1 1 chapter four 4-managerial process 4.1 estimating project time and costs 4-2 project cash flows...

119
1 1 C H A P T E R F O U R C H A P T E R F O U R 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control. Management tools, accounts, general cost control systems.

Upload: marcia-houston

Post on 31-Dec-2015

215 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

11

CH

AP

TE

R F

OU

R

CH

AP

TE

R F

OU

R

CH

AP

TE

R F

OU

R

CH

AP

TE

R F

OU

R

4-MANAGERIAL PROCESS

4.1 Estimating project time and costs

4-2 Project cash flows4.3 Performance and payment bonds

4-5 Cost Control. Management tools, accounts, general cost control systems.

Page 2: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

5–2

Where We Are NowWhere We Are NowWhere We Are NowWhere We Are Now

Page 3: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

5–3

Estimating Projects Estimating Projects Estimating Projects Estimating Projects

• Estimating–The process of forecasting or approximating the time

and cost of completing project deliverables.–The task of balancing expectations of stakeholders

and need for control while the project is implemented.

• Types of Estimates–Top-down (macro) estimates: analogy, group

consensus, or mathematical relationships–Bottom-up (micro) estimates: estimates of elements

of the work breakdown structure

Page 4: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

5–4

Why Estimating Time and Cost Are ImportantWhy Estimating Time and Cost Are ImportantWhy Estimating Time and Cost Are ImportantWhy Estimating Time and Cost Are Important

EXHIBIT 5.1

• To support good decisions.

• To schedule work.

• To determine how long the project should take and its cost.

• To determine whether the project is worth doing.

• To develop cash flow needs.

• To determine how well the project is progressing.

• To develop time-phased budgets and establish the project baseline.

Page 5: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

5–5

Factors Influencing the Quality of EstimatesFactors Influencing the Quality of EstimatesFactors Influencing the Quality of EstimatesFactors Influencing the Quality of Estimates

Quality of Estimates

Quality of Estimates

ProjectDuration

ProjectDuration

PeoplePeople

Project Structure and Organization

Project Structure and Organization

PaddingEstimates

PaddingEstimates

OrganizationCulture

OrganizationCulture

Other (Nonproject)Factors

Other (Nonproject)Factors

Planning HorizonPlanning Horizon

Page 6: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

5–6

Estimating Guidelines for Times, Estimating Guidelines for Times, Costs, and ResourcesCosts, and Resources

Estimating Guidelines for Times, Estimating Guidelines for Times, Costs, and ResourcesCosts, and Resources

1. Have people familiar with the tasks make the estimate.

2. Use several people to make estimates.

3. Base estimates on normal conditions, efficient methods, and a normal level of resources.

4. Use consistent time units in estimating task times.

5. Treat each task as independent, don’t aggregate.

6. Don’t make allowances for contingencies.

7. Adding a risk assessment helps avoid surprises to stakeholders.

Page 7: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

5–7

Top-Down versus Bottom-Up EstimatingTop-Down versus Bottom-Up EstimatingTop-Down versus Bottom-Up EstimatingTop-Down versus Bottom-Up Estimating

• Top-Down Estimates–Are usually are derived from someone who uses

experience and/or information to determine the project duration and total cost.

–Are made by top managers who have little knowledge of the processes used to complete the project.

• Bottom-Up Approach–Can serve as a check on cost elements in the WBS

by rolling up the work packages and associated cost accounts to major deliverables at the work package level.

Page 8: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

5–8

Top-Down versus Bottom-Up EstimatingTop-Down versus Bottom-Up EstimatingTop-Down versus Bottom-Up EstimatingTop-Down versus Bottom-Up Estimating

TABLE 5.1

Conditions for Preferring Top-Down or Bottom-up Time and Cost Estimates

Condition Macro Estimates Micro Estimates

Strategic decision making X

Cost and time important X

High uncertainty X

Internal, small project X

Fixed-price contract X

Customer wants details X

Unstable scope X

Page 9: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

5–9

Estimating Projects: Preferred ApproachEstimating Projects: Preferred ApproachEstimating Projects: Preferred ApproachEstimating Projects: Preferred Approach

• Make rough top-down estimates.

• Develop the WBS/OBS.

• Make bottom-up estimates.

• Develop schedules and budgets.

• Reconcile differences between top-down and bottom-up estimates

Page 10: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

5–10

Top-Down Approaches for Estimating Top-Down Approaches for Estimating Project Times and CostsProject Times and Costs

Top-Down Approaches for Estimating Top-Down Approaches for Estimating Project Times and CostsProject Times and Costs

• Consensus methods

• Ratio methods

• Apportion method

• Function point methods for software and system projects

• Learning curves

Project EstimateTimesCosts

Page 11: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

5–11

Apportion Method of Allocating Project Costs Apportion Method of Allocating Project Costs Using the Work Breakdown StructureUsing the Work Breakdown Structure

Apportion Method of Allocating Project Costs Apportion Method of Allocating Project Costs Using the Work Breakdown StructureUsing the Work Breakdown Structure

FIGURE 5.1

Page 12: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

5–12

Simplified Basic Function Point Count Process Simplified Basic Function Point Count Process for a Prospective Project or Deliverablefor a Prospective Project or Deliverable

Simplified Basic Function Point Count Process Simplified Basic Function Point Count Process for a Prospective Project or Deliverablefor a Prospective Project or Deliverable

TABLE 5.2

Page 13: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

5–13

Example: Function Point Count MethodExample: Function Point Count MethodExample: Function Point Count MethodExample: Function Point Count Method

TABLE 5.3

Page 14: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

5–14

Bottom-Up Approaches for Estimating Bottom-Up Approaches for Estimating Project Times and CostsProject Times and Costs

Bottom-Up Approaches for Estimating Bottom-Up Approaches for Estimating Project Times and CostsProject Times and Costs

• Template methods

• Parametric procedures applied to specific tasks

• Range estimates for the WBS work packages

• Phase estimating: A hybrid

Page 15: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

5–15

Support Cost Estimate WorksheetSupport Cost Estimate WorksheetSupport Cost Estimate WorksheetSupport Cost Estimate Worksheet

FIGURE 5.2

Page 16: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

5–16

Phase Estimating over Product Life CyclePhase Estimating over Product Life CyclePhase Estimating over Product Life CyclePhase Estimating over Product Life Cycle

FIGURE 5.3

Page 17: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

5–17

Top-Down and Bottom-Up EstimatesTop-Down and Bottom-Up EstimatesTop-Down and Bottom-Up EstimatesTop-Down and Bottom-Up Estimates

FIGURE 5.4

Page 18: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

5–18

Level of DetailLevel of DetailLevel of DetailLevel of Detail

• Level of detail is different for different levels of management.

• Level of detail in the WBS varies with the complexity of the project.

• Excessive detail is costly.–Fosters a focus on departmental outcomes

–Creates unproductive paperwork

• Insufficient detail is costly.–Lack of focus on goals

–Wasted effort on nonessential activities

Page 19: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

5–19

Types of CostsTypes of CostsTypes of CostsTypes of Costs

• Direct Costs–Costs that are clearly chargeable

to a specific work package.•Labor, materials, equipment, and other

• Direct (Project) Overhead Costs–Costs incurred that are directly tied to an identifiable

project deliverable or work package.•Salary, rents, supplies, specialized machinery

• General and Administrative Overhead Costs–Organization costs indirectly linked to a specific

package that are apportioned to the project

Page 20: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

5–20

Contract Bid Summary CostsContract Bid Summary CostsContract Bid Summary CostsContract Bid Summary Costs

FIGURE 5.5

Direct costs $80,000

Direct overhead $20,000

Total direct costs $100,000

G&A overhead (20%) $20,000

Total costs $120,000

Profit (20%) $24,000

Total bid $144,000

Page 21: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

5–21

Three Views of CostThree Views of CostThree Views of CostThree Views of Cost

FIGURE 5.6

Page 22: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

5–22

Refining EstimatesRefining EstimatesRefining EstimatesRefining Estimates

• Reasons for Adjusting Estimates–Interaction costs are hidden in estimates.

–Normal conditions do not apply.

–Things go wrong on projects.

–Changes in project scope and plans.

• Adjusting Estimates–Time and cost estimates of specific activities are

adjusted as the risks, resources, and situation particulars become more clearly defined.

Page 23: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

5–23

Creating a Database for EstimatingCreating a Database for EstimatingCreating a Database for EstimatingCreating a Database for Estimating

FIGURE 5.7

Page 24: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

5–24

Key TermsKey TermsKey TermsKey Terms

Apportionment methods

Bottom-up estimates

Contingency funds

Delphi method

Direct costs

Function points

Learning curves

Overhead costs

Padding estimates

Phase estimating

Range estimating

Ratio methods

Template method

Time and cost databases

Page 25: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

5–25

WBS FigureWBS FigureWBS FigureWBS Figure

TABLE 5.4

Page 26: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

5–26

Learning Curves Unit ValuesLearning Curves Unit ValuesLearning Curves Unit ValuesLearning Curves Unit Values

TABLE A5.1

Page 27: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

5–27

Learning Curves Cumulative ValuesLearning Curves Cumulative ValuesLearning Curves Cumulative ValuesLearning Curves Cumulative Values

TABLE A5.2

Page 28: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

28

Project Cash Flow Project Cash Flow AnalysisAnalysis

Project Cash Flow Project Cash Flow AnalysisAnalysis

Page 29: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

29

Elements of Investment Decision

• Identification of Investment Opportunities

• Generation of Cash Flows

• Measures of Investment Worth

• Project Selection

• Project Implementation

• Project-Control/Post-Audit

Our focus in this chapter is to develop the format of after-tax

cash flow statements.

Page 30: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

30

Types of Cash Flow Elements in Project Analysis

Differential or incremental cash flow: cash flow due asset

Page 31: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

31

Approach 1

Income Statement Approach

Approach 2

Direct Cash Flow Approach

Operating revenues

Cost of goods sold

Depreciation

Operating expenses

Interest expenses

Taxable income

Income taxes

Net income

+ Depreciation

Operating revenues

- Cost of goods sold

- Operating expenses

- Interest expenses

- Income taxes

Cash flow from operation

Cash Flows from Operating Activities

Page 32: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

32

A Typical Format used for Presenting Cash Flow Statement

Income statement Revenues Expenses Cost of goods sold Depreciation Debt interest Operating expensesTaxable incomeIncome taxesNet income

Cash flow statement

+ Net income+Depreciation

-Capital investment+ Proceeds from sales of depreciable assets- Gains tax- Investments in working capital+ Working capital recovery

+ Borrowed funds-Repayment of principal Net cash flow

Operatingactivities

Investing activities

Financingactivities

+

+

Page 33: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

33

Example 9.1 When Projects Require only Operating and Investing Activities

• Project Nature: Installation of a new computer control system • Financial Data:

– Investment: $125,000– Project life: 5 years– Working capital investment: $23,331– Salvage value: $50,000– Annual labor savings: $100,000– Annual additional expenses:

• Labor: $20,000• Material: $12,000• Overhead: $8,000

– Depreciation Method: 7-year MACRS– Income tax rate: 40%– MARR: 15%

Page 34: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

34

Questions

• (a) Develop the project’s cash flows over its project life.

• (b) Is this project justifiable at a MARR of 15%?

• (c) What is the internal rate of return of this project?

Page 35: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

35

When Projects Require Working Capital Investments Working capital means

the amount carried in cash, accounts receivable, and inventory that is available to meet day-to-day operating needs.

How to treat working capital investments: just like a capital expenditure except that no depreciation is allowed.

Page 36: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

36

• (a) Step 1: Depreciation Calculation– Cost Base = $125,000– Recovery Period = 7-year MACRS

N

MACRS Rate

Depreciation Amount

Allowed Depreciation Amount

1 14.29% $17,863 $17,863

2 24.49% $30,613 $30,613

3 17.49% $21,863 $21,863

4 12.49% $15,613 $15,613

5 8.93% $11,150 $5,575

6 8.92% $11,150 0

7 8.93% $11,150 0

8 4.46% $5,575 0

Page 37: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

37

(a) Step 2: Gains (Losses) associated with Asset Disposal

• Salvage value = $50,000• Book Value (year 5) = Cost Base – Total Depreciation

= $125,000 - $ 91,525= $ 33,475

• Taxable gains = Salvage Value – Book Value= $50,000 - $ 33,475= $16,525

• Gains taxes = (Taxable Gains)(Tax Rate)= $16,525 (0.40)= $6,610

Page 38: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

38

Income Statement

0 1 2 3 4 5

Revenues $100,000

$100,000

$100,000

$100,000

$100,000

Expenses:

Labor 20,000 20,000 20,000 20,000 20,000

Material 12,000 12,000 12,000 12,000 12,000

Overhead 8,000 8,000 8,000 8,000 8,000

Depreciation 17,863 30,613 21,863 15,613 5,581

Taxable Income $42,137 $29,387 $38,137 $44,387 $54,419

Income Taxes (40%) 16,855 11,755 15,255 17,755 21,768

Net Income $25,282 $17,632 $22,882 $26,632 $32,651

Step 3 – Create an Income StatementStep 3 – Create an Income Statement Step 3 – Create an Income StatementStep 3 – Create an Income Statement

Page 39: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

39

Step 4 – Develop a Cash Flow Statement

Cash Flow Statement 0 1 2 3 4 5

Operating Activities:

Net Income $25,282 $17,632

$22,882

$26,632

$32,651

Depreciation 17,863 30,613 21,863 15,613 5,581

Investment Activities:

Investment (125,000)

Working capital (23,331) 23,331

Salvage 50,000

Gains Tax (6,613)

Net Cash Flow ($148,331) $43,145 $48,245 $44,745 $42,245 $104,950

Page 40: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

40

An Excel WorksheetAn Excel WorksheetAn Excel WorksheetAn Excel Worksheet

Page 41: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

41

Example 9.1 - Net Cash Flow Table Generated by Traditional Method Using Approach 2

A B C D E F G H I J

Year End

Investment & Salvage Value

Revenue Labor Expenses Materials

Overhead Depreciation Taxable Income

Income Taxes

Net Cash Flow

0 -$125,000

-23,331

-$125,000

1 $100,000 20,000 12,000 8,000 $17,863 42,137 16,855 $43,145

2 100,000 20,000 12,000 8,000 30,613 29,387 11,755 $48,245

3 100,000 20,000 12,000 8,000 21,863 38,137 15,255 $44,745

4 100,000 20,000 12,000 8,000 15,613 44,387 17,755 $42,245

5 100,000 20,000 12,000 8,000 5,581 54,419 21,678 $38,232

50,000*

23,331

16,525 6,613 $43,387

23,331

Information required tocalculate the income taxes

*Salvage value Note thatH = C-D-E-F-GI = 0.4 * HJ= B+C-D-E-F-I

Page 42: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

42

Cash Flow Diagram including Working Capital

0 1 2 3 4 5

$23,331Years

$23,331

Working capital recovery cycles

01 2 3 4 5

$43,145$48,245 $44,745

$42,245$81,619

Working capitalrecovery

$23,331

$125,000 Investment in physical assets

$23,331 Investment inworking capital

$23,331

$23,331

Page 43: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

43

Question (b):• Is this investment justifiable at

a MARR of 15%?

• PW(15%) = -$148,331 + +$43,145(P/F, 15%, 1) + . . . . + $104,950 (P/F, 15%, 5)

= $31,420 > 0

–Yes, Accept the Project !

0

1 2 3 4 5

$148,331

$43,145

$48,245 $44,745 $42,245

$104,950

Years

Page 44: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

44

Question (C): IRR

A B

1 Period Cash Flow

2 0 ($148,331)

3 1 43,145

4 2 48,245

5 3 44,745

6 4 42,245

7 5 104,950

=IRR(B2:B7,0.10)

IRR = 22.55%

Page 45: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

45

Rate of Return Analysis (IRR = 22.55%)

n = 0 n =1 n = 2 n = 3 n = 4 n = 5

Beginning

Balance

-$148,331 -$138,635 -$121,652 -$104,339 -$85,622

Return on

Investment

(interest)

-$33,449 -$31,262 -$27,432 -$23,528 -$19,328

Payment -$148,331 $43,145 $48,245 $44,745 $42,245 $104,950

Project

Balance

-$148,331 -$138,635 -$121,652 -$104,339 -$85,622 0

Page 46: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

46

When Projects are Financed with When Projects are Financed with Borrowed FundsBorrowed Funds

When Projects are Financed with When Projects are Financed with Borrowed FundsBorrowed Funds

• Key issue: Interest payment is a tax-deductible expense.

• What Needs to Be Done: Once a loan repayment schedule is known, separate the interest payments from the annual installments.

• What about Principal Payments? As the amount of borrowing is NOT viewed as income to the borrower, the repayments of principal are NOT viewed as expenses either– NO tax effect.

Page 47: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

47

Loan Repayment Schedule (Example 9.2)

End of

Year

Beginning

Balance

Interest Payment

Principal Payment

Ending

Balance

1 $62,500 $6,250 $10,237 $52,263

2 52,263 5,226 11,261 41,002

3 41,002 4,100 12,387 28,615

4 28,615 2,861 13,626 14,989

5 14,989 1,499 14,988 0

Amount financed: $62,500, or 50% of total capital expenditureFinancing rate: 10% per yearAnnual installment: $16,487 or, A = $62,500(A/P, 10%, 5)

$16,487

Page 48: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

48

Additionalentries related

to debt financing

Table 9.4

Page 49: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

49

When Projects Results in Negative When Projects Results in Negative Taxable IncomeTaxable Income

When Projects Results in Negative When Projects Results in Negative Taxable IncomeTaxable Income

• Negative taxable income (project loss) means you can reduce your taxable income from regular business operation by the amount of loss, which results in a tax savings.

• Handling Project Loss

Regular Business

Project Combined Operation

Taxable income

Income taxes (35%)

$100M

$35M

(10M)

?

$90M

$31.5M

Tax Savings = $35M - $31.5M = $3.5MOr (10M)(0.35) = -$3.5M

Tax savings

Page 50: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

50

Effects of Inflation on Project Cash Effects of Inflation on Project Cash FlowsFlows

Effects of Inflation on Project Cash Effects of Inflation on Project Cash FlowsFlows

Item Effects of Inflation

Depreciation expense

Depreciation expense is charged to taxable income in dollars of declining values; taxable income is overstated, resulting in higher taxes

Note: Depreciation expenses are based on historical costs andalways expressed in actual dollars

Page 51: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

51

Item Effects of Inflation

Salvage value Inflated salvage value combined with book values based on historical costs results in higher taxable gains.

Page 52: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

52

Item Effects of Inflation

Loan repayments

Borrowers repay historical loan amounts with dollars of decreased purchasing power, reducing the debt-financing cost.

Page 53: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

53

Item Effects of Inflation

Working capital requirement

Known as working capital drain, the cost of working capital increases in an inflationary environment.

Page 54: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

54

Item Effects of Inflation

Rate of Return and NPW

Unless revenues are sufficiently increased to keep pace with inflation, tax effects and/or a working capital drain result in lower rate of return or lower NPW.

Page 55: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

55

178

91112131415161718192021222324

252627282930313233343536

A B C D E F G H

Example 9.3 Cash Flow Statement for the Automated Machining Center Project

Income StatementInflation Rate 0 1 2 3 4 5

Revenues 5% 105,000$ 110,250$ 115,763$ 121,551$ 127,628$ Expenses: Labor 5% 21,000 22,050 23,153 24,310 25,526 Material 5% 12,600 13,230 13,892 14,586 15,315 Overhead 5% 8,400 8,820 9,261 9,724 10,210 Depreciation 17,863 30,613 21,863 15,613 5,581

Taxable Income 45,137$ 35,537$ 47,595$ 57,317$ 70,996$ Income Taxes (40%) 18,055 14,215 19,038 22,927 28,398

Net Income 27,082$ 21,322$ 28,557$ 34,390$ 42,598$

Cash Flow Statement

Operating Activities: Net Income 27,082 21,322 28,557 34,390 42,598 Depreciation 17,863 30,613 21,863 15,613 5,581 Investment Activities: Investment (125,000) Salvage 5% 63,814 Gains Tax (12,139) Working Capital 5% (23,331) (1,167) (1,225) (1,287) (1,351) 28,361

Net Cash Flow (148,331)$ 43,778$ 50,710$ 49,133$ 48,652$ 128,215$ (in actual dollars)

Page 56: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

56

Example 9.4 Cash Flow Statement for AMC Project under Inflation (Multiple Price Indices)

Income StatementInflation Rate 0 1 2 3 4 5

Revenues 6% 106,000$ 112,360$ 119,102$ 126,248$ 133,823$ Expenses: Labor 5% 21,000 22,050 23,153 24,310 25,526 Material 4% 12,480 12,979 13,498 14,038 14,600 Overhead 5% 8,400 8,820 9,261 9,724 10,210 Depreciation 17,863 30,613 21,863 15,613 5,581

Taxable Income 46,257$ 37,898$ 51,327$ 62,562$ 77,906$ Income Taxes (40%) 18,503 15,159 20,531 25,025 31,162

Net Income 27,754$ 22,739$ 30,796$ 37,537$ 46,744$

Cash Flow Statement

Operating Activities: Net Income 27,754 22,739 30,796 37,537 46,744 Depreciation 17,863 30,613 21,863 15,613 5,581 Investment Activities: Investment (125,000) Salvage 3% 57,964 Gains Tax (9,799) Working Capital 5% (23,331) (1,167) (1,225) (1,287) (1,351) 28,361

Net Cash Flow (148,331)$ 44,450$ 52,127$ 51,372$ 51,799$ 128,851$ (in actual dollars)

Example 9.4 Applying Specific Inflation Rates

Page 57: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

57

Rate of Return Analysis under InflationRate of Return Analysis under InflationRate of Return Analysis under InflationRate of Return Analysis under Inflation

• Principle:True (real) rate of return should be based on constant dollars.

• If the rate of return is computed based on actual dollars, the real rate of return can be calculated as:

n

Net cash flows in actual dollars

Net cash flows in constant dollars

0

1

2

3

4

-$30,000

13,570

15,860

13,358

13,626

-$30,000

12,336

13,108

10,036

9,307

IRR 31.34% 19.40%

ii

f'

.

..40%

_

1

11

1 0 3134

1 0 101

19

f_

10%

Page 58: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

58

Decision CriterionDecision CriterionDecision CriterionDecision Criterion

• If you use 31.34% as your IRR, you should use a market interest rate (or inflation-adjusted MARR) to make an accept and reject decision.

• If you use 19.40% as your IRR, you should use an inflation-free interest rate (inflation-free MARR) to make an accept and reject decision.

Page 59: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

59

Input OutputTax Rate(%) = 40 PW(i) = $37,761

MARR(%) = 15 IRR(%) = 33.74%

0 1 2 3 4 5 6Income Statement

Revenues (savings) $38,780 $38,780 $38,780 $38,780 $38,780 $38,780Expenses: Depreciation 9,817 16,825 12,016 8,581 6,135 3,064

Taxable Income $28,963 $21,955 $26,764 $30,199 $32,645 $35,716Income Taxes (40%) 11,585 8,782 10,706 12,080 13,058 14,286

Net Income $17,378 $13,173 $16,059 $18,120 $19,587 $21,430

Cash Flow StatementOperating Activities: Net Income 17,378$ 13,173$ 16,059$ 18,120$ 19,587$ 21,430$ Depreciation 9,817$ 16,825$ 12,016$ 8,581$ 6,135$ 3,064$ Investment Activities: Investment (68,701)$ Salvage 3,500$ Gains Tax 3,505$

Net Cash Flow ($68,701) $27,195 $29,998 $28,074 $26,700 $25,722 $31,499

Page 60: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

Surety Surety

BondsBonds

Surety Surety

BondsBondsThe Sensible Choice For Managing Risk

60

Page 61: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

Can Surety Bonds Can Surety Bonds Help You?Help You?

Can Surety Bonds Can Surety Bonds Help You?Help You?

• How do you evaluate & manage risk?

• How do you ensure projects are completed on time, on budget, and to contract specifications?

• How do you ensure contractors successfully meet obligations?

5–61

Page 62: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

Can Surety Bonds Can Surety Bonds Help You?Help You?

Can Surety Bonds Can Surety Bonds Help You?Help You?

• Bid Bond• Performance Bond• Payment Bond

5–62

Page 63: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

Surety Bonds vs. Traditional InsuranceSurety Bonds vs. Traditional InsuranceSurety Bonds vs. Traditional InsuranceSurety Bonds vs. Traditional Insurance

Surety Bonds Insurance3-party 2-party

Risk transfer Risk transfer

Duty to obligee Duty to insured

Regulated by State Insurance Departments

Regulated by State Insurance Departments

Premium fee for prequalification services

Premium actuarially determined

Project specific Usually term specific

Penal sum Policy limits5–63

Page 64: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

Contract Surety BondsContract Surety BondsContract Surety BondsContract Surety Bonds

• Bid Bond• Performance Bond• Payment Bond

5–64

Page 65: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

Contract Surety BondsContract Surety BondsContract Surety BondsContract Surety Bonds

• Bid Bond• Performance Bond• Payment Bond

5–65

Page 66: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

Contract Surety BondsContract Surety BondsContract Surety BondsContract Surety Bonds

• Bid Bond• Performance Bond• Payment Bond

5–66

Page 67: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

Fundamentals of SuretyFundamentals of SuretyFundamentals of SuretyFundamentals of Surety

Contractor default is preventable

Surety companies & producers prequalify contractors

Surety companies back the bond with their own assets

5–67

Page 68: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

The 3 Cs The 3 Cs Of PrequalificationOf Prequalification

The 3 Cs The 3 Cs Of PrequalificationOf Prequalification

Capital

Capacity

Character

Capital

Capacity

Character5–68

Page 69: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

Analyzing Financial StrengthAnalyzing Financial StrengthAnalyzing Financial StrengthAnalyzing Financial Strength

CapitalFinancial

statements

Working capital

Work-in-progress

Indemnity

5–69

Page 70: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

Evaluating Ability Evaluating Ability To PerformTo Perform

Evaluating Ability Evaluating Ability To PerformTo Perform

CapitalFinancial

statements

Working capital

Work-in-progress

Indemnity

CapacityResumes

Contingency plan

Business plan

Equipment

5–70

Page 71: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

Assessing Assessing ReputationReputationAssessing Assessing ReputationReputation

CapitalFinancial

statements

Working capital

Work-in-progress

Indemnity

CapacityResumes

Contingency plan

Business plan – short & long term

Equipment

CharacterReputation

Relationships

References

5–71

Page 72: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

Reviewing Business VenturesReviewing Business VenturesReviewing Business VenturesReviewing Business Ventures

Document business commitments that can affect the contractor’s business

– Owning property

– Side ventures

Surety

5–72

Page 73: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

Contractor FailureContractor FailureContractor FailureContractor Failure

Number of Years Failed Contractors Were in Business

6-10 Years29%

0-5 Years32%

10+ Years39%

Source: Dun & Bradstreet

5–73

Page 74: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

Why Do Contractors Fail?Why Do Contractors Fail?Why Do Contractors Fail?Why Do Contractors Fail?

Failure

MaterialsShortages

OverExpansion

NewOwner

Cost Escalations

SubFailure

Change inScope

Inadequate Management

Failure

5–74

Page 75: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

Why Do Contractors Fail?Why Do Contractors Fail?Why Do Contractors Fail?Why Do Contractors Fail?

Work Environment

EconomicDownturn

Death or Illness of Key Employee

OnerousTerms

Inclement Weather

FailureFailure

5–75

Page 76: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

ClaimsClaimsClaimsClaims

Surety

ObligeePrincipal

5–76

Page 77: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

Expediting Expediting The Claims ProcessThe Claims Process

Expediting Expediting The Claims ProcessThe Claims Process

• Clearly define default in contract

• Submit status reports to surety

• Promptly notify surety of performance or payment problems

• Owner must file formal declaration of default

5–77

Page 78: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

Responsibility Responsibility Of The SuretyOf The Surety

Responsibility Responsibility Of The SuretyOf The Surety

• Acknowledge claim

• Investigate claim

• Determine & fulfill obligations

Surety

5–78

Page 79: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

Performance Bond ProtectionPerformance Bond ProtectionPerformance Bond ProtectionPerformance Bond Protection

• Re-let the job

• Provide replacement contractor

• Retain original contractor

• Reimburse owner penal sum

Surety

5–79

Page 80: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

Payment Bond Payment Bond ProtectionProtection

Payment Bond Payment Bond ProtectionProtection

• Assures payment

• No mechanics’ liens

• Keeps subcontractors on the job

Surety

5–80

Page 81: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

Surety Bonds vs. Surety Bonds vs. Letters of CreditLetters of Credit

Surety Bonds vs. Surety Bonds vs. Letters of CreditLetters of Credit

Surety Credit Bank CreditPremium Interest

Expect reimbursement if loss

Repay loan

Principal benefit of surety credit

Borrower has benefit of bank $

5–81

Page 82: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

The Value The Value Of Surety BondsOf Surety Bonds

The Value The Value Of Surety BondsOf Surety Bonds

• Bid Bonds• Performance Bonds• Payment Bonds

5–82

Page 83: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

The Value The Value Of Surety BondsOf Surety Bonds

The Value The Value Of Surety BondsOf Surety Bonds

• Bid Bonds• Performance Bonds• Payment Bonds

5–83

Page 84: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

• Bid Bonds• Performance Bonds• Payment Bonds

The Value The Value Of Surety BondsOf Surety Bonds

The Value The Value Of Surety BondsOf Surety Bonds

5–84

Page 85: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

Cost of Surety BondsCost of Surety BondsCost of Surety BondsCost of Surety Bonds

Project Amount

Approx. Bond Premium

$1 Million $7,700 – $13,500

$5 Million $33,200 – $47,250

$10 Million $56,950 – $81,000

$20 Million $101,950 – $146,000

* Premiums may vary depending on size, type & contractors bonding capacity.

*For a small and emerging contractor, premiums can start around 2.5-3%.

5–85

Page 86: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

Premium Calculation ExamplesPremium Calculation ExamplesPremium Calculation ExamplesPremium Calculation Examples

• Established Contractor–$500,000 Contract–Reviewed/Audited Financial Statements–Frequent Bond User–<1.0-1.5% Bond Rate (average – 1.35%)

•<$5,000-7,500

–Likely no other costs involved (collateral, escrow, SBA)

5–86

Page 87: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

Premium Calculation ExamplesPremium Calculation ExamplesPremium Calculation ExamplesPremium Calculation Examples

• Emerging Contractor–$500,000 Contract–Limited Financial Info. (Tax Returns/Quickbooks)–Limited Bonding History–1.8-3.0% Flat Rate (average – 2.5%)

•$9,000-12,500

–May not include cost of getting bond (i.e., funds control, collateral, SBA fees)

5–87

Page 88: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

How Is Premium Paid?How Is Premium Paid?How Is Premium Paid?How Is Premium Paid?

• Premium is billed BY the contractor TO the owner• Usually paid on first billing, along with:

–Mobilization–General Conditions–Bond

• Cost of bond is included in final contract price• Contractor pays the bond premium to the surety

– Prompt Pay Is Key To A Contractor’s Success!

5–88

Page 89: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

The Underlying AgreementThe Underlying AgreementThe Underlying AgreementThe Underlying Agreement

• Look at obligations• Determine risks• Match capable principal to fulfill

agreement

Surety

5–89

Page 90: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

1. Owner specifies surety bonds in contract documents

2. Contractor contacts surety bond producer

3. Producer guides contractor through prequalification

4. Contractor obtains bonds & delivers to owner

Bond SpecificationsBond SpecificationsBond SpecificationsBond Specifications

5–90

Page 91: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

COST MANAGEMENT

5–91

Page 92: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

COST MANAGEMENTCOST MANAGEMENTCOST MANAGEMENTCOST MANAGEMENT

• Includes processes required to ensure that the project is completed within the approved budget.

• Processes involved are:

1- Resource Planning

2- Cost Estimating

3- Cost Budgeting

4- Cost Control5–92

Page 93: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

1- Resource Planning1- Resource Planning1- Resource Planning1- Resource Planning

Involves determining what physical resources (people, equipment, materials etc) and what quantities of each should be used to perform project activities.

5–93

Page 94: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

Inputs to Resource PlanningInputs to Resource PlanningInputs to Resource PlanningInputs to Resource Planning

1. Work Breakdown Structure:

A deliverable-oriented grouping of project elements that organizes and defines the total scope of the project. It Identifies the project elements that will need resources.

2. Historical Information

3. Scope Statement:

Contains the project justification and the project objectives.

5–94

Page 95: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

Inputs to Resource PlanningInputs to Resource PlanningInputs to Resource PlanningInputs to Resource Planning

4. Resource Pool Description:

Knowledge of what resources are potentially available.

5. Organizational Policies:

The policies of the performing organization regarding staffing and the rental or purchase of supplies and equipment.

5–95

Page 96: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

Tools and Techniques to Resource PlanningTools and Techniques to Resource PlanningTools and Techniques to Resource PlanningTools and Techniques to Resource Planning

1. Expert Judgment

2. Alternative identifications:

To adopt different approaches for the same problem.

5–96

Page 97: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

Outputs from Resource PlanningOutputs from Resource PlanningOutputs from Resource PlanningOutputs from Resource Planning

1. Resource Requirements:

Description of what types of resources are required and in what quantities for each element of the work break down structure.

5–97

Page 98: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

Cost EstimatingCost EstimatingCost EstimatingCost Estimating

• Developing an approximation (estimates) of the costs of the resources needed to complete project activities.

• Includes identifying and considering various costing alternatives.

5–98

Page 99: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

Cost Estimating and PricingCost Estimating and PricingCost Estimating and PricingCost Estimating and Pricing

• Cost Estimating involves developing an assessment of the likely quantitative result-how much will it cost the performing organization to provide the product or service involved.

• Pricing is a business decision-how much will the performing organization charge for the product or service

5–99

Page 100: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

Inputs to Cost EstimatingInputs to Cost EstimatingInputs to Cost EstimatingInputs to Cost Estimating

• Work Breakdown Structure• Resource Requirement• Resource Rates:

scheduled or non-scheduled• Activity Duration Estimates• Historical Information• Chart of Accounts:

Describes the coding structure used by the performing organization to report financial information in its general ledger

5–100

Page 101: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

Tools and Techniques for Cost EstimatingTools and Techniques for Cost EstimatingTools and Techniques for Cost EstimatingTools and Techniques for Cost Estimating

Analogous Estimating / Top-down Estimating:

Using the actual cost of a previous, similar project as the basis for estimating the cost

of the current project. It is less costly but less accurate. (Rough-cost Estimate)

Parametric Modeling:

Using project characteristics (parameters) in a mathematical model to predict project

costs.5–101

Page 102: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

Tools and Techniques for Cost EstimatingTools and Techniques for Cost EstimatingTools and Techniques for Cost EstimatingTools and Techniques for Cost Estimating

• Bottom-up Estimating:Estimating the cost of individual work items, then summarizing or rolling up

the individual estimates to get a project title. (Detailed Estimate)

• Computerized Tools:Use of computerized tools such as project management software and

spreadsheets to assist with cost estimating.

5–102

Page 103: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

Outputs from Cost EstimatingOutputs from Cost EstimatingOutputs from Cost EstimatingOutputs from Cost Estimating

• Cost Estimates• Supporting Details like Scope of work,

Calculation sheet, Assumptions made, Possible range of results, etc.

• Cost Management Plan describing how cost variances will be managed.

5–103

Page 104: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

Cost BudgetingCost BudgetingCost BudgetingCost Budgeting

Allocation of overall cost estimates to individual work items in order to establish a cost baseline for measuring project performances.

5–104

Page 105: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

Inputs to Cost BudgetingInputs to Cost BudgetingInputs to Cost BudgetingInputs to Cost Budgeting

• Cost Estimates• Work Breakdown Structure• Project Schedule

5–105

Page 106: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

Tools and Techniques for Cost BudgetingTools and Techniques for Cost BudgetingTools and Techniques for Cost BudgetingTools and Techniques for Cost Budgeting

Tools and Techniques for developing project Cost Estimates are used to develop budgets for work items as well

5–106

Page 107: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

Outputs from Cost BudgetingOutputs from Cost BudgetingOutputs from Cost BudgetingOutputs from Cost Budgeting

• Cost Baseline

A time-phased budget that will be used to measure and monitor cost performance

on the project. It is developed by summing estimated costs by period and is usually displayed in the form of an S-curve.

5–107

Page 108: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

5–108

Page 109: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

Cost ControlCost ControlCost ControlCost Control

Cost Control is concerned with(a) Influencing the factors which create changes to the cost baseline to ensure that changes are beneficial.(b) Determining that the cost baseline has changed(c) Managing the actual changes when and as they occur

5–109

Page 110: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

Cost ControlCost ControlCost ControlCost Control

Cost Control includes: Monitoring cost performances to detect variances

from plan. Ensuring that all appropriate changes are

recorded accurately in the cost baseline Preventing incorrect, inappropriate, or

unauthorized changes from being included in the cost baseline.

Informing appropriate stakeholders of authorized changes.

5–110

Page 111: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

Inputs to Cost ControlInputs to Cost ControlInputs to Cost ControlInputs to Cost Control

• Cost Baseline• Performance Reports

Provide information about cost performance such as which budgets have been met and which have not. It also alerts the project

team to issues which may cause problems in the future.

5–111

Page 112: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

Inputs to Cost ControlInputs to Cost ControlInputs to Cost ControlInputs to Cost Control

• Change Requests

These may occur in many forms-oral or written, direct or indirect, externally or internally initiated, and legally mandated or optional. These may require

increasing the budget or may allow decreasing it.

5–112

Page 113: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

Tools and Techniques for Cost ControlTools and Techniques for Cost ControlTools and Techniques for Cost ControlTools and Techniques for Cost Control

• Cost Change Control System

It defines the procedures by which the cost baseline may be changed. It includes the paperwork, tracking systems, and approval levels necessary for authorizing changes.

• Performance Measurement

It helps to assess the magnitude of any variations which do occur.

5–113

Page 114: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

Tools and Techniques for Cost ControlTools and Techniques for Cost ControlTools and Techniques for Cost ControlTools and Techniques for Cost Control

• Additional Planning

Perspective changes may require new or revised cost estimates or analysis of

alternate approaches.

• Computerized Tools

5–114

Page 115: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

Outputs from Cost ControlOutputs from Cost ControlOutputs from Cost ControlOutputs from Cost Control

• Revised Cost Estimates• Budget Updates• Corrective Action• Estimate at Completion

It is a forecast of total project costs based on project performance.

• Lessons Learned

5–115

Page 116: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

OBJECTS OF COST CONTROLOBJECTS OF COST CONTROL OBJECTS OF COST CONTROLOBJECTS OF COST CONTROL

1 – To have a knowledge of the profit and loss of the project throughout the duration of the project.

PROJECT PROFITS1) Client payments.2) Sale of surplus or scrap material and plant3) Payments for plants or labor by others, where, this plant or labor is , from time to time not required for the project.PROJECT LOSSES1) Labor and site office costs2) Plant costs3) Site overheads i.e. site facilities, access roads and office etc4) Cost of tendering including bonds, insurance, etc.5) Material costs.6) Head office overheads proportioned over all current projects.

5–116

Page 117: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

OBJECTS OF COST CONTROLOBJECTS OF COST CONTROLOBJECTS OF COST CONTROLOBJECTS OF COST CONTROL

2 – To have a comparison between the actual project performance and that conceived in the original project plan.

Comparison is basically done according to the following bases:

1) According to units of production2) According to line items; e.g., labour, material,

equipment, overheads, ---

3 – Provides feedback data on actual project performance to future project planning

5–117

Page 118: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

THANK YOUTHANK YOUTHANK YOUTHANK YOU

5–118

Page 119: 1 1 CHAPTER FOUR 4-MANAGERIAL PROCESS 4.1 Estimating project time and costs 4-2 Project cash flows 4.3 Performance and payment bonds 4-5 Cost Control

The Owner’s ResponsibilitiesThe Owner’s ResponsibilitiesThe Owner’s ResponsibilitiesThe Owner’s Responsibilities

• Provide working set of plans and specifications

• Establish terms of the agreement

• Ensure full & timely payment

• Maintain adequate insurance

• Pay property taxes

• Communicate

Owner

5–119