1 the siting acts electrical power plant siting act electrical transmission line siting act natural...
TRANSCRIPT
1
The “Siting” Acts
Electrical Power Plant Siting Act
Electrical Transmission Line Siting Act
Natural Gas Transmission Pipeline Siting Act
The Certification Process and Agency Involvement
Created forSiting Workshop – Altamonte Springs
February 5, 2008http://www.dep.state.fl.us/siting
2
Electrical Power Plant Siting Act
The Certification Process and Agency Involvement
3
Electrical Power Plant Siting Act
Created by Florida Legislature in 1973
Revised in 2006
Sections 403.501- 403.518, Florida Statutes
Supporting Rule: 62-17, Part I, F.A.C.
Multi-agency review with ultimate approval by Governor & Cabinet (“Siting Board”)
4
Power plants prior to 1973 continue being licensed through regular permitting processes.
Some sites have generation units which were permitted both prior to the passage of the Act, and after the Act. Different procedures and coordination contacts may apply for the same site’s differing units.
The Department of Environmental Protection’s (DEP) website contains a listing of sites regulated under the
Power Plant Siting Act: (http://www.dep.state.fl.us/siting/certification.htm).
Electrical Power Plant Siting Act
5
Thresholds:
Steam electric power plants > 75 megawatts (MW) (gross steam component)
Solar power plants which are > 75 MW
Steam plants may be combined-cycle units, nuclear units, IGCC, pulverized coal units, or conventional oil/gas-fired.
Combustion turbines can be permitted in conjunction with a certified facility, or as an addition via the modification process, but alone do not trigger the certification process.
Electrical Power Plant Siting Act
6
1) Determination of Need – PSC (Public Service Commission)
2) Site Certification Application (SCA) Review – DEP with affected agencies
3) Federal Permits – Must be in at least “Draft” stage prior to certification hearing. (PSD, NPDES, UIC, RCRA)
Site Certification ProcedureCertification Requirements
7
Site Certification ProcedureAffected Agencies
Department of Community Affairs
The Water Management District
Each Local Government
Fish and Wildlife Conservation Commission
Regional Planning Council
Department of Transportation
Any other agency, if requested by the Department (Dept. of State, Dept. of Agriculture)
8
Certification (Licensing) supersedes and encompasses ALL state and local permits and approvals.
Certification does not supersede Federal permitting processes (PSD, NPDES, UIC, RCRA)
Electrical Power Plant Siting Act
9
Licensing is for the “Life of the Facility”
May include “associated facilities” distant from or extending from the main site such as:
• Landfills
• Natural gas pipelines
• Rail lines
• Roadways
• Electrical transmission lines
Electrical Power Plant Siting Act
10
Associated facilities certification may be for a “corridor”, within which the right-of-way (ROW), associated facility, and access and maintenance roads will eventually be located.
Corridor may be up to a mile in width, with unlimited length.
Review process is for entire corridor, with focus on where a ROW would not be appropriate or permittable.
Corridor will be reduced to the boundary of the ROW after certification.
Electrical Power Plant Siting Act
11
PPSA Certification Procedures
The certification process is a legal proceeding.
DEP (The Siting Office):
administers the processing of applications
administers and manages the terms and conditions of the certification order for the life of the facility
The schedule and proceeding incorporates a “Land Use Determination” (which is made by the local government) with final approval of land use by the Siting Board.
Depending on whether the project is disputed, the Final Order of certification will be issued by the Siting Board or the DEP Secretary.
12
PPSA Certification ProceduresLand Use Determination
This is not a step that the Districts or WM Districts will be involved in.
However, since a hearing may occur in the case of a dispute, with newspaper and other public notice
published, staff need to be aware of this step (may occur after completeness review but prior to
Preliminary Statements of Issues).
Refer any questions to the Siting Coordination Office.
13
PPSA Certification Procedures
Timelines of Certification are Controlled by Statute.
Once the applicant submits the Application, DEP (Office of General Counsel) must immediately file
the application with the Department of Administrative Hearings (DOAH).
Within 7 days of receipt of SCA, DEP must propose a schedule and request the appointment of an
Administrative Law Judge (ALJ).
14
PPSA Certification ProcedureCompleteness Review
Affected Agency comments/recommendations on completeness are due to DEP within 30 days of filing of the Application.
DEP (Siting) must file a Completeness Determination (1st) with DOAH within 40 days of filing of the Application.
The applicant has 30 days to submit additional information. (can also ask for more time)
Agencies have 15 days from receipt of additional information to comment on completeness.
15
PPSA Certification ProcedureCompleteness Review
DEP (Siting) has 7 more days to file the 2nd Completeness Determination with DOAH.
The second completeness step continues until the application is found complete.
This is a funneling process. No new issues unless related to answers to previous questions.
Most applications are found complete on the second go-round.
16
PPSA Certification ProcedurePreliminary Statements of Issues
Required by Statute – Agencies (WMDs/DEP Districts/Bureaus)
Due 40 days after application is “complete”.
This is a “heads up” to DEP and applicant on things that could be a barrier to certification.
Gives the applicant a chance to contact the agency and work on solving the issues.
Failure to raise an issue here “shall not preclude the issue from being raised in the agency’s report”.
17
PPSA Certification ProcedureAgency Reports
Required by Statute for all statutory agencies. DEP’s Siting Office report constitutes the DEP report.
Due 100 days after application is “complete”
Includes:
A Report on Matters Within the Agency’s Jurisdiction
Which may Potentially be Affected by the Proposed Project
Recommendation on Approval or Denial of Project
Conditions of Certification (COC)
18
PPSA Certification ProcedureConditions of Certification
These are the conditions that would normally go into the “standard” state issued permit.
Conditions should be comprehensive.
Must have regulatory authority (proposed conditions are required to include citations).
Even if an agency recommends Denial of the project, a full set of COC should be submitted as the project may still be certified.
19
PPSA Certification ProcedureConditions of Certification
● Proposed COC should include the following as applicable: regulatory citations supporting requirement/condition;
frequency, starting timeframes, and duration of reporting requirement;
identify maps or special details (if necessary);
management plans;
section of DEP/WMD/agency to receive reports/management plans - no addresses and phone numbers (include notification to the Siting Office.
Review COC for the projects in your area, and evaluate for necessary updates or corrections. Notify the Siting Office when a modification may be necessary and include proposed Condition language.
20
PPSA Certification ProcedureConditions of Certification
If not all plans are known, draft a condition that requires a “post-certification submittal” for review and approval. These may include:
● Management Plans
● Site-specific details for rights-of-ways and equipment only generically described to be located within an associated facility corridor.
Example: Stormwater Plans
21
PPSA Certification ProcedureProject Analysis & Draft COC
Drafted by the Siting Office and filed with the Administrative Law Judge (ALJ) 130 days after application
deemed “complete”.
Includes: DEP’s report Copies of other Agency Reports DEP recommendation (Approval/Denial) Comments received from any other agency or person Status of any Federal permit
Note: If Federal permits are not at least in “draft” stage, certification will not move forward and Siting will file for extension of time.
22
PPSA Certification ProcedureHearing Before the ALJ
Required
a) PSC has determined a “Need” for the project.
b) The Proposed Site Conforms to the Land Use Plan or Zoning Ordinances (or the Siting Board has granted relief).
c) There have been no requests for extension of time.
d) No Stipulation.
e) Draft Federal permits have been issued.
If requirements are met, a Certification Hearing Shall be Held with the ALJ no later than 265 days after the filing of the Application.
23
PPSA Certification ProcedureHearing Before the ALJ
Hearing will be held in the “vicinity” of the proposed power plant.
DEP, WMD, and other agency staff may be requested to testify, either as fact or expert witnesses.
Hearings may last one or two days to several weeks.
If petitions against draft federal permits, these may be consolidated into the Site Certification Hearing
24
PPSA Certification ProcedureSiting Board Hearing
ALJ submits a Recommended Order to the Siting Board within 45 days after filing of hearing transcript.
The Siting Board, by written order, approves or denies certification within 60 days after receiving ALJ’s
recommendation.
Issues raised in the Board Hearing are limited to matters raised in the ALJ hearing or raised in the ALJ
Recommended Order.
25
PPSA Certification ProcedureStipulation Between All Parties
If all parties to the proceeding stipulate that there are no disputed issues of fact or law, DEP or the applicant may request to cancel the ALJ hearing.
If request is “granted”, the ALJ relinquishes jurisdiction to DEP.
The DEP Secretary will then act, by written order, upon the application.
26
1) Citizens may attend the Informational Public Meeting if held*;
2) “Affected persons” may challenge a local government’s Land Use Determination, resulting in a Hearing;
3) Citizens may attend the Land Use Hearing (ALJ) if held;
4) Citizens may attend the Certification Hearing (ALJ) if held;
5) Citizens may attend Siting Board Meeting for Land Use if held;
6) Citizens may attend Siting Board Meeting for Certification if held.
Note: Additional opportunities for involvement exist within the PSC Need Determination and Federal Permitting processes which are not
outlined here.
PPSA Certification ProcedureOpportunities for Public Intervention
27
PPSA Certification
Potential actions/requirements after certification, include:
Post-Certification submittal reviewAmendmentsModificationsMonitoringEnforcement
28
Post Certification Submittals
Submittals required by a specific COC.
Reports, drawings, plans, etc.
Compliance demonstration of certification.
Submitted to Siting and appropriate reviewing agency.
Review period of 90 days or less required by Statute.
29
Post Certification Amendments
Any change or revisions to the application that do not alter conditions of certifications require the licensee to submit a written Request for Amendment.
All Requests for Amendment should come through the Siting Office!
The Siting Office will distribute the Request to affected district offices and agencies for their input.
30
Post Certification Amendments
We have 30 days to:
a) Determine that the request IS an amendment (NOT a modification) and issue a written approval if an amendment (no fee required).
b) Determine that the request is NOT an amendment, and provide written notice that the request will require a modification to the COC; or
c) Determine that more information is needed, and request the information in writing. (15-day review period for additional information)
31
Modification of Certification
403.503 Definitions - Modification
“means any change in the certification order
after issuance, including a change in the
Conditions of Certification.”
32
Modification of Certification
If the proposed change/activity at the facility…
Would normally require a state permit and is not “covered” under the existing COC,
This is a modification and requires changes/additions to the COC.
Fee Required (Note: For Certification applications and modifications, no fees are to be collected for state or local permitting actions.)
33
Modification of Certification
Certifications may be modified in one of the following ways:
1) Siting Board Initiates
2) Licensee files a petition (Fee Required)
3) Department Initiates
4) Update for consistency with Federal permit(“Auto-Mod)
5) Update for consistency with subsequently adopted rules (“Auto-Mod”)
34
Modification of Certification
When Petition for Modification is filed by Licensee:
Agencies (and districts) have 25 days to file
completeness recommendations.
Siting has 30 days to issue completeness determination
We rely on district offices and affected agencies to evaluate and propose any necessary changes/additions to the COC.
35
Monitoring
Technical monitoring at the site will be done by the
jurisdictional agency/District.
Siting must be notified if discrepancies with the conditions are found.
Discrepancies may be grounds for Enforcement Actions.
36
Enforcement
Enforcement actions including Consent Orders are initiated by the District/Bureaus but coordination with the Siting Office and the Siting Program attorney is necessary. Since no state or local permits are issued, violations are against the Certification, not a permit.
37
Electrical Power Plant Siting Act
Questions???
http://www.dep.state.fl.us/siting
38
Electrical Transmission Line Siting Act(TLSA)
Created by Florida Legislature in 1980
Revised in 2006
Sections 403.52 – 403.5365, Florida Statutes
Supporting Rule: 62-17, Part II, F.A.C.
Multi-agency review with ultimate approval by Governor & Cabinet sitting as the “Siting Board”
39
Electrical Transmission Line Siting Act
Thresholds: 230 kiloVolts or higher in electric transmission
capacity Must cross a county line Are 15 miles or longer (Applicant may elect to use certification process
for smaller/shorter lines)
40
Electrical Transmission Line Siting Act
Transmission lines under the TLSA: Extend from an existing or proposed
substation or power plant (but not including it)
To an existing or proposed transmission network or substation, or right-of-way
May include terminal or existing substations
41
Electrical Transmission Line Siting Act
Certification is for a “Corridor”, within which the right-of-way, towers, access and maintenance roads will eventually be located
Corridor may be up to a mile in width, with unlimited length
Review process is for entire corridor, with focus on where a right-of-way would not be appropriate or permittable
Corridor will be reduced to the boundary of the right-of-way after certification.
42
Electrical Transmission Line Siting Act
Certification (Licensing) supersedes and encompasses ALL state and local permits and approvals.
However, transmission lines are exempt from Local Land Use Plan requirements.
43
Transmission Line Siting Certification Procedures
Differences between the PPSA and TLSA:
Process clocks and steps are not identical (TLSA is shorter with some significantly different steps)
No Land Use Determination is required
Largely wetland/ERP issues
May be subsets of main certification hearing (local component hearings) in counties other than main hearing
Alternative Corridors may be proposed by third-parties
44
Transmission Line Siting Certification Procedures
Alternative corridor reviews are a mini-certification process, with their own timeclock steps
Same type of reviews required as for original corridor, but with shorter timeframes
Typically shorter corridors
45
Transmission Line Siting Certification Procedures
Steps and requirements that are the same as the PPSA: PSC Need Determination Completeness Review Local Government Informational Meetings Preliminary Statements of Issues Agency Reports Project Analysis, with proposed Conditions of
Certification Certification hearing
46
Transmission Line Siting
Like the PPSA:Certification is for the life of the facility!May be many actions/requirements after
certification, including: Post-Certification submittal review Amendments Modifications Monitoring Enforcement
47
Electrical Transmission Line Siting
Questions???
http://www.dep.state.fl.us/siting
48
Natural Gas Transmission Pipeline Siting Act (NGPSA)
Created by Florida Legislature in 1992
Sections 403.9401 – 403.9425, Florida Statutes
Supporting Rule: 62-807, Part II, F.A.C.
Multi-Agency approvals require Governor & Cabinet, sitting as the “Natural Gas
Transmission Pipeline Siting Board” as the approving authority
49
Natural Gas Transmission Pipeline Siting Act
Only applies to natural gas pipelines that are in-state Inter-State are licensed by the Federal Energy
Regulatory Commission Other Thresholds:
Must cross a county line Is 15 miles or longer (Applicant may elect to use certification process for
smaller/shorter pipelines)
50
Natural Gas Transmission Pipeline Siting Act
Provisions and process steps are similar to Electrical Transmission Line Siting Act, with following exceptions:
Certification hearing is mandatory
“Sufficiency” process is the equivalent of “completeness” under PPSA and TLSA
Different timeclocks
Corridor width limitation is 1/3 mile wide, instead of 1 mile wide
51
Natural Gas Transmission Pipeline Siting Act
Questions???
http://www.dep.state.fl.us/siting
52
List of ContactsMike Halpin
Siting Administrator
Program Administrator 850-245-8005
Cindy Mulkey
Engineer
Power Plant Case Manager 850-245-8006
Ann Seiler
Environmental Specialist
Transmission Line Case Manager 850-245-8008
Jill Stoyshich
Environmental Consultant
Everything else (legislation, budget) 850-245-8007
Toni Sturtevant
Attorney
Legal Counsel 850-245-2257
53
DEP District Siting Liaisons
Northeast Chris Kirts
Northwest Darryl Boudreau
Central Jim Bradner
Southeast Tim Gray
Southwest Mara Nasca
South Audrey Wright
54
Contents of CD
Application Guides Flow Charts Other Useful Information
Current and Anticipated Applications (timeline) Current and Anticipated Applications Applications by DEP
district Siting Statistics
Rules Statutes Training Presentation