    COST PLANNING

    Presented by: Joe Martin, BCIS Executive Director

    Date: 19 May 2009

  • 7/27/2019 106273976-Cost-Planning-RIBA-05-09

    2/17

    RIBA London CPD, 19-May-09

    What is it going to cost? Early cost advice

    Order of cost estimate

    Setting a budget

    Developing a cost plan From elementals to design elements

    From elements to trades

    Life Cycle Cost Planning

  • 7/27/2019 106273976-Cost-Planning-RIBA-05-09

    3/17

    RIBA London CPD, 19-May-09

    RIBA/BCIS Building Cost Calculator

    BCIS Onl ine

    BCIS Building Running Costs Onl ine

  • 7/27/2019 106273976-Cost-Planning-RIBA-05-09

    4/17

    RIBA London CPD, 19-May-09

    What is it going to cost?

  • 7/27/2019 106273976-Cost-Planning-RIBA-05-09

    5/17

    RIBA London CPD, 19-May-09

    What cost do we mean?

    Capital Cost

    Best Value

    Life Cycle Cost

    Most Economically Advantageous Tender

    Whole Life Cost

    Whole Life Value

  • 7/27/2019 106273976-Cost-Planning-RIBA-05-09

    6/17

    RIBA London CPD, 19-May-09

    What are we going to cost

    Schedule of functional requirements

    Schedule of accommodation

    Sketch design

    Outline design

  • 7/27/2019 106273976-Cost-Planning-RIBA-05-09

    7/17

    RIBA London CPD, 19-May-09

    What are we going to cost?

    Schedule of accommodation

    Offices 5000m2

    Shops 1000m2Catering 1000m2

    Theatre 500m2

    Archive 2000m2

  • 7/27/2019 106273976-Cost-Planning-RIBA-05-09

    8/17

    RIBA London CPD, 19-May-09

    What are we going to cost?

  • 7/27/2019 106273976-Cost-Planning-RIBA-05-09

    9/17

    RIBA London CPD, 19-May-09

    What are we going to cost?

    Bunker solution (QS design?)

    Everything else needs to represent

    added value to the client

  • 7/27/2019 106273976-Cost-Planning-RIBA-05-09

    10/17

    RIBA London CPD, 19-May-09

    Developing a cost plan

  • 7/27/2019 106273976-Cost-Planning-RIBA-05-09

    11/17

    RIBA London CPD, 19-May-09

    Developing the cost plan

    Costing at Appraisal, Design Brief Benchmark estimates

    Costing the functional requirements

    Sets the budget

    Costing at concept design Part functional

    Part costing a design

    Costing as design develops Costing a design solution

  • 7/27/2019 106273976-Cost-Planning-RIBA-05-09

    12/17

    RIBA London CPD, 19-May-09

    Developing the cost plan

    Costing at Appraisal, Design Brief Cost per m2 building

    Cost per m2 elements

    Costing at concept design Cost per element unit quantities

    Cost of designed elements, composite

    Costing as design develops Costing a design solution

  • 7/27/2019 106273976-Cost-Planning-RIBA-05-09

    13/17

    RIBA London CPD, 19-May-09

    Elements and designed elements

    Element

    Frame

    Designed elementSteel Frame

    Weight (tonnes)

    Designed elementConcrete

    Length (m)

    Designed elementTimber

    Area (m2)

  • 7/27/2019 106273976-Cost-Planning-RIBA-05-09

    14/17

    RIBA London CPD, 19-May-09

    Design elements and trades

    Designed element

    Profiled sheet cladding

    'Trade'Brickwork

    'Trade'Blockwork

    'Trade'Insulation

    'Trade'Etc

    Designed element

    Brick/block

    Designed element

    curtain walling

    Element

    External walls

  • 7/27/2019 106273976-Cost-Planning-RIBA-05-09

    15/17

    RIBA London CPD, 19-May-09

    Developing the cost plan

    NRM

    New Rules of Measurement Order of cost

    estimating and elemental cost planning

    Provides a structured basis for measuring building work and

    presenting a consistent approach for dealing with other key

    cost components associated with a building project. The rules

    represent essential good practice

  • 7/27/2019 106273976-Cost-Planning-RIBA-05-09

    16/17

    RIBA London CPD, 19-May-09

    Life cycle cost plan

  • 7/27/2019 106273976-Cost-Planning-RIBA-05-09

    17/17

    RIBA London CPD, 19-May-09

    COST PLANNING

    Presented by: Joe Martin, BCIS Executive DirectorDate: 19 May 2009