1 general issues in international construction. summary: 1 international performance characteristics...
TRANSCRIPT
![Page 1: 1 General Issues in International Construction. Summary: 1 International Performance Characteristics (lecture 19 and Appendix 7). 2 International Contracts](https://reader036.vdocuments.net/reader036/viewer/2022072017/56649f095503460f94c1df00/html5/thumbnails/1.jpg)
1
General Issues in International Construction.
Summary:1 International Performance Characteristics (lecture 19 and Appendix 7).
2 International Contracts and Payments (lecture 20).
3 International Disputes and Arbitration (lectures 21 & 22).
4 Boycotts and Bribes (lecture 24).
5 Selecting Consultants, Engineers and CMs (lecture 25).
6 Examples from the Near East, N Africa, and Developing Nations (lectures 26, 27, & 28).
7 FIDIC (lectures 29 & 30).
![Page 2: 1 General Issues in International Construction. Summary: 1 International Performance Characteristics (lecture 19 and Appendix 7). 2 International Contracts](https://reader036.vdocuments.net/reader036/viewer/2022072017/56649f095503460f94c1df00/html5/thumbnails/2.jpg)
2
1 International Performance Characteristics.
• Performance standards in international construction can vary significantly from the domestic scene:– timely completion of work (quite similar to domestic):
• contractor can be excused in certain circumstances:– force majeure - particularly relevant to the international international scene, and includes factors beyond control such as:
• war and new import/export restrictions;• but also earthquakes, floods, riots, etc..;
• foreign governments and employers often require greater assurance that the international contractor has the necessary expertise and financial support:
– due to less knowledge of the contractor;– reduced ability to sue the contractor in the event of total default;
![Page 3: 1 General Issues in International Construction. Summary: 1 International Performance Characteristics (lecture 19 and Appendix 7). 2 International Contracts](https://reader036.vdocuments.net/reader036/viewer/2022072017/56649f095503460f94c1df00/html5/thumbnails/3.jpg)
3
– quality expectations of owners may be different internationally:• lower in many developing countries:
– however, often international contracts are large, prestigious facilities where quality must meet the highest international standards;
• ISO 9000 (International Standards Organization):– aimed at providing a quality system that helps ensure a product that meets the purchasers requirements;– increasingly adopted in industry (but still minimal in construction);– see Appendix 7 for overview of this standard.
– safety standards may be different:• may be stricter or less strict than US, however:
– must meet legal requirements (make sure you understand your obligations, relevant agencies, actions to take in case of accidents);– humanitarian, moral, ethical obligations;– economic issues (reduced premium if good safety record);
![Page 4: 1 General Issues in International Construction. Summary: 1 International Performance Characteristics (lecture 19 and Appendix 7). 2 International Contracts](https://reader036.vdocuments.net/reader036/viewer/2022072017/56649f095503460f94c1df00/html5/thumbnails/4.jpg)
4
2 International Contracts and Payments.
• Documentary payments:– An added dimension in international contracts is:
• buyer wants to receive goods and services before payment (large delivery lag times, greater probability of damage..);
• the seller would like payment before it hands over the product:– a solution to this dilemma is to operate payments through an international bank system:
• a common form of this is the Documentary Credit System:
• an international bank (issuing agent) is used for this purpose;
buyer inform bankof payment
issuingbank
produce documentaryevidence of existenceand shipment of goods
sellerpayment
![Page 5: 1 General Issues in International Construction. Summary: 1 International Performance Characteristics (lecture 19 and Appendix 7). 2 International Contracts](https://reader036.vdocuments.net/reader036/viewer/2022072017/56649f095503460f94c1df00/html5/thumbnails/5.jpg)
5
3 International Disputes and Arbitration.
• Disputes are commonplace in construction contracts:– for international contracts:
• greater risk and more uncertainty = greater possibility of disputes;
• as a foreign contractor, often less likely to get a fair judgement in local courts;
• legal process likely to be unfamiliar = disadvantage.
![Page 6: 1 General Issues in International Construction. Summary: 1 International Performance Characteristics (lecture 19 and Appendix 7). 2 International Contracts](https://reader036.vdocuments.net/reader036/viewer/2022072017/56649f095503460f94c1df00/html5/thumbnails/6.jpg)
6
• Litigation can be:– expensive;– cause delays;– lead to a poor working relationship;– the foreign contractor is often at a disadvantage.
• therefore, try to avoid litigation:– negotiation is the best approach if an amicable solution can be achieved in a reasonable period of time;– placing an engineer between the contractor and owner can facilitate the negotiation;– the next level of recourse is conciliation - introduction of a third independent party (in place of the engineer)
• can suggest, but not compel the terms of a settlement;
![Page 7: 1 General Issues in International Construction. Summary: 1 International Performance Characteristics (lecture 19 and Appendix 7). 2 International Contracts](https://reader036.vdocuments.net/reader036/viewer/2022072017/56649f095503460f94c1df00/html5/thumbnails/7.jpg)
7
– the next level of recourse may be arbitration:• provides an impartial forum (equality for both parties);• its independent of the jurisdiction of a foreign legal system;• often faster than referring to the judicial process.
– FIDIC contracts provide for dispute resolution through arbitration via the ICC Court (International Chamber of Commerce):• consequently, 20-25 % of the 300 cases started annually are construction cases;• however, the local arbitral center may not accommodate the use of the ICC rules.
![Page 8: 1 General Issues in International Construction. Summary: 1 International Performance Characteristics (lecture 19 and Appendix 7). 2 International Contracts](https://reader036.vdocuments.net/reader036/viewer/2022072017/56649f095503460f94c1df00/html5/thumbnails/8.jpg)
8
4 Boycotts and Bribes.
• Boycotts:– a technique whereby one state attempts to exert economic pressure on another to achieve some
desired political end:• primary boycotts: country X refuses to do business with country Y;• secondary boycotts: country X refuses to do business with companies in country Z that do business with
country Y.
– beware, this can impact your companies ability to secure future contracts;
![Page 9: 1 General Issues in International Construction. Summary: 1 International Performance Characteristics (lecture 19 and Appendix 7). 2 International Contracts](https://reader036.vdocuments.net/reader036/viewer/2022072017/56649f095503460f94c1df00/html5/thumbnails/9.jpg)
9
• Bribes:– most countries criminalize bribery:
• yet, in some countries, it may be accepted as a way of doing business, and rife even at the government level;• differentiate from legitimate agency/commission fees paid to bona-fide person for rendering services necessary to do
business in a foreign country;• keep thorough records of all financial transactions in case you are audited;• penalties can be severe, with heavy fines and years of imprisonment;• depending on the current political environment, you could find yourself being made an example.
![Page 10: 1 General Issues in International Construction. Summary: 1 International Performance Characteristics (lecture 19 and Appendix 7). 2 International Contracts](https://reader036.vdocuments.net/reader036/viewer/2022072017/56649f095503460f94c1df00/html5/thumbnails/10.jpg)
10
Required General Reading:
• Chapter 27: Construction in Kuwait.
• Chapter 28: Contract Arrangements in Developing Nations
• Chapters 29 & 30: FIDIC Clauses