imported signals in the ”View Signal Tree”.

ABB Oy 20-38

Page 21: 05.RTU560 Step by Step

ABB OyPSS/SASRTU560

Revision: 4 Cities RTU560 Step By Step

Check that your project file does contain the imported signals in the ”View Hardware Tree”.

ABB Oy 21-38

Page 22: 05.RTU560 Step by Step

ABB OyPSS/SASRTU560

Revision: 4 Cities RTU560 Step By Step

3.5 Build RTU files

Select ”Project” and then ”Build RTU Files”

Accept your RTU ”RHK”. (In standard projects is normally only one RTU available. Default name for the RTU file: ”RTU name.iod”. Continue with Browse!

ABB Oy 22-38

Page 23: 05.RTU560 Step by Step

ABB OyPSS/SASRTU560

Revision: 4 Cities RTU560 Step By Step

Check that the path and filename of the RTU file is correct! Continue with Next!

ABB Oy 23-38

Select your project directory! Name the RTU file for example RTU name & build dateThis name can be seen on the CPU after down loading. Continue with Select!

Page 24: 05.RTU560 Step by Step

ABB OyPSS/SASRTU560

Revision: 4 Cities RTU560 Step By Step

RTUtil NT prompts for Plausibility Check. Continue with Plausibility

Ensure there are no Errors, Warnings or Information’s. This requires that the RTU configuration is build in a way that no plausibility messages is generated. Continue with Generate File!

During RTU File generation a DOS window can be noticed.

ABB Oy 24-38

Page 25: 05.RTU560 Step by Step

ABB OyPSS/SASRTU560

Revision: 4 Cities RTU560 Step By Step

Finally RTUtil NT reports ”RTU files are generated” Continue with ”OK”. The window will

close.

ABB Oy 25-38

Page 26: 05.RTU560 Step by Step

ABB OyPSS/SASRTU560

Revision: 4 Cities RTU560 Step By Step

Close the session with ”File” and ”Exit”.

Check the generated files in the directory “rtufile”

ABB Oy 26-38

Page 27: 05.RTU560 Step by Step

ABB OyPSS/SASRTU560

Revision: 4 Cities RTU560 Step By Step

4. RTU560 Web Server

4.1 Precondition

Refer to manual “User’s Guide to RTU560 Web Server Installation and Configuration Release”

Chapter: PPP Installation and RAS Configuration Chapter: Establish PPP-Connection

4.2 Establish PPP- Connection

Connection is establishing…..

ABB Oy 27-38

Establish PPP-Connection. Continue with Dial

No passwort is required. Continue with OK.

Connected to: PPPLine speed: 38 400 bps

Field is flashing due to active link.

Page 28: 05.RTU560 Step by Step

ABB OyPSS/SASRTU560

Revision: 4 Cities RTU560 Step By Step

ABB Oy 28-38

Page 29: 05.RTU560 Step by Step

ABB OyPSS/SASRTU560

Revision: 4 Cities RTU560 Step By Step

4.3 Start Internet Explorer with address http//10.0.10.50

You will get the basic picture with the menu list on the left hand side. Choose Configuration.

Enter User Name and Password and accept with OK.

ABB Oy 29-38

Page 30: 05.RTU560 Step by Step

ABB OyPSS/SASRTU560

Revision: 4 Cities RTU560 Step By Step

4.4 Load config.iod (I/O Data)

“Load the basic Configuration files to the RTU” window appears. Continue with Browse.

ABB Oy 30-38

Page 31: 05.RTU560 Step by Step

ABB OyPSS/SASRTU560

Revision: 4 Cities RTU560 Step By Step

Browse for the config.iod file in your project rtufile directory and select Open.

ABB Oy 31-38

Page 32: 05.RTU560 Step by Step

ABB OyPSS/SASRTU560

Revision: 4 Cities RTU560 Step By Step

Check for correct selected file. And continue with Load RTU.

Uploading takes from aprox. 1 to 5 minutes depending of the size of configuration.

ABB Oy 32-38

Page 33: 05.RTU560 Step by Step

ABB OyPSS/SASRTU560

Revision: 4 Cities RTU560 Step By Step

File succsessfully transferred! Continue with Configuration

4.5 Load config.gcd (General Configuration Data)

Browse for the config.gcd file in your project rtufile directory and select Open.

ABB Oy 33-38

Page 34: 05.RTU560 Step by Step

ABB OyPSS/SASRTU560

Revision: 4 Cities RTU560 Step By Step

Check for correct selected file. And continue with Load RTU.

Uploading takes only a few seconds depending of the size of configuration.

ABB Oy 34-38

Page 35: 05.RTU560 Step by Step

ABB OyPSS/SASRTU560

Revision: 4 Cities RTU560 Step By Step

File succsessfully transferred! Continue with Configuration.

4.6 Load config.iod (Texts from Archiv or Printer)

Browse for the config.ptx file in your project rtufile directory and select Open.

ABB Oy 35-38

Page 36: 05.RTU560 Step by Step

ABB OyPSS/SASRTU560

Revision: 4 Cities RTU560 Step By Step

Check for correct selected file. And continue with Load RTU.

Uploading takes only a few seconds depending of the size of configuration.

ABB Oy 36-38

Page 37: 05.RTU560 Step by Step

ABB OyPSS/SASRTU560

Revision: 4 Cities RTU560 Step By Step

File succsessfully transferred! Continue with Configuration.

4.7 Restart RTU560

Reset RTU to activate the new configuration files. Continue with Reset.

ABB Oy 37-38

Page 38: 05.RTU560 Step by Step

ABB OyPSS/SASRTU560

Revision: 4 Cities RTU560 Step By Step

Connection lost due to restart of RTU

Establish the web Server connection again and check the System Diagnostic for possible errors. Check the new functionality of the RTU560 and make also spot checks of the old functionality.

ABB Oy 38-38