  • 7/29/2019 12 Using PIP for Project Baseline Planning

    1/22

    This report is provided by the development team for project management course of Huawei.

    Huawei confidential information, spread unapproved prohibited 1

    Using PIP

    for

    Project Baseline PlanningFeb 14, 2004

  • 7/29/2019 12 Using PIP for Project Baseline Planning

    2/22

    This report is provided by the development team for project management course of Huawei.

    Huawei confidential information, spread unapproved prohibited 2

    Course Objective

    1. Understand and familiarize with the design

    concepts and basic operations of the PIP

    tool.

    2. Able to use PIP tool to produce project

    baseline

  • 7/29/2019 12 Using PIP for Project Baseline Planning

    3/22

    This report is provided by the development team for project management course of Huawei.

    Huawei confidential information, spread unapproved prohibited 3

    Design Concepts of PIP Tool

    Brief Introduction of PIP Tool

    Operation Guide of PIP Tool

    Contents

  • 7/29/2019 12 Using PIP for Project Baseline Planning

    4/22

    This report is provided by the development team for project management course of Huawei.

    Huawei confidential information, spread unapproved prohibited 4

    Design Concepts of PIP tool

    Manage scope, schedule and cost on the same integrated

    platform.

    Manage work packages at every level conveniently and

    efficiently.

    Maintain performance baseline

    Output data to budget and PA systems accurately and

    quickly.

    Refresh the implementation progress quickly and adjust the

    plan conveniently.

    Generate earned value report conveniently and quickly

    Easy to learn and use.

  • 7/29/2019 12 Using PIP for Project Baseline Planning

    5/22

    This report is provided by the development team for project management course of Huawei.

    Huawei confidential information, spread unapproved prohibited 5

    Design Concepts of PIP Tool

    Brief Introduction of PIP Tool

    Operation Guide of PIP Tool

    Contents

  • 7/29/2019 12 Using PIP for Project Baseline Planning

    6/22

    This report is provided by the development team for project management course of Huawei.

    Huawei confidential information, spread unapproved prohibited 6

    Brief Introduction of PIP Tool

    A set of project PIP templates:

    (corresponding product) PIP_English Template

    (corresponding product) PIP_Chinese Template

    Template for the earned value report:

    EV Report _Template

    A set of methods for standard earned value management

    process .

    PIP Guide (English / Chinese)

    Training materials for Earned Value

    Management.

  • 7/29/2019 12 Using PIP for Project Baseline Planning

    7/22

    This report is provided by the development team for project management course of Huawei.

    Huawei confidential information, spread unapproved prohibited 7

    Design Concepts of PIP Tool

    Brief Introduction of PIP Tool

    Operation Guide of PIP Tool

    Contents

  • 7/29/2019 12 Using PIP for Project Baseline Planning

    8/22

    This report is provided by the development team for project management course of Huawei.

    Huawei confidential information, spread unapproved prohibited 8

    5. Distribute resources

    1. Create project environment

    2. Definition of WBS3. Task duration and sequence

    4. Define resources

    6. Adjust resource distribution

    7. Optimize the plan8. output the budget

    9. Refresh the project schedule

    10. EV report

    Operation Guide of PIP Tool

  • 7/29/2019 12 Using PIP for Project Baseline Planning

    9/22

    This report is provided by the development team for project management course of Huawei.

    Huawei confidential information, spread unapproved prohibited 9

    1. Create project environment: (operation)

    1.1 Take PIP template as the basis of a new projects.

    1.2 Set the toolbar required by PIP: resource

    management and analysis

    1.3 Input: document attributes

    1.4 Set project options: currency, schedule and

    calculation mode

    1.5 Set project information: start (or end) time andproject calendar

    1.6 Store the new project

    Operation Guide of PIP Tool

  • 7/29/2019 12 Using PIP for Project Baseline Planning

    10/22

    This report is provided by the development team for project management course of Huawei.

    Huawei confidential information, spread unapproved prohibited 10

    2. Definition of WBS (Operation)

    2.1 Take PIP template as the basis of a new project.

    2.2 Set WBS Code

    Operation Guide of PIP Tool

  • 7/29/2019 12 Using PIP for Project Baseline Planning

    11/22

    This report is provided by the development team for project management course of Huawei.

    Huawei confidential information, spread unapproved prohibited 11

    2Definition of WBS (Notes)

    Keep the structure of the level-2 template unchanged

    WBS vs. OBS Too coarse

    Too detail

    Operation Guide of PIP Tool

  • 7/29/2019 12 Using PIP for Project Baseline Planning

    12/22

    This report is provided by the development team for project management course of Huawei.

    Huawei confidential information, spread unapproved prohibited 12

    3Task duration and sequence : (Operation)

    3.1 Take PIP template as the basis of a new project .

    3.2 Estimate duration (PERT) 3.3 Assign Task calendar

    3.4 Link activities (Relation Diagram)

    3.5 Observe constraints

    Operation Guide of PIP Tool

  • 7/29/2019 12 Using PIP for Project Baseline Planning

    13/22

    This report is provided by the development team for project management course of Huawei.

    Huawei confidential information, spread unapproved prohibited 13

    3 Task duration and sequence: (Notes)

    Try NOT to enter dates directly

    Check missing links carefully

    Operation Guide of PIP Tool

  • 7/29/2019 12 Using PIP for Project Baseline Planning

    14/22

    This report is provided by the development team for project management course of Huawei.

    Huawei confidential information, spread unapproved prohibited 14

    4 Define resources: (Operation)

    4.1 Take PIP template as the basis of a new project .

    4.2 Define human resources 4.3.Define OPEX costs

    4.4.Define sub-con costs

    Operation Guide of PIP Tool

  • 7/29/2019 12 Using PIP for Project Baseline Planning

    15/22

    This report is provided by the development team for project management course of Huawei.

    Huawei confidential information, spread unapproved prohibited 15

    4 Define resources: (Notes)

    Enter standard rate with /d (or /w, /m)

    Remember to reflect max available unit

    Keep consistent with the resource names in the

    budget table

    Calendar:Hotel & Allowance use 7Days Calendar

    Material standard rate should be 1 or a known rate Most accrueat should be default Prorated

    Operation Guide of PIP Tool

  • 7/29/2019 12 Using PIP for Project Baseline Planning

    16/22

    This report is provided by the development team for project management course of Huawei.

    Huawei confidential information, spread unapproved prohibited 16

    5 Distribute resources: (Operation)

    5.1 Assign resource using Resource Work Form

    5.2 Define delay start date with Resource

    Schedule Form

    5.3 Adjust contour and cost rate with Assignment Info

    Operation Guide of PIP Tool

  • 7/29/2019 12 Using PIP for Project Baseline Planning

    17/22

    This report is provided by the development team for project management course of Huawei.

    Huawei confidential information, spread unapproved prohibited 17

    5 Distribute resources: (Notes)

    Assignment of resource can affect task duration

    Assign all work first, then material

    Leave out Contingency at this step

    Operation Guide of PIP Tool

  • 7/29/2019 12 Using PIP for Project Baseline Planning

    18/22

    This report is provided by the development team for project management course of Huawei.

    Huawei confidential information, spread unapproved prohibited 18

    6 Adjust resource distribution: (Operation)

    6.1 Find overallocation

    6.2 Level it manually

    Operation Guide of PIP Tool

  • 7/29/2019 12 Using PIP for Project Baseline Planning

    19/22

    This report is provided by the development team for project management course of Huawei.

    Huawei confidential information, spread unapproved prohibited 19

    6 Adjust resource distribution: (Notes)

    Not to use auto leveling

    Manual leveling at beginning and end of task may

    affect task duration

    Operation Guide of PIP Tool

  • 7/29/2019 12 Using PIP for Project Baseline Planning

    20/22

    This report is provided by the development team for project management course of Huawei.

    Huawei confidential information, spread unapproved prohibited 20

    7 Optimize the plan: (Operation)

    7.1 Optimize schedule

    Use CPM

    Introduce Buffer (Allocate contingency)

    7.2 Optimize cost

    Check resource over-allocation

    Check idle time Check sharing of resources

    Operation Guide of PIP Tool

  • 7/29/2019 12 Using PIP for Project Baseline Planning

    21/22

    This report is provided by the development team for project management course of Huawei.

    Huawei confidential information, spread unapproved prohibited 21

    7 Optimize the plan: (Notes)

    Keep the backup copy of the plan

    Operation Guide of PIP Tool

  • 7/29/2019 12 Using PIP for Project Baseline Planning

    22/22

    This report is provided by the development team for project management course of Huawei.

    Huawei confidential information, spread unapproved prohibited 22

    Q&A