COST PLANNING
Presented by: Joe Martin, BCIS Executive Director
Date: 19 May 2009
-
7/27/2019 106273976-Cost-Planning-RIBA-05-09
2/17
RIBA London CPD, 19-May-09
What is it going to cost? Early cost advice
Order of cost estimate
Setting a budget
Developing a cost plan From elementals to design elements
From elements to trades
Life Cycle Cost Planning
-
7/27/2019 106273976-Cost-Planning-RIBA-05-09
3/17
RIBA London CPD, 19-May-09
RIBA/BCIS Building Cost Calculator
BCIS Onl ine
BCIS Building Running Costs Onl ine
-
7/27/2019 106273976-Cost-Planning-RIBA-05-09
4/17
RIBA London CPD, 19-May-09
What is it going to cost?
-
7/27/2019 106273976-Cost-Planning-RIBA-05-09
5/17
RIBA London CPD, 19-May-09
What cost do we mean?
Capital Cost
Best Value
Life Cycle Cost
Most Economically Advantageous Tender
Whole Life Cost
Whole Life Value
-
7/27/2019 106273976-Cost-Planning-RIBA-05-09
6/17
RIBA London CPD, 19-May-09
What are we going to cost
Schedule of functional requirements
Schedule of accommodation
Sketch design
Outline design
-
7/27/2019 106273976-Cost-Planning-RIBA-05-09
7/17
RIBA London CPD, 19-May-09
What are we going to cost?
Schedule of accommodation
Offices 5000m2
Shops 1000m2Catering 1000m2
Theatre 500m2
Archive 2000m2
-
7/27/2019 106273976-Cost-Planning-RIBA-05-09
8/17
RIBA London CPD, 19-May-09
What are we going to cost?
-
7/27/2019 106273976-Cost-Planning-RIBA-05-09
9/17
RIBA London CPD, 19-May-09
What are we going to cost?
Bunker solution (QS design?)
Everything else needs to represent
added value to the client
-
7/27/2019 106273976-Cost-Planning-RIBA-05-09
10/17
RIBA London CPD, 19-May-09
Developing a cost plan
-
7/27/2019 106273976-Cost-Planning-RIBA-05-09
11/17
RIBA London CPD, 19-May-09
Developing the cost plan
Costing at Appraisal, Design Brief Benchmark estimates
Costing the functional requirements
Sets the budget
Costing at concept design Part functional
Part costing a design
Costing as design develops Costing a design solution
-
7/27/2019 106273976-Cost-Planning-RIBA-05-09
12/17
RIBA London CPD, 19-May-09
Developing the cost plan
Costing at Appraisal, Design Brief Cost per m2 building
Cost per m2 elements
Costing at concept design Cost per element unit quantities
Cost of designed elements, composite
Costing as design develops Costing a design solution
-
7/27/2019 106273976-Cost-Planning-RIBA-05-09
13/17
RIBA London CPD, 19-May-09
Elements and designed elements
Element
Frame
Designed elementSteel Frame
Weight (tonnes)
Designed elementConcrete
Length (m)
Designed elementTimber
Area (m2)
-
7/27/2019 106273976-Cost-Planning-RIBA-05-09
14/17
RIBA London CPD, 19-May-09
Design elements and trades
Designed element
Profiled sheet cladding
'Trade'Brickwork
'Trade'Blockwork
'Trade'Insulation
'Trade'Etc
Designed element
Brick/block
Designed element
curtain walling
Element
External walls
-
7/27/2019 106273976-Cost-Planning-RIBA-05-09
15/17
RIBA London CPD, 19-May-09
Developing the cost plan
NRM
New Rules of Measurement Order of cost
estimating and elemental cost planning
Provides a structured basis for measuring building work and
presenting a consistent approach for dealing with other key
cost components associated with a building project. The rules
represent essential good practice
-
7/27/2019 106273976-Cost-Planning-RIBA-05-09
16/17
RIBA London CPD, 19-May-09
Life cycle cost plan
-
7/27/2019 106273976-Cost-Planning-RIBA-05-09
17/17
RIBA London CPD, 19-May-09
COST PLANNING
Presented by: Joe Martin, BCIS Executive DirectorDate: 19 May 2009