Risk Analysis and Management

Page 2: 11_SoftwareRisks

Look Out!!

• If you don't actively attack the risks, they will actively attack you.– Tom Gilb

Page 3: 11_SoftwareRisks

Risk Characteristics

• uncertainty – an risk may or may not happen

• loss – an risk has unwanted consequences or losses

Page 4: 11_SoftwareRisks

Risk Definitions• Risk is the potential for realization of unwanted

negative consequences of an event. – [Rowe, William D. An Anatomy of Risk 1988]

• Risk is the measure of the probability and severity of adverse effects.

– [Lowrance, William W. Of Acceptable Risk 1976]

• Risk is the possibility of suffering loss, injury, disadvantage, or destruction. – [Webster's Third New International Dictionary 1981]

Page 5: 11_SoftwareRisks

MIS Risks

Risk Occurrences

Creeping user requirements 80

Excessive schedule pressure 65

Low quality 60

Cost Overruns 55

Inadequate Conf. Control 50

Page 6: 11_SoftwareRisks

System Software Risks

Risk Occurrence

Long schedule 70

Inadequate cost estimation 65

Excessive paperwork 60

Error-prone modules 50

Cancelled Projects 35

Page 7: 11_SoftwareRisks

Commercial Software Risks

Risk Occurrences

Inadequate User documentation

70

Low User satisfaction 55

Excessive time to market 50

Harmful competitive actions 45

Litigation expenses 30

Page 8: 11_SoftwareRisks

Defense Software Risks

Risk Occurrences

Excessive paperwork 90

Low productivity 85

Long Schedules 75

Creeping user requirements 70

Unusable software 45

Page 9: 11_SoftwareRisks

Contract Software Risks

Risk Occurrences

High Maintenance costs 60

Contractor Vs Client frictions 50

Creeping user requirements 45

Unanticipated acceptance criteria

30

Legal ownership 20

Page 10: 11_SoftwareRisks

End-user Software Risks

Risk Occurrences

Non-transferable applications 80

Hidden errors 65

Non maintainable software 60

Redundant applications 50

Legal Ownership 20

Page 11: 11_SoftwareRisks

Risk Analysis

– Risk Identification– Risk Projection– Risk Assessment– Risk Management

Page 12: 11_SoftwareRisks

Risk Identification

• Project Risks • Technical Risks • Business Risks

Page 13: 11_SoftwareRisks

Project Risks

• Potential budgetary, schedule, personnel, resources, customer and requirements problems and their impact.

• Project complexity, size and structural uncertainty are determining factors.

Page 14: 11_SoftwareRisks

Technical Risks

• Potential design, implementation, interfacing, verification and maintenance problems.

• Specification ambiguity, technical uncertainty, technical obsolescence and leading edge technology.

Page 15: 11_SoftwareRisks

Business Risks • Market Risk

– building a product that no one really wants.

• Product Risks– building a product that no longer fits into the

overall product strategy for the company.– building a product that the sales force doesn't

understand how to sell.

• Management Risk: – losing the support of senior management due to a

change in focus or people.

• Budget Risk– losing budgetary or personnel commitment.

Page 16: 11_SoftwareRisks

Risk-item checklist

• Product size• Business impact• Customer characteristics• Process definition• Development environment• Technology to be built• Staff size and experience

Page 17: 11_SoftwareRisks

Product size risks

• Estimated size of the product in LOC or FP?

• Estimated size of product in number of programs, files, and transactions?

• Percentage of deviation in size of product from average for previous products?

• Size of database created or used by the product?

Page 18: 11_SoftwareRisks

Product size risks

• Number of users of the product?• Number of projected changes to

the requirements for the product?• Number of changes before

delivery? After delivery?• Amount of reused software?

Page 19: 11_SoftwareRisks

Business impact risks• Effect of this product on company revenue?• Visibility of this product by senior

management?• Reasonableness of delivery deadline?• Number of customers who will use this

product and the consistency of their needs relative to the product?

• Number of other products or systems with which this product must be interoperable?

• Sophistication of end users?

Page 20: 11_SoftwareRisks

Business impact risks• Amount and quality of product

documentation that must be produced and delivered to the customer?

• Governmental regulatory constraints on the construction of the product?

• Costs associated with late delivery?• Costs associated with a defective

product?

Page 21: 11_SoftwareRisks

Customer characteristics risks

• Have you worked with the customer in the past?

• Does the customer have a solid idea of what is required? Will the customer agree to spend time in FAST meetings to identify project scope?

• Is the customer willing to establish rapid communication links with the developer?

Page 22: 11_SoftwareRisks

Customer characteristic risks• Is the customer willing to participate in

reviews?• Is the customer technically

sophisticated in the product area?• Is the customer willing to let your

people do their job i.e., will the customer resist looking over your shoulder during detailed technical work?

• Does the customer understand the SE process?

Page 23: 11_SoftwareRisks

Process definition risks• Does your senior management support a

written policy statement that defines a process for software development?

• Are specific documentation formats defined?

• Are formal technical reviews of the SRS, design, test procedures and test cases and code conducted regularly?

• Is SCM used to maintain consistency among system /software requirements, design, code, and test cases?

Page 24: 11_SoftwareRisks

Process definition risks• Is more than 90 % of your code written

in a high-order language?• Are software tools used to support

planning and tracking activities?• Are CASE tools used to support the

software analysis and design process, prototyping, test support, documentation?

• Are quality and productivity metrics collected for all software projects?

Page 25: 11_SoftwareRisks

Technology risks• Is the technology to be built new to your

organization?• Do the customer’s requirements

demand the creation of new algorithms or input or output technology?

• Does the software interface with new or unproven hardware?

• Does the software to be built interface with vendor-supplied software products that are unproven?

Page 26: 11_SoftwareRisks

Technology risks• Does the software to be built interface with

a database system whose function and performance have not been proved in this application area?

• Is a specialized user interface demanded by product requirements?

• Do requirements for the product demand the creation of program components that are unlike any previously developed by your organization? What percentage of components are new?

Page 27: 11_SoftwareRisks

Technology risks• Do requirements demand the use of new

analysis, design, or testing methods?• Do requirements demand the use of

unconventional software development methods, such as formal methods, AI based approaches, or artificial neural networks?

• Do requirements put excessive performance constraints on the product?

• Is the customer uncertain that the functionality requested is “doable”?

Page 28: 11_SoftwareRisks

Checklist for staffing risk• Are the best people available? • Are enough (too many) people available? • Do the people have the right combination of

skills? • Have staff members received the necessary

training? • Is the staff committed for the entire project

duration? • Will some staff members only be part time? • Will staff turnover be low enough for continuity?

Page 29: 11_SoftwareRisks

Risk Projection (Estimation)

• Attempts to rate each risk in two ways: – Likelihood that the risk is real. – Consequences of the problems

associated with the risk, should it occur.

Page 30: 11_SoftwareRisks

Risk projection activities

• Establishing a scale that reflects the perceived likelihood of a risk: Boolean, qualitative, quantitative

• Delineating the consequences of a risk.

• Establishing the impact of the risk on the project and the product.

• Noting the overall accuracy of the risk projection.

Page 31: 11_SoftwareRisks

Probability Quantification

impossible toimprobable

probable frequent value

Prob. value (0, 0.4) (0.4, 0.7) (0.7, 1)Performance ------------- -------------Cost ------------- -------------Schedule ------------- -------------support ------------- -------------

Page 32: 11_SoftwareRisks

Risk Drivers

Performance Cost Schedule support

Requirements Requirements Resources Design

Constraints Personnel Need dates Responsibilities

Technology Reusable SW Technology Tools, env

Dev. approach Tools, env Requirements Supportability

Page 33: 11_SoftwareRisks

Impact Assessment

Performance Cost Schedule support

Catastrophic

Critical

Marginal

negligible

Page 34: 11_SoftwareRisks

Risk Assessment

frequent probable improbable impossible

Prob. value (0.7, 1) (0.4, 0.7) (0, 0.4) 0

catastrophic

critical

marginal

negligible

HIGH

MODERATE

LOW

NONE

Page 35: 11_SoftwareRisks

Factors affecting Impact• Risks are weighted by perceived impact and

then prioritized. Three factors affect impact: • The nature of the risk indicates the

problems that are likely if it occurs. • The scope of a risk combines its severity

with its overall distribution. • The timing of a risk determines when and

for how long the impact will be felt. • The importance of risk impact and

probability is linked to their effect on management concerns.

Page 36: 11_SoftwareRisks

Risk Assessment

Risks can be represented as a set of triplets of the form: [r,l,x] where – r is risk – l is the likelihood (probability) of

the risk – x is the impact of the risk.

Page 37: 11_SoftwareRisks

Risk Assessment

During risk assessment the following actions occur: – An examination of the accuracy of the

estimates made during risk projection. – A prioritization of the risks that have

been uncovered. – A preliminary examination of the ways

to control and/or avert likely risks.

Page 38: 11_SoftwareRisks

Risk Referent Level • At a certain level of risk, or a combination

of risks, a project will have to be terminated.

• A risk referent level has a single point, called the referent or break point, at which time the decision to proceed or terminate are equally acceptable.

• Cost, schedule, support and performance represent typical risk referent levels.

Page 39: 11_SoftwareRisks

Risk Referent Level

Projected cost overrun

Pro

ject

ed s

ched

ule

over

run

Referent point

High risk area

Page 40: 11_SoftwareRisks

Risk Assessment Checklist

• Define the risk referent levels for the project. Referents are stated as a probability of failure or the probability of success level for each individual risk or the system as a whole.

• A value should be agreed upon where it is decided that a project should not continue.

Page 41: 11_SoftwareRisks

The system risk referent can be: • an aggregate of individual risks, or one or

more prioritized high impact risks • Attempt to develop a relationship between

each [r,l,x] and each of the referent levels. • Predict the set of referent points that

define a region of termination, bounded by a curve or areas of uncertainty.

• Try to predict how compound combinations of risks will affect a referent level.

Page 42: 11_SoftwareRisks

Risk Evaluation Outcomes

Comparing the evaluated risk against its risk referent has three possible outcomes:

1.Acceptable : the evaluated risk is less than the referent.

2.Impossible : the evaluated risk is much greater than the referent.

3.Infeasible : the evaluated risk is greater than, but almost equal to, the referent.

Page 43: 11_SoftwareRisks

What is Risk Management?

• Making informed decisions by consciously assessing what can go wrong and the severity of its impact.

• A comprehensive risk management strategy, as part of total quality management approach, aims at anticipating and eliminating all the causes of risk

Page 44: 11_SoftwareRisks

Why Do Risk Management

– Eliminate surprises– Anticipate issues - prevent

problems– Begin programs on the "right"

foot and stay on track– Reach business goals

Page 45: 11_SoftwareRisks

SEI Risk Management Paradigm

Page 46: 11_SoftwareRisks

RMMP Outline

I. Introduction II. Risk analysis III. Risk managementIV. Appendixes

Page 47: 11_SoftwareRisks

RMMP - Introduction A. Scope and purpose of documentB. Overview

1. Objectives, 2. Risk aversion priorities

C. Organization1. Management, 2. Responsibilities, 3. Job descriptions

D. Aversion program description1. Schedule, 2. Major milestones and reviews, 3. Budget

Page 48: 11_SoftwareRisks

RMMP - Risk analysis

A. Identification1. Survey or risks, a. Sources of risk, 2. Risk taxonomy

B. Risk estimation1. Estimate probability of risk, 2. Estimate consequence of risk, 3. Estimation criteria, 4. Possible sources of estimation error

C. Evaluation1. Evaluation methods to be used, 2. Method assumptions and limitations, 3. Risk referents, 4. Results

Page 49: 11_SoftwareRisks

RMMP - Risk management

A. RecommendationsB. Risk aversion optionsC. Risk aversion recommendationsD. Risk monitoring procedures

Page 50: 11_SoftwareRisks

IV. Appendixes

A. Risk estimate of the situationB. Risk abatement plan

Page 51: 11_SoftwareRisks

References

• Assessment and Control of Software Risks– Capers Jones

• http://www.baz.com/kjordan/swse625/htm/tp-rm.htm

• http://www.leitner.org/courses/du/isys420-0103/risks.pdf

• http://www.sei.cmu.edu/organization/programs/sepm/risk/