1-5 thursday_extreme weather pumping dewatering project-iai.pptx

19
Extreme Weather Pumping & Dewatering WEDA Midwest Chapter Spring 2012 Meeting April 26, 2012 Presented by Scott Ponstein

Upload: doanduong

Post on 05-Jan-2017

214 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 1-5 Thursday_Extreme Weather Pumping Dewatering Project-IAI.pptx

Extreme Weather Pumping & Dewatering

WEDA Midwest Chapter Spring 2012 MeetingApril 26, 2012Presented by Scott Ponstein

Page 2: 1-5 Thursday_Extreme Weather Pumping Dewatering Project-IAI.pptx

2

Project Overview Preferred Sands silica sand mine Woodbury, MN January 2012 Sand silica waste, by-product of silica sand

washing process Pump sand waste from frozen settling pond Dewater in geotextile tubes

WEDA Midwest Chapter Spring 2012Extreme Weather Pumping & Dewatering

Page 3: 1-5 Thursday_Extreme Weather Pumping Dewatering Project-IAI.pptx

3

Preferred Sands

WEDA Midwest Chapter Spring 2012Extreme Weather Pumping & Dewatering

Page 4: 1-5 Thursday_Extreme Weather Pumping Dewatering Project-IAI.pptx

4

Scope of Work Very short time frame (3 days from

approval to mobilization) Remove 2 million gallons of material from

frozen settling pond Utilize Pit Hog pumps to move material Geotextile tubes to dewater

WEDA Midwest Chapter Spring 2012Extreme Weather Pumping & Dewatering

Page 5: 1-5 Thursday_Extreme Weather Pumping Dewatering Project-IAI.pptx

5

Equipment Chain saw Gantry crane & truck-mounted boom crane (2) Pit Hog pumps with hydraulic power packs (2) 6” diameter HDPE pipelines 22 gph polymer makedown & injection system (2) Geotextile tubes, 75’ by 200’ 10,000 lb off road forklift Miscellaneous torches and heaters.

WEDA Midwest Chapter Spring 2012Extreme Weather Pumping & Dewatering

Page 6: 1-5 Thursday_Extreme Weather Pumping Dewatering Project-IAI.pptx

6

MethodHoles cut in ice using chain saw

Pumps, suspended by cranes, lowered down into pond

Pumped sand slurry injected with polymer

Sand slurry-polymer mixture pumped into geotextile tube for dewatering

Geotextile tube weep water pumped back to pond

WEDA Midwest Chapter Spring 2012Extreme Weather Pumping & Dewatering

Page 7: 1-5 Thursday_Extreme Weather Pumping Dewatering Project-IAI.pptx

7

Site Photos

WEDA Midwest Chapter Spring 2012Extreme Weather Pumping & Dewatering

Hole cut in ice

Page 8: 1-5 Thursday_Extreme Weather Pumping Dewatering Project-IAI.pptx

8

Site Photos

WEDA Midwest Chapter Spring 2012Extreme Weather Pumping & Dewatering

Pump suspended with crane truck

Page 9: 1-5 Thursday_Extreme Weather Pumping Dewatering Project-IAI.pptx

9

Site Photos

WEDA Midwest Chapter Spring 2012Extreme Weather Pumping & Dewatering

Pumping operation

Page 10: 1-5 Thursday_Extreme Weather Pumping Dewatering Project-IAI.pptx

10

Site Photos

WEDA Midwest Chapter Spring 2012Extreme Weather Pumping & Dewatering

Polymer system hut with crane truck & pond in background

Page 11: 1-5 Thursday_Extreme Weather Pumping Dewatering Project-IAI.pptx

11

Site Photos

WEDA Midwest Chapter Spring 2012Extreme Weather Pumping & Dewatering

Geotextile tube prior to filling

Page 12: 1-5 Thursday_Extreme Weather Pumping Dewatering Project-IAI.pptx

12

Site Photos

WEDA Midwest Chapter Spring 2012Extreme Weather Pumping & Dewatering

Geotextile tube during pumping

Page 13: 1-5 Thursday_Extreme Weather Pumping Dewatering Project-IAI.pptx

13

Site Photos

WEDA Midwest Chapter Spring 2012Extreme Weather Pumping & Dewatering

Weep water drainage

Page 14: 1-5 Thursday_Extreme Weather Pumping Dewatering Project-IAI.pptx

14

Site Photos

WEDA Midwest Chapter Spring 2012Extreme Weather Pumping & Dewatering

Weep water return pipeline

Page 15: 1-5 Thursday_Extreme Weather Pumping Dewatering Project-IAI.pptx

15

Challenges

WEDA Midwest Chapter Spring 2012Extreme Weather Pumping & Dewatering

Below zero temps nearly every day Working on ice (slips/falls, breaking

through) Keeping ice from forming around the

pumps Polymer system freezing up Pipelines freezing during shutdowns Geotextile tube freezing overnight

Page 16: 1-5 Thursday_Extreme Weather Pumping Dewatering Project-IAI.pptx

16

Complications of the Cold Actual polymer dose was up to 4 times

what was expected Had to disassemble pipelines and

completely drain them every night to prevent freezing

Stress on mechanical equipment (pumps) Geotextile tubes performed differently 3-4” ice formed on geotextile tubes

overnight; hard to dewater in the morningWEDA Midwest Chapter Spring

2012Extreme Weather Pumping & Dewatering

Page 17: 1-5 Thursday_Extreme Weather Pumping Dewatering Project-IAI.pptx

17

Summary

Level of the pond lowered 3 ft Depth of sand waste lowered 5 ft Project completed in 14 days (including

mobilization & demobilization) Satisfied client

WEDA Midwest Chapter Spring 2012Extreme Weather Pumping & Dewatering

Page 18: 1-5 Thursday_Extreme Weather Pumping Dewatering Project-IAI.pptx

18

Questions about the project?

WEDA Midwest Chapter Spring 2012Extreme Weather Pumping & Dewatering

Page 19: 1-5 Thursday_Extreme Weather Pumping Dewatering Project-IAI.pptx

19

Contact Information Scott Ponstein, Field Engineer

[email protected] Infrastructure Alternatives

7888 Childsdale Ave NERockford, MI 49341616-866-1600

www.InfrastructureAlternatives.comWEDA Midwest Chapter Spring

2012Extreme Weather Pumping & Dewatering