Program Release 2008

Update to the Administrative Council

August 9, 2007

Page 2: 1 Program Release 2008 Update to the Administrative Council August 9, 2007

2

Program Release Scope Strategic

Administrative Projects ATS Effort Grants LAST SFS Supply Chain /

APPO

Strategic Interoperability Points ACH Commitment

Control DOA IAA Non-Sponsored

Projects Person Data PCBU/Activity ID Project

Numbering Project Status

Control Salary Cost

Transfer

Page 3: 1 Program Release 2008 Update to the Administrative Council August 9, 2007

3

Program Release Timeline July 2007

Implementation of JET, Madison APPO

July – August 2007 Systems Testing – two cycles for

each project October 2007

Planned ECRT implementation September 2007 – January 2008

Strategic Systems Integration Testing – all teams

Page 4: 1 Program Release 2008 Update to the Administrative Council August 9, 2007

4

Current Challenges Release of PeopleSoft

Maintenance Pack on August 30, 2007 Contains PeopleSoft Bundles 16

and 17 which are of interest to ATS Timing is challenging because it

may impact the start of Strategic Systems Integrated Testing

Sub-group to develop framework for making decision on how to proceed with the Maintenance Pack

Page 5: 1 Program Release 2008 Update to the Administrative Council August 9, 2007

5

Risks and Action Plans Risk identification sessions were held

for all major stakeholder groups Approximately 140 risks were

identified for the Program Release A number of the risks were duplicates Some of the risks were facts, not risks

The risks were prioritized by each team Rated on probability and impact (scale

1-4)

Page 6: 1 Program Release 2008 Update to the Administrative Council August 9, 2007

6

Risks and Action Plans Risks were grouped into categories:

Business Process Constraints (Scope, Schedule, Resources,

etc.) Coordination / Decision Making Data Conversion Performance / Operations Testing Training

Sub-groups of the Joint Steering Committee are developing action plans to address the highest risks

Page 7: 1 Program Release 2008 Update to the Administrative Council August 9, 2007

7

Communication Plan One of the areas identified as a risk

to the Program Release was Communication and Organizational Change Management Identified the need for structured,

consistent communication about all of the changes being introduced by the Program Release

A sub-group of the Joint Steering Committee was formed to address this issue Team includes Alice Gustafson and

Brian Rust

Page 8: 1 Program Release 2008 Update to the Administrative Council August 9, 2007

8

Communication Plan A communication template was

developed and completed for each Strategic Administrative Project Project name, description, target

audience, specific goals, timeline, what’s in it for me, possible surprises, and other

A communication plan has been drafted

Links for the Program Release and the projects will be place on www.vc.wisc.edu

Page 9: 1 Program Release 2008 Update to the Administrative Council August 9, 2007

9

Strategic Systems Integration Testing Strategic Systems Integration Testing

(SSIT) is the integrated testing of all projects within the Program Release in a shared environment

There are six iterations of testing planned We may have to modify this to

accommodate the need for two month-end cycles

Testing will be conducted by the project team members and extended staff

Page 10: 1 Program Release 2008 Update to the Administrative Council August 9, 2007

10

SSIT Goals All key functional business

requirements are met System performs at acceptable

levels Operational guidelines are in

place Current SFS functionality is not

negatively impacted Program Release meets “Go

Live” readiness criteria

Page 11: 1 Program Release 2008 Update to the Administrative Council August 9, 2007

11

Determining Readiness for Go-Live How do we determine whether or not

the Program Release is ready for implementation?

Criteria to be used for determining readiness: Business Process Readiness Testing – quality and completeness Performance – online and batch Defined Support Plan User Readiness Defined Security Plan Documentation

Page 12: 1 Program Release 2008 Update to the Administrative Council August 9, 2007

12

Determining Readiness for Go-Live

The Joint Project Managers are adding further detail to the criteria and more specific measurements

The criteria will be reviewed by the Joint Steering Committee

The goal is to have the criteria for assessing readiness defined prior to having to make a decision