11/08/2001 FSW/GS Splinter Meeting 3 rd FSW/GS Splinter November 8, 2001 @ Bal COS WFC3 (morning session, auditorium O. Lupie, WFC3 STScI Review of Goals and Action Items from last time (O. Lupie)--5 min WFC3 and COS Instrument Development Status (G. Blue)--10 min WFC3 FSW Status and Schedule (G. Blue)--20 min WFC3 MOU & Ground System Development Status (O. Lupie & W. Baggett)--15 min Consolidated WFC3 Schedule (B. Rehm) --20 min Break 20 minutes COS FSW Status and Schedule (G. Blue) --20 min COS MOU & Ground System Development Status (C. Keyes & Wayne Baggett)--15 min WFC3 ICAL Status and Schedule (D. Fineberg) – 15 minutes Transition Planning (Grant Blue) --15 min Discussion & Lunch Agenda 1

Upload: adele-snow

Post on 16-Dec-2015

212 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 11/08/2001 FSW/GS Splinter Meeting 3 rd FSW/GS Splinter November 8, 2001 @ Ball COS WFC3 (morning session, auditorium) O. Lupie, WFC3 STScI Review of Goals

11/08/2001

FSW/GS Splinter Meeting 3rd FSW/GS SplinterNovember 8, 2001 @ BallCOS

WFC3

(morning session, auditorium)

O. Lupie, WFC3 STScI

Review of Goals and Action Items from last time (O. Lupie)--5 min

WFC3 and COS Instrument Development Status (G. Blue)--10 min

WFC3 FSW Status and Schedule (G. Blue)--20 min

WFC3 MOU & Ground System Development Status (O. Lupie & W. Baggett)--15 min

Consolidated WFC3 Schedule (B. Rehm) --20 min

Break 20 minutes

COS FSW Status and Schedule (G. Blue) --20 min

COS MOU & Ground System Development Status (C. Keyes & Wayne Baggett)--15 min

WFC3 ICAL Status and Schedule (D. Fineberg) – 15 minutes

Transition Planning (Grant Blue) --15 min

Discussion & Lunch

Agenda

1

Page 2: 11/08/2001 FSW/GS Splinter Meeting 3 rd FSW/GS Splinter November 8, 2001 @ Ball COS WFC3 (morning session, auditorium) O. Lupie, WFC3 STScI Review of Goals

11/08/2001

FSW/GS Splinter Meeting 3rd FSW/GS SplinterNovember 8, 2001 @ BallCOS

WFC3

(morning session, auditorium)

O. Lupie, WFC3 STScI

Schedule and schedule drivers review.

Provide forum for discussion.

Linkages and Interface clarification.

Improve Information flow.

Next splinter meeting planning.

Talk directly with team counterparts.

Establish perspective – how each piece fits into whole.

Renew commitment for timely information exchange.

Revisit Goals:

2

Page 3: 11/08/2001 FSW/GS Splinter Meeting 3 rd FSW/GS Splinter November 8, 2001 @ Ball COS WFC3 (morning session, auditorium) O. Lupie, WFC3 STScI Review of Goals

11/08/2001

FSW/GS Splinter Meeting 3rd FSW/GS SplinterNovember 8, 2001 @ BallCOS

WFC3

(morning session, auditorium)

O. Lupie, WFC3 STScI

Schedule and schedule drivers review.

Provide forum for discussion.

Linkages and Interface clarification.

Improve Information flow.

Next splinter meeting planning.

Talk directly with team counterparts.

Establish perspective – how each piece fits into whole.

Renew commitment for timely information exchange.

Revisit Goals:

3

Page 4: 11/08/2001 FSW/GS Splinter Meeting 3 rd FSW/GS Splinter November 8, 2001 @ Ball COS WFC3 (morning session, auditorium) O. Lupie, WFC3 STScI Review of Goals

11/08/2001

FSW/GS Splinter Meeting 3rd FSW/GS SplinterNovember 8, 2001 @ BallCOS

WFC3

(morning session, auditorium)

O. Lupie, WFC3 STScI

Action Items from March 27th Splinter1. Plan for WFC3 and COS splinter at Ball Summer 2001 CLOSED2. Initiate Tracking of WFC3 FSW and Ground System Development CLOSED (Brian, Grant, Olivia, Wayne)

[tracking and dependencies now included in Thai’s development schedule]3. Initiate Tracking of COS FSW and Ground System Development OPEN (unassigned)4. WFC3 and COS need updated schedules for the delivery of test data suites CLOSED (G. Blue)5. Investigate merging of stimulus keywords with science data keywords – CLOSED – Plan OK (ICAL)6. WFC3 MOU updated to reflect new schedules and March 27 splinter CLOSED - O. Lupie7. WFC3 MOU to address real-time TV support and connection to STScI CLOSED – O. Lupie8. Investigate COS and WFC3 Transition Plan Requirements IN WORK B. Friedman to present @ splinter.9. Scrub DRD Delivery Dates CLOSED (G. Blue)10. Get COS and WFC3 Timing Tests on Grant’s Schedule – Grant to work with Tom Wheeler INWORK 11. Address Fire-Wall issues for remote access to COS and WFC3 Telemetry CLOSED

Closed Actions from previous splinters:Have SISEs participate in WOWG and COWG CLOSED (R. Henry, STScI)Address details of Tom Wheelers’ support of ACS, COS< and WFC3 timing tests CLOSED (C. Blades, STScI)Link from GSFC Private WFC3 pages to GSFC FSW/OPS site CLOSED (Ball)Provide Instructions to Ball and GSFC for accessing the STScI OPR system CLOSED (W. Baggett, STScI)DM-05 to be placed on Web CLOSED (M. Draugelis, Ball)

Page 5: 11/08/2001 FSW/GS Splinter Meeting 3 rd FSW/GS Splinter November 8, 2001 @ Ball COS WFC3 (morning session, auditorium) O. Lupie, WFC3 STScI Review of Goals

11/08/2001

FSW/GS Splinter Meeting 3rd FSW/GS SplinterNovember 8, 2001 @ BallCOS

WFC3

(morning session, auditorium)

O. Lupie, WFC3 STScI

STScI - WFC3 Achievements since last time:

Ops Telecon support: New error message review process is working well.Ground System: functionality available for basic UVIS Accum, IR Multi-

Accum, Lamp Operation, Darks/Biases (Mike Robinson, Wayne Baggett).

WFC3 Pipeline and Archive CDR – held on 10/16/2001 (Howard Bushouse)Delivery of AV-03 (Calibration Requirements) – October, 2001.

TV Science Calibration report submission (Neill Reid, Frank Bartko).

TV software support information gathering meeting – 08/2001.

Recommendation for TV Data Handling System submission – 10/2001.

ICA

LF

ron

t-en

dP

ipel

ine

5

Page 6: 11/08/2001 FSW/GS Splinter Meeting 3 rd FSW/GS Splinter November 8, 2001 @ Ball COS WFC3 (morning session, auditorium) O. Lupie, WFC3 STScI Review of Goals

11/08/2001

FSW/GS Splinter Meeting 3rd FSW/GS SplinterNovember 8, 2001 @ BallCOS

WFC3

(morning session, auditorium)

O. Lupie, WFC3 STScI

STScI WFC3 Memorandum of Understanding:

Driven by Thermal Vac.

Documents interfaces/dependencies Ball, STScI, GSFC,

ICAL.

Now focuses on two categories of STScI support:

Long-Term – OPUS Pipeline processing and long term Hubble Archive Storage.

Time-Critical- Specialized system for quick-look analysis with real-time archive.

recent addition

6

Page 7: 11/08/2001 FSW/GS Splinter Meeting 3 rd FSW/GS Splinter November 8, 2001 @ Ball COS WFC3 (morning session, auditorium) O. Lupie, WFC3 STScI Review of Goals

11/08/2001

FSW/GS Splinter Meeting 3rd FSW/GS SplinterNovember 8, 2001 @ BallCOS

WFC3

(morning session, auditorium)

O. Lupie, WFC3 STScI

5. Delivery of WFC3 OPS Test Bench Images – March 1, 2002 Source: Grant Blue, Ball

Recipient: WFC3 Science IPT

6. Completion of Code and Unit Test Build 3.0 – March 30, 2002Source: Grant Blue, BallRecipient: STScI – ESS (T. Wheeler & FSET )

7. Delivery of Images from the Integrated Optical Bench - June 1, 2002.Source: Grant Blue, BallRecipient: WFC3 Science IPT

8. Delivery of TV-Specific and Optical Stimulus Keywords Initial version –October 31, 2001, Complete version – May, 2002

Source: WFC3 ICAL Recipient: WFC3 Science IPT

Key MOU Items – version 10/15/2001

7

Page 8: 11/08/2001 FSW/GS Splinter Meeting 3 rd FSW/GS Splinter November 8, 2001 @ Ball COS WFC3 (morning session, auditorium) O. Lupie, WFC3 STScI Review of Goals

11/08/2001

FSW/GS Splinter Meeting 3rd FSW/GS SplinterNovember 8, 2001 @ BallCOS

WFC3

(morning session, auditorium)

O. Lupie, WFC3 STScI

9. Delivery of TV-Specific and Optical Stimulus Keywords Initial version 10/31/2001, Complete version 05/2002. Source: WFC3 ICAL Recipient: WFC3 Science IPT (H. Bushouse, WFC3 Pipeline and Archive)

11. OPUS Staging Disk Implementation – December, 2002 Source: WFC3 ICAL Recipient: STScI OPUS

12. Delivery of Beta Version of OPUS - June 1, 2002 (Final Version October 2002) Source: STScI OPUS Recipient: WFC3 Science IPT and WFC3 ICAL

Key MOU Items – version 10/15/2001

8

Page 9: 11/08/2001 FSW/GS Splinter Meeting 3 rd FSW/GS Splinter November 8, 2001 @ Ball COS WFC3 (morning session, auditorium) O. Lupie, WFC3 STScI Review of Goals

11/08/2001

FSW/GS Splinter Meeting 3rd FSW/GS SplinterNovember 8, 2001 @ BallCOS

WFC3

(morning session, auditorium)

O. Lupie, WFC3 STScI

Thermal VAC

Beta OPUS

Final OPUS

TV Readiness Test

Test Bench “Early” Images

Test Bench Image Suite

Build 3 C/U Complete

ICAL ProtoTesting

DM-06 – snapshot telemetry and internal header data

SMGT

Integrated Optical Bench Images

Archive

OPUSKeywords

JUN, 2003

DEC, 2002

JUN, 2002

DEC, 2001

MAR, 2002

SEPT, 2002

MAR, 2003

SEPT, 2001

Science SMS Testing Begins

Complete SMS Testing for SMGT

OS, TV Keywords

ICAL Development

Version October 15, 2001

Pipeline/Archive Front End

TV Cal SupportTV

KEY

SMS timing trials

9

Page 10: 11/08/2001 FSW/GS Splinter Meeting 3 rd FSW/GS Splinter November 8, 2001 @ Ball COS WFC3 (morning session, auditorium) O. Lupie, WFC3 STScI Review of Goals

11/08/2001

FSW/GS Splinter Meeting 3rd FSW/GS SplinterNovember 8, 2001 @ BallCOS

WFC3

(morning session, auditorium)

O. Lupie, WFC3 STScI

STScI Ground System Development Linkages:

1yr between Build 3 C/U & SMGT

2mo between Full Suite Ops Bench Images and Beta OPUS

4mo between Beta OPUS and Final OPUS Deliveries

Final Opus ready for TV Readiness Test – Dec, 2002

2mo from TV Readiness Test to start of TV.

10

Page 11: 11/08/2001 FSW/GS Splinter Meeting 3 rd FSW/GS Splinter November 8, 2001 @ Ball COS WFC3 (morning session, auditorium) O. Lupie, WFC3 STScI Review of Goals

11/08/2001

FSW/GS Splinter Meeting 3rd FSW/GS SplinterNovember 8, 2001 @ BallCOS

WFC3

(morning session, auditorium)

O. Lupie, WFC3 STScI

SEPT, 2001

Thermal VAC@ GSFC

TV Readiness Test

DM-06

SMGT

OPUSKeywords

JUN, 2003

DEC, 2002

JUN, 2002

DEC, 2001

MAR, 2002

SEPT, 2002

MAR, 2003

OS, TV Keywords

BETA OPUS

Final OPUS

ICAL ProtoTesting

Archive

Start SMS Testing

Complete SMS Testing

ICAL Development

ICAL limited to test of real-time system

Archive not ready forTV Readiness. No test-time

SMS timing trials

Minimal testing of Final OPUS; no ICAL tests

Test Bench “Early” Images

Test Bench Image Suite

Build 3 C/U Complete

Integrated Optical Bench Images

Version November 1, 2001

Pipeline/Archive Front End

TV Cal SupportTV

KEY

Schedule-Incompatibility

1-2 month slip

Incomplete SMS testing. Risk final Phase development effort. 11