E4068 v1 rev

The World Bank-financed

Ma'anshan Cihu River Basin Improvement Project

Environmental Management Plan

Leading Group Office for Ma’anshan Cihu River Project under World Bank Loan

Nov. 2012

Content

1 Preface1

2 Basis for preparation1

2.1Laws on environmental protection1

2.2Regulations, bylaws and normative documents on environmental protection2

2.3Technical standards on environmental protection3

2.4Relevant documents of the World Bank3

2.5Other relevant documents4

2.6Documents related to the Project5

2.7 assessment standards5

3. Basic Information of the Project6

3.1 Construction tasks6

3.2 Flood control and drainage design indicators6

3.3 Consist of the project7

3.4 Impact of Land Acquisition and Resettlement10

4 Environmental impact analysis10

4.1Identification of environmental impact factors10

4.2 Environmental impact analysis11

5 Environmental management procedures14

5.1 Generic Environmental Code of Practices14

5.2 Site-specific environmental Mitigation Measures18

6. Environmental Management19

6.1 Environmental Protection Management Plan19

6.1.1 The overall goal of environmental management19

6.1.2 Environmental management institutions20

6.1.3 Duties and personnel allocation of the environmental management system agencies22

6.2 Environmental Monitoring Plan24

6.2.1 Formulate objectives and principles24

6.2.2 Environment monitoring agency24

6.2.3 Environmental monitoring scheme24

6.3 EMP training program27

6.3.1 Training purpose27

6.3.2 Training objects27

6.3.3 Training content27

6.3.4 Training plans28

6.4 Environmental Supervision & Management Plan (ESMP)29

6.4.1 Environmental supervision organization during the construction period29

6.4.2 Guideline of environmental supervision29

6.4.3 Environmental supervision scope29

6.4.4 Work pattern of environmental supervision30

6.4.5 Specific working procedure of environmental supervision30

6.4.6 Environmental supervision organization and work system.31

6.4.7 Engineering environmental supervision plan32

6.4.8 Document compilation of environmental supervision34

6.4.9 Environmental supervision archives management34

6.5 Public complaints and feedback mechanism35

6.5.1 Public complaints mechanism35

6.5.2 Public feedback mechanism36

6.6 Report mechanism of Environmental management plan37

6.6.1 Reorganize and save of Monitoring data37

6.6.2 Information exchange37

6.6.3 Recording37

6.6.4 Reports37

6.7 Investment Estimation of Environment Protection38

3

1 Preface

This Environmental Management Plan, which based on the EIA report of The World Bank-financed Ma'anshan Cihu River Basin Improvement Project, as an free-standing document, include the arrangement of institutions, environmental management plan during construction period and operation period, and provided an action principles and work frame for the mitigation measures, environmental management and monitoring plan of the project during construction period and operation period. The main content include:

(1) Project overview

(2) Potential environmental impact of the project

(3) The project organization and responsibility

(4) Environmental management plan

(5) Environmental monitoring plan

Feasibility study and environmental impact assessment has been taken on the World Bank-financed Ma'anshan Cihu River Basin Improvement Project, in order to reduce and alleviate the negative impact of the project to the society and environment, and to develop a series mitigation measures to solve the environmental issue.

The purpose of Environmental management plan is to list the environmental mitigation measures and monitoring and supervision organization plan, to avoid or mitigate the negative impacts during the construction period and operation period. The environmental management plan will be the important connection between implemention and the management defined in the EIA, for the aim to achieve management objectives through the implementation of the environmental management plan.

2 Basis for preparation2.1Laws on environmental protection

1.Environmental Protection Law of the PRC (1989.12.26);

2.Environmental Impact Assessment Law of the PRC (2003.9.1);

3.Law of the PRC on Ambient Noise Pollution Prevention and Control (1997.3.1);

4.Law of the PRC on Atmospheric Pollution Prevention and Control (2000.9.1);

5.Law of the PRC on Water Pollution Prevention and Control (2008.2.28);

6.Law of the PRC on Solid Waste Pollution Prevention and Control (2005.4.1);

7.Law of the PRC on Water and Soil Conservation (2011.3.1);

8.Flood Control Law of the PRC (1998.1.1);

9.Land Administration Law of the PRC (2004.8.28);

10.Law of the PRC on the Preservation of Cultural Relics (2007.12.29)

2.2Regulations, bylaws and normative documents on environmental protection

1.Decision of the State Council on Several Issues Concerning Environmental Protection, SC [1996] No.31;

2.Regulations on the Administration of Environmental Protection in Construction Projects, Decree No.253 of the State Council (1998);

3.Notice on Issuing the National Environmental Protection Outline, SC [2000] No.38;

4.Regulations on the Protection of Basic Farmland, Decree No.257 of the State Council (1998);

5.Regulations for the Implementation of the Law of the PRC on Water and Soil Conservation, Decree No.120 of the State Council (1993);

6.Regulations of the PRC on Nature Reserves, Decree No.167 of the State Council (1994);

7.Categorized Administrative List of Environmental Impact Assessment for Construction Projects, Decree No.2 of the Ministry of Environmental Protection (2008);

8.Interim Measures for Public Participation in Environmental Impact Assessment, MEP [2006] No.28;

9.Administrative Measures for Water and Soil Conservation Programs for Development and Construction Projects, WSC [1994] No.512;

10.Opinions on Further Improvements in the Protection of Basic Agricultural Land, MLR [2005] No.196;

11.Guiding Catalogue for Industrial Structure Adjustment (2011), Decree No.9 of the National Development and Reform Commission of the PRC;

12.National Ecological Function Zoning, Announcement No.35 of the Ministry of Environmental Protection (2008);

13.Notice on Strengthening the Administration of Environmental Impact Assessment in Projects Financed by International Financial Organizations, EM [1993] No.324;

14.Environmental Protection Regulations of Anhui Province (2010.11.1);

15.Notice on Issuing the Measures of Anhui Province for the Implementation of Environmental Supervision Trials in Construction Projects (2012.4.1);

16.Measures of Anhui Province for the Implementation of the Law of the PRC on Solid Waste Pollution Prevention and Control (2006.6.29);

17.Measures of Anhui Province for the Implementation of the Land Administration Law of the PRC (2004.7.1);

18.Regulations on Agricultural Environmental Protection of Anhui Province (1999.8.1);

19.Decision of the Anhui Provincial Government on Strengthening Environmental Protection Practically (1997.4.17);

20.Opinions of the Anhui Provincial Government on the Implementation of the Decision of the State Council on Carrying out a Scientific Outlook on Development and Strengthening Environmental Protection (2006.9.14)

2.3Technical standards on environmental protection

1.Technical guidelines for environmental impact assessment—General program (HJ2.1-2011);

2.Technical guidelines for environmental impact assessment—Atmospheric environment (HJ2.2-2008);

3.Technical guidelines for environmental impact assessment—Surface water environment (HJ/T2.3-1995);

4.Technical guidelines for environmental impact assessment—Groundwater environment (HJ610-2011);

5.Technical guidelines for environmental impact assessment—Acoustic environment (HJ2.4-2009);

6.Technical guidelines for environmental impact assessment—Ecological impacts (HJ19-2011);

7.Technical guidelines for environmental impact assessment—Hydropower and water resources projects (HJ/T88-2003);

8.Technical code on soil and water conservation for development and construction projects (SL204-98)

2.4Relevant documents of the World Bank

The Project includes river course management and dike reinforcement mainly. Based on the Feasibility Study Report and the field investigation, the Project involves no resettlement, and no nature reserve, protected cultural relic or any other sensitive target. The World Bank has 10 safeguard policies in total, and the policies related to the Project is OP 4.01 and OP 4.12. The EHS of IFC considered in the EA development include the General EHS Guideline and the Waste Management Guideline, see Table 1-1.

Table 1Correlation Analysis between the Project and World Bank Safeguard Policies

No.

World Bank safeguard policy

Relevance with the Project

Remarks

1

OP4.01: Environmental Assessment

Relevant

2

OP4.04: Natural Habitats

Irrelevant

There is no nature reserve in the project area.

3

OP4.09: Pest Management

Irrelevant

4

OP4.10: Indigenous Peoples

Irrelevant

The Project involves no ethnic minority.

5

OP4.11: Physical Cultural Resources

Irrelevant

The municipal-level cultural relic Wudangang is located in the project area. The nearest distance between the project area and this relic is about 210m. and this relic will not be affected by the Project during construction.

6

OP4.12: Involuntary Resettlement

Relevant

7

OP4.36: Forests

Irrelevant

8

OP4.37: Safety of Dams

Irrelevant

9

OP7.50: Projects on International Waterways

Irrelevant

10

OP7.60: Projects in Disputed Areas

Irrelevant

2.5Other relevant documents

1.Urban Master Plan of Ma’anshan Municipality (2002-2020), 2004.03;

2.Urban Drainage Engineering Plan of Ma’anshan Municipality (2005-2020), 2006.03;

3.Urban Flood Control Planning Report of Ma’anshan Municipality, 2006.11;

4.Plan for Integrated Water Environment Management of the Cihu River Basin of Ma’anshan Municipality, 2011.08;

5.Preliminary Design for the Ma’anshan Middle Cihu River (East Ring Road—Linli Road) Integrated Management Project, 2012.02;

6.Feasibility Study Report for the Upper Cihu River Surface Water Management Project, 2009.08;

7.Feasibility Study Report for the Ma’anshan Yuanxiang Mountain Troilite Mine Geologic Environment Management Project, 2010.04;

8.Measures for Division of Urban Suitable Functional Areas for Surface Water, Atmospheric and Noise Environment of Ma’anshan Municipality, 2011.6;

9.Notice of the Ma’anshan Municipal Government on Issuing the Integrated Environmental Management Plan for the Cihu River Basin (MMG [2008] No.48);

10.Master Plan for Mineral Resources of Ma’anshan Municipality (2006-2015);

11.Outline of the Master Land Utilization Plan of Ma’anshan Municipality (2006-2020);

12.Master Ecological Construction Plan of Ma’anshan Municipality (2004-2020)

2.6Documents related to the Project

1.Feasibility Study Report for the World Bank-financed Ma'anshan Cihu River Basin Improvement Project, Central and Southern China Municipal Engineering Design and Research Institute;

2.Notice of the National Development and Reform Commission, and the Ministry of Finance on the Request for Instructions on China’s Plan for Candidate Projects to be Financed by the World Bank in Fiscal Years 2011-2013 (NDRC FC [2010] No.2617);

3.Notice of the National Development and Reform Commission, and the Ministry of Finance on China’s Plan for Candidate Projects to be Financed by the World Bank in Fiscal Years 2011-2013 forwarded by the Anhui Provincial Development and Reform Commission (ADRC FC [2010] No.1306)

2.7 assessment standards

The standards proposed for the EIA are as follows:

1.Environmental quality standards

Table 2 Environmental Quality Standards

Item

Standards

Class

Ambient air:

Ambient Air Quality Standard (GB3095-1996), and the 2000 Amendment

Class II

Surface water

Environmental Quality Standard for Surface Water (GB3838-2002)

Class III (Yangtze river) and V (Cihu river) standards

Groundwater

Quality Standard for Groundwater (GB/T14848-93)

Class III

Acoustic environment

Acoustic Environment (GB3096-2008)

Class 4 standard in the Quality Standard for Acoustic Environment (GB3096-2008) for both sides of trunk traffic lines, Class 3 standard for Cihu Industrial Zone, and Class 2 standard for other areas

Soil environment

Quality Standard for Soil Environment (GB15618-1995)

Class III

2.Pollutant emission standards

Table 3Emission Standards

Item

Emission Standard

Class

Raise dust

Integrated Emission Standard for Air Pollutants (GB16297-1996)

---

Odor pollutants

Emission Standard for Odor Pollutants (GB14554-93)

Class II

Construction noise

Environment Noise for Boundary of Construction Site (GB12523-2011)

---

Noise of pump station operation

Environment Noise for Boundary of factory(GB12348-2008)

Class III

Solid waste

Agricultural sediment the pollutant control standard(GB4284-84)

---

3. Basic Information of the Project3.1 Construction tasks

1.To improve the flood carrying capacity of the Cihu River by improving the Cihu River and the branch river systems, increase the flood control standard of both banks, and improve the flood control system of Ma’anshan Municipality;

2.To improve water quality and landscape, create a harmonious and efficient society in which human and nature coexist, and improve urban environment and people’s living standard;

3.2 Flood control and drainage design indicators

According to the Urban Flood Control Planning Report of Ma’anshan Municipality and Urban Drainage Plan of Ma’anshan Municipality (2005-2020), the design flood control standard of the Cihu River is resisting floods that occur every 20 years, to be reviewed based on the standard of resisting floods that occur every 50 years; the design flood drainage standard for the pump drainage area of the Cihu River is resisting floods that occur once a year.

3.3 Consist of the project

(1) Component 1: Rehabilitation of Cihu River and Improvement of Urban Drainage

Management of the Cihu River course in which the upper river course is 6.8km long, including ecological revetment construction, landscaping and dike top road construction; and the lower river course is 6.24km long, including dredging, dike body reinforcement, revetment, landscaping, dike top road construction etc.; demolition and re-construction of 5 flood control pumping stations.

(2) Component 2: Rehabilitation of Tributaries

This Component comprises management of 22 branch rivers including 2 ponds as rainwater regulation systems, with a total length of 32.05 km, including ecological revetment construction and landscaping. This Component also comprise management of left side of Lijianwan river, including dike reinforcement, slope protection, landscaping and dike top road construction, and 19 branch river systems, including dredging, slope protection, landscaping, and dike top road construction.

(3) Component 3: Environmental management and monitoring

This Component comprise Installation of an auto surface water quality monitoring station; development and implementation of water resource monitoring plan; preparation of mine closure guideline..

(4) Component 4: Capacity Building and Implementation Support

This Component comprise hiring consulting companies to support the project management, training and abroad investigation of staff in project office and construction units, facilities of the project office and operation agency.

See detailed in table 4

Table 4 list of the constructions contents

No.

Name

Standard

Material / structure

unit

amount

The scope of construction

Component 1

Management of Cihu river

 

 

 

 

 

1.1

Upper Cihu river

 

 

 

 

1.1.1

Provincial Highway 313-hunan east road

bottom width23.5m,top width33.0m,canal depth3.5m

soil

m

3800

Ecological revetment, greening, road construction

1.1.2

Hunan east road – East ring road

bottom width33.0m,top width44.0m,canal depth4.0m

soil

m

3000

Ecological revetment , greening , road construction

1.2

Lower Cihu river

 

 

 

 

 

1.2.1

Tianran river mouth – Linli Bridge

bottom width25.0m,top width69.0m,dike height7.5m

soil

m

890

Dike reinforcement , revetment , greening , road construction on dike top , pond filling , dredging

1.2.2

Cihu river mouth – Tianran river mouth

bottom width20.0m,top width68.0m,dike height8.0m

soil

m

5350

Dike reinforcement , revetment , greening , road construction on dike top , pond filling , dredging

1.3

Drainage pumping station

 

 

 

 

 

3.1.1

Tongyi (2)

Design discharge 6.3m3/s

Reinforced concrete

set

1

 

3.1.2

Jiandanzha

Design discharge 11.5m3/s

Reinforced concrete

set

1

 

3.1.3

Zhaoming

Design discharge 6.9m3/s

Reinforced concrete

set

1

 

3.1.4

Tailai

Design discharge 4.2m3/s

Reinforced concrete

set

1

 

3.1.5

Xiaonanwei

Design discharge 5.2m3/s

Reinforced concrete

set

1

 

Component 2

Management of branch river systems

 

 

 

 

 

2.1.1

Jiandan river water system

bottom width4~6m,top width4~6m,canal depth2.5m

rubble

m

1210

dredging , ecological revetment , greening

2.1.2

Hupo pond water system

Revetment height 4.0m

rubble

m

3320

ecological revetment , greening

2.1.3

Yaochang pond water system

Revetment height 4.0m

rubble

m

1770

ecological revetment , greening

2.1.4

Ditch of dianye road

bottom width6m,top width12m,canal depth2.0m

rubble

m

1086

dredging , ecological revetment , greening

2.1.5

East side ditch of Ningwu rail road

bottom width10m,top width16m,canal depth2.0m

rubble

m

1642

dredging , ecological revetment , greening

2.1.6

North side ditch of tianran river

bottom width10m,top width16m,canal depth2.0m

rubble

m

1233

dredging , ecological revetment , greening

2.1.7

Nantang river

bottom width11m,top width11m,canal depth2.0m

rubble

m

1898

dredging , ecological revetment , greening

2.1.8

Cross stream in Xindu community

bottom width5m,top width12.5m,canal depth2.5m

rubble

m

1169

dredging , ecological revetment , greening

2.1.9

Wangebaitan water system

bottom width17m,top width23m,canal depth3.0m

rubble

m

820

dredging

2.1.10

Yangqiao stream water system

bottom width14m,top width14m,canal depth2.0m

rubble

m

772

dredging

2.1.11

Xitang water system

bottom width15m,top width21m,canal depth2.0m

rubble

m

1094

dredging , ecological revetment , greening

2.1.12

Xiaohecha main stream

bottom width19m,top width25m,canal depth2.0m

rubble

m

240

dredging , ecological revetment , greening

2.1.13

Xiaohecha branc stream

bottom width8m,top width14m,canal depth2.0m

rubble

m

1230

dredging , ecological revetment , greening

2.1.14

Qiaoshan stream

bottom width8m,top width8m,canal depth2.0m

rubble

m

1253

dredging , ecological revetment , greening

2.1.15

Geyang water system

bottom width10m,top width10m,canal depth2.0m

rubble

m

539

dredging , ecological revetment , greening

2.1.16

Wudangang east stream

bottom width10.5m,top width18m,canal depth2.5m

rubble

m

1980

dredging , ecological revetment , greening

2.1.17

Wudangang west stream

bottom width14.5m,top width22m,canal depth2.5m

rubble

m

2120

dredging , ecological revetment , greening

2.1.18

North stream on right bank of shanghu river

bottom width1.5m,top width9m,canal depth2.5m

rubble

m

990

dredging , ecological revetment , greening

2.1.19

Shanghu river

bottom width18.5m,top width26m,canal depth2.5m

rubble

m

3670

dredging , ecological revetment , greening

2.1.20

Fengshou south stream

bottom width9m,top width9m,canal depth2.0m

rubble

m

900

dredging

2.1.21

Qianjin stream

bottom width10m,top width10m,canal depth2.0m

rubble

m

1410

dredging , ecological revetment , greening

2.1.22

Left side of Lijianwan river

soil

m

1700

Dike reinforcement, grouting , revetment , road construction on dike top , pond filling

Componet 3

Environmental management and monitoring

Including Cihu river watershed management system, Cihu river water quality monitoring system, Cihu river watershed environmental warning system and mining management system.

Componet 4

Ability building and project implementationsupport

Including hiring consulting companies to support the project management, training and abroad investigation of staff in project office and construction units, facilities of the project office and operation agency.

3.4 Impact of Land Acquisition and Resettlement

According to the ‘Resettlement Action Plan of Ma'anshan Cihu River Basin Improvement Project’ compiled by the Immigrations Center of Hehai University, the project impacting scope include three districts (Huashan district, Jinjiazhuang district, Cihugaoxin district), one county, two blocks (Cihu county and Huoli block), with 552 households and 1714 persons. This project doesn’t involve housing demolition and relocation. The main impacts are the acquisition of collective-owned and state-owned land. The total land acquisition are 1788.89 mu., including 1253.89mu. collective-owned land, which are all non-prime arable land. The permanent land acquisition of national-owned land is 535 mu., which are all unused land along the river and branches. The temporary land acquisitions are all inside the blueline of Cihu river, without extra land acquisition or demolition.

See detailed in table 5.

Table 5 Land acquisition and resettlement of the project

Items

Units

River management

Branches

Pumping station

Total

Upper river

Lower river

Permanent land acquisition of collective -owned

Mu.

445

266.85

533.84

8.2

1253.89

Permanent land acquisition of national-owned

Mu.

0

150.35

367.65

17

535

Directly impact

Household

140

35

377

0

552

Person

434

116

1164

0

1714

4 Environmental impact analysis4.1Identification of environmental impact factors

The environmental impact factors of the Project at the construction and operation stages have been identified based on its environmental impact profile and the surrounding environmental characteristics, as shown in Table 6

Table 6Identification of Environmental Impact Factors

Construction behavior

Environmental resources

Construction stage

Operation stage

River course broadening

River course dredging

Dike reinforcement

Pumping station construction

Pumping station operation

Social environment

Employment

+1D

+1D

+1D

+1D

+1C

Economy

+1D

+1D

+1D

+1D

+2C

Quality of life

-1D

-1D

-1D

-1D

+2C

Ecological environment

Landscape

-1D

-1D

-1D

-1D

Soil

-1D

-1D

-1D

-1D

Agriculture

-1D

-1D

-1D

-1D

Vegetation

-1D

-1D

-1D

-1D

Fauna

-1D

-1D

-1D

-1D

Water loss and soil erosion

-1D

-1D

-1D

-1D

Environmental quality

Surface water environment

-1D

Acoustic environment

-1D

-1D

-1D

-1D

-1C

Atmospheric environment

-1D

-1D

-1D

-1D

Notes: 1.In the above table, “+” denotes a positive benefit and “-” a negative benefit’

2.The numbers in the table indicate relative degree of impact, where “1” denotes a minor impact, “2” a medium impact and “3” a major impact;

3.“D” denotes a short-term impact and “C” a long-term impact.

4.2 Environmental impact analysis

4.2.1 Construction period

The term of this construction work, which will be divided into sections and done by stages, runs from 2013 to March, 2017. During the construction, it is inevitable to occupy the land and tread on plants, causing damage to local ecological environment. Besides, noise, waste water, fugitive dust, stench, mud and other side effects resulted from construction will exert ill influence on the surrounding environment.

1. Wastewater

Sand gravels used in this project are outsourced with no need for washing in site, and only some simple mechanical maintenance will be done on the construction site without cleaning. Therefore, the waste water, generated within construction time, were mainly the remaining water of dredging engineering and sewage of the construction crew’ life.

(1) Remaining water of dredging engineering

The project applies dredging of cofferdam dry field way in its branches, and hydraulic dredging in the downstream of Cihu river. The sediments will be transported to the sediment yard through piles. So the waste water from the dredging engineering was mainly the supernatant fluid. The main pollution factors of the supernatant fluid is SS, which affects little to the surface water after precipitation, and could discharge into Cihu river directly.

(2) Sewage of the construction crew’ life

The sewage of the construction crew’ life containing water pollution factors such as COD, NH3-N and SS. See Table 3-1 for the number of workers and construction period for each construction section.

2. Waste gas

The impact upon air environment mainly comes from air pollutants within the construction period, mainly fugitive dust, malodorous gas , and waste gas emission.

(1) Fugitive dust

Fugitive dust is mainly generated in the processes such as the transportation and stacking of materials, river dredging, dam reinforcement etc., where with the help of wind, the construction site and their surrounding will be polluted. In addition, passing transport vehicles will cause second pollution of fugitive dust on the road. Measures, such as regular road-surface watering, stacked materials covering and transport vehicles blanketing, are designed in this project to control fugitive dust within construction period.

(2) Malodorous gas

Malodorous gas , mainly NH3-N and H2S, will emerge during dredging and the stacking of bottom mud, and its intensity generally ranks level two or three, according to analog data.

(3) Influence of waste gas emission

Waste gas, which is mainly caused by the fuel burning of construction machinery and transport vehicles, includes smoke, sulphur dioxide, nitrogen oxides, carbon monoxide, and other pollutants.

3. Noises

Noises, engendered by construction machinery such as excavators, auto-dumpers, bulldozers, dredge pumps, generally range from 90 to 95 dB(A)and will have certain negative influence on sound-sensitive places along the river.

Therefore, low-noise equipments are planned to be used in this project, and other measures will also be carried out in order to alleviate noise impact, such as reasonable time management, proper equipment arrangement, and fencing etc.

4. Solid waste

Solid waste produced in this construction includes dredging sediments, waste solid and domestic garbage of workers.

(1) River bottom sediment

This project will carry out dredging with hydraulic way in the downstream of Cihu, which amounts to 77,000m3,. This project will also carry out dredging with cofferdam dry field in its branches, which amounts to 95,000 m3. The sediments will transport to the Xiangshan Life landfill site as the sealing field overlying soil.

(2) Waste slag

This project is balance of cut and fill, without any need to set up borrow area or spoil ground. The earth from slope cutting and revetment could be used in the dike enforcement. The waste slag are mainly the construction waste from the reconstruction of the 5 pumping stations, which the estimated area of demolition is 1000 m2, the waste slag index from demolition area is 1350kg/m2, so the estimated construction slag is 1350t. The waste slag will be transported to the third construction slag deposition field, which located in the upstream watershed of Cihu river, 12km away from downstream.

(3)Domestic garbage

Within construction time, domestic garbage will be produced by workers in their daily life. Domestic garbage shall be stacked at fixed point instead of mixing with building waste, and should be delivered to places designated by sanitation departments to be treated timely.

5. Impact on ecological environment

The influences on the ecological environment within construction period fall into the following four aspects: firstly, disturbance and damage to soil and plants caused by the trampling of machines, vehicles and workers during watercourse dredging and widening, pumping station construction and so on; secondly, change of land use patterns resulted from temporary or permanent land occupation; thirdly, reduction of farming and vegetation area due to land occupation, which will have a negative effect on agricultural production; and finally, certain soil erosion may happen if re-vegetation fails in temporary occupied area.

6. Impact on social environment

This project doesn’t involve housing demolition and relocation. The main impacts of immigration are the acquisition of collectively-owned and national-owned land. The total land acquisition are 1788.89 mu., including 1253.89mu. collective-owned land, which are all non-prime arable land. The permanent land acquisition of national-owned land is 535 mu., which are all unused land along the river and branches. According to Measures for Land Expropriation Compensation and Resettlement in Ma’anshan Municipality, compensation will be made to the affected persons.

4.2.2 Operation period

Since this is a water environment treatment project, no waste gas or water will be produced during runtime. And the impact on surrounding environment comes from the operation noises of pumping stations.

This project plans to demolish and re-construct the five pumping stations along the downstream of Cihu River, each of which will be equipped with 3 pumps. And the power of each pump in Tongyi (No.2), Zhaoming, and Xiaonanwei pumping stations will come to 250kw and that in Sulfuric Acid Plant and Tailai 180kw. In the operation of pumping stations, noises mainly come from the operation pump motors, the noise intensity of each of which ranges between 75 and 85dB (A)

5 Environmental management procedures

Environmental management procedures cover design, construction and operation periods

Environmental management procedures include the General environmental management measures during construction and operation period, specific environmental management measures during construction period (related to the sensitive points).

5.1 Generic Environmental Code of Practices

The generic ECOPs showed in table 7

Table 7 Generic ECOPs

Items

PMitigation Measures

Implementation units

Supervision units

Design period

Balance the earthwork, do not setup extra spoil ground

Design consulting unit

Municipality project office

The sediment yard should be set up within the blue line of land acquisition to avoid the exact land occupation.

Construction period

Preparation period

Confirm land occupation and Relevant formalities

contractors

Ma’anshan Caishi River & Cihu River Comprehensive Development Co. LTD,, Environmental Protection Bureau of Ma’anshan municipality

Atmospheric environment

Materials that are easy to produce dust shall be humidified or shielded with tarpaulin from wind in temporary storage.

Watering over dust points and roads 4-5 times at regular time every day.

Strengthen the management of transport vehicles; in the process of transportation, the materials should be sealed with tarpaulin.

Earthwork should stop in the windy days of greater than Level 4 winds

Use commercial concrete

Machines and vehicles should be chosen according to the National health protection standard, to guarantee the tail gas and smoke to meet emission standards.。

Surface water environment

The constructors could use the civil infrastructure in the nearby villages

contractors

Ma’anshan Caishi River & Cihu River Comprehensive Development Co. LTD,, Environmental Protection Bureau of Ma’anshan municipality

Apply advance equipments to control strictly leakage of the construction machinery.

Apply Cotton, wood chip, oil absorption to absorb the machinery leakage.

Establish equipment maintenance, maintenance records, conduct regular maintenance according to the operation of equipment;

Repair construction machinery only in nearby private workshop, only consider the replacement of mechanical parts on construction site

Acoustic environment

Strictly control of construction time to avoid the construction between (22:00~06:00), otherwise permit for construction in night must be applied and approved and the public should agree

contractors

Ma’anshan Caishi River & Cihu River Comprehensive Development Co. LTD,, Environmental Protection Bureau of Ma’anshan municipality

Sludge pump should be at least 60m away from the residential areas.

Temporary barrier should be set for the sensitivity points within 40m from the site

Fixed strong noise source should be equipped with sound insulation cover or placed in indoor for operation

Construction unit should only choose the construction machinery and transport vehicles which meet the relevant national standards, try choosing low noise construction machinery

Strengthen the maintenance of all construction equipment, in order to fundamentally reduces the noise and vibration

Solid waste

The construction solid waste should be transported to the third construction waste disposal field of Ma’anshan in time

contractors

Ma’anshan Caishi River & Cihu River Comprehensive Development Co. LTD,, Environmental Protection Bureau of Ma’anshan municipality

Domestic solid waste should be stockpiled on the construction site and transported out for disposal by the sanitation department.

Solid waste and spoil storage sites should be established far away from the river.

Sediments

Set up 4 sediments stockpiling sites within the land to be permanently occupied

Dredging works should not be conducted in summer; meanwhile, the boundary of the sediments storage yard should be controlled. And the distance from the yard to the residential buildings should be more than 30m

contractors

Ma’anshan Caishi River & Cihu River Comprehensive Development Co. LTD,, Environmental Protection Bureau of Ma’anshan municipality

The transportation vehicle should be sealed to avoid scattered and reeking. The transportation line should be away from residential area. the sediments should be transported to the Xinagshan Sanitary Landfill for further drying and use as cover soil.

Landscaping with vegetation after construction is finished

Set sedimentation tank and discharge supernatant from the sediment storage site into Cihu river after sedimentation

.

Water and soil loss

It is better to construct during dry seasons.

contractors

Ma’anshan Caishi River & Cihu River Comprehensive Development Co. LTD,, Environmental Protection Bureau of Ma’anshan municipality

With the aim of restoring the original surface productivity, topsoil layer must be removed and stockpiled before the project construction. The stripping thickness is 0.3m.Conduct land reclamation at the end of construction and refills the topsoil with 30cm thickness for vegetation recovery.。

Retained with woven bag around temporary sediments stockpiling site along the river, to avoid the soil loss to runoff.

Use cement to harden the construction field.

The project construction should be carried out in stages and batches. Mitigation measures should be taken for the exposed surface excavated, trying to minimize the exposure time and reduce the soil and water losses.

Landscape impact control

Enlarging the environmental propaganda, improve the environmental protection consciousness of the management and construction person. Discarding domestic waste without control is banned.

contractors

Ma’anshan Caishi River & Cihu River Comprehensive Development Co. LTD,, Environmental Protection Bureau of Ma’anshan municipality

Strictly define the area of operation

After the completion of the project, garbage should be cleared in time in the construction site. Leveling the ground, try to restore original landform and vegetation,

Cultural relics

If physical cultural relics are found during construction, (including ancient sites and ancient tombs), construction should be suspended immediately. The construction site should be closed and protected under the supervision of the engineering supervisor and report to local cultural departments. Without the permit from the cultural department the construction should not be resumed.

contractors

Ma’anshan Caishi River & Cihu River Comprehensive Development Co. LTD,,, City culture committee

Construction traffic management

Reasonably arrange the project construction schedule, to shorten the temporary land occupation.

contractors

Ma’anshan Caishi River & Cihu River Comprehensive Development Co. LTD,, Environmental Protection Bureau of Ma’anshan municipality

Construction should be scheduled on the basis of section by section to reduce the impact on local residents’ travleling.

Arrange the vehicle route to ensure that local residents travel unimpeded

Before the start of the construction, access roads should be reinforced and reconstructed, or service road connecting with the original road should be built. Serious damage of the road shall be promptly repaired or pay compensation to the local road management departments.

Transportation of construction materials during night should be banned, where there are residents within 50m from the roads.

Construction transport vehicles should avoid local road traffic peak time.

Construction vehicles should be stipulated in the driveway of the road, it is strictly prohibited to change driving route。

Construction safety

Set up warning marks

contractors

Ma’anshan Caishi River & Cihu River Comprehensive Development Co. LTD,,

Equipped the constructors with safety helmets, belts, suits and shoes etc.

Apply low noise equipment, automation technology, to reduce the mechanical noise. Provide earplugs to the workers.

During the high temperature, cooling equipment or materials should be provided in site and the rest schedule should be carefully arranged.

Public participation

At the entrance of the construction site, a bulletin should be set up indicating the project information and content, schedule, and the contact people and hotline;

Ma’anshan Caishi River & Cihu River Comprehensive Development Co. LTD,, Environmental Protection Bureau of Ma’anshan municipality

Environmental professionals will be designated to respond to the public concerns on environmental impacts;.

Where construction at night is necessary, the relevant procedure should be followed and public announcement should be made to the adjacent residents which indicates the timing of the construction and the permit issued by local EPB;

The public concerns or questions raised by local people should be recorded and responded immediately. All the information of the question and response should be kept file and subject to the review of the supervision institution.

Operation period

Pump station noise

Pumps with low noise should be selected in the pumping stations and the base for the pumps should be cushioned.

Contractors

Ma’anshan Caishi River & Cihu River Comprehensive Development Co. LTD,,

5.2 Site-specific environmental Mitigation Measures

The Environment Mitigation Measures to the sensitive points are showed in table 8.

Table 8 Site-specific Mitigation Measures

Issue

Protection and Mitigation Measures

Unit price

(yuan)

Amount

total price

(10 thousan yuan)

Implement units

Supervison units

Noise

Setup temporary fences at Anhui industial university

with height of 1.8m, length of 230m

300

230

6.9

Engineering contractors

Ma’anshan Caishi River & Cihu River Comprehensive Development Co. LTD,, Environmental Protection Bureau of Ma’anshan municipality

Setup temporary fences at Fenzhuang village Xiaxi group with height of 1.8m, length of 50 m

300

50

1.5

Setup temporary fences at Shuguang No.1 village and Cihu community, with height of 1.8m, length of 220m

300

220

6.6

Setup temporary fences at Tangchalou village,height of 1.8m, length of 320m

300

320

9.6

Setup temporary fences at Shiqiao village, height of 1.8m, length of 50m

300

50

1.5

6. Environmental Management6.1 Environmental Protection Management Plan6.1.1 The overall goal of environmental management

Gradually implement the design, construction and operation of the proposed projects on the basis of project design scheme and the prevention and mitigation measures laid down in environmental evaluation documents by formulating systematic, scientific environmental management plan to achieve the coordination between project construction and environmental protection by coinciding the design, construction and utilization of environmental protection measures and main construction work and reducing the impacts of project construction and operation on ecological environment, acoustic environment and ambient air to the limited scope required by relevant laws & regulations and standards.

6.1.2 Environmental management institutions

Institutions of environmental management showed in Fig. 8-1 and table 8-1.

Table 8-1 Institutions of environmental management

Type

Name

Duty

Management institutions

Municipality project office

Responsible for project implementation and management, Appoint special environment administrator, Responsible for the project environmental protection work in planning, design and implementation stages, Determine the working procedures to meet the domestic and the world bank’s requirements of environmental assessment and environmental management, Responsible for monitoring the implementation of the environmental management plan, Ensure environmental reduction measures were included in the bidding documents and contract, Responsible for the implementation of Component 4, See detailed in chapter ‘8.1.3 Duties and personnel allocation of the environmental management system agencies’

Ma’anshan Caishi River & Cihu River Comprehensive Development Co. LTD.

Responsible for the implementation of Component 1 and 2, Appoint special environmental protection specialist, for environmental protection acceptance after project completion, for daily environmental supervision and management during project construction period, make the environmental adverse effect reduced to minimal or acceptable level, Implement all the necessary project funds of environmental protection work, collected and archive the relevant documents, See detailed in chapter ‘8.1.3 Duties and personnel allocation of the environmental management system agencies’.

Environmental Protection Bureau of Ma’anshan municipality

Responsible for the implementation of Component 3

Supervision institutions

The world bank inspection Group

Send environmental technology experts, Supervise and inspect the implementation of the environmental protection practice, See detailed in chapter ‘8.1.3 Duties and personnel allocation of the environmental management system agencies’.

Environmental Protection Bureau of Ma’anshan municipality

Supervise and inspect whether the project procedures meet China's environmental management requirements, and whether the pollution prevention and control measures meet the needs of environmental protection in China. See detailed in chapter ‘8.1.3 Duties and personnel allocation of the environmental management system agencies’.

Implementation institutions

Civil engineering contractors

Appoint site environment supervision engineers,

Carry out the environmental protection and water and soil conservation content in the contract and the bidding documents, Meet the environmental protection requirements of the world bank and the local administrative department of environmental protection, Preparation and submission environmental report during construction period monthly, See detailed in chapter ‘8.1.3 Duties and personnel allocation of the environmental management system agencies’.

Consulting services institutions

EIA consulting unit

Prepare the EIA report, See detailed in chapter ‘8.1.3 Duties and personnel allocation of the environmental management system agencies’.

Design consulting unit

Prepare feasible research report and construction design scheme, and to ensure that the measures in environmental management plan applied in the feasible research report and construction design scheme. See detailed in chapter ‘8.1.3 Duties and personnel allocation of the environmental management system agencies’.

Environmental supervision unit

supervision and management the daily production of the construction unit, See detailed in chapter ‘8.1.3 Duties and personnel allocation of the environmental management system agencies’.

Monitoring institutions

Environmental monitoring agency

Responsible for the environmental monitoring during the project construction period and operation period, See detailed in chapter ‘8.1.3 Duties and personnel allocation of the environmental management system agencies’.

Municipality project office

Contractors

Ma’anshan Caishi River & Cihu River Comprehensive Development Co. LTD.

Environmental monitoring agency

Design consulting unit

EIA consulting unit

Environmental Protection Bureau of Ma’anshan municipality

Environmental supervision unit

Municipality project office

Environemtal Management and implementation institutions during operation period

Environemtal Management and implementation institutions during Design stage, construction period

Fig.8-1 Institutions setup

6.1.3 Duties and personnel allocation of the environmental management system agencies

The integrated environmental management system comprises project management institution, regulatory institution, implementation institution, consulting service institution, monitoring institution. All institutions have different duties. The Leading Group Office for Ma’anshan Cihu River Project under World Bank Loan is leading the operation of the projects, ensure the local and world bank’s requirements are fulfilled. The implementation unit is Ma’anshan Caishi River & Cihu River Comprehensive Development Co. LTD. see detailed in table 8-2.

Table 8-2 Duties and personnel allocation of the environmental management system agencies

Name

Type

Person

Duties

World bank

Supervision institutions

1

1. Sent inspection group to conduct special inspection on project implementation every year

1. Inspect implementation of the agreement of loan and the EMP

Environmental Protection Bureau of Ma’anshan municipality

Supervision institutions

1

1. Environmental monitoring and supervise and manage this project in accordance with the process, including: approvement of project environmental impact assessment report, Environmental monitoring and supervision and management during contruction and operation

Municipality project office

Management institutions

2

1. Supervise the implementation of EMP, Ensure EMP measures were included in the bidding documents and contract, organize trainings

1. Coordinate the implementation of local and world bank’s requirements of environmental managemnt

1. Submit the related report to the world bank every half year

1. Check the environmental management work

1. Coordinate with other departments on major environmental problems

1. Entrust external environment expert group for the project inspection

Ma’anshan Caishi River & Cihu River Comprehensive Development Co. LTD.

Management institutions

1

1. Supervise the implementation of the project environment management rules and regulations

2. Supervises and coordinates the engineering supervision (Qualification, responsibilities, management)

3. Organization research or the relevant investigation

4. Record the complaints during the engineering construction and operation process, public the processing results, solve problems of public appeal

5. Review environmental supervision and environmental consulting report

6. submit reports or forms every quarter

7. sign the Site check list of construction units and supervision units reported, checked and documented.

8. Accept environmental work inspection (including the world bank’s inspection)

EIA consulting unit

EIA consulting institutions

Several

1. Conduct field surey and assess the environmental impacts,

1. Prepare the EMP and provide consulting service

Engineering Project Supervisor (Environmental supervision)

Consulting service institutions

1-2

1. Engineering Project Supervisor hired by the project office individually, supervise the implementation of the water and soil loss control, garbage, exhaust gas and noise control measures,

1. Regular fill in the environmental management check list of Environmental protection Norms and procedures

1. Propose solution to the environmental problem raised in the construction period

1. Submit reports or forms every week to the project office

Engineering contractors

Implementation institutions

Several

1. Prepare environmental protection measures during construction period

1. Accept the environmental supervision and inspection from Engineering Project Supervisor, World Bank and Environmental Protection Bureau,

1. Establish a feedback mechanism to conduct rectify and reform in 3 days after informed, (ten days if coordination with management institutions is needed)

1. Finish the Construction site check list with Engineering Project Supervisor, and submit to the project office.

1. report to the Engineering Project Supervisor every week.

Environmental monitoring agency

Monitoring institutions

1-2

1. Conduct environmental monitoring during project construction and operation periods, according to the monitoring scheme

6.2 Environmental Monitoring Plan6.2.1 Formulate objectives and principles

Environmental monitoring shall be carried out promptly on the basis of the environmental impact prediction results to keep track of the potential new problems and the various degrees of impact the project may have on environment and provide foundation for implementation time and scheme of environmental protection measures by promptly adjusting action plan on the basis of monitoring results.

6.2.2 Environment monitoring agency

Monitoring can be entrusted to Ma’anshan municipal environmental monitoring station Construction unit shall sign monitoring agreement related to construction period with monitoring station before construction and sign monitoring agreement related to operation period before the delivery for use of the project.

6.2.3 Environmental monitoring scheme

Take sensitive focus points with more apparent character for pollution as the monitoring points on the basis of the environmental impact prediction results and select acoustic environment, ambient air easily to be impacted as monitoring content on the basis of pollution conditions during construction period and operation period. Monitoring factor shall be determined by pollution characteristics factor in project analysis, monitoring analysis methods adopt that related to the project specified in Environmental Monitoring Technical Specifications and evaluation criterion follows national standards confirmed by Environmental Impact Assessment (EIA).Confirm environmental monitoring content during construction period and operation period, according to project and environmental characteristics. See Table 8-3 for specific information.

Table 8-5 Environmental monitoring plan during construction period and operation period

Period

Environmental factor

Monitoring content

Monitoring indicators

Monitoring location

Monitoring time and frequency

Executive standards

Monitoring cost (RMB Ten thousand Yuan)

Daily monitoring unit

Regular supervision unit

Construction period

Atmospheric environment

Construction raised dust

TSP

5 Sensitive points along the line

Once each year during construction peak period

Class II standard for Ambient Air Quality Standard

0.10

Municipal environmental monitor station or qualified monitor units

Environmental protection bureau

Odour

H2S, NH3

Sediment yard

Xiangshan Landfill

Once within usage period of 4 sediment yards

Sediment drying site in landfill

Class II Emission standards for odor pollutants

0.32

Acoustic environment

Noise from construction machinery

Leq

5 Sensitive points along the line

One construction peak time each year and monitoring its operation once at both daytime and night.

Class II of Environmental quality standard for Noise in

0.10

Wastewater

Supernatant from settling tanks of sediments yards

SS

Sediments settling tanks

Once per week

Class II of Wastewater integrated Discharge Standard

0.4

Sediments1

Sediments quality in the section to be dredged in Cihu River

Total metal

Same location with the surface water monitoring points

One time, one columnar sample each time

Ambient Soil Quality Standard

1.0

Qualified Environmental Monitoring Institute

Surface water

Surface water quality in Cihu River

COD,NH3-N,TP,pH, SS,DO

Auto monitoring station financed under the project

Once per month

Class V of Surface Water Environmental Standard

200

Ma’anshan Environmental Monitoring Center

Operation period

Acoustic environment

Draining pump station running noise

Leq

1m out of pump station field

Monitoring its operation once each year during draining pump station operation period and once at both daytime and night

Class III of Industrial enterprise Field Environmental Noise standard

0.10

Total

202.02

Note: 1. prior to the dredging works in Cihu River, the contractor should engage an independent qualified institute to sample and test the sediments in accordance with relevant domestic requirements. In case that if the sediments are found to be hazardous materials, they should be handled on site with relevant hazardous waste management regulations and requirements in Chin and EHS, and sent to the secured facility for proper disposal. Based on the information available, there is only one hazardous waste disposal center in Shenyang capable of disposing of hazardous soil/sediments in such large quantity. So if the sediments are found to be hazardous, they will sent to Shenyang Hazardous Waste Disposal Center.

6.3 EMP training program6.3.1 Training purpose

The purpose of the EMP training is to guarantee the successful operation of the environmental management, to make the associate staff to be familiar with the content and procedure of the environmental management, to build ability of environmental management and to ensure the effectively implement of all environmental protection measures. The main objects of environment ability construction are environmental managers and environmental superviser. Their training is a part of the project technical support. The training objects also include constructors and workers. Before the construction, all the construction units and management units are require and forced to attend the Environmental, health and safety training.

6.3.2 Training objects

Training objects:project office, implementation untis of each project compenent, all environmental supervisers、represents of environemental monitoring units, major contractors.

6.3.3 Training content

1. The understood and application of The world bank environmental policy and the domestic environmental protection laws and regulations, environmental standards;

2. Environmental management pattern and the environmental loan agreement terms in the World Bank loan project;

3. EMP of the project;

4. the duties and relationships of Environmental management, environmental supervision personnel, environmental monitoring staff and contractors;

5. the preparation of Environmental management work report, environmental supervision work report, environmental monitoring report, the contractor log, monthly report, interim report and annual reports.

6.3.4 Training plans

The major negative environemental impacts came from the contruction period, the relative environmental protection staff should be trained, to enhance the level of environmental management. see detailed in table 8-6.

Table 8-6 Ability building and training plans

topic

Trainging objects

contents

times

day/time

persons/time

budget

(ten thousands)

Environmental protection laws,regulations and policy

Project office, Water Resources Bureau of Ma’anshan municipality, Ma’anshan Caishi River & Cihu River Comprehensive Development Co. LTD., contractors

① Environmental protection laws and regulations

1

0.5

4

0.45

② Environmental policy and planning

1

0.5

4

③ EMP

1

0.5

4

Implementation of EMP

Project office, Water Resources Bureau of Ma’anshan municipality, Ma’anshan Caishi River & Cihu River Comprehensive Development Co. LTD., contractors

①Environmental protection duties during project construction period

1

0.5

4

0.9

② main task of environmental protection during project construction period

1

0.5

4

③ main contents of environmental protection during project construction period

1

0.5

4

④Reports in EMP

1

0.5

4

⑤Improvement or fixed of EMP

1

0.5

4

⑥Monitoring method, data collection method

1

0.5

4

Total

1.35

6.4 Environmental Supervision & Management Plan (ESMP)6.4.1 Environmental supervision organization during the construction period

Environmental supervision during the construction period means the environmental protecting efforts to be implemented during the construction period. Environmental supervision work during the construction period must be undertaken by relatively authorized construction supervision organization, which has to have special environmental supervision engineer taking charge of environmental management and supervision during the construction period.

The environmental supervision unit is responsible for establishing an Environmental Supervision Team (EST) to implement specific supervision and management.

The Environmental Supervision Team EST needs to initiate the specific environmental supervision plan, in accordance with Environmental Impact Report hereto in terms of content of environmental supervision, meanwhile, conforming to the practical situation, and afterwards, Environmental Supervision Team should submit such environmental supervision plan to the related environmental authority and the construction unit.

6.4.2 Guideline of environmental supervision

Any unit performing environmental supervision shall practice under the guideline of legal principle, integrity and reasonability. In order to establish and identify the core-principle of environmental supervision p, as a Third Party, the obligation of environmental supervision unit & property owner and the authority must be strictly separated, and environmental supervision unit shall firmly stick to the principle of serving the property owner and the authority. It is especially important to maintain and confirm the inter-relationships among the property owner, the construction unit, the Engineering Supervision& Management Unit, the environmental supervision unit, the environmental monitoring unit, and the related authorities, for the purpose of creating favorable condition for the ESM works. The environmental supervision unit shall, according to the characteristics of the engineering hereto, establish a supervision and management rule that is regular and suitable for the practical condition, in order to standardize the engineering hereof.

6.4.3 Environmental supervision scope

1. Environmental supervision scope

The construction area and the project direct-influencing area include the construction site, walkway of the permanent and temporary work and the existed local roads involved with large number of transportation.

Content of environmental supervision: comprehensive ecological protection, planting, pollution control, public environment, etc.

2. Scopes of Project

Include all the areas polluted by the construction sites, construction roads and the construction above mentioned.

3 Periods of environmental supervision

The environmental supervision of the construction project comprises three main periods, which namely are preparing period, construction period, and delivery, acceptance, and defect liability period.

6.4.4 Work pattern of environmental supervision

Environmental supervision must be dynamically managed according to the project progress. Environmental supervision of the project is based on regular inspection, at large, and necessary environmental monitoring as supplement in order to promptly adjust the environmental supervision strength. Major pollutant construction procedure shall be supervised and managed throughout the entire construction in order to make sure all the contractors have fulfilled their obligation in accordance with the related environmental protection law, administrative regulations and conditions and terms as stated in the Contract.

The environmental supervisor is required to learn the content, in the Environment Impact Report, concerned of the said engineering

6.4.5 Specific working procedure of environmental supervision

An Environmental Supervising Unit, who strictly complies with the conditions and terms as stated in the Contract and the relative laws and administrative regulations, is a economically independent third party standing alone with regard to the property owner and the contractor. Such Environmental Supervising Unit’s obligation is implementing every work under the guideline of justice and independence, that is, it shall secure the legal rights and interests of both the property owner and the contractor. Meanwhile, as a environmental supervision Unit is a important component of environmental supervision, it is closely related to ESM and stand alone and boast differences to some extent. The specific environmental supervision procedure is as follows:

1. Review whether the environmental protection measures devised in preliminary design drawing of project has been implemented in line with the approved environmental protection measures in environmental impact statement;

2. Assist the construction unit to organize the environmental protection training for staff in construction, design and management;

3. Verification of the Tender Document and the terms of Engineering Contract involved with environmental protection.

4 Presentation of environmental-protection advice and suggestion concerning with construction organization plan, technical plan, and construction progress plan, on-site verification of construction equipment, etc.

5 Supervise the measures of reducing the influence generated thereby to the ecological environment, the water, the atmosphere and the acoustic environment and the construction quality of the environmental protection engineering, and conduct stage acceptance and signature in accordance with the relative standards.

6 Conduct regular patrol and supervision on a daily basis; and systematically record environmental influence, practical effect, and construction quality of the environmental protection engineering.

7 As for any environmental problem found in the inspection, Record and give oral notification or form memorandum and demand the contractor to make a rectification within a deadline.

8 Supervise the main polluting source in the site of construction area; if necessary, advice the property owner on employing specialist and qualified monitoring unit to implement environmental implementation; and appropriately deal with existing environmental problem according to the monitoring result. As for major environmental problem, which is required the contractor to deal within a deadline, issue the Rectification Notice for Environmental Problems after negotiation with the owner

9 Promptly reflect to the Leading Team of environmental supervision on the concerned problem of environmental protection design and emerging construction problems, and present solution advice.

10. Take responsibility for drafting the environmental supervision work plan and summary

6.4.6 Environmental supervision organization and work system.

In order to make the environmental management work conduct smoothly, the engineering environmental supervision is included into the engineering supervision system. The construction unit shall entrust a unit with engineering qualification and has been trained for environmental protection operation to undertake the engineering environmental supervision.

The main work content of the environmental supervision mainly includes: work record, worker environment training, report, correspondence, regular meeting, award & punishment and filing of environmental supervision,.

6.4.7 Engineering environmental supervision plan

1. Construction preparation stage

Examine the practical implementation of the environmental protection specified in the Construction Contract, verify the concerned environmental protection measures of the construction organization plan, verify, optimize and review the construction area with the undertaking unit, design unit, engineering supervision unit, and the construction unit. See Table 8-7 for environmental supervision plan.

Table 8-7 Environmental supervision emphasis during the construction preparation period

Construction Activities

Supervision emphasis

Supervision methods

Means

Construction bidding

Compile engineering environment supervision work Plan

Review and terms on environmental protection in the Construction Contract

Document review

Review of sensitive items and protected object on the construction site.

Inspection

Field recording

Review the environmental measures of the construction organization plan made by the contractor.

Document review

Verification of the environmental managing plan during the construction period made by the contractor.

Document review

Verification of the construction plan and the related environmental protection plan during the application of the sections.

Document review

2. Construction stage

The environmental supervision during the construction shall be implemented along with the engineering, which mainly include river desilting, dam reinforcement, pumping station construction, etc. See Table 8-8 for Supervision Plan

Table 8-8 Main environmental supervision content during the Construction Period

Environmental factor

Supervision object

Main environmental supervision content

Main environmental supervision forms

Solutions of excessive pollutants or violation.

Water environment

Construction sites

Reinforce management and maintenance of the construction machines, discharge remaining water of sediment yard into Cihu river after sedimentation.

Patrolling and inspecting the temporary land occupancy.

Notice the undergoing unit and the construction unit for remedial measure.

Ambient air

①Transportation and stocking of building materials; ②Sediment yard

① Transporting vehicles need to transport materials with all the materials sealed; the unloading site needs to be prepared with dust-control measure, and such sites need to be watered on a regular basis. ②There shall be no more than 30m distance between the Sediment yard and residential area

Conduct air quality monitoring and inspect all the construction areas and the temporary land occupancy.

Notification of remedies to the undergoing unit and the construction unit.

Acoustic environment

①Construction and transportation Road

②Construction area

① Appropriately arrange construction Time Plan

②Using low-noise equipment

③ Setup fences around sensitivity points

Conduct acoustic environment monitoring and inspect all the construction areas and the temporary land occupancy.

Notify the undergoing unit and the construction unit for remedial measure.

Social environment

Major construction sites

①Reduce the influence of the construction on transportation to the local city, for example, by avoiding the rush hour.

Inspect the construction site during the construction period, and learn the local inhabitants’ feelings who live about the construction sites.

Noticing the undergoing unit and the construction unit for remedial measure.

Ecological environment

Temporary land occupation

Ecological restoration of temporarily-occupied areas

Identify the location of temporarily-occupied areas which should be patrolled during the construction time, and an inspection of the restoration shall be guaranteed when construction is finished

Notify for remedies to the contractor and the construction unit.

3. Delivery, Acceptance and Defects Liability Period

Summarizing the data on environment protection acceptance after the completion of the project, construction of the environment protection engineering, and restoration and maintenance of the construction site and temporarily-occupied areas in the defects liability period are among the main tasks during this period.

6.4.8 Document compilation of environmental supervision

1. General plan compilation of environmental protection supervision

General plan of environmental protection supervision refers to that when an environmental protection supervision unit accepting a business entrustment , it shall develop a plan on the environmental protection supervision of the project according to the Contract, environment assessment requirements, construction plan and the actual conditions of construction , to identify the range, content, methods and goals of the work of environmental protection supervision.

2. Implementing rules compilation of environmental protection supervision

Based on the general plan of environmental protection supervision, the implementing rules of environmental protection supervision are interpreted as the executable documents made by professional environmental protection supervision engineers from the project environmental protection supervision institution for the purpose of the compilation of single construction. Implementing rules shall be made according to the actual conditions of the construction and environment assessment requirements.

3. General report compilation of environmental supervision

When environmental supervision work ends, the environmental supervision organization shall make a prompt summery and deliver the construction unit a general report, which mainly includes the implementation summary of the commission supervision Contract, evaluation of supervision tasks and goals implementation.

6.4.9 Environmental supervision archives management

Environmental supervision archives shall include relevant documents and data of environmental supervision.

1. Documents of environmental supervision mainly include plan, implementing rules, general report, etc of environmental supervision.

2. Environmental supervision data mainly include:

① Daily work log: Mainly recording the work of environmental supervision, and the measures environmental supervision members take and their implementation when unexpected situation happens;

②Monthly environmental supervision report: Summarizing and documenting the work of environmental supervision during the month and record the work content and the measures environmental supervision members take and their implementation when unexpected situation happens;

③Correspondences between the environmental supervision unit and the property owner and other documents on construction unit and other relevant materials.

Archives management of the environment supervision shall formulate relevant management systems and assign the specified staff to be responsible for the gathering, classification, sorting and filing of various environmental supervision data, which are significant to the acceptance and management of the project environment protection.

6.5 Public complaints and feedback mechanism6.5.1 Public complaints mechanism

Public complaints mechanism of the immigrants should be established, besides the official ones, in order to make the problems rasied during compilation and implementation of the project can be effectively solved, and to gurantee the implementation of land acquisition and project construction. The public complaints mechanism should be as following:

Stage 1 If any rights violations happened during the land acqusition, the immigrants could report to local management departments, or to the municipality petition offices directly. The petition office should record the complaints and negociate with local management departments and petitioners for solutions in 2 weeks.

Stage 2 If the petitioners do not satisfied with the solutions come out in stage 1, the petitioners could lodge a complaint to the Leading Group Office for Ma’anshan Cihu River Project under World Bank Loan, after the solution decision of stage 1 was made. The project office should response in 2 weeks.

Stage 3 If the petitioners do not satisfied with the solutions come out in stage 2, after the solution decision of stage 2 was made, the petitioners could lodge a complaint to the administrative departments, according to the ‘Administrative Procedure Law of the Peoples Republic of China’. Ask for arbitration.

Stage 4 If the petitioners still do not satisfied on the arbitration, they could prosecute to the Civil court, according to the Civil Procedural Law.

The immigrants could complain about all aspects including the compasation standard, during the immigration resettlement.

The Public complaints mechanism will be inform to the immigrants through meentings and other effective ways, including the media.

No charge on the petitioners, all cost paid by the contingencies.

6.5.2 Public feedback mechanism

Establish a pulic feedback mechanism, The EIA units and construction units should respond to the environmental complaint and rectification notice immediately, and public the solutions. Problems should be solved in 3 days (10 days if coordination with management institutions is needed)

The feedback mechanism divided into 2 stages:

Stage 1: The construction unit and the EIA unit should conduct meetings and questionnaires to collect residents’s opinions. The public could purpose suggestions and opnions through meetings, questionnaires, letters, phonecalls, fax, emails. Also written opinion to the administrative department of environmental protection is available. The construction unit, the EIA unit and the administrative department of environmental protection should backup and document the original files.

Stage 2: The public could purpose suggestions and opnions through letters, phonecalls, fax, emails, petition office and Environmental Protection Bureau of Ma’anshan municipality to the construction unit, during the project construction and operation period;

According to the public opinions, based on the environmental monitoring reports and supervision reports, modifications and improvement should be made in the EMP.

If major deviations are found, or the modification of project will raise extra massive negative environmental impacts or extra influened people, the project office should consult the EIA cousulting units and the EIA group founded by World Bank, to conduct extra EIA. If necessary, extra public consulting is needed as well. The modified EMP shold be copied to the construction units and contractors to inform them the modified contents.

6.6 Report mechanism of Environmental management plan6.6.1 Reorganize and save of Monitoring data

Implement based on the ‘Environmental monitoring technical specifications’ and ‘Soil and water conservation monitoring procedures’. 4 copies of original monitoring data and files should be submitted to the administrative department of environmental protection as backup and to the designing units as a information feedback.

6.6.2 Information exchange

Necessary information exchange was required among the different departments and duties by the environmental management, meanwhile to the external (relative units and public).

Internal information exchange could be conducted by meetings and briefs, at least once a month of the meeting. All information exchanged should be recorded and filed.

External information exchange could be held annually or once half year, which also should be recorded and filed.

6.6.3 Recording

For the effective operation of environmental management, the organization should establish a comprehensive recording system, include following aspects of recording:

(1)Laws and regulations;

(2)license;

(3)Environmental factors and the relevant environmental impact;

(4)training;

(5)Examination, check and maintenance activities

(6)Monitoring data

(7)problem in Environmental management and environmental protection work

(8) Corrective and preventive measures effectiveness;

(9)Related party information;

In addition, necessary control should be done on above all kinds of records, including: Records identification, collection, cataloging, filing, storage, management, maintenance, query, retention time, disposal and so on.

6.6.4 Reports

The project office, environement supervision units should record and report to the relevant departments in time, of the progress of the project, management plan (EMP) implementation, environmental quality monitoring results, etc in the project implementation process, including:

(1) Records of the execution of the EMP and the Monitoring data should be submitted to the project office as weekly report and monthly report, by the environmental supervision engineer.

(2) Quarterly project progress report, including the progress of EMP, should be prepared by the Ma’anshan Caishi River & Cihu River Comprehensive Development Co. LTD., and submitted to the project office and the Environmental Protection Bureau of Ma’anshan municipality.

(3) The monitoring report should submitted to the project office and environmental supervision engineer in time as long as it been prepared.

(4) Project progress report prepared by the project office (such as monthly report, quarterly report and yearly report) should be included the progress of EMP and effects, especially the monitoring results.

(5) Environmental supervision engineer and the project office should report to the local administrative department of environmental protection, even the higher administrative department, when violation in environment happens.

(6) Annual implementation report of EMP should be hand into the world bank before the March 31st of the next year. Annual implementation report of EMP should include:

a The implementation of the training plan;

b Project progress,

c Implementation of environmental protection measures, environmental monitoring and results,

d Whether there is any public complaint, if there is any complaint, records the main content, solutions and public satisfaction,

e The implementation plan of EMP next year.

6.7 Investment Estimation of Environment Protection

The total cost of environmental management is 69.7 thousand yuan, see table 8-9.

Table 8-9 Estimation of Environmental Management Cost

Item

Environmental monitoring

(Thousand yuan)

Environmental supervision (Thousand yuan)

Training

(Thousand yuan)

合计(Thousand yuan)

The World Bank-financed

Ma'anshan Cihu River Basin Improvement Project

6.2

50

13.5

69.7