BTSE commissioning Siemens MN1784EU12MN_0001 © 2002 Siemens AG 1 Contents 1 Commissioning procedure 3 2 Visual inspection of BTSE 7 3 Reset CCTRL 11 4 Download BTSE software 15 5 Activate BTSE software 21 6 Set rack 25 7 Create hardware related managed objects 29 7.1 CREATE ENVABTSE 32 7.2 Set attributes for BTS site equipment 33 7.3 Creation of Bport 34 7.4 Enter BTS site manager attributes 36 7.5 LAPDLE creation 38 8 Verify module state/status 41 9 Manually switch to phase three 43 10 Generate backup files 45 11 BTSE restart verification 49 12 Functional structure 53 13 Exercises 59 BTSE commissioning

Upload: freddy-e-munoz-b

Post on 17-Jul-2016

13 views

Category:

Documents


4 download

DESCRIPTION

ssfvsd

TRANSCRIPT

Page 1: 08 Mn1784eu12mn 0001 Btse Commissioning

BTSE commissioning Siemens

MN1784EU12MN_0001 © 2002 Siemens AG

1

Contents 1 Commissioning procedure 3 2 Visual inspection of BTSE 7 3 Reset CCTRL 11 4 Download BTSE software 15 5 Activate BTSE software 21 6 Set rack 25 7 Create hardware related managed objects 29 7.1 CREATE ENVABTSE 32 7.2 Set attributes for BTS site equipment 33 7.3 Creation of Bport 34 7.4 Enter BTS site manager attributes 36 7.5 LAPDLE creation 38 8 Verify module state/status 41 9 Manually switch to phase three 43 10 Generate backup files 45 11 BTSE restart verification 49 12 Functional structure 53 13 Exercises 59

BTSE commissioning

Page 2: 08 Mn1784eu12mn 0001 Btse Commissioning

Siemens BTSE commissioning

MN1784EU12MN_0001© 2002 Siemens AG

2

Page 3: 08 Mn1784eu12mn 0001 Btse Commissioning

BTSE commissioning Siemens

MN1784EU12MN_0001 © 2002 Siemens AG

3

1 Commissioning procedure

Page 4: 08 Mn1784eu12mn 0001 Btse Commissioning

Siemens BTSE commissioning

MN1784EU12MN_0001© 2002 Siemens AG

4

To bring-up the BTSE, follow the "Procedures" chapter in the ITMN:BTSE BS XX. In the CML:BTSE you will find more information about the meaning of specific attributes.

Page 5: 08 Mn1784eu12mn 0001 Btse Commissioning

BTSE commissioning Siemens

MN1784EU12MN_0001 © 2002 Siemens AG

5

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Manually Switchto Phase Three

Reset CCTRL

Download BTSE Software

Activate BTSE Software

Create Hardware RelatedManaged Objects

Set Environmental Alarmsand BTS Site Equipment

Set Rack Attributes

Enter BTS Site ManagerAttributes

Verify ModuleState/Status

Create Bport and Xconnect

Fig. 1 BTSE bring-up

Page 6: 08 Mn1784eu12mn 0001 Btse Commissioning

Siemens BTSE commissioning

MN1784EU12MN_0001© 2002 Siemens AG

6

Page 7: 08 Mn1784eu12mn 0001 Btse Commissioning

BTSE commissioning Siemens

MN1784EU12MN_0001 © 2002 Siemens AG

7

2 Visual inspection of BTSE

Page 8: 08 Mn1784eu12mn 0001 Btse Commissioning

Siemens BTSE commissioning

MN1784EU12MN_0001© 2002 Siemens AG

8

Visually inspect the BTSE mechanics, electrics and modules. Follow the appropriate chapters in the ITMN:BTSE BS XX.

Page 9: 08 Mn1784eu12mn 0001 Btse Commissioning

BTSE commissioning Siemens

MN1784EU12MN_0001 © 2002 Siemens AG

9

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

BBSIG

BBSIG

CB FP

AIR FILTER

ACOM

ACOM

ACOM

RXMUC

RXMUC

RXMUC

RXMUC

RXMUC

RXMUC

RXMUC

RXMUC

RXMUC

RXMUC

RXMUC

RXMUC

PA

TPU

PA

TPU

PA

TPU

PA

TPU

PA

TPU

PA

TPU

PA

TPU

DCPA

DCTPU

DCTPU

DCPA

DCPA

DCTPU

DCTPU

DCPA

DCPA

DCTPU

DCPA

DCTPU

GPSU

BBSIG

BBSIG

BBSIG

BBSIG

MCLK

CCTRL

LI

ALCO

FANS

Fig. 2 Visual inspection of BTSE

Page 10: 08 Mn1784eu12mn 0001 Btse Commissioning

Siemens BTSE commissioning

MN1784EU12MN_0001© 2002 Siemens AG

10

Page 11: 08 Mn1784eu12mn 0001 Btse Commissioning

BTSE commissioning Siemens

MN1784EU12MN_0001 © 2002 Siemens AG

11

3 Reset CCTRL

Page 12: 08 Mn1784eu12mn 0001 Btse Commissioning

Siemens BTSE commissioning

MN1784EU12MN_0001© 2002 Siemens AG

12

Press the small black push button on the CCTRL board. After about 15 seconds the CCTRL reaches the start connection status. LED Indication of CCTRL: RY: green RBM: red ACT: yellow PRGA: off SPA1: off SPA2: green, flashing

Page 13: 08 Mn1784eu12mn 0001 Btse Commissioning

BTSE commissioning Siemens

MN1784EU12MN_0001 © 2002 Siemens AG

13

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

TAD

LED green

LED yellow

Pushbutton

RY

ACT

RES

LED red

LED red

CCTRL

LED green LED greenSPA 1 SPA 2

PRGA

RBM

Fig. 3 CCTRL front plate with LED and reset button

Page 14: 08 Mn1784eu12mn 0001 Btse Commissioning

Siemens BTSE commissioning

MN1784EU12MN_0001© 2002 Siemens AG

14

Page 15: 08 Mn1784eu12mn 0001 Btse Commissioning

BTSE commissioning Siemens

MN1784EU12MN_0001 © 2002 Siemens AG

15

4 Download BTSE software

Page 16: 08 Mn1784eu12mn 0001 Btse Commissioning

Siemens BTSE commissioning

MN1784EU12MN_0001© 2002 Siemens AG

16

In BTSE phase 1 only very few commands are available. One of them is DNLALLEXE: LMT tree: MANAGED-ELEMENT --> SOFTWARE-MANAGEMENT Command: DNLALLEXE Name: none Attributes: SCRDIR=<path where the SW Load is stored on the LMT>

HEADER=<enter header according to the SW Load e.g.: HSxxxxxx.SWL> OVERWRITE=YES

Submit Command line: DNLALLEXE:SRCDIR="<path where the SW Load is stored on the LMT>", HEADER="HSxxxxxx.swl", OVERWRITE=YES; The result is a complete SW download, on LMT the load progress in % is indicated. The entire procedure requires about ca 10 minutes. During the download procedure the CCTRL PRGA LED is flashing. Check during downloading whether all BTSE executable files (*.swi files) are successfully transferred.

Page 17: 08 Mn1784eu12mn 0001 Btse Commissioning

BTSE commissioning Siemens

MN1784EU12MN_0001 © 2002 Siemens AG

17

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Fig. 4 Software download to BTSE

Page 18: 08 Mn1784eu12mn 0001 Btse Commissioning

Siemens BTSE commissioning

MN1784EU12MN_0001© 2002 Siemens AG

18

SW Image Description Module btsarc01.swi analog radio controller TPU/TRXA

btsdrx01.swi digital radio controller TPU/TRXD

btsdrx03.swi digital radio controller TPU/TRXD2

btsbbx01.swi baseband and signaling processors BBSIG

btsbbx03.swi baseband and signaling processors BBSIG44

btsbmc01.swi base station master controller CCTRL

btscac01.swi central alarm controller ALCO

btscck01.swi common clock CCLK

btslic01.swi link interface controller LI

btslic04.swi link interface controller LI BTSE executable files

Page 19: 08 Mn1784eu12mn 0001 Btse Commissioning

BTSE commissioning Siemens

MN1784EU12MN_0001 © 2002 Siemens AG

19

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

LMT

download software

CCTRL Flash EPROM

Fig. 5 Download BTSE software

Page 20: 08 Mn1784eu12mn 0001 Btse Commissioning

Siemens BTSE commissioning

MN1784EU12MN_0001© 2002 Siemens AG

20

Page 21: 08 Mn1784eu12mn 0001 Btse Commissioning

BTSE commissioning Siemens

MN1784EU12MN_0001 © 2002 Siemens AG

21

5 Activate BTSE software

Page 22: 08 Mn1784eu12mn 0001 Btse Commissioning

Siemens BTSE commissioning

MN1784EU12MN_0001© 2002 Siemens AG

22

From LMT perform the following steps: LMT tree: MANAGED-ELEMENT --> BSS-FUNCTIONAL --> BTS --> BTSM Command: ACTIVATE BTSM Name: NAME=BTSM:0 Attributes: FID=<Name of the Software Load Header file: HSxxyyzz.SWL>

FV=<Software Load Header: SS-VV-RR-PR-LL-CL_Year-Month-Day Submit Command line: ACTSW BTSM:NAME=BTSM:0,FID=<Name of the Software Load Header file: HSxxyyzz.SWL>, FV=<Software Load Header: SS-VV-RR-PR-LL-CL_Year-Month-Day This procedure requires about 1 minute. The BTSE switches from phase 1 to phase 2 and therefore a new Logon is necessary.

Page 23: 08 Mn1784eu12mn 0001 Btse Commissioning

BTSE commissioning Siemens

MN1784EU12MN_0001 © 2002 Siemens AG

23

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Fig. 6 Activate BTSM

CCTRL Flash EPROM

activate software

RAM of Processors

Fig. 7 Activate BTSE software

Page 24: 08 Mn1784eu12mn 0001 Btse Commissioning

Siemens BTSE commissioning

MN1784EU12MN_0001© 2002 Siemens AG

24

Page 25: 08 Mn1784eu12mn 0001 Btse Commissioning

BTSE commissioning Siemens

MN1784EU12MN_0001 © 2002 Siemens AG

25

6 Set rack

Page 26: 08 Mn1784eu12mn 0001 Btse Commissioning

Siemens BTSE commissioning

MN1784EU12MN_0001© 2002 Siemens AG

26

To enter the rack attributes, perform the following steps from LMT: LMT tree: MANAGED-ELEMENT --> BSS-EQUIPMENT --> BTSE --> RACK Command: SET RACK Name: NAME=RACK:0 Attributes: BATTBAK=<installed or not_installed>

TYPBTSE=BSxx TYPRFSR=<Type of RF Subrack: horizontal or vertical>

Submit Command line: SET RACK:NAME=RACK:0,BATTBAK=<installed or not_installed>,TYPBTSE=BSxx, TYPRFSR=<Type of RF Subrack: horizontal or vertical>;

BA TTBAK This attribute indicates whether or not a battery backup is installed.

TYPBTSE This attribute identifies the type of BTSE. Validity range: BS20, BS21E, BS60, BS61E, BS22.

TYPRFSR This attribute identifies the type of the RF subrack. Validity range: RF_SUBRACK_V1 (horizontal design), RF_SUBRACK_V2 (vertical design).

Rack attributes

Page 27: 08 Mn1784eu12mn 0001 Btse Commissioning

BTSE commissioning Siemens

MN1784EU12MN_0001 © 2002 Siemens AG

27

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Fig. 8 Set rack attributes

Page 28: 08 Mn1784eu12mn 0001 Btse Commissioning

Siemens BTSE commissioning

MN1784EU12MN_0001© 2002 Siemens AG

28

Page 29: 08 Mn1784eu12mn 0001 Btse Commissioning

BTSE commissioning Siemens

MN1784EU12MN_0001 © 2002 Siemens AG

29

7 Create hardware related managed objects

Page 30: 08 Mn1784eu12mn 0001 Btse Commissioning

Siemens BTSE commissioning

MN1784EU12MN_0001© 2002 Siemens AG

30

The CCTRL is the only module, which is created automatically by the system. All other modules have to be created by manually. Creating these so called hardware related managed objects means that the modules are defined in the local database of the BTSE, which is stored on the CCTRL Flash EPROM. For each BTSE up to 14 different types of hardware related managed objects have to be created. For each module (type), which is equipped in the specific BTSE you are just commissioning, perform the following steps from the LMT: LMT tree: MANAGED-ELEMENT --> BSS-EQUIPMENT --> BTSE --> RACK -->

Module Command: CREATE Module Name: NAME=RACK:0/Module:<Module Number> Attributes: depending on the module type Submit Command line: CREATE Module:NAME=NAME=RACK:0/Module:<Module Number>,Attributes According to this scheme, create all the modules, which are equipped in the specific BTSE you are just commissioning. Refer to the corresponding procedure in the ITMN:BTSE BS XX. The following table summarizes the different types of possible managed objects. Refer to the customer specific documentation in order to determine the managed objects, which need to be created for the site.

Page 31: 08 Mn1784eu12mn 0001 Btse Commissioning

BTSE commissioning Siemens

MN1784EU12MN_0001 © 2002 Siemens AG

31

Module Parameter range

ACOM/TXAMOD 0...2

ALCO 0

BBSIG 0...5

CCLK 0

FAN 0...2

GPSU 0

LI 0

PA 0...5

RXAMOD 0...5

RXMUCO/RXAMCO 0...7

TPU 0...5

AC_DC 0

FICOM_VSWR 0...2

FICOM_TNF 0...5 List of the hardware related managed objects

Fig. 9 Example: Creation of ACOM (wiring data)

Page 32: 08 Mn1784eu12mn 0001 Btse Commissioning

Siemens BTSE commissioning

MN1784EU12MN_0001© 2002 Siemens AG

32

7.1 CREATE ENVABTSE To configure external alarms perform the following steps from LMT: LMT tree: MANAGED-ELEMENT --> BSS-EQUIPMENT --> BTSE --> RACK -->

ENVABTSE Command: CREATE ENVABTSE Name: NAME=RACK:0/ENVABTSE:<Number of environmental alarm> Attributes: INTINF=<interfaceInformation>

ASEV=<associatedSeverity> ASTRING=<associatedString>

Submit Command line: CREATE ENVABTSE:NAME=RACK:0/ENVABTSE:<Number of environmental alarm>, INTINF=<interfaceInformation>, ASEV=<associatedSeverity>, ASTRING=<associatedString>

Number of environmental alarm This attribute selects one of the 20 possible environmental alarms. Validity range: 0 - 19.

associatedSeverity This attribute allows the operator to define a specific severity level for the failure event report related to an environmental alarm. Validity range: CRITICAL, MAJOR, MINOR, WARNING.

associatedString This attribute allows the operator to define a specific text string for the failure event report related to an environmental alarm. Validity range: STRING with max. 26 ASCII characters.

interfaceInformation Depending on the type of external alarm sensor this attribute must be set to high for a break contact (‘’normal closed’’) or to low for a make contact (‘’normal open’’).

Attributes of BTSE environmental alarms

Page 33: 08 Mn1784eu12mn 0001 Btse Commissioning

BTSE commissioning Siemens

MN1784EU12MN_0001 © 2002 Siemens AG

33

7.2 Set attributes for BTS site equipment

Fig. 10 Set BTSE attributes

locationName This attribute identifies a location. Validity range: a string of 1 to n, n = 37 characters (default: EARTH).

vendorName This attribute identifies the vendor of the associated object. Validity range: a string of 1 to n, n = 37 characters (default: SIEMENS).

swLoadSafety This attribute describes the file ID and the version number of the SW Load stored in the BTSE as the most trusted SW load that is used if the intended SW is damaged in some way.

salesUniqueName With the help of this attribute a sales unique name can be set. This sales unique name must be a string with min = max = 11 characters.

Important BTS site equipment attributes

Page 34: 08 Mn1784eu12mn 0001 Btse Commissioning

Siemens BTSE commissioning

MN1784EU12MN_0001© 2002 Siemens AG

34

7.3 Creation of Bport Before the BTSM attributes can be set, the Bports must be created. The range of possible values for BS2x/6x is "0,2" A layer1 control timeslot (16 kbit/s) is needed when the line configuration is "loop" or when two PCMB lines are connected to the BTSE. These two configurations are mutually exclusive.

Page 35: 08 Mn1784eu12mn 0001 Btse Commissioning

BTSE commissioning Siemens

MN1784EU12MN_0001 © 2002 Siemens AG

35

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Fig. 11 Creation of Bport

Page 36: 08 Mn1784eu12mn 0001 Btse Commissioning

Siemens BTSE commissioning

MN1784EU12MN_0001© 2002 Siemens AG

36

7.4 Enter BTS site manager attributes Here, the attributes of the BTS_Site_Manager (BTSM) are set. The BTS Site Manager represents the O&M functionality related to a site and not to any specific BTS. A site is a logical grouping of one or more BTS (maximum 3) at a single physical location with common management needs. This configuration has to match with the related LPDLM-Object in the BSC. Note: the LAPD signaling on BTSM must terminate on Bport 0.

ABISTIME This attribute provides the time-of-day time of the BTSE. This attribute functions as a reference for all time stamp activities in the BTSE. Validity range: Year 1000-9999, Month 1-12, Day 1-31, Hour 0-23, Minute 0-59, Second 0-59.

ABISCH This attribute identifies the LAPD signaling Timeslot Number (and Subslot Number) allocated on the Abis-interface. Validity range: Timeslot_Number: 1-31 (PCM30), 1-24 (PCM24). Subslot Number: a (bits 1,2)=0, b (bits 3,4)=1, c (bits 5,6)=2, d (bits 7,8)=3, 64 kb/s signal.=0xFF.

TEI This attribute contains the Terminal Endpoint Identifier used in the layer2 addressing on the Abis-Interface for the logical O&M Link. The TEI is used to identify a specific point-to-point connection; each BTSM normally has one associated TEI. Validity range: 0-63.

BTS site manager attributes

Page 37: 08 Mn1784eu12mn 0001 Btse Commissioning

BTSE commissioning Siemens

MN1784EU12MN_0001 © 2002 Siemens AG

37

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Fig. 12 Set BTSM attributes

Page 38: 08 Mn1784eu12mn 0001 Btse Commissioning

Siemens BTSE commissioning

MN1784EU12MN_0001© 2002 Siemens AG

38

7.5 LAPDLE creation The object LAPDLE identifies the time slot on Abis used for communication between BSC and BTSE (as viewed from BTSE). Its counterpart on the BSC side is called "LPDLM". It is possible to configure up to 8 LAPDLE/LPDLM objects on two PCMB lines. Each line must carry at least one LAPDLE/LPDLM. The LAPD links are either all 64 kbit/s (3 and more TRX per BTSE) or all 16 kbit/s (max 2 TRX/BTSE), and either all satellited or all not satellited. Note: The object "LPDLM" on the BSC command tree indicates a time slot, which may carry both LPDLM and LPDLR type LAPD signaling. The settings for LAPDLE (BTSE commissioning) and LPDLM (BSC database) must be consistent.

Page 39: 08 Mn1784eu12mn 0001 Btse Commissioning

BTSE commissioning Siemens

MN1784EU12MN_0001 © 2002 Siemens AG

39

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Fig. 13 LAPDLE creation

Page 40: 08 Mn1784eu12mn 0001 Btse Commissioning

Siemens BTSE commissioning

MN1784EU12MN_0001© 2002 Siemens AG

40

Page 41: 08 Mn1784eu12mn 0001 Btse Commissioning

BTSE commissioning Siemens

MN1784EU12MN_0001 © 2002 Siemens AG

41

8 Verify module state/status

Page 42: 08 Mn1784eu12mn 0001 Btse Commissioning

Siemens BTSE commissioning

MN1784EU12MN_0001© 2002 Siemens AG

42

Check the state and status of all the hardware modules created. For all successfully created objects the administrative state must be unlocked and the operational state must be enabled. From LMT, perform the following steps: LMT tree: MANAGED-ELEMENT --> BSS-EQUIPMENT --> BTSE --> RACK -->

<module> Command: GET <Module Name> Name: NAME=RACK:0/<Module Name> Attributes: REQATTL=AST&OST Submit Command line: GET Module:NAME=RACK:0/<Module Name>, REQATTL=AST&OST;

Page 43: 08 Mn1784eu12mn 0001 Btse Commissioning

BTSE commissioning Siemens

MN1784EU12MN_0001 © 2002 Siemens AG

43

9 Manually switch to phase three

Page 44: 08 Mn1784eu12mn 0001 Btse Commissioning

Siemens BTSE commissioning

MN1784EU12MN_0001© 2002 Siemens AG

44

For forced switchover to phase three a special command (connect BSC to BTSM command) must be entered at the LMT. LMT tree: MANAGED-ELEMENT --> BSS-FUNCTIONAL --> BTS --> BTSM Command: CONNBSC BTSM Name: NAME=BTSM:0 Attributes: none Submit Command line: CONNBSC BTSM:NAME=BTSM:0; To unlock the BTSM, perform the following steps from LMT: LMT tree: MANAGED-ELEMENT --> BSS-FUNCTIONAL --> BTSM --> Command: UNLOCK BTSM Name: NAME=BTSM:0 Attributes: none Submit Command line: UNLOCK BTSM:NAME=BTSM:0;

Page 45: 08 Mn1784eu12mn 0001 Btse Commissioning

BTSE commissioning Siemens

MN1784EU12MN_0001 © 2002 Siemens AG

45

10 Generate backup files

Page 46: 08 Mn1784eu12mn 0001 Btse Commissioning

Siemens BTSE commissioning

MN1784EU12MN_0001© 2002 Siemens AG

46

In order to save the latest BTSplus configuration, a backup copy is generated and stored on site, e.g. on a floppy disk. By default; all files necessary to perform the backup and restore procedure are stored in subdirectory C:/Siemens/LMTxxx/BkBts/BTSplusyy on the LMT hard disk (where yy can be 16, 17 or 18 to indicate BR7.0, BR8.0 or BR9.0 SW version used in the BTS, respectively). BTSplus backup files are generated in phase 2 or 3 by performing the following steps:

• start BTS Backup tool (from LMT Evolution , menu View)

• Select the command GET (button or file menu) The objects and attributes of the BTSE are stored in up to 8 TXT files (e.g. GETBPORP) describing the current configuration. For the restoring these files are converted into script files (e.g. script1p.lmt) generated. These script files should be backed up on CD and left in the BTSE so that you can use them in case of a COBA failure.

Page 47: 08 Mn1784eu12mn 0001 Btse Commissioning

BTSE commissioning Siemens

MN1784EU12MN_0001 © 2002 Siemens AG

47

Fig. 14 Start BKBTS tool

Fig. 15 Folder for backup files

Page 48: 08 Mn1784eu12mn 0001 Btse Commissioning

Siemens BTSE commissioning

MN1784EU12MN_0001© 2002 Siemens AG

48

Page 49: 08 Mn1784eu12mn 0001 Btse Commissioning

BTSE commissioning Siemens

MN1784EU12MN_0001 © 2002 Siemens AG

49

11 BTSE restart verification

Page 50: 08 Mn1784eu12mn 0001 Btse Commissioning

Siemens BTSE commissioning

MN1784EU12MN_0001© 2002 Siemens AG

50

Power off and on the BTSE to ensure that the BTSE recovers without errors in case of a total loss of power.

Page 51: 08 Mn1784eu12mn 0001 Btse Commissioning

BTSE commissioning Siemens

MN1784EU12MN_0001 © 2002 Siemens AG

51

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

BBSIG

BBSIG

CB FP

AIR FILTER

ACOM

ACOM

ACOM

RXMUC

RXMUC

RXMUC

RXMUC

RXMUC

RXMUC

RXMUC

RXMUC

RXMUC

RXMUC

RXMUC

RXMUC

PA

TPU

PA

TPU

PA

TPU

PA

TPU

PA

TPU

PA

TPU

PA

TPU

DCPA

DCTPU

DCTPU

DCPA

DCPA

DCTPU

DCTPU

DCPA

DCPA

DCTPU

DCPA

DCTPU

GPSU

BBSIG

BBSIG

BBSIG

BBSIG

MCLK

CCTRL

LI

ALCO

FANS

Fig. 16 Restart verification

Page 52: 08 Mn1784eu12mn 0001 Btse Commissioning

Siemens BTSE commissioning

MN1784EU12MN_0001© 2002 Siemens AG

52

Page 53: 08 Mn1784eu12mn 0001 Btse Commissioning

BTSE commissioning Siemens

MN1784EU12MN_0001 © 2002 Siemens AG

53

12 Functional structure

RXAMCO1

TPU 0

TPU 1

DCTPU0

DCTPU1

DCPA0

DCPA1

FAN 0

BackupBatteryGPSU 0

PDB

...Diversity

-48 V 230 V AC

ALCO 0

ALCO 0

MCUX 0

BBSIG 0

MSG 0

LI 0

LMT

Site Inputs

Site Outputs

BU

S 1

BU

S 2

Abis

RXAMCO1

Cell 0

DUKITfx (2:1)

PA 1

PA 0

DUKIT0

1

0

1

1

0

0

0

DCBreaker AC/DC 0

Fig. 17 Functional blocks of a 2 carrier BTSE (BS20) with DUKIT (configured for 1 cell with 2 carriers)

Page 54: 08 Mn1784eu12mn 0001 Btse Commissioning

Siemens BTSE commissioning

MN1784EU12MN_0001© 2002 Siemens AG

54

TPU 0

TPU 1

DCTPU 0

DCTPU 1

DCPA 1

DCPA 1

FAN 0

GPSU 0 BackupBattery

HOSTEXCHANGE HOSTER

AC/DC 0

AC/DC 1

PDB

ALCO 0

CCTRL 0

MCLK 0

BBSIG 1

MCLK 0

LI 0

LMT

Site Inputs

Site Outputs

BU

S 2

BU

S 1

LinkEquipment

Abis

Cell 0

DUKITfx (2:1)

RXAMCO0

RXAMCO1

230 V AC

...Diversity

-48 VDC

Breaker

PA 0

PA 1

DUKIT 0

0

1

0

1

0

0

1

Fig. 18 Functional blocks of a 2 carrier BTSE (BS21E) with DUKIT (configured for 1 cell with 2 carriers)

Page 55: 08 Mn1784eu12mn 0001 Btse Commissioning

BTSE commissioning Siemens

MN1784EU12MN_0001 © 2002 Siemens AG

55

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

DUCOMT

PA TPU

RXAMCO

RXAMCO

FCB 0...Diversity

BU

S 1

LI

CCLK

CCTRL

ALCO

BBSIG

Abis

BU

S 2

LMT

FP230V AC

ACMDC

Fig. 19 Functional blocks of a 2 carrier BTSE (BS22) with DUCOMT (configured for 1 cell with 2 carriers)

Page 56: 08 Mn1784eu12mn 0001 Btse Commissioning

Siemens BTSE commissioning

MN1784EU12MN_0001© 2002 Siemens AG

56

HYCOMPA TPU BBSIG

CCLK

CCTRL

ALCO

GPSU FP-48 V DCDCTPUDCPA

FAN 2

FAN 1

FAN 0

RXMUCORXAMOD

RXMUCORXAMOD

LMT

Site Inputs

Site Outputs

LI

Abis(OVPT, NTPM or µWave)

...Diversity

BU

S 2

BUS

1

Fig. 20 Functional blocks of a 6 carrier BTSE with HYCOM (configured for 1 cell with 4 carriers)

Page 57: 08 Mn1784eu12mn 0001 Btse Commissioning

BTSE commissioning Siemens

MN1784EU12MN_0001 © 2002 Siemens AG

57

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

DLCOM

RXAMCO

RXAMCO

DCPA DCTPUFAN 2

FAN 1

FAN 0

...Diversity ALCO

CCLK

GPSU FP

LMT

SiteInput

SiteOutput

-48 V DC

BUS

2

Abis

BBSIG

LI

CCTRL

TPUPA

BU

S 1

Fig. 21 Functional blocks of a 6 carrier BTSE with DUCOM (configured for 1 cell with 4 carriers)

Page 58: 08 Mn1784eu12mn 0001 Btse Commissioning

Siemens BTSE commissioning

MN1784EU12MN_0001© 2002 Siemens AG

58

FICOM

RXAMCORXFIL

RXAMCORXFIL

RXMUCO

RXMUCO

DCPA DCTPU

GPSU FP

ALCO

CCTRL

CCLK

LITPUPA

BU

S 1

BU

S 2

BBSIG

-48 V DC

LMT

Site Inputs

Site Outputs

...Diversity

FAN 2

FAN 1

FAN 0

Abis

Fig. 22 Functional blocks of a 6 carrier BTSE with FICOM (configured for 1 cell with 6 carriers)

Page 59: 08 Mn1784eu12mn 0001 Btse Commissioning

BTSE commissioning Siemens

MN1784EU12MN_0001 © 2002 Siemens AG

59

13 Exercises

Page 60: 08 Mn1784eu12mn 0001 Btse Commissioning

Siemens BTSE commissioning

MN1784EU12MN_0001© 2002 Siemens AG

60

Page 61: 08 Mn1784eu12mn 0001 Btse Commissioning

BTSE commissioning Siemens

MN1784EU12MN_0001 © 2002 Siemens AG

61

Exercise 1 Commission a BTSE in the Training Center. Remember, in the Training Center you will find an already running system. Therefore, before you follow chapters 1, 2 and 3 of this register, you have to do some previous work and to add some additional steps in order to bring the system down. Previous work to be done:

• Write down the name of the software load header file and the software load header itself for the BTSE. Take a look to the subdirectory containing the BTSE software on your LMT hard disk. Compare it with the information in the BSC database.

• With which command can you display the currently running software on the BTSE?

• Find out the configuration (star, loop or multidrop chain) of the BTSE.

• Find out the TEI and SalesUniqueName of the BTSE.

• Find out which timeslot is used for LAPD signaling.

• Find out whether a 64 kbit/s or a 16 kbit/s timeslot is used for LAPD signaling.

• Find out whether or not CRC is used.

• Find out whether or not environmental alarms have to be equipped. Usually „find out“ means: ask your boss or your colleagues. Since we have a running system in the Training Center you can also interrogate the system itself. Therefore use the following commands from LMT: LMT tree: MANAGED-ELEMENT --> BSS-EQUIPMENT --> BTSE Command: GET BTSE Name: NAME=BTSE:0 Attributes: REQATTL= SWLDINT, SWLDSAF, SWLDST; Submit Command line: GET BTSE SWL: NAME=BTSE:0, REQATTL= SWLDINT, SWLDSAF, SWLDST;

Page 62: 08 Mn1784eu12mn 0001 Btse Commissioning

Siemens BTSE commissioning

MN1784EU12MN_0001© 2002 Siemens AG

62

LMT tree: MANAGED-ELEMENT --> BSS.FUNCTIONAL --> BTSM Command: GET BTSM Name: NAME=BTSM:0 Attributes: REQATTL= ABISCH, TEI; Submit Command line: GET BTSM: NAME=BTSM:0, REQATTL= ABISCH, TEI; LMT tree: MANAGED-ELEMENT --> BSS-EQUIPMENT --> BTSE --> RACK -->

LI Command: GET LI Name: NAME=RACK:0/LI:0 Attributes: REQATTL= BERT, LCONF, ALRMT1/2/3, ALRMCOUNTER; Submit Command line: GET LI: NAME=RACK:0/LI:0, REQATTL= REQATTL= BERT, LCONF, ALRMT1/2/3, ALRMCOUNTER;

Page 63: 08 Mn1784eu12mn 0001 Btse Commissioning

BTSE commissioning Siemens

MN1784EU12MN_0001 © 2002 Siemens AG

63

Exercise 2 Additional steps in order to bring the system down

I) Lock BTSM and disconnect (by command) BTSE from BSC From LMT, enter the following commands: LMT tree: MANAGED-ELEMENT --> BSS-FUNCTIONAL --> BTSM Command: LOCK BTSM Name: NAME=BTSM:0 Attributes: none Submit Command line: LOCK BTSM: NAME=BTSM:0; LMT tree: MANAGED-ELEMENT --> BSS-FUNCTIONAL --> BTSM Command: DISCBSC Name: NAME=BTSM:0; Attributes: none Submit Command line: DISCBSC BTSM: NAME=BTSM:0; BTSE switches from phase 3 to phase 2. A new Logon is necessary.

Page 64: 08 Mn1784eu12mn 0001 Btse Commissioning

Siemens BTSE commissioning

MN1784EU12MN_0001© 2002 Siemens AG

64

Page 65: 08 Mn1784eu12mn 0001 Btse Commissioning

BTSE commissioning Siemens

MN1784EU12MN_0001 © 2002 Siemens AG

65

Exercise 3 I) Format CCTRL Flash EPROM

From LMT, perform the following steps: LMT tree: MANAGED-ELEMENT --> BSS-EQUIPMENT --> BTSE Command: FORMAT BTSE FLASH Name: NAME=BTSE:0; Attributes: none Submit Command line: FORMAT BTSE FLASH: NAME=BTSE:0; This procedure requires about 1-2 minutes. The BTSE switches from phase 2 to phase 1. A new Logon is necessary.

II) Power off the BTSE Switch off all fuses. Follow now chapters 1, 2 and 3 of this register to commission the BTSE.