12 plaxis bulletin-with shotcrete

Upload: geomahesh

Post on 01-Jun-2018

241 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/9/2019 12 Plaxis Bulletin-with Shotcrete

    1/24

    P L X S P L X S Nº 12 - JUNE 2002

    Editorial

    Some time has passed since the appearance

    of our last bulletin no 11, but the PLAXIS

    team did not sit still. Not only was a new

    director appointed for PLAXIS B.V. which

    will be introduced further on, also a

    number of other new team-members havecome to work for PLAXIS. The Plaxis-team

    has extended with four new people in

    order to improve the capability to

    accommodate for the demand on new

    plaxis developments. The Plaxis-team

    consist of 14 people. In the next bulletin,

    we will briefly introduce them to you.

    New Developments which will be discussed in

    the contribution by Dr Brinkgreve, the head ofour development team. He will discuss further

    developments such as for the release of Plaxis

    Version 8, the progress on the PLAX-flow

    program and the other 3D developments. With

    respect to PLAXIS 2D, Version 8 is due to be

    expected after the summer holidays, as Beta

    testing of this new program is underway, and

    the users in our regular PLAXIS course in

    Noordwijkerhout in January and also the

    attendants of the advanced course have hadsome opportunity to experience this new

    program.

    In his regular column Prof. Vermeer will discuss

    the use of soil parameters and especially

    parameter estimation. Not always is it possible

    to do a direct test for a parameter. Or sometimes

    in a pre-design stage there is only limited

    information of the soil stratification. In that case

    it is often very convenient to have some

    correlations between different soil-parameters

    in order to be able to proceed with a

    geotechnical design. In this issue Prof. Vermeer

    discusses Oedometer stiffness of Soft Soils.

    In addition to the aforementioned, Prof.

    Schweiger who also is a regular contributor toour bulletin discusses the relation between

    Skemptons pore pressure parameters A and B

    and the performance of the Hardening Soil

    model.

    Furthermore we are fortunate to have new

    contributions with respect to Benchmarking;

    two contributions on benchmarking are

    presented here, one on Shield tunnelling and

    another on excavations.

    Again we are glad to have a number of practical

    applications; Among which are a contribution

    by Dr. Gysi, on a multi-anchored retaining wall,

    and another one by Mr. Cheang from

    Singapore on a complicated retaining wall with

    Jack-In Anchors.

    Finally in the Users Forum it is shown how a

    more complicated 3D situation of a Retainingwall with anchors is practically modelled with

    PLAXIS 2D.

    Editorial Staff:

    Martin de Kant, Plaxis Users Association (NL)

    Marco Hutteman, Plaxis Users Association (NL)

    Peter Brand, Plaxis B.V.

    Scientific Committee:

    Prof. Pieter Vermeer, Stuttgart University

    Dr. Ronald Brinkgreve, Plaxis bv

    1

    Bulletin of the

    PLAXISUsers Association (NL)

    Plaxis bulletinPlaxis B.V.P.O. Box 5722600 AN DelftThe NetherlandsE-mail:[email protected]

    IN THIS ISSUE:

    Editorial 1

    Column Vermeer 2

    New developments 4

    Note on pore pressure 6

    Benchmarking I 9

    Benchmarking II 12

    Recent Activities 13

    Plaxis practice I 14

    Plaxis practice II 17

    Users forum 22

    Some Geometries 22

    Agenda 24

  • 8/9/2019 12 Plaxis Bulletin-with Shotcrete

    2/24

  • 8/9/2019 12 Plaxis Bulletin-with Shotcrete

    3/24

    P L X S be seen in Fig. 1. Engel ’s data for * leads toFigures 2 and 3. From Fig. 2 it can beconcluded that the correlation

    * 0.3l p has some shortcomings. A close

    inspection shows that it is nice for clays with

    plasticity indices above the A-line in

    Casagrande ’s plasticity chart, but not for silts

    with I p below the A-line. To include such silts

    one could better use the correlation,

    * 0.2(w L- 0.1) as demonstrated in Fig. 3. On

    plotting * as a function of the liquid limit, asdone in Fig. 3, it is immediately clear that there

    is an extremely nice correlation.

    It should also be recalled that the correlation

    * 0.2(w L- 0.1) is not only supported by

    Engel ’s database, but that it is also fully in line

    with the work of Wroth & Wood as well as

    Terzaghi & Peck on correlations for C c.

    Let us now consider the oedometer stiffness.

    To this end the logarithmic compression law

    = * . ln ’ can be written in the differential

    form d /dln = * and one obtains

    d ’/ d = ’/ The tangent stiffness in

    oedometer-compression, also refered to as

    the constrained modulus, is thus proportionalto stress. Hence, E oed = '/ *, where E oed is also

    denoted as M or E s, depending on conventions

    in different countries. This linear stress

    dependency of soil stiffness is nice for fine-

    grained NC-soils, but not for coarse-grained

    ones. Therefore Ohde (1939) and Janbu (1963)

    proposed a generalisation of the form:

    Eoed = Eoed ( '/P ref )m with P ref = 100kPa (4)

    where m is an empirical exponent. This

    equation reduces to the linear stress

    dependency of soil stiffness for m=1.

    In the special case of m=1, one thus obtains

    the logarithmic compression law for fine-

    grained NC-soils. For coarse grained soils, much

    lower exponents of about m=0.5 are reported

    by Janbu (1963), Von Soos (2001) and other

    researchers.

    The above power law of Ohde, Janbu and Von

    Soos has been incorporated into the Hardening

    Soil Model of the Plaxis code. Here it should be

    noted that the above authors define

    Eoed = v. P ref , where v is a so-called modulus

    number. Instead of the dimensionless modulus

    number, the Hardening Soil Model involves

    Eoed as an input parameter, i.e. the constrained

    modulus at a reference stress of

    ’= p ref = 100kPa. For the coming Version 8 ofthe Plaxis code, we have also considered the

    use of alternative input parameters. Instead of

    Eoed , we have discussed the modulus number

    1/ * as well as the modified compression index

    itself, as it yields

    * P ref / E oed (5)

    In fact, this simple relationship between the

    oedometer stiffness and the modified

    compression index triggered our thinking on

    alternative input parameters. Finally we decided

    3

    Fig. 2: Compression indices as measured by Engel as a

    function of I p

    ref

    ref

    ref

    ref

    ref

    Fig. 3: Compression indices

    correlate nicely with the liquid limit

  • 8/9/2019 12 Plaxis Bulletin-with Shotcrete

    4/24

    P L X S to go one step further and use the traditionalcompression index C c by implementing theequations:

    Eoed =P ref =

    (1+e) ln10. P ref (6)* Cc

    Within the new Version 8, users will have thechoice between the input of E oed and the

    alternative of C c. Similarly, the so-called swelling

    index C s will be used as an alternative input

    parameter for the unloading-reloading stiffness

    Eur . On inputting C c one also has to prescribe

    a value for the void ratio.

    Here, a default value of e=1 will be introduced.

    This will make the Hardening Soil Model easier

    to use in the field of soft soil engineering.

    P.A. Vermeer, Stuttgart University

    REFERENCES:

    Engel, J., Procedures for the Selection of

    Soil Parameters (in German), Habilitation study,

    Department of Civil Engineering, Technical

    University of Dresden, 2001, 188 p.

    Janbu, N., "Soil Compressibility as Determinedby Oedometer and Triaxial Tests", Proceedings

    3rd European Conference on Soil Mechanics

    and Foundation Engineering, Vol. 1,

    Wiesbaden, 1963, pp. 19-25.

    Ohde, J. , "On the Stress Distribution in the

    Ground" (in German), Bauingenieur, Vol. 20, No.

    33/34, 1939, pp. 451-459.

    Terzaghi, K. and Peck, R. B., "Soil Mechanics inEngineering Practice", 2nd Ed, John Wiley and

    Sons, New York, 1967, 729 p.

    Soos von, P., "Properties of Soil and Rock" (in

    German), Grundbautaschenbuch, Vol. 1, 6th

    Ed., Ernst & Sohn, Berlin, 2001, pp. 117-201

    Wroth, C. P. and Wood, D. M. , "The Correlation

    of Index Properties with Some Basic

    Engineering Properties of Soils", Canadian

    Geotechnical Journal, Vol. 15, No. 2, 1987, pp.

    137-145.

    New Developments

    In a few months, Plaxis version 8 will be

    released. This new 2D program is one of the

    results of a recently finished two-years project on Plaxis developments. Another

    results of this project is the 3D Tunnel

    program, which was released last year. In

    this bulletin some new features of Plaxis

    version 8 will be mentioned. The new

    features are divided into three groups:

    Modeling features, calculation options and

    user friendliness.

    MODELING FEATURES

    Plaxis (2D) version 8 has several new features

    for the modeling of tunnels and underground

    structures. Some of these features were

    already implemented in the 3D tunnel

    program, such as:

    - Extended tunnel designer, including thicktunnel linings and tunnel shapes composed

    of arcs, lines and corners.

    - Application of user-defined (pore) pressure

    distribution in soil clusters to simulate grout

    injection.

    - Application of volume strain in soil clusters

    to simulate soil volume loss or

    compensation grouting.

    - Jointed Rock model

    Other new modeling features are aimed at

    the modeling of soil, structures and soil

    structure interaction:

    4

    ref

  • 8/9/2019 12 Plaxis Bulletin-with Shotcrete

    5/24

    P L X S - Input of Skempton's B-factor for partiallyundrained soil behavior.- Hinges and rotation springs to model beam

    connections that are not fully rigid.

    - Separate maximum anchor forces

    distinction between extension and

    compression).- De-activation of interface elements to

    temporarily avoid soil-structure interaction

    or impermeability.

    - Special option to create drains and wells for

    a groundwater flow calculation.

    CALCULATION OPTIONS

    Regarding the new calculation options, most

    new features are in fact improvements of

    'inconsistencies' from previous versions.Examples of such improvements are:

    - Staged Construction can be used as loading

    input in a Consolidation analysis.

    - A Consolidation analysis can be executed as

    an Updated Mesh calculation.

    - In an Updated Mesh calculation, the update

    of water pressures with respect to the

    deformed position of elements and stress

    points can be included. In this way, the

    settlement of soil under a continuousphreatic level can be simulated accurately.

    - Loads can be applied in Staged

    Construction, which enables a combination

    of construction and loading in the same

    calculation phase. The need to use

    multipliers to apply loading has decreased.

    This makes the definition of calculation

    phases more logical and it enhances the

    flexibility to use different load combinations.

    - Preview (picture) of defined calculationphase in a separate calculations tab sheet.

    - Improved robustness of steady-state

    groundwater flow calculations. Simplified

    input of groundwater head boundary

    conditions based on general phreatic level.

    In addition, a separate program for transient

    groundwater flow is planned to be released

    at the end of 2002.

    USER FRIENDLINESS

    Many new features in the framework of 'user

    friendliness' are based on users' suggestions

    from the past. Examples of these features are:

    - Reflection of input data and applied loads

    in the output program.

    - Report generation, for a complete

    documentation of a project (including input

    data and applied loads).

    - Complete output of stresses (effective, total,water), presented both as principal stresses,

    cartesian stresses;

    also available in cross sections and in the

    Curves program.

    - Equivalent force in cross-section plots of

    normal stresses.

    - Force envelopes, showing the maximum

    values of structural forces over all

    proceeding calculation phases.

    - Scale bar of plotted quantities in the outputprogram.

    - Color plots plotted as bitmaps rather than

    meta-files. This avoids the loss of colors

    when importing these plots in other

    software.

    - Parameters in material data sets can be

    viewed (not modified) in Staged

    Construction.

    - User-defined material data set colors.

    A special feature that is available in Version 8 is

    the user-defined soil models option. This

    feature enables users to include self-

    programmed soil models in the calculations.

    Although this option is most interesting for

    researchers and scientists at universities and

    research institutes, it may also be interesting

    for practical engineers to benefit from this

    work. In the future, validated and well-

    documented user-defined soil models maybecome available via the Internet. More

    information on this feature will be placed on

    our web site www.plaxis.nl.

    Registered Plaxis users will be informed when

    the new version 8 is available; they can benefit

    from the reduced upgrade prices. Meanwhile,

    new developments continue. More and more

    developments are devoted to 3D modeling. We

    will keep you informed in future bulletins.

    Ronald Brinkgreve, PLAXIS BV

    5

  • 8/9/2019 12 Plaxis Bulletin-with Shotcrete

    6/24

    P L X S NOTE ON POREPRESSURE

    SOME REMARKS ON PORE PRESSURE

    PARAMETERS A AND B IN UNDRAINED

    ANALYSES WITH THE HARDENING SOILMODEL

    In undrained analyses Skempton ’ s pore

    pressure parameters A and B (Skempton,

    1954) are frequently used to estimate

    excess pore pressures. If we consider triaxial

    conditions, Skempton ’ s equation reads

    u = B [ 3 + A ( 1 - 3 ) ]

    where 1 and 3 are changes in total minor

    and major principal stresses respectively. For

    fully saturated conditions, assuming pore water

    being incompressible, B is 1.0. Furthermore,

    for elastic behav iour of the soil skeleton, A

    turns out to be 1/3.

    A frequently asked question in PLAXIS courses

    is “What pore pressure parameters A and B does

    PLAXIS use”, if an undrained analysis isperformed in terms of effective stresses setting

    the material type to undrained? The answer is

    “You don ’t know ”, except for the trivial cases

    of elastic or elastic-perfectly plastic behaviour.

    In order to investigate this in more detail

    undrained triaxial stress paths are investigated

    with the Mohr Coulomb model with and

    without dilatancy, and with the Hardening Soil

    model. In the latter the influence of variousassumptions of E 50 and E oed has been studied.

    Soil Parameters

    The following parameter sets have been used

    and the model number given below is referred

    to in the respective diagrams. A consolidation

    pressure of 100 kN/m2

    has been applied to alltest simulations followed by undrained

    shearing of the sample.

    Pore Pressure Parameter B

    In order to check the value of parameter B in

    an undrained PLAXIS analysis a hydrostatic

    stress state has been applied after

    consolidation. By doing so, the parameter A

    does not come into picture and B can be

    directly calculated from u and 3 , when

    using undrained behaviour as material type.PLAXIS does not yield exactly 1.0 because a

    slight compressibility of water is allowed for

    numerical reasons and therefore a value of

    0.987 is obtained for the given parameters for

    the Mohr Coulomb model. For the HS model

    the value depends slightly on E 50 and E oed , but

    also on the power m and changes with loading.

    The differences however are in the order of

    about 3.0 to 5.0 % for the parameter sets

    investigated here. So it is correct to say thatSkempton ’s pore pressure parameter B is

    approximately 1.0 in PLAXIS, when using

    undrained behaviour as material type.

    Pore Pressure Parameter A

    The value of parameter A is more difficult to

    determine. However one can evaluate A from

    the results of the numerical simulations and

    this has been done for various parameter

    combinations for the Hardening Soil model andthe Mohr Coulomb model.

    6

    Table 1 Parameter sets for Hardening Soil model

    Model Number E 50 ref Eur ref Eoed ref c ur p ref m K0nc R fkN/m 2 kN/m 2 kN/m 2 ° ° kN/m 2 - kN/m 2 - - -

    HS_1 30 000 90 000 30 000 35 0 / 10 0.0 0.2 100 0.75 0.426 0.9

    HS_2 50 000 150 000 50 000 35 0 0.0 0.2 100 0.75 0.426 0.9

    HS_3 15 000 45 000 15 000 35 0 0.0 0.2 100 0.75 0.426 0.9

    HS_4 30 000 90 000 40 000 35 0 0.0 0.2 100 0.75 0.426 0.9

    HS_5 30 000 90 000 15 000 35 0 0.0 0.2 100 0.75 0.426 0.9

    HS_6 50 000 150 000 30 000 35 0 0.0 0.2 100 0.75 0.426 0.9

    Parameters for MC Model: E = 30 000 kN/m 2; = 0.2; = 35 °; = 0 ° and 10 °

  • 8/9/2019 12 Plaxis Bulletin-with Shotcrete

    7/24

    P L X S Comparison Mohr Coulomb –Hardening SoilIn this comparison we consider the Mohr

    Coulomb criterion and the parameter set 1 for

    the Hardening Soil model for dilatant ( = 10 °)

    and non dilatant ( = 0 °) behaviour. The p ’-q-

    diagramm (Fig. 1) firstly shows that theeffective stress path observed in a typical

    undrained triaxial test is only obtained for the

    Hardening Soil model because the Mohr

    Coulomb model remains in the elastic range

    and thus no change in effective mean normal

    stress takes place. The well known fact that

    dilatant behaviour leads to an increase of

    strength in the undrained case is reproducedby both models in a similar way. It is important

    to point out that although the effective

    strength parameters are the same for both

    models the undrained shear strength is

    different due to different effective stress paths

    produced by both models, the Hardening Soil

    model giving an almost 15% lower value (see

    also Fig. 2). The pore pressure vs vertical strain

    diagram in Fig. 3 shows the expected increase

    of excess pore water pressure followed by arapid decrease for the dilatant material

    behaviour. It is worth noting that in the case

    of the Mohr Coulomb model there is a sharp

    transition when the excess pore water pressure

    starts to decrease (at the point where the

    failure envelope is reached) whereas for the

    Hardening Soil model this transition is smooth.

    The pore pressure parameter A (Fig. 4) is 1/3

    for the non dilatant Mohr Coulomb model (this

    is the theoretical value for elastic behaviour)and is independent of the loading stage and

    thus the vertical strain. For the Hardening Soil

    model A is not a constant but increases with

    deviatoric loading to a final value of approx.

    0.44 for this particular parameter set. Of course

    the parameter A tends to become negative for

    dilatant behaviour.

    Hardening Soil – Influence of E 50 ref and

    Eoed ref

    The reference parameter set is HS_1 of Table

    1. Based on this, the reference values of E 50and Eoed have been varied (HS_2 to HS_6). Only

    non dilatant material behaviour is considered.

    Fig. 5 shows effective stress paths in the p ’-q-

    space and it is interesting to see that for E 50= Eoed the stress path is the same for all values

    of E 50 leading to the same undrained shear

    strength although the vertical strain (and thus

    the shear strain) at failure is different (Fig. 6).

    If E50 is different from E oed , different stress

    paths and hence different undrained shear

    7

    Fig. 1Stress path in

    p’-q-space /MC – HS model

    Fig. 2 q- 1 - diagram / MC – HS model

    Fig. 3u- 1 - diagram / MC – HS model

    Fig. 4 A- 1 - diagram / MC – HS model

    p a r a m e t e r A

    e x c e s s p o r e p r e s s u r e [ k N / m 2 ]

    q [ k N / m 2 ]

    q [ k N / m 2 ]

  • 8/9/2019 12 Plaxis Bulletin-with Shotcrete

    8/24

    P L X S strengths are predicted. The differencebetween HS_4 and HS_5 is more than 30%which is entirely related to the difference in

    Eoed . This is perhaps not so suprising because

    Eoed controls much of the volumetric

    behaviour which in turn is very important for

    the undrained behaviour. However one has tobe aware of the consequences when using

    these parameters in boundary value problems.

    In Fig. 6 deviatoric stress is plotted against

    vertical strain and – unlike in a drained test

    where E oed has only a minor influence on the

    q- 1-curve – both parameters have a strong

    influence on the results. E 50 governs, as

    expected, the behaviour at lower deviatoricstresses but when failure is approached the

    influence of E oed becomes more pronounced.

    A very similar picture is obtained when excess

    pore pressures are plotted against vertical

    strain (Fig. 7). In Fig. 8 the pore pressure

    parameter A is plotted against vertical strain

    and it follows that for E oed > E 50 (parameter

    set HS_4) the pore pressure parameter A is

    approx. 0.34, i.e. close to the value for elastic

    behaviour. If E oed < E 50 (parameter sets HS_5and HS_6) the parameter A increases rapidly

    with loading, finally reaching a value of

    approximately A = 0.6.

    Summary

    It has been shown that the pore pressure

    parameters A and B obtained with PLAXIS from

    undrained analysis of triaxial stress paths using

    a Mohr Coulomb failure criterion are very close

    to the theoretical values given by Skempton(1954) for elastic material behaviour, i.e. B is

    approx. 1.0 and A is 1/3. For more complex soil

    behaviour as introduced by the Hardening Soil

    model the parameter A is no longer a constant

    value but changes with loading and is

    dependent in particular on the value of E oed in

    relation to E 50 . For a given E 50 the parameter

    A at failure is higher for lower E oed -values,

    which in turn results in lower undrained shear

    strength. E oed < E 50 is usually assumed fornormally consolidated clays experiencing high

    volumetric strains under compression which

    corresponds to a higher value for A in the

    undrained case. It is therefore justified to say

    that PLAXIS predicts the correct trend, care

    however has to be taken when choosing E oed ,

    because the influence of this parameter, which

    may be difficult to determine accurately for in

    situ conditions, is significant and may have a

    strong influence on the results when solving

    practical boundary value problems under

    undrained conditions.

    8

    Fig. 5Stress path in

    p ’ -q-space / Hardening Soil

    Fig. 6 q- 1 - diagram / Hardening Soil

    Fig. 7 u- 1 - diagram / Hardening Soil

    Fig. 8 A- 1 - diagram / Hardening Soil

    p a r a m e t e r A

    e x c e s s p o r e p r e s s u r e [ k N / m 2 ]

    q [ k N / m 2 ]

    q [ k N / m 2 ]

  • 8/9/2019 12 Plaxis Bulletin-with Shotcrete

    9/24

    P L X S ReferenceSkempton, A.W. (1954). The Pore-PressureCoefficients A and B. Geotechnique, 4, 143-

    147.

    H.F. Schweiger

    Graz University of Technology

    Benchmarking I

    PLAXIS BENCHMARK NO.1: SHIELD TUNNEL

    1 - RESULTS

    Introduction

    Unfortunately the response of the PLAXIS community to the call for solutions for the

    first PLAXIS benchmark example was not a

    success at all. Probably the example

    specified gave the impression of being so

    straightforward that everybody would

    obtain the same results and thus it would

    not be worthwhile to take the time for this

    exercise. However, I had distributed the

    example on another occasion within a

    different group of people dealing withbenchmarking in geotechnics. In the

    following I will show the results of this

    comparison together with the few PLAXIS

    results I have got. As mentioned in the

    specification of the problem no names of

    authors or programs are given, so I will not

    disclose which of the analyses have been

    obtained with PLAXIS.

    I hope, that the summary of the firstbenchmark example provides sufficient

    stimulation for taking part in the second call

    for solutions for PLAXIS Benchmark No.2,

    published in this bulletin, so that we can go

    ahead with this section and as awareness for

    necessity of validation procedures grow,

    proceed to more complex examples. The

    specification of Benchmark No.1 is not repeated

    here; please refer to the Bulletin No.11.

    Results Analysis A – elastic, no lining

    Figure 1 shows calculated settlements of the

    9

    Fig. 1: Surface

    settlements - analysis A

    Fig. 2:Horizontal

    displacements at surface -analysis A

    Fig. 3: Displacements of

    slected points - analysis A

    Fig. 4: Surface

    settlements - analysis B

    Fig. 5: Horizontal

    displacements at surface -analysis B

    h o r i z o n t a l d i s p l a c e m e n t s [ m m ]

    v e r t i c a l d i s p l a c e m e n t s [ m m ]

    d i s p l a c e m

    e n t s [ m m ]

    h o r i z o n t a l d i s p l a c e m

    e n t s [ m m ]

    v e r t i c a l d i s p l a c e m e n t s [ m m ]

  • 8/9/2019 12 Plaxis Bulletin-with Shotcrete

    10/24

    P L X S surface and it follows that even in the elasticcase some scatter in results is observed. Some of the discrepancies are due to differentboundary conditions. ST5, for example,restrained vertical and horizontal displacements

    at the lateral boundary, others introduced an

    elastic spring or a stress boundary condition.

    The effect of the lateral boundary is not so

    obvious from Figure 1 but becomes morepronounced when Figure 2, showing the

    horizontal displacement at the surface, is

    examined. Figure 3 summarizes calculated

    values at specific points, namely at the surface,

    the crown, the invert and the side wall (for

    exact location see specification). A maximum

    difference of 10 mm (this is roughly 20%) in

    the vertical displacement of point A (at the

    surface) is observed and this is by no means

    acceptable for an elastic analysis.

    Results Analysis B – elastic-perfectly

    plastic, no lining

    Figures 4 and 5 show settlements and

    horizontal displacements at the surface for the

    plastic solution with constant undrained shear

    strength. In Figure 4 a similar scatter as in

    Figure 1 is observed with the exception of ST4,

    ST9 and ST10 which show an even larger

    deviation from the "mean" of all analysessubmitted. Again ST5 restrained vertical

    displacements at the lateral boundary and thus

    the settlement is zero here. ST9 used a von-

    Mises and not a Tresca failure criterion which

    accounts for the difference. The strong

    influence of employing a von-Mises criterion

    as follows from Figure 4 has been verified by

    separate studies. It is emphasized therefore

    that a careful choice of the failure criterion is

    essential in a non-linear analysis even for asimple problem as considered here. The

    significant variation in predicted horizontal

    displacements, mainly governed by the

    placement of the lateral boundary condition,

    is evident from Figure 5. Figure 6 compares

    values for displacements at given points. Taking

    the settlement at the surface above the tunnel

    axis (point A) the minimum and maximum

    value calculated is 76 mm and 159 mm

    respectively. Thus differences are - as expected

    - significantly larger than in the elastic case but

    again not acceptable.

    10

    Fig. 6: Displacements of

    selcted points - analysis B

    Fig. 7: Surface

    settlements - analysis C

    Fig. 8: Horizontal

    displacements at surface analysis C

    Fig. 9: Displacements of

    selcted points - analysis C

    Fig. 10: Normal forces and contact pressure -

    analysis C

    n o r m a l f o r c e s [ k N ] / c o n t a c t p r e s s u r e [ k P a ]

    d i s p l a c e m e n t s [ m m ]

    h o r i z o n t a l d i s p l a c e m e n t s [ m m ]

    v e r t i c a l d i s p l a c e m e n t s [ m m ]

    d i s p l a c e m e n t s [ m m

    ]

  • 8/9/2019 12 Plaxis Bulletin-with Shotcrete

    11/24

    P L X S Results Analysis C – elastic-perfectlyplastic, lining and volume lossFigure 7 plots surface settlements for the

    elastic-perfectly plastic analysis with a specified

    volume loss of 2% and the wide scatter in

    results is indeed not very encouraging. The

    significant effect of the vertically andhorizontally restrained boundary condition

    used in ST5 is apparent. However in the other

    solutions no obvious cause for the differences

    could be found except that the lateral

    boundary has been placed at different

    distances from the symmetry axes and that

    the specified volume loss is modelled in

    different ways. Figure 8 shows the horizontal

    displacements at the surface and a similar

    picture as in the previous analyses can be

    found. Figure 9 depicts displacements at

    selected points. The range of calculated values for the surface settlement above the tunnel

    axis is between 1 and 25 mm and for the

    crown settlement between 17 and 45 mm

    respectively. The normal forces in the lining

    and the contact pressure between soil and

    lining do not differ that much (variation is

    within 15 and 20% respectively), with the

    exception of ST9 who calculated significantly

    lower values (Figure 10).

    Results with lateral boundary at distance

    of 100 m from tunnel axis

    Due to the obvious influence of the lateral

    boundary conditions a second round of analysis

    has been performed asking all authors to redo

    the analysis with a lateral boundary at 100 m

    distance from the line of symmetry with the

    horizontal displacements fixed. As follows from

    Figures 11 and 12 which depicts these results

    for case A, all results are now within a smal lrange and thus it has been confirmed that the

    discrepancies described from the previous

    chapter are entirely caused by the boundary

    condition. In addition to finite element results

    an analytical solution by Verruijt is included for

    comparison. Vertical displacements are in very

    good agreement and also horizontal

    displacements are acceptable in the area of

    interest (i.e. in the vicinity of the tunnel). For

    case B similar results are obtained althoughsome small differences are still present. For case

    C the comparison also matches much better

    now but some differences remain here and this

    is certainly due to the fact that the programs

    involved handle the specified volume loss in a

    different way.

    Comparison undrained – drained

    conditions

    In order to show that the influence of the

    lateral boundary is especially important under

    undrained conditions (constant volume) an

    11

    Fig. 11: Surface

    settlements analysis A / lateral

    boundary at 100 m

    Fig. 12: Horizontal

    displacements at surface analysis A / lateral boundary

    at 100 m

    Fig. 13: Surface

    settlements analysis A / undrained -

    drained

    Fig. 14: Horizontal

    displacements at surface analysis A

    / undrained - drained

    h o r i z o n t a l d i s p l a c e m e n t s [ m m ]

    v e r t i c a l d i s p l a c e m e n t s [ m m ]

    h o r i z o n t a l d i s p l a c e m e n t s [ m m ]

    v e r t i c a l d i s p l a c e m e n t s [ m m ]

  • 8/9/2019 12 Plaxis Bulletin-with Shotcrete

    12/24

    P L X S

    Fig. 1: Geometric data

    benchmark excavation

    Table 1.Parameters for

    sheet pile wall and strut

    analysis has been performed for case A with

    exactly the same parameters except for

    Poisson's ratio, chosen now to correspond to

    a drained situation, i.e. deformation under

    constant volume is no longer enforced (for

    simplicity the difference of Young's module

    between drained and undrained conditions hasbeen neglected). It follows from Figure 13 that

    for the drained case the surface settlements

    are virtually independent of the distance of the

    lateral boundary (results for mesh widths of

    50 m and 100 m are shown respectively). The

    horizontal displacements (Figure 14) show

    some differences of course but in the area of

    interest they are negligible in the drained case.

    SummaryThe outcome of this benchmark example

    clearly emphasizes the necessity of performing

    these types of exercises in order to improve

    the validity of numerical models. Given the

    discrepancies in results obtained for this very

    simple example much more scatter can be

    expected for real boundary value problems.

    One of the lessons learned from this example

    is that the influence of the boundary

    conditions can be much more severe in an

    undrained analysis than in a drained one and

    whenever possible a careful check should be

    made whether or not the placement of the

    boundary conditions affects the results one is

    interested in. One may argue that this is a trivial

    statement, practice however shows that dueto time constraints in projects it is not always

    feasible to check the influence of all the

    modelling assumptions involved in a numerical

    analysis of a boundary value problem. It is one

    of the goals of this section to point out

    potential pitfalls in certain types of problems

    which may not be obvious even to experienced

    users and to promote the development of

    guidelines for the use of numerical modelling

    in geotechnical practice.

    Helmut F. Schweiger, Graz University of

    Technology

    Benchmarking II

    PLAXIS BENCHMARK NO. 2: EXCAVATION 1

    The second benchmark is an excavation in

    front of a sheet pile wall supported by a

    strut. Geometry, excavation steps and

    location of the water table are given in

    Figure 1. Fully drained conditions are

    postulated. The soil is assumed to be a

    homogeneous layer of medium dense sand

    and the parameters for the Hardening Soil

    model, the sheet pile wall and the strut are

    given in Tables 1 and 2 respectively.

    The following computational steps have to be

    performed in a plane strain analysis:

    - initial phase (K 0 = 0.426)

    - activation of sheet pile, excavation step 1

    to level – 2.0 m

    12

    dry wet E50ref Eur

    ref Eoedref c ur pref m K0nc R f Rinter T-Strength

    kN/m 3 kN/m 3 kPa kPa kPa ° ° kPa - kPa - - - - kPa

    19.0 20.0 45 000 180 000 45 000 35 5 1.0 0.2 100 0.55 0.426 0.9 0.7 0.0

    Table 2. Parameters for HS-model

    EA EI W V

    kN/m kN 2/m kN/m/m -

    Sheet pile wall 2.52E6 8064 0.655 0.0

    Strut 1.5E6

  • 8/9/2019 12 Plaxis Bulletin-with Shotcrete

    13/24

    P L X S

    13

    - activation of strut at level –1.50 m,

    excavation step 2 to level – 4.0 m,

    - groundwater lowering inside excavation to

    level – 6.0 m

    - excavation step 3 to level – 6.0 m

    - phi-c-reduction

    REQUIRED RESULTS

    1. bending moments and lateral deflections of

    sheet pile wall (including values given in a

    table)

    2. surface settlements behind wall (including

    values given in a table)

    3. strut force

    4. factor of safety obtained from phi-c-

    reduction for the final excavation step

    Note: As far as possible results should be

    provided not only in print but also on disk

    (preferably EXCEL) or in ASCII-format respectively.

    Alternatively, the entire PLAXIS-project may be

    provided. Results may also be submitted via e-

    mail to the address given below.

    Results should be sent no later than

    August 1st, 2002 to:

    Prof. H.F. Schweiger

    Institute for Soil Mechanics and Foundation

    Engineering

    Computational Geotechnics Group

    Graz University of Technology

    Rechbauerstr. 12, A-8010 Graz

    Tel.: +43 (0)316 – 873-6234

    Fax: +43 (0)316 – 873-6232

    E-mail: [email protected]://www.tu-graz.ac.at/geotechnical_group/

    Recent Activities

    NEW DIRECTOR OF PLAXIS B.V.

    We are pleased to introduce the new

    director of PLAXIS BV, Dr. Klaas Jan Bakker.

    Dr. Bakker who started the first of February

    takes over the chair of Mr. Hutteman, who

    temporary occupied the chair on behalf of

    MOS Grondmechanica BV.

    Since the very beginning Dr. Bakker has been

    actively involved in the program(ming) of

    PLAXIS and is a key figure in the PLAXIS

    network. In his last position he was Head of

    Construction and Development at the Tunnel-engineering department for the Dutch Ministry

    of Public Works. Furthermore he is a lecturer

    at Delft University of Technology.

    COURSES

    In 2001 over 400 people attended one of

    the 13 Plaxis courses that were held in

    several parts of the world. Most of these

    courses are held on a regular basis, whileothers take place on an single basis.

    Regular courses:

    Traditionally, we start the year with the standard

    International course “Computational

    Geotechnics ” that takes place during the 3rd

    week of January in the Netherlands. The

    Experienced users course in the Netherlands

    is traditionally organised during the 4th week

    of March each year. Besides these standardcourses in the Netherlands, some other regular

    courses are held in Germany (March), England

    (April), France (Autumn), Singapore (Autumn),

    Egypt, and the USA. For the USA the course

    schedule is a bit different, as we plan to have

    an Experienced users course per two years and

    two standard courses in the intermediate

    periods. In May, 2002, we had the Experienced

    users course in Boston, which was organised

    in cooperation with the Massachusetts Institute

    of Technology (MIT). For January 2003, a

    standard course is scheduled in Berkeley in

  • 8/9/2019 12 Plaxis Bulletin-with Shotcrete

    14/24

    P L X S cooperation with the University of California.For August, 2003, another standard course isorganised in Boulder in cooperation with the

    University of Colorado. It is our intention to

    repeat this scheme of courses for the Western

    hemisphere. For the Asian region, we have

    planned a similar schedule that also includesan experienced users course once every two

    years.

    Other courses:

    Besides the above regular courses, other

    courses are organised in different parts of the

    world. In the past year, courses were held in

    Mexico, Vietnam, Turkey, Malaysia, etc. On the

    last page of this bulletin, you can see the

    agenda, which lists all scheduled courses and

    some other events. Our web-site www.plaxis.nl

    on the other hand will always give you the

    most up-to-date information.

    PLAXIS Practice I

    1. Introduction

    In W ü renlingen (Switzerland), for the

    temporary storage of nuclear waste, an

    extension of the existing depository was

    required. To facilitate this, a 7.5 - 9.0 m deep

    excavation was necessary. This bordered

    immediately adjacent pre-existing structures. Furthermore, along one of it ‘ s

    sides there is a route used for the

    transportation of nuclear waste.

    2. Project

    Length of excavation: 98 m

    Width of excavation: 33 m

    Maximum depth: 9 m

    Start of works: Spring 2001

    End of construction: Summer 2001

    3. Geotechnical conditions

    In the W ü renlingen area, significant deposits

    of the Aare River dominate, which comprises

    predominantly gravels and sands. The

    groundwater table lies at a depth of ca. 9.5 m

    below the surface prior to excavation. The

    gravels and sands are known as good

    foundation material, with some low apparent

    cohesion, allowing for the temporaryconstruction of vertical cuttings of low height.

    4. Construction procedure

    Due to space restrictions, a sloped earthworks

    profile is not possible. Therefore, it was

    concluded to undertake the excavation using

    14

    Model Behavior unsat sat E50 ref Eoed ref m E ur ref ur c Rinter- kN/m3 kN/m3 kPa kPa - KPa - kPa ° ° -

    HS Drained 22.0 22.0 33 000 37 500 0.5 99 000 0.25 1.0 32 6 1.0

    Table 1. Soil parameters

    Photo 1:Participants in the Experienced users

    course, March 2002, the Netherlands.

    Photo 2:Plaxis short course,

    October 2001, Mexico

    Photo 3:Plaxis short course,

    November 2001,Vietnam.

  • 8/9/2019 12 Plaxis Bulletin-with Shotcrete

    15/24

    P L X S a soil nailing option. Correspondingly, theexcavation had to proceed in benched stages.Each bench had a height of 1.30 m and a width

    of 4.5 to 6.0 m. The free face was immediately

    covered with an 18 cm thick layer of shotcrete

    and tied back with untensioned soil nails.

    The bond strength of the soil nails wasestablished by pullout tests. Usually the soil

    nails are cemented along their full length. For

    the pullout tests, however, the bond length

    was reduced to between 3.0 and 4.0 m with a

    total length of 7.0 m. The individual nails have

    a cross-sectional area of 25 mm and yield

    strength of 246 kN. During the pullout tests,

    it was possible to tension the nails to yield point

    without any indication of creep or failure.

    In total five benches were necessary to reachexcavation depth. The wall itself is vertical, with

    nail spacing of 1.5 m and 1.3 m, horizontal and

    vertical respectively. The nails were tightened

    three days after installation with a torque key,

    to secure a fast seat to the shotcrete. A pre-

    tensioning with fully cemented nails is not

    sensible (see fig. 1).

    5. CalculationsThe initial calculations were performed with

    the usual statical programs based on beam

    theory and limiting equilibrium loading. Due

    to the particular safety requirements in

    connection with nuclear transport additional

    deformation predictions were made. These

    calculations were carried out with Plaxis version

    7. Geotextile elements were used to model the

    nails. Due to the good bonding of the soil nails

    proven by the pullout attempts, no reduction

    was made for loading transfer along the

    geotextile elements.

    The calculations were performed with the

    following parameters:

    Hardening soil model

    Plane strain with 6 node elements

    649 elements

    Due to the simple geology, only one soil layer

    was used (see table 1)Due to good bonding between soil and

    shotcrete wall no reduction in interface

    friction was made.

    The calculations were performed without

    groundwater.

    Shotcrete wall of 18 cm thickness with

    reinforced wire mesh, modeled as beam

    elements. EA = 5.4 x 10 6 kN/m, EI =

    1.458 x 104 kNm 2/m and = 0.2

    Soil nails are modeled as geotextile elements.EA = 6.87 x 10 4 kN/m and = 0.Results

    Final excavation stage

    Maximum deformation of shotcrete wall;

    17 mm (see fig. 2a and fig. 3).

    Maximum horizontal deformation of

    shotcrete wall; 14 mm (see fig. 2d).

    Maximum force in geotextile element; 49

    kN/m, or 73.5 kN per nail (see fig. 4).

    Maximum bending moment in shotcretewall; 11.5 kNm/m (see fig. 2b).

    Maximum axial force in shotcrete wall; -67

    kN/m (see fig. 2c).

    It must be noted, that the tensile forces in the

    geotextile elements at the final excavation

    stage did not calculate to zero at the toe of

    the nail, as should be in reality. This could be

    due to a too wide FE-net around the geotextile

    elements, additionally due to the use of only

    6-nodes instead of the more precise 15-nodeelement.

    6. Measurement on site

    In total, deformation of the excavation was

    taken at five stations. Prior to excavation

    clinometers were placed ca. 1.0 m behind the

    proposed shotcrete wall, with a depth of 7 m

    below excavation level. Figure 7 shows the

    measured horizontal deformations of two

    cross-sections with equal depths (7.2 and 9.0

    mm). Figure 6 contains the calculated

    horizontal deformations along a vertical line

    15

    Fig. 1:Typical section

    with horizontal displacements

  • 8/9/2019 12 Plaxis Bulletin-with Shotcrete

    16/24

    P L X S 1m behind the shotcrete wall (14.9 mm). Acomparison shows that the calculateddeformations are greater than the measured.

    Conspicuous is, that below the excavation base

    there is practically no movement measurable.

    Plaxis, however, has predicted some 4 mm

    deformation. This may be due to an initial

    offset or due to stiffer behavior at the bottom

    of the excavation.

    The maximum measured horizontaldeformation was between 7.2 and 9.0 mm at

    the wall head. Plaxis calculated 14.9 mm

    horizontal deformation at this point.

    If only relative measurements are considered,

    assuming that no movement takes place at the

    wall toe, then the prediction from Plaxis lays

    very close to the actual maximum measured.

    The forms of the measured and calculated

    deformation curves correspondwell well with

    each other.

    7. Conclusions

    The calculated deformation of the nailed wall

    corresponds well with the measured values,

    especially if the predicted deformations of

    Plaxis below excavation level are not

    considered.

    The soil parameters used correspond to

    conservative average values, evaluated from a

    large number of previous sites under similarconditions. It is plausible that the deformation

    parameters are underestimated.

    The Plaxis calculation illustrates

    comprehensively, that the soil nailing system

    (soil-nail-wall) works as an interactive system. It

    shows further, that the maximum nail force

    does not necessarily act at the nail head, but

    according to the distribution of soil movements

    may also lie far behind the head of the nail. Thismeans that displacements are necessarily taking

    place before the nail force is activated.

    On the one hand, it shows that the shotcrete

    wall in vertical alignment is stressed by bending

    and compression, and that the wall ’s foot

    transmits compressive stresses to the soil. On

    the other hand, the shotcrete wall in horizontal

    alignment is only loaded by bending, whereby

    in the absence of lateral restrictions of

    deformation there could also be tension. Finally

    it is clear to see, that nail head support and

    pullout failure should be considered (see fig. 4).

    16

    Fig. 2: Output in

    shotcrete wall

    Fig. 3:Deformation of

    geotextile

    Fig. 4:Axial Forces in

    geotextile

    Fig. 5: Measured

    displacements

    Fig. 6: Calculated

    displacement

  • 8/9/2019 12 Plaxis Bulletin-with Shotcrete

    17/24

    Thanks to prior deformation calculation with

    Plaxis and measurement control by clinometer

    installation during the construction stage, the

    safety of the works in relation to nuclear

    transportation could be assessed at all times.

    H.J. Gysi, G.Morri, Gysi Leoni Mader AG,Zü rich - Switzerland

    Calculation procedure

    Phase 1: Initial stresses, using Mweight = 1.

    Phase 2: Live load (5 kN/m 2 and 10 kN/m 2)

    Phase 3: Excavation to top level of

    wall (-0.80 m).

    Phase 4: First excavation stage,

    including shotcrete of wall

    and installation of first rowof soil nails (-2.10 m).

    Phase 5: Second excavation stage with

    shotcrete wall (-3.40 m).

    Phase 6: Installation of second row

    of soil nails.

    Phase 7: Third excavation stage

    with shotcrete wall (-4.70 m).

    Phase 8: Installation of third row of soil nails.

    Phase 9: Fourth excavation stage

    with shotcrete wall (-6.00 m).Phase 10: Installation of fourth row

    of soil nails.

    Phase 11: Fifth excavation stage

    with shotcrete wall (-7.30 m).

    Phase 12: Installation of fifth row of soil nails.

    PLAXIS Practice II

    FINITE ELEMENT MODELLING OF A DEEP

    EXCAVATION SUPPORTED BY JACK-IN

    ANCHORS

    1. INTRODUCTION

    A mixed development project that is located

    at UEP Subang Jaya, Malaysia consists of three

    condominium towers of 33 storeys and a single

    20-storey office tower. Due to the huge

    demand for parking space, an approximately

    three storey deep vehicular parking basement

    was required. The deep excavation, through a

    filled layer of very loose silty sand and very soft

    peaty clay varies from 11m to 13m. Due to the

    presence of very soft soil condition and the

    fast track requirement of the project,

    Contiguous Bored Pile (CBP) walls supported

    by soil nails were used to support the

    excavation process. This hybrid technique wasenvisaged and implemented due to its speed

    in construction and the ability of the Jack-in

    Anchors 1) in supporting excavations in

    collapsible soils, high water table and in soft

    soils conditions (Cheang et al., 1999 & 2000,

    Liew et al, 2000). The use of soil nailing in

    excavations and slope stabilisation has gained

    wide acceptance in Southeast Asia, specifically

    in Malaysia and Singapore due to its

    effectiveness and huge economic savings.Adopting the observational method, numerical

    analyses using ‘PLAXIS version 7.11 ’ a finite

    element code were conducted to study the

    soil-structure interaction of this relatively new

    retaining system. Numerical predictions were

    compared with instrumented field readings and

    deformation parameters were back analysed

    and were used in subsequent prediction of wall

    movements in the following excavation stages.

    2. SUBSURFACE GEOLOGY

    The general subsurface soil profile of the site,

    shown in Table 1 consists in the order of

    succession of loose clayey SILT, loose to

    medium dense Sand followed by firm to hard

    clayey SILT. The residual soils (Figure 1) are inter-

    layered by 9m thick soft dark peaty CLAY. For

    analysis purposes the layers were simplified

    P L X S

    17

    Photo 1: Jack-in Anchor Technique

    1) Jack-in Anchor Technique ™ is a patented product by Specialist Grouting Engineers Sdn. Bhd. Malaysia

  • 8/9/2019 12 Plaxis Bulletin-with Shotcrete

    18/24

    P L X S into representative granular non-cohesive andcohesive material, such as:

    3. THE RETAINING SYSTEM

    In view of the close proximity of commercial

    buildings to the deep excavation, a very stiff

    retaining system is required to ensure minimal

    ground movements the retained side of theexcavation. Contiguous Bored Pile that acts as

    an earth retaining wall during the excavation

    works were installed along the perimeter of

    the excavation and supported by jack-in

    anchors. The retaining wall system consist of

    closely spaced 1000mm diameter contiguous

    bored piles supported by hollow pipes which

    functions as soil nails are installed by hydraulic

    jacking using the Jacked-in Soil Anchor

    Technology ™ as shown in photo 3. Figure 2illustrates the soil nail supported bored pile wall

    system.

    18

    Photo 2:The Retaining System: Contiguous Bored Pile

    Wall Supported by Jack- in Anchors that function

    as Soil Nails

    Photo 3:Hydraulic Jacking Fig. 2b: The Retaining System

    Fig. 1: Typical Subsurface Profile

    Fig. 2a: The Retaining System

    DEPTH (m) DESCRIPTION SPT ‘N’ VALUE

    LAYER 1 0 to 9 Clayey SILT 18

    LAYER 4 27 to 35 Dense SILT >50

    Table 1. Soil Layers

  • 8/9/2019 12 Plaxis Bulletin-with Shotcrete

    19/24

    P L X S This method has proven to be an efficient andeffective technique for excavation support,where conventional soil nails and ground

    anchors have little success in such difficult soft

    soil conditions. Such conditions are sandy

    collapsible soil, high water table and in very

    soft clayey soils where there is a lack of short-term pullout resistance.

    Relatively, larger movements are required to

    mobilise the tensile and passive resistance of

    the jacked-in pipes when compared to ground

    anchors. However it was anticipated that the

    ground settlement at the retained side and

    maximum lateral displacement of the wall

    using this system would still be within the

    required tolerance after engineeringassessment.

    4. GEOTECHNICAL INSTRUMENTATION

    In view of this relatively new excavation

    support technique used for in-situ soft soil

    conditions and the close proximity of the

    commercial buildings to the deep excavation,

    a performance monitoring program was

    provided. Firstly, as a safety control. Second,

    to refine the numerical analysis using field

    measurements obtained at the early stages of

    construction and third, to provide an insightinto the possible working mechanisms of the

    system.

    The geotechnical instrumentation program

    consists of 18 vertical inclinometer tubes

    located strategically along the perimeter

    within the Contiguous Bored Pile wall and 30

    optical survey makers (surface settlement

    points) near the vicinity of the commercial

    buildings. The locations of these instruments

    are detailed in Fig. 4 for the inclinometers.Fig. 5 illustrates the restrained trend of

    horizontal displacement of the wall as

    measured through inclinometers installed at

    the site

    5. FINITE ELEMENT MODELLING

    EQUIVALENT PLATE MODEL

    Equivalence relationships have to be developed

    between the 3D structure and 2D numerical

    model. Non 2-D member such as soil nails mustbe represented with ‘equivalent ’ properties that

    reflect the spacing between such elements.

    Donovan et al. (1984) suggested that properties

    of the discrete elements could be distributed

    over the distance between the elements in a

    19

    Fig. 4: Geotechnical

    Instruments

    Fig. 5: Measures deflection

    profile

  • 8/9/2019 12 Plaxis Bulletin-with Shotcrete

    20/24

    P L X S uniformly spaced pattern by linear scaling.Unterreiner et al. (1997) adopted an approachsimilar to Al-Hussaini and Johnson (1978) where

    an equivalent plate model replaces the discrete

    soil-nail elements by a plate extended to full

    width and breadth of the retaining wall. Nagao

    and Kitamura (1988) converted the propertiesof the 3-D discrete elements into an equivalent

    composite plate model by taking into account

    the properties of the adjacent soil. The two-

    dimensional finite element analysis performed

    hereafter uses the ‘composite plate model ’

    approach.

    Finite Element Analysis

    The finite element analyses were performed

    using ‘PLAXIS’ (Brinkgreve and Vermeer, 1998).The Contiguous Bored Pile wall and steel tubes

    were modelled using a linear-elastic Mindlin

    plate model (Figure 6). The nails were ‘pinned ’

    to the CBP wall. The soil-nail soil interface was

    modelled using the elastic-perfectly-plastic

    model where the Coulomb criterion

    distinguishes between the small displacement

    elastic behaviour and ‘slipping ’ plastic behaviour.

    The surrounding soils were modelled using the

    Mohr-Coulomb soil model. Table 2 and 3 showsthe properties used for the analyses.

    6. COMPARISON OF FIELD INSTRUMENTED

    AND PREDICTED DISPLACEMENT READINGS

    Measured And Predicted Lateral Deflection

    Figure 7 compares the in-situ, predicted and

    back analysed lateral deflection of the soil nail

    supported wall. The measured lateral deflection

    is showing a trend of restrained cantilever and

    the jack-in anchors are restraining the

    horizontal displacement of the wall. Initial finite

    element prediction (Prediction No.1) based on

    soil strengths correlated from laboratory

    20

    Table 2: Soil Properties Layer 1 Layer 2 Layer 3 Layer 4

    E (kN/m 2) 34000 9000 30000 200000

    soil (kN/m 3) 19 20 20 19

    0.25 0.25 0.25 0.2525 0 35 30

    C 2 12 2 2

    0 0 0 0

    Table 3: Nail and Contiguous Bored Pile Wall Properties

    ENAIL 2.90E+06 kN/m 2

    ECONC. 2.00E+07 kN/m 2

    Figure 7:Lateral Deflection of Soil Nailed

    Contiguous Bored Pile Wall

    Figure 8:Lateral Deflection of ‘ Stiff ’ and ‘ Flexible ’

    Soil Nail System

    Fig 6:2-Dimensional finite element mode

  • 8/9/2019 12 Plaxis Bulletin-with Shotcrete

    21/24

    P L X S results. Excavation involves mainly theunloading of adjacent soil, the ground stiffnessis dependent on stress level and wall

    movements. These aspects were taken into

    account in prediction no.2, the trend is similar

    and a better prediction was obtained.

    Subsequent finite element runs were madebase on the improved parameters.

    7. SOIL-NAIL-SOIL-STRUCTURE

    INTERACTION

    Lateral Bending Stiffness of Soil Nails

    A flexible nail system with a bending stiffness

    of 1/220 of the stiff nail system was numerically

    simulated. It was hypothesised that if bendingstiffness of the inclusions were insignificant in

    the performance of the nail system, there

    would be no difference in the lateral

    displacement of the wall. However figure 8

    shows that bending stiffness is significant, at

    least in a soil nail supported embedded wall.

    With a stiff nail system, the lateral displacement

    was significantly reduced. Figure 9 illustrates

    that the influence increases as excavation

    proceeds further, this is due to the fact thatlarger movements are required to mobilised

    lateral bending resistance of the nails.

    8. CONCLUSION

    The soil-nail-soil-structure interaction of a nailed

    wall is complex in nature. Soil nails are subjected

    to tension, shear forces and bending moments.

    The outcome of this numerical investigation of

    a real soil-nailed supported Contiguous Bored

    Pile wall in soft residual soils is that nail bending

    stiffness has a significant effect as deformation

    progresses, at least in this hybrid support

    system. Soil-nail lateral resistance is dependent

    not only on the relative stiffness and yield

    strengths of the soil and nail, but also on the

    local lateral displacement across the shear zone.

    Due to the hybrid nature of this system, the

    results indicated that the relative stiffness of

    the nail and wall too governs the developmentof bending i.e., lateral resistance of the soil nail.

    In soft soils, numerical results indicated greater

    bending moments in the nails due to larger wall

    deflection. The implication of this study is

    additional analysis of different working

    mechanisms in various soil types should be

    envisaged.

    9. REFERENCE

    1. Al-Hussaini, M.M., Johnson, L., (1978),Numerical Analysis of Reinforced Earth Wall,

    Proc. Symp. On Earth Reinforcement ASCE

    Annual Convention, p.p. 98-126.

    2. Brinkgreve, R.B.J., Vermeer, P.A., (1998),

    Plaxis- Finite Element Code for Soil and Rock

    Analyses- Version 7.11,A.A.Balkema.

    3. Cheang, W.L., Tan, S.A., Yong, K.Y., Gue, S.S,,

    Aw, H.C., Yu, H.T., Liew, Y.L., (1999), Soil Nailing

    of a Deep Excavation in Soft Soil,

    Proceedings of the 5Th InternationalSymposium on Field Measurement in

    Geomechanics, Singapore, Balkema.

    4. Cheang, W.L., Luo, S.Q., Tan, S.A., Yong, Y.K.,

    (2000), Lateral Bending of Soil Nails in an

    Excavation, International Conference on

    Geotechnical & Geological Engineering,

    Australia. ( To be Published)

    5. Donovan, K., Pariseau, W.G., and Cepak,

    M.,(1984), Finite Element Approach to Cable

    Bolting in Steeply Dipping VCR Slopes,Geomechanics Application in Underground

    Hardrock Mining, pp.65-90.New York: Society

    of Mining Engineers.

    6. Liew, S.S., Tan, Y.C., Chen, C.S., (2000), Design,

    Installation and Performance of Jack-In-Pipe

    Anchorage System For Temporary Retaining

    Structures, International Conference on

    Geotechnical & Geological Engineering,

    Austraila. ( To be Published)

    7. Nagao, A., Kitamura, T., (1988), Filed

    Experiment on Reinforced Earth and its

    Evaluation Using FEM Analysis, International

    21

    Figure 9: Influence of Nail Stiffness

  • 8/9/2019 12 Plaxis Bulletin-with Shotcrete

    22/24

    P L X S Symposium on Theory and Practice of EarthReinforcement, Japan, pp.329-334.8. Unterreiner, P., Benhamida, B., Schlosser, F.,

    (1997), Finite Element Modelling Of The

    Construction Of A Full-Scale Experimental Soil-

    Nailed Wall. French National Research Project

    CLOUTERRE, Ground Improvement, p.p. 1-8.

    W.L.Cheang, Research Scholar,

    E-mail: [email protected],

    S.A.Tan, Associate Professor,

    E-mail: [email protected],

    K.Y.Yong, Professor, Department of Civil

    Engineering, National University of

    Singapore

    Users Forum

    BEAM TO PILE PROPERTIES

    IN PLAXIS

    Properties for anchors are entered per anchorso : EA = [kN] per anchor

    Ls = [m] is spacing centre to centre

    Beams and geotextiles are continuous in the

    z-direction (perpendicular to the screen).

    Therefore, a beam /geotextile will be a

    continuous plate/textile in the z-direction. The

    properties are entered per meter

    in the z-direction EA = [kN/m], EL = [kN/m 2/m]

    Modelling a row of piles or a row of grout

    bodies in the z-direction can be done by

    dividing the EA real and EL real by

    the centre-to-centre distance Ls.

    For a beam:

    EAreal =Ereal *d real *b real [kN]EAplaxis = EAreal /Ls [kN/m]

    For a grout body:

    EAreal =Ereal *d real *b real [kN]

    EAplaxis = EAreal /Ls [kN/m]

    22

    Fig 1.Partial geometry for shieldtunnel

    project

    Some geometries

    In the past bulletins, a few articles were related

    to experience with the 3D Tunnel program.

    Since it ’s release last year, the 3D Tunnel

    program has been used in practice for some

    interesting projects. In the below graphs,

    without further explanation you will find a brief

    overview of possible projects and geometries.

    The printed figures also indicate that the 3D

    Tunnel program can deal with projects beyond

    tunneling.

  • 8/9/2019 12 Plaxis Bulletin-with Shotcrete

    23/24

    P L X S

    Fig 4.Partial geometry for anchored retaining wall.

    Fig 5.Deformed mesh for interacting tunnels.

    23

    Fig 2. Partial geometry for pile-

    raft foundation

    Fig 3.Displacement

    contours for shield tunnel project

  • 8/9/2019 12 Plaxis Bulletin-with Shotcrete

    24/24

    P L X S ACTIVITIES8-10 MAY, 2002

    International course for experienced Plaxis users

    (English)

    Boston, USA

    16 MAY, 2002

    2nd French Plaxis Users meeting (French)

    Paris, France

    14-18 OCTOBER, 2002

    Short course on Computational Geotechnics

    (Arabic, English)

    Cairo, Egypt

    25-26 OCTOBER, 2002Short course on Computational Geotechnics

    (Portuguese, English)

    Sao Paulo, Brazil

    7-8 NOVEMBER, 2002

    11th European Plaxis Users meeting (English)

    Karlsruhe, Germany

    18-20 NOVEMBER, 2002

    Short course on Computational Geotechnics(English)

    Trondheim, Norway

    27-29 NOVEMBER, 2002

    Short course on Computational Geotechnics

    (French)

    ‘Pratique des é lé ments finis en G é otechnique ’

    Paris, France

    6-9 JANUARY, 2003Short course on Computational Geotechnics &

    dynamics (English)

    Berkeley, USA

    19-22 JANUARY, 2003

    Short course on Computational Geotechnics

    (English)

    Noordwijkerhout, The Netherlands

    10-12 MARCH, 2003

    Short course on Computational Geotechnics

    (German)

    Stuttgart, Germany

    23-26 MARCH, 2003

    International course for experienced Plaxis users

    (English)

    Noordwijkerhout, The Netherlands

    8-10 APRIL, 2003

    Short course on Computational Geotechnics

    (English)

    Manchester, England

    28-30 APRIL, 2003

    Short course on Computational Geotechnics

    (Italian)

    Napoli, Italy

    31 JULY –2 AUGUST, 2003

    Experienced Plaxis users course (English)

    Singapore

    For more information on these activities

    please contact:

    PLAXIS bv

    P.O. Box 572

    2600 AN DELFT

    The Netherlands

    Tel: +31 15 26 00 450

    Fax: +31 15 26 00 451

    E-mail: [email protected]