BUS 4017 Project Management Wk. 5Agenda:
. Scheduling lecture, Network Diagrams, Critical paths, FloatGANTT charts -methodsResponsibility Matrix
MS Project. Create GANTT and Network diagram as per text Ch. 5, 6
Groups work for Final ProjectReview forms submitted by Group Members. Sign Preliminary Charter for Group
Supplementary handouts- H.R. career Ad. For Decision Matrix
WBS, Schedule and Estimate Quiz – take home
Salt Lake City, Mormon Convention Centre. No upper balcony supports. Holds 21,000 people!
![Page 2: 1 BUS 4017 Project Management Wk. 5 Agenda:. Scheduling lecture, Network Diagrams, Critical paths, Float GANTT charts -methods Responsibility Matrix MS](https://reader035.vdocuments.net/reader035/viewer/2022072014/56649e845503460f94b86079/html5/thumbnails/2.jpg)
2
Today’s class as a WBS
F in an c ia l m od e l revis it A n sw ers to L earn R eview
R eview
S am e g rou p sfin ish th e
exerc ise from las t w eek .
S ch ed u le
R eview fo rm s
F orm F in a l G rou p s
G rou p w ork
N etw orks d iag .C rit ica l P a th
F loa t
S ch ed u lin g
N ew lea rn in g.
B rie f - ve ry b rie f
H ou sekeep in g
W eek 5 C lass
![Page 3: 1 BUS 4017 Project Management Wk. 5 Agenda:. Scheduling lecture, Network Diagrams, Critical paths, Float GANTT charts -methods Responsibility Matrix MS](https://reader035.vdocuments.net/reader035/viewer/2022072014/56649e845503460f94b86079/html5/thumbnails/3.jpg)
3
Responsibility Matrix after WBS
Who Fred Students
Groups Class
What
Lecture R
MS Project
I R
Charter RHouse
KeepingF
Home assign
R
Legend: R=Responsible. I = Inform etc. F=Feedback
![Page 4: 1 BUS 4017 Project Management Wk. 5 Agenda:. Scheduling lecture, Network Diagrams, Critical paths, Float GANTT charts -methods Responsibility Matrix MS](https://reader035.vdocuments.net/reader035/viewer/2022072014/56649e845503460f94b86079/html5/thumbnails/4.jpg)
4
Scheduling detail-continued. Ch. 6 & 7Note we will cover controls after Mid Term.• Discuss Donnelly case. P. 143• See P. 162 – Info. Systems scheduling challenges • What scheduling challenges do you experience in
your life? • How can P.M. method help?• Would P.E.R.T. calculation help?• R=O+P+4M/6• Start with data and requirements
![Page 5: 1 BUS 4017 Project Management Wk. 5 Agenda:. Scheduling lecture, Network Diagrams, Critical paths, Float GANTT charts -methods Responsibility Matrix MS](https://reader035.vdocuments.net/reader035/viewer/2022072014/56649e845503460f94b86079/html5/thumbnails/5.jpg)
5
Donnelly Case – Gido and ClementsP. 143
RR Donnelley P. 143 – scheduling success Knowing the skills needed and recruiting to meet the
needs was key for this international printing company. (HR !)
Facilities were in 200 locations/18,00 users. They were in the process of a major IT changeover-hardware, network architecture and standardizing an Email system. (IT Mgr.)
Creating task lists and using the WBS to identify (PM) relationships. Scheduling in identifiable sections.
Creating good team environments and an open systems approach to giving and getting feedback. (PM)e.g. Admit mistakes, take responsibility, allocate resources, fix problems. (Teams)
![Page 6: 1 BUS 4017 Project Management Wk. 5 Agenda:. Scheduling lecture, Network Diagrams, Critical paths, Float GANTT charts -methods Responsibility Matrix MS](https://reader035.vdocuments.net/reader035/viewer/2022072014/56649e845503460f94b86079/html5/thumbnails/6.jpg)
6
WBS into a Schedule
• Review Market Study WBS diagram. Remove the Summary tasks
• Arrange the tasks into a Network diagram use the previous slide as a guide
or using Predecessors given • Complete the PERT boxes with all information
available ( see example next slide)• Calculate the critical path.
![Page 7: 1 BUS 4017 Project Management Wk. 5 Agenda:. Scheduling lecture, Network Diagrams, Critical paths, Float GANTT charts -methods Responsibility Matrix MS](https://reader035.vdocuments.net/reader035/viewer/2022072014/56649e845503460f94b86079/html5/thumbnails/7.jpg)
7
Scheduling and predecessors
• What now?• What comes before?• What comes after?• What can be done at the same time?
• Practice first. With partner draw network diagramP 130 Gido and Clements Question 11
![Page 8: 1 BUS 4017 Project Management Wk. 5 Agenda:. Scheduling lecture, Network Diagrams, Critical paths, Float GANTT charts -methods Responsibility Matrix MS](https://reader035.vdocuments.net/reader035/viewer/2022072014/56649e845503460f94b86079/html5/thumbnails/8.jpg)
8
Try this Scheduling warm upTask Predecessor Time
A None 5
A A 4
B B, D 6
D A 2
E D 5
F C, E 8
ED FCBA
![Page 9: 1 BUS 4017 Project Management Wk. 5 Agenda:. Scheduling lecture, Network Diagrams, Critical paths, Float GANTT charts -methods Responsibility Matrix MS](https://reader035.vdocuments.net/reader035/viewer/2022072014/56649e845503460f94b86079/html5/thumbnails/9.jpg)
9
This is Activity on Arrow diagram AOA – we use the
Activity on Node (box) method AON
![Page 10: 1 BUS 4017 Project Management Wk. 5 Agenda:. Scheduling lecture, Network Diagrams, Critical paths, Float GANTT charts -methods Responsibility Matrix MS](https://reader035.vdocuments.net/reader035/viewer/2022072014/56649e845503460f94b86079/html5/thumbnails/10.jpg)
10
Add the P.E.R.T. elements onto the network diagram – place in the boxes.
Be able to draw a box as per book showing above.
Float/slack: Look at the PERT box and note difference between the ES and the LS times.
Critical path is defined by the overall times of PERT boxes in which there is no float.
Where do we get this info. from?
ES = Earliest Start. EF Earliest Finish. LS = Latest Start LF= Finish
Task ID #
Time
(duration)
ES LS
EF LF
Float
![Page 11: 1 BUS 4017 Project Management Wk. 5 Agenda:. Scheduling lecture, Network Diagrams, Critical paths, Float GANTT charts -methods Responsibility Matrix MS](https://reader035.vdocuments.net/reader035/viewer/2022072014/56649e845503460f94b86079/html5/thumbnails/11.jpg)
11
Critical Path
• Add the Duration times in all the boxes on each path. Calculate the length of paths
• The longest path is the critical path
• The shorter paths have some items that do not have to be done on a strict schedule – they have float or slack.
• Calculate the slack for one item
![Page 12: 1 BUS 4017 Project Management Wk. 5 Agenda:. Scheduling lecture, Network Diagrams, Critical paths, Float GANTT charts -methods Responsibility Matrix MS](https://reader035.vdocuments.net/reader035/viewer/2022072014/56649e845503460f94b86079/html5/thumbnails/12.jpg)
12
Critical path – apply learning• P. 158 and P.159
• Calculate the length of all 4 paths
• Answers-discuss
• Which is the critical path and why?
• What makes scheduling difficult?
![Page 13: 1 BUS 4017 Project Management Wk. 5 Agenda:. Scheduling lecture, Network Diagrams, Critical paths, Float GANTT charts -methods Responsibility Matrix MS](https://reader035.vdocuments.net/reader035/viewer/2022072014/56649e845503460f94b86079/html5/thumbnails/13.jpg)
13
Slack or float-another look, also p. 155–Gido and Clements.
The Graph example I have provided below shows both the ES minus LS = Float and the EF minus LF = Float.
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
B B B B E E E E E
E E E E E
Task. E Time. 5 days
Earliest start. 5 Latest start
15
EF 9 LF 19
Float 10 days
E FLOAT TIME 10 DAYS
P.E.R.T. Box.
LF
ES EF
LS
![Page 14: 1 BUS 4017 Project Management Wk. 5 Agenda:. Scheduling lecture, Network Diagrams, Critical paths, Float GANTT charts -methods Responsibility Matrix MS](https://reader035.vdocuments.net/reader035/viewer/2022072014/56649e845503460f94b86079/html5/thumbnails/14.jpg)
14
Review scheduling• What is a formula for Float?
• What s the formula for P.E.R.T.?
• Define critical path
• Which comes first – WBS or Schedule?
• Visit www.spmn.com/lessons learned
• Why do we teams use the GANTT rather than Network diagrams?
• Given a list with predecessors could you draw a net work?
• diagram. Go to class web site for link and try the example?
• Are you ready to take a list, estimate it, create a WBS from it, draw a Network diagram and convert it into A GANTT chart?
![Page 15: 1 BUS 4017 Project Management Wk. 5 Agenda:. Scheduling lecture, Network Diagrams, Critical paths, Float GANTT charts -methods Responsibility Matrix MS](https://reader035.vdocuments.net/reader035/viewer/2022072014/56649e845503460f94b86079/html5/thumbnails/15.jpg)
15
Work in Groups for Final Group Project
• Choose a Project Manager in for each group• Discuss potential projects• Sign a Charter and hand in to Instructor
committing to work together – name project if decided – get approval so there is no duplication.
• See detailed handout for marking scheme, timelines
![Page 16: 1 BUS 4017 Project Management Wk. 5 Agenda:. Scheduling lecture, Network Diagrams, Critical paths, Float GANTT charts -methods Responsibility Matrix MS](https://reader035.vdocuments.net/reader035/viewer/2022072014/56649e845503460f94b86079/html5/thumbnails/16.jpg)
16
P.M. forms you have collected from Web etc.
What do you do with them?
Share them with your group and discuss.
Decide which sample of form you wan to include in your Final Group Project.
Modify the Charter or start completing it to start your project.
Assign one person the Responsibility of keeping a form inventory as more forms are located.
![Page 17: 1 BUS 4017 Project Management Wk. 5 Agenda:. Scheduling lecture, Network Diagrams, Critical paths, Float GANTT charts -methods Responsibility Matrix MS](https://reader035.vdocuments.net/reader035/viewer/2022072014/56649e845503460f94b86079/html5/thumbnails/17.jpg)
17
![Page 18: 1 BUS 4017 Project Management Wk. 5 Agenda:. Scheduling lecture, Network Diagrams, Critical paths, Float GANTT charts -methods Responsibility Matrix MS](https://reader035.vdocuments.net/reader035/viewer/2022072014/56649e845503460f94b86079/html5/thumbnails/18.jpg)
18
Home Assignments
• Finalize your project choice. Work with your Group to move your Project ahead during Week.
• Each Team Member creates a WBS and Network diagram for their part of the project. If you have not finalized your part of the project create and submit documents that indicate your ability to create these forms. Must use PowerPoint or equivalent software for the WBS and MS Project software for the Network Diagram.
• PM submits above forms for the Hi level overview (Definition) of the project.
• Complete the WBS Self Quiz - not on line, during the week. Review
in class next week.